4"x3''ø PVC wye reducer 7 length 68.00 476.

00
4"ø pvc coupling 4 pcs. 65.00 260.00
4"ø pvc 1/8'' bend 3 pcs. 65.00 195.00
4"ø pvc sweep tee 3 pcs. 65.00 195.00
3"ø 45 deg. Elbow 3 pcs. 65.00 195.00
2"ø 90 deg. elbow 3 pcs. 65.00 195.00
sub-total 28772.00
TILES & ACCESSORIES
B. 20 X30 Glazed Tiles 485 pcs. 36.00 17460.00
20 X 20 Unglazed Tiles 345 pcs. 18.00 6210.00
Tile Trim 12 length 118.00 1416.00
Tile Grout 2 pack 68.00 136.00
Tile Adhesive 18 bags 390.00 7020.00
sub-total 32242.00

X1.
A. PAINTING WORKS
a.1. WALLING 210.2 sq.m
a.2. Latex Flatwall 12 gal. 445.00 5340.00
a.3. Latex Gloss (refer to owners color choice) 8 gal. 568.00 4544.00
B. Latex Green (baseline) 1 gal. 568.00 568.00
b.1. CEILING 47 sq.m
b.2. Enamel Flatwall 4 gal. 445.00 1780.00
b.3. Enamel Gloss 4 gal. 548.00 2192.00
C. Paint Thinner 8 gal. 398.00 3184.00
C.1. PAINTING ACCESSORIES
C.2. 8" Roller Brush 4 pcs. 68.00 272.00
C.3. 2' Paint Brush 2 pcs. 45.00 90.00
C.4. Paint Tray Mixer 1 pcs. 135.00 135.00
C.5. Putty Knife w/o Handle 4 pairs 32.00 128.00
C.5. # 120 cc Sand Paper 20 pcs. 32.00 640.00
# 1000 cc Sand Paper 20 pcs. 32.00 640.00
sub-total 19513.00

Total Material Cost 476156.50


Total Labor Cost 45% 214,555.28
Total Construction Cost 690,711.78