Você está na página 1de 4

Determination of Piles Settlement by

Load Test

Determination of settlement of pile foundations by load test method, equipment


required, procedure and reporting of results in discussed.

Equipment for Pile Settlement


Determination Test
Various types of equipments are required for determination of settlement of pile
foundations.

Following is the list of equipment required:

(a) Kentledge, anchor piles or other anchorages supported or installed at suitable


locations to provide adequate reactions against jacking.

(b) A load-measuring device which shall consist of a load column, pressure cell, or
other appropriate system, calibrated before and after each series of tests, or whenever
adjustments are made to the device, or at time intervals recommended by the
manufacturer of the equipment.

(c) Four deflectometers accurate to 0.025 mm.

(d) Precision levelling equipment accurate to 0.25 mm.

(e) A reference frame for supporting deflectometers and providing a datum for
deflectometer measurements.

(f) Working platforms.

(g) Screens and protection from exposure to conditions which may affect the test.

(h) Hydraulic loading equipment.


Procedure of Pile Settlement
Determination Test
The procedure before testing shall be as
follows:
(a) The kentledge, anchor piles or other anchorages shall be installed. The centre of
each anchor pile shall be at least 2 m or three times the pile diameter, whichever is
greater, from the
centre of the pile to be tested and from the centre of any adjacent pile.
(b) If required, the pile to be tested shall be extended from cut-off level to ground
level. The strength of piles at joints shall not be less than any normal section of the
pile.

(c) A temporary square pile cap designed by the Contractor shall be constructed.

(d) Working platforms, screens and protection shall be installed.

(e) The reference frame shall be set up on supports which are at least 2 m or three
times the pile diameter, whichever is greater, from the test pile and anchor pile. The
four deflectometers shall be mounted on the reference frame to measure the deflection
of the four corners of the temporary pile cap.

Fig: Pile load test for Burj Khalifa (Dubai)


Procedure: Pile Load Test
The procedure for the pile load test shall be
as follows:
(a) Preliminary piles shall be tested to not less than twice the working load of the pile
or other loads stated in the Contract. Working piles shall be tested to not less than 1.8
times working load. Reductions for group or boundary effects shall not be made in
determining the test loads.

(b) Test loads shall be applied and removed in three stages as stated in Table – 1.

(c) Unless otherwise permitted by the Engineer, the test loads shall be applied in
increments, and removed in decrements, of 25% of the working load. Increments of
load shall not be applied until the rate of settlement of the pile is less than 0.1 mm in
20 minutes.

(d) The full test loads for Stage I shall be applied in increments and shall then be
maintained for at least 24 hours after the rate of settlement has reduced to less than 0.1
mm per hour. The test loads shall be removed in decrements and the recovery of the
pile determined before loading is resumed.

(e) The procedure stated above in (d) shall be repeated for Stage II loading.

(f) The procedure stated above in (d) shall be repeated for Stage III loading unless the
Engineer instructs the loading to be maintained for a longer period.

(g) The settlement of the pile shall be measured at hourly intervals or other intervals
agreed by the Engineer. The settlement of the pile under each increment and
decrement of loading shall be measured. The exact times at which increments are
applied and decrements are removed shall be recorded. Settlements shall be measured
and times shall be recorded in the presence of the Engineer.

(h) The level of the reference beam shall be checked at regular intervals agreed by the
Engineer during the test.

Table – 1: Test loading stages


Stage Test Load

I 25% max. test load

II 50% max. test load

III 100% max. test load


Procedure: after testing
After testing, equipment shall be removed, temporary pile caps shall be demolished
and pile extensions shall be removed to cut-off level. Unless otherwise permitted by
the Engineer, anchor piles shall be withdrawn.

Reporting of Test Results


The following shall be reported:

(a) The loads applied to the nearest 0.05 t.

(b) The settlement of the pile to the nearest 0.05 mm at hourly intervals and under
each increment and decrement of loading.

(c) The exact times at which increments were applied and decrements removed.

(d) The levels of the reference beam, to the nearest 0.05 mm.

Read More on Pile Foundations

Você também pode gostar