Escolar Documentos
Profissional Documentos
Cultura Documentos
Scope
1) [I] This Global Practice (GP) covers the design and construction of concrete structures.
2) [I] An asterisk (*) indicates that additional information from Owner is required or approval by Owner
is required.
Table of Contents
4. Construction .......................................................................................................... 8
4.1. Placement .................................................................................................... 8
4.2. Joints ............................................................................................................ 8
4.3. Finishing ....................................................................................................... 8
5. Concrete Design.................................................................................................... 9
Table of Tables
1. Required References
1) This Section lists Practices and Standards that are referenced and assumed to be a part of this
document. Unless otherwise specified herein, use the latest edition.
2) [I] Local codes and standards may be substituted for the ones referenced herein, provided the
following provisions are met:
a) The resultant design meets the safety and serviceability criteria attained through this GP.
b) Substitution is accepted by the authorities where the facility is to be located and by the Owner's
Engineer.
2. Additional References
1) The following Practices and Standards shall be used with this GP as applicable.
2) [I] Local codes and standards may be substituted for the ones referenced herein, provided the
following provisions are met:
a) The resultant design meets the safety and serviceability criteria attained through this GP.
b) Substitution is accepted by the authorities where the facility is to be located and by the Owner's
Engineer.
RFCH For ExxonMobil Use Only Version 2.0.0
3. Materials
1) [I] Concrete shall be per ACI 318/318R.
2) [R] All reinforcing bars shall be ASTM A 615/A 615M Grade 60 unless otherwise specified.
3) * [I] Contractor shall submit a statement detailing the concrete mix design for approval by the
Owner's Engineer. This statement shall include properties of the materials, proportions of cement,
water and aggregates by weight and type, and quantity of admixtures (if any) proposed for each class
of concrete required.
4) [R] Concrete mix design shall consider environmental exposure and potential chemical attack and
shall specify the use of beneficial admixtures such as air entrainment, fly ash, and other pozzolanic
materials.
5) [R] Maximum water cementitious ratio shall be minimized to maximize durability but shall in no case
be more than 0.50. The maximum water cementitious ratio shall be 0.40 where the concrete will be
exposed to either a chloride or marine environment and 0.45 when exposed to freezing/thawing
conditions, deicing chemicals, or a sulfate environment.
6) Concrete mix design should consider the potential for alkali silica reaction in the concrete and
whether field tests are required.
7) [R] Design strength of concrete mixes shall be in accordance with ACI 318/318R for service exposure
and not less than those given in Table 1 and the following:
a) In countries where testing is done on cubes, cylinders shall also be made and tested in order to
establish a correlation between the required strengths for the cylinder and the cube specimens.
b) Lacking adequate laboratory facilities for testing such cylinders, the 28-day compressive
strengths of 4 in., 6 in., and 8 in. cubes (100, 150, and 200 mm) must be at least 130 percent, 125
percent, and 120 percent respectively, of specified cylinder strengths.
8) * [R] Cement shall be per ASTM C 150 and selection of cement type shall be governed by the
following:
a) For concrete exposed to soils or other materials having low pH values (less than 5.0 if continuous
replenishment of acidity), special cement type or other measures may be required as directed by
the Owner's Engineer.
b) Selection of cement type for concrete for structures exposed to seawater environment shall be per
ACI 318/318R for "moderate exposure," except that the maximum water-cement ratio shall be
0.40.
9) * [R] Admixtures shall be approved by the Owner's Engineer. Calcium chloride admixtures shall not
be used.
Minimum
Compressive
Group Application
Strength (2)
psi (MPa)
A Concrete for structures located in a marine environment 5000 (34.5)
B Prestressed or precast concrete structures 4000 (27.6)
Precast piling
Liquid retaining structures
Concrete for fireproofing
C Precast pipe 3500 (24.1)
Precast concrete sills, copings, and all ornamental concrete
Reinforced concrete chimneys
Foundations for tanks in sulfuric acid service
D Girders, beams, walls, slabs, piers, and columns 3000 (20.7)
Superstructure for docks and bridges
Pipe supports
Concrete on or below grade, such as footings, cast-in-place
piles, pile caps, tie beams, grade beams, anchor blocks,
pump blocks, catch basins, manholes, sidewalks and
paving(1)
Concrete for structures not listed
E Concrete for underground electrical (protective cover, etc.) 2000 (13.8)
F Low strength concrete for filling purposes where mass, 1500 (10.3)
rather than strength, is the principal requirement
Notes:
(1) For concrete exposed to moderate sulfate attack (per ACI 318/318R) and where
cement with less than 8 percent C3A is not available, cement with up to 12 percent
C3A may be used if approved by Owner's Engineer, and provided that concrete
strength is increased to at least 3500 psi.
(2) The values above represent the 28-day compressive strength of normal Portland
cement concrete (or 7-day compressive strength of high-early strength concrete) as
determined by tests on 6 in. diameter by 12 in. high (150 mm x 300 mm) cylinders per
ASTM C 31/C 31M or ASTM C 192/C 192M.
4. Construction
[I], [R] Concrete construction shall be per ACI 301 and ACI 318/318R and the following:
4.1. Placement
1) * [R] Concrete shall not be placed prior to approval from the Owner's Engineer.
2) [R] Concrete placement shall be in accordance with the recommendations per ACI 306R when the
ambient temperature drops below 40°F (4°C).
3) [R] Concrete placement shall be in accordance with the recommendations per ACI 305R when the
ambient temperature exceeds 90°F (32°C).
4) [R] Field alterations of the concrete mix proportions are prohibited unless approved by Manufacturer
and Owner's Engineer.
5) [R] Concrete poured against earth shall have the soil prewetted or sealed with a vapor barrier to
prevent excessive loss of moisture from the fresh concrete.
4.2. Joints
* [I] Construction, contraction, and expansion joints shall be located as specified. Any additional joints
shall be approved by the Owner's Engineer. Expansion joints shall be constructed with approved
preformed filler material and adequately sealed with an approved sealant.
4.3. Finishing
1) [R], [M] Surface finishes for horizontal surfaces shall be as specified in Table 2 unless otherwise
specified.
Surface Finish
Area Paving Broom or Belt
Compressor House Floors Broom or Belt
Cooling Tower Basin, Flume Floated
Curbs Broom or Belt
Foundations and Pedestals to be Grouted Scratched
Platforms, Stair Pads, Concrete Stairs Broom or Belt
Pumps Slabs Broom or Belt
Seal Slabs None
Surfaces to be Covered with Resilient Flooring (Asphalt Tile, Etc.) Troweled
Stucco or Mortar Base Scratched
Surface Finish
2) [R] Unless otherwise specified, the vertical surfaces of walls, foundations, and other formed
structures shall be finished as follows:
a) Surfaces shall remain as they are when the forms are removed, except holes left by withdrawal of
form ties shall be filled solid with grout and finished to match the surrounding surface.
b) Rubbing of surfaces is not required.
3) [R] All exposed corners and edges of concrete shall have 3/ 4 in. chamfer unless otherwise specified on
the design drawings.
4) [R] Concrete curing shall be per ACI 308R. Minimum time for form removal after concrete
placement shall be per Table 3 provided that the forms are not necessary for the structural support of
the concrete.
Side Forms 24 18
5. Concrete Design
1) [I] Concrete design shall be per ACI 318/318R.
2) * [O], [R] For inground structures the safety factor against flotation shall be not less than 1.2 for both
normal operation and erection. Buoyant forces shall be calculated with the ground water level
assumed to be at the finished grade elevation. Pressure relief systems, deliberate flooding, or other
extraordinary methods to prevent flotation shall only be used if approved by the Owner's Engineer.
3) * [I] The extent of paving and toes walls within process unit areas to control spillage, and for drainage
of storm, process and firewater shall be specified.
4) * [R] Pump slab areas handling corrosive chemicals shall have the paved areas around the pumps and
other equipment and toe walls coated as specified.
5) * [I] Concrete duct designs for air temperatures greater than 200°F (93°C) shall be approved by the
Owner's Engineer.
6) [I] Embedded items, such as inserts, hangers, pipe supports and sleeves, conduits and drains, shall be
adequately secured before concrete is placed.
7) [R] When the least dimension of a concrete element is greater than 4 ft (1.2 m), concrete construction
and temperature control shall be per ACI 207.1R and ACI 207.2R to prevent thermally induced
cracking during hydration.
4) Selection of cement type for concrete for structures exposed to seawater environment shall be
designed and constructed per ACI 357R.
Record of Change
Version 1.0.0 Date: 02/02
Location Action Description
Initial Publish.