Você está na página 1de 4

Project Report

2019 TI+ GT 1.1 PLTGU GRATI


8 Maret 2019 s/d 11 Mei 2019
Author : Fauzan Fauziansyah

DAY : 38

CUACA : CERAH
PROJECT PROGRESS

REALISASI PEKERJAAN HARI INI

PEKERJAAN PROGRESS (%)


BIDANG MEKANIK TURBIN
PM CLEANING & REPAIR EXHAUST CYLINDER 87
PM ASSEMBLY BEARING #1 100
PM ASSEMBLY BEARING #2 100
PM INSTALL BEARING #1 (L/H) 100
PM INSTALL BEARING #2 (L/H) 100
PM INSTALL & SETTING ROTOR 100
BIDANG MEKANIK AUXILIARY
PM TURNING GEAR, INSTALL CYCLO DRIVE INCLUDING AC TURNING 50
PM TURNING GEAR, ALIGNMENT CYCLO DRIVE-DRIVEN SPROCKET SHAFT 50
PM AUXILIARY GEAR, ALIGNMENT AUX GEAR - EXC SHAFT 100
BIDANG LISTRIK
GENERATOR – PULL OUT SCOPE
PM INSTALL EXC. ENCLOUSRE 30
MOTOR
PM MFOP, ASSEMBLY & INSTALL MAIN FUEL OIL PUMP MOTOR 70
RUN OUT MOTOR EMERGENCY LUBE OIL PUMP 100
RELAY PROTEKSI
PM PANEL PROTEKSI DAN SINKRON 100
BIDANG KONTROL INSTRUMEN
GT FIELD AREA
PM FUEL OIL PRIMARY MANIFOLD DRAIN VALVE 100
PM FUEL OIL SECONDARY MANIFOLD DRAIN VALVE 100

RENCANA PEKERJAAN BESOK

BIDANG MEKANIK TURBIN


PM CLEANING & REPAIR EXHAUST CYLINDER (LANJUTAN)
PM INSTALL & CLEARANCE CHECK BEARING #1 (U/H)
PM INSTALL & CLEARANCE CHECK BEARING #2 (U/H)
PM INSTALL SEAL HOUSING BEARING #1 (U/H)
PM INSTALL EXHAUST CYLINDER (U/H)
BIDANG MEKANIK AUXILIARY
PM TURNING GEAR, INSTALL CYCLO DRIVE INCLUDING AC TURNING (LANJUTAN)
PM TURNING GEAR, ALIGNMENT CYCLO DRIVE-DRIVEN SPROCKET SHAFT (LANJUTAN)
BIDANG LISTRIK
GENERATOR – PULL OUT SCOPE
PM INSTALL AIR GUIDE RING & LABYRINTH RING EE
PM INSTALL AIR GUIDE RING & LABYRINTH RING TE
MOTOR
PM MFOP, ASSEMBLY & INSTALL MAIN FUEL OIL PUMP MOTOR (LANJUTAN)
BIDANG KONTROL INSTRUMEN
GT FIELD AREA
PM FUEL OIL NOZZLE SWEEP GAS SUPPLY DAN VENT VALVE
PM FUEL OIL MINIMUM FLOW CONTROL VALVE
DOKUMENTASI PEKERJAAN HARI INI

PM TURNING GEAR, INSTALL CYCLO DRIVE


PM INSTALL & SETTING ROTOR
INCLUDING AC TURNING

PM FUEL OIL PRIMARY MANIFOLD DRAIN


PM PANEL PROTEKSI DAN SINKRON
VALVE