ID Task Task Name Duration Start Finish 3rd Quarter 4th Quarter 1st Quart

Mode W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31
1 MATERIAL ON SITE, INSTALLATION, TESTING & COMMISSIONING 196 days Fri 6/1/18 Thu 12/13/18
2 SITE ARRANGGEMENT 14 days Tue 7/31/18 Tue 8/14/18
3 Subcontractor ME On Site 0 days Tue 7/31/18 Tue 7/31/18 7/31
4 Subcontractor T&C On Site 0 days Tue 8/14/18 Tue 8/14/18 8/14
5 Available Temporary Lighting 0 days Fri 8/10/18 Fri 8/10/18 8/10
6 Avalable Power Supply 380, 3 ph, 3X64 Amp 0 days Fri 8/10/18 Fri 8/10/18 8/10
7
8 OUTDOOR MATERIAL 89 days Fri 8/10/18 Wed 11/7/18
9 HV Apparatus 89 days Fri 8/10/18 Wed 11/7/18
10 DS ‐ Receive at Site 0 days Tue 8/14/18 Tue 8/14/18 8/14
11 CB ‐ Receive at Site 0 days Fri 9/14/18 Fri 9/14/18 9/14
12 SA ‐ Receive at Site 0 days Fri 8/10/18 Fri 8/10/18 8/10
13 LT, CVT, CT ‐ Receive at Site 0 days Wed 11/7/18 Wed 11/7/18 11/7
14 GANTRY & SUPPORT 0 days Mon 10/1/18 Mon 10/1/18 10/1
15 Steel Structure on Site 0 days Mon 10/1/18 Mon 10/1/18 10/1
16 HV Appharatus Support 0 days Mon 10/1/18 Mon 10/1/18 10/1
17 STRINGING MATERIAL 39 days Wed 8/15/18 Sun 9/23/18
18 Insulator ‐ Receive at Site 0 days Wed 8/22/18 Wed 8/22/18 8/22
19 String Hardware ‐ Receive at Site 0 days Sat 9/1/18 Sat 9/1/18 9/1
20 HV Connector ‐ Receive at Site 0 days Sun 9/23/18 Sun 9/23/18 9/23
21 HV Conductor & GSW ‐ Receive at Site 0 days Wed 8/15/18 Wed 8/15/18 8/15
22 Installation Material ‐ Receive at Site 0 days Mon 8/20/18 Mon 8/20/18 8/20
23 INDOR MATERIAL 117 days Fri 6/1/18 Wed 9/26/18
24  PROTECTION PANEL 117 days Fri 6/1/18 Wed 9/26/18
25 SAS and Relay ( RCP ) ‐ Receive at Site 0 days Sat 8/25/18 Sat 8/25/18 8/25
26 Telecommunication ‐ Receive at Site 0 days Wed 9/26/18 Wed 9/26/18 9/26
27 Fault Recorder ‐ Receive at Site 0 days Sat 7/14/18 Sat 7/14/18 7/14
28 Energy Meter ‐ Delivery to SAS Panel Maker 1 day Fri 6/1/18 Fri 6/1/18
29  AUX. PANEL & EQUIPMANT 42 days Fri 8/10/18 Fri 9/21/18
30 Inverter ‐ Receive at Site 0 days Mon 9/17/18 Mon 9/17/18 9/17
31 LV Panel AC DC Panel ( KSO )‐ Receive at Site 0 days Wed 8/15/18 Wed 8/15/18 8/15
32 Battery and Charger ‐ Receive at Site ( By KSO ) 0 days Mon 9/17/18 Mon 9/17/18 9/17
33 MV Switchgear ‐ Receive at Site 0 days Fri 8/10/18 Fri 8/10/18 8/10
34 Earthing Trafo ‐ Receive at Site 0 days Fri 9/21/18 Fri 9/21/18 9/21
35 Auxilliary Transformer ‐ Receive at Site 0 days Fri 9/21/18 Fri 9/21/18 9/21
36 Emergency Diesel Genset ‐ Receive at Site 0 days Fri 8/10/18 Fri 8/10/18 8/10
37 CABLE, Earthing Material Acc ( Clamp ) 40 days Fri 8/10/18 Wed 9/19/18
38 Optic Cable Armoured ‐ Receive at Site 0 days Wed 9/19/18 Wed 9/19/18 9/19
39 LV Cable ‐ Receive at Site 0 days Wed 8/15/18 Wed 8/15/18 8/15
40 Cable Tray and Ladder ‐ Receive at Site 0 days Wed 8/15/18 Wed 8/15/18 8/15
41 MV Cable ‐ Receive at Site 0 days Fri 8/10/18 Fri 8/10/18 8/10
42 Termination Kit ‐ Receive at Site 0 days Mon 9/3/18 Mon 9/3/18 9/3
43 HV Cable & Sealing End ‐ Receive at Site 0 days Sat 9/15/18 Sat 9/15/18 9/15
44 BCC 0 days Wed 8/15/18 Wed 8/15/18 8/15
45 Earthing Material Acc ( Clamp ) 0 days Sat 9/1/18 Sat 9/1/18 9/1
46 INSTALLATION TESTING & COMISSIONING 107 days Wed 8/15/18 Thu 11/29/18
47 OUTDOOR INSTALLATION 107 days Wed 8/15/18 Thu 11/29/18
48 Cable Tray & Eathing  91 days Wed 8/15/18 Tue 11/13/18
49 Install Cable Tray and Ladder 5 days Mon 10/1/18 Fri 10/5/18 Group 1 Cabling ( 15 MP )
50 Laying LV, Control  Cable BY Kios to MK 15 days Sat 10/6/18 Sat 10/20/18 Group 1 Cabling ( 15 MP ),Group 2 Cabling ( 15 MP )
51 Termination LV, Control   15 days Tue 10/30/18 Tue 11/13/18
52 Install ‐ Switchyard Earthing 40 days Wed 8/15/18 Sun 9/23/18
53 Install ‐ Gantry Steel Structure  60 days Mon 10/1/18 Thu 11/29/18
54 Dia 1 Gantry Unit 10, 8 Beam 14 days Mon 10/1/18 Sun 10/14/18
55 Gantry 1 ~ 4 4 days Mon 10/1/18 Thu 10/4/18 Group 1 Primary 12 MP,Crane 25 Tons 1
56 Gantry 5 ~ 8 4 days Fri 10/5/18 Mon 10/8/18 Group 1 Primary 12 MP,Crane 25 Tons 1
57 Gantry 9 ~ 10 2 days Tue 10/9/18 Wed 10/10/18 Group 1 Primary 12 MP,Crane 25 Tons 1
58 Beam Assemble & Install 4 days Thu 10/11/18 Sun 10/14/18 Group 1 Primary 12 MP,Crane 25 Tons 1
59 Diameter 1 Completed 0 days Sun 10/14/18 Sun 10/14/18 10/14
60 Dia 2 Gantry Unit 8, 6 Beam 15 days Mon 10/1/18 Mon 10/15/18
61 Gantry 1 ~ 2 3 days Mon 10/1/18 Wed 10/3/18 Group 2 Primary 12 M,Crane 25 Tons 2
62 Gantry 3 ~ 4 3 days Thu 10/4/18 Sat 10/6/18 Group 2 Primary 12 M,Crane 25 Tons 2
63 Gantry 5 ~ 8 3 days Sun 10/7/18 Tue 10/9/18 Group 2 Primary 12 M,Crane 25 Tons 2
64 Beam Assemble & Install 6 days Wed 10/10/18 Mon 10/15/18 Group 2 Primary 12 M,Crane 25 Tons 2
65 Diameter 2 Completed 0 days Mon 10/15/18 Mon 10/15/18 10/15
66 Dia 3 Gantry Unit 8, 6 Beam 12 days Mon 10/1/18 Fri 10/12/18
67 Gantry 1 ~ 4 4 days Mon 10/1/18 Thu 10/4/18 Group 3 Primary 12 MP,Crane 25 Tons 3
68 Gantry 5 ~ 8 4 days Fri 10/5/18 Mon 10/8/18 Group 3 Primary 12 MP,Crane 25 Tons 3
69 Beam Assemble & Install 4 days Tue 10/9/18 Fri 10/12/18 Group 3 Primary 12 MP,Crane 25 Tons 3
70 Diameter 3 Completed 0 days Fri 10/12/18 Fri 10/12/18 10/12
71 Dia 4 Gantry Unit 10, 8 Beam 16 days Mon 10/1/18 Tue 10/16/18
72 Gantry 1 ~ 4 4 days Mon 10/1/18 Thu 10/4/18 Crane 25 Tons 4,Group 4 Primary 12 MP
73 Gantry 5 ~ 8 4 days Fri 10/5/18 Mon 10/8/18 Crane 25 Tons 4,Group 4 Primary 12 MP
74 Gantry 9 ~ 10 4 days Tue 10/9/18 Fri 10/12/18 Crane 25 Tons 4,Group 4 Primary 12 MP
75 Beam Assemble & Install 4 days Sat 10/13/18 Tue 10/16/18 Crane 25 Tons 4,Group 4 Primary 12 MP
76 Diameter 4 Completed 0 days Tue 10/16/18 Tue 10/16/18 10/16
77 IBT Area & 150 KV 10 days Mon 10/15/18 Wed 10/24/18
82 Langsir 60 days Mon 10/1/18 Thu 11/29/18 Truck Crane 8 Tons,Langsir Material 3 MP
83 SORTIR 60 days Mon 10/1/18 Thu 11/29/18 Sortir Material 4 MP
84 STRINGING WORKS 31 days Sat 10/13/18 Mon 11/12/18
85 Install ‐ Stringing 275 & 150 KV 9 days Sat 10/13/18 Sun 10/21/18
93 install ‐ HV Apparatus 150 KV 10 days Mon 10/29/18 Wed 11/7/18
97 Install ‐ HV Apparatus 275KV 23 days Sun 10/21/18 Mon 11/12/18
103 HV Cable Works 14 days Sat 9/15/18 Fri 9/28/18
104 HVCable Laying 6 days Sat 9/15/18 Thu 9/20/18 Group 1 Cabling ( 15 MP )
105 HV Cable Termination 6 days Fri 9/21/18 Wed 9/26/18 Group 1 Cabling ( 15 MP )
106 HIGH POT CABLE 2 days Thu 9/27/18 Fri 9/28/18 Group 1 Cabling ( 15 MP )
107 INDOOR WORKS 49 days Fri 8/10/18 Thu 9/27/18
108 Install ‐ Inverter 1 day Mon 9/17/18 Mon 9/17/18 Group 2 Cabling ( 15 MP )
109 Install ‐ Auxilliary Transformer 2 days Fri 9/21/18 Sat 9/22/18 Group 3 Cabling ( 15 MP )
110 Install ‐ Battery and Charger 4 days Mon 9/17/18 Thu 9/20/18 Group 5 Cabling ( 15 MP )
111 Install ‐ LV Panel 4 days Sat 8/25/18 Tue 8/28/18 Group 2 Cabling ( 15 MP )
112 Install ‐ Emergency Diesel Genset 3 days Fri 8/10/18 Sun 8/12/18 Group 1 Cabling ( 15 MP )
113 Install ‐ Earthing Trafo 1 day Fri 9/21/18 Fri 9/21/18
114 Install ‐ Telecommunication 2 days Wed 9/26/18 Thu 9/27/18 Group 2 Cabling ( 15 MP )
115 Install ‐ SAS ( HMI & SERVER ) 3 days Sat 8/25/18 Mon 8/27/18 Group 1 Cabling ( 15 MP )
116 Install ‐ Fault Recorder 2 days Fri 9/21/18 Sat 9/22/18 Group 2 Cabling ( 15 MP )
117 Laying LV, Control  Cable Indooor  5 days Wed 8/15/18 Sun 8/19/18 Group 1 Cabling ( 15 MP )
118 Terminition LV, Control Cable 4 days Wed 8/29/18 Sat 9/1/18 Group 1 Cabling ( 15 MP ),Group 2 Cabling ( 15 MP ),Group 3 Cabling ( 15 MP )
119 MV System Installation & Sealing End 35 days Fri 8/10/18 Thu 9/13/18
120 Install ‐ MV Switchgear 4 days Fri 8/10/18 Mon 8/13/18 Group 3 Cabling ( 15 MP ),Group 4 Cabling ( 15 MP )
121 Tertiary Cable  4 days Mon 9/3/18 Thu 9/6/18 Group 4 Cabling ( 15 MP )
122 Incoming MV Cubicle 3 days Fri 9/7/18 Sun 9/9/18 Group 4 Cabling ( 15 MP )
123 Aux. Transformer 2 days Mon 9/10/18 Tue 9/11/18 Group 4 Cabling ( 15 MP )
124 IBT Netral  2 days Wed 9/12/18 Thu 9/13/18 Group 4 Cabling ( 15 MP )
125
126 TESTING & COMMISSIONING 123 days Mon 8/13/18 Thu 12/13/18
127 INDIVIDUAL TEST HV Apparatus 18 days Thu 11/1/18 Sun 11/18/18
128 Testing ‐ HV Apparatus  150KV ( DS, CB ) 3 days Thu 11/1/18 Sat 11/3/18 T&C Control # 1
129 Testing ‐ HV Apparatus 275KV ( DS, CB ) 8 days Sun 11/4/18 Sun 11/11/18 T&C Control # 1
130 Testing ‐ HV Apparatus 275KV ( CT, CVT  ) 6 days Tue 11/13/18 Sun 11/18/18 T&C Control # 2
131 Auxilliary Power Supply 46 days Mon 8/13/18 Thu 9/27/18
132 Individual Test ‐ Inverter 1 day Mon 9/24/18 Mon 9/24/18 Group 2 Cabling ( 15 MP )
133 Individual Test ‐ MV Switchgear 4 days Tue 8/14/18 Fri 8/17/18 T&C Control # 1,T&C Protection # 1
134 Individual Test ‐ Auxilliary Transformer 1 day Sun 9/23/18 Sun 9/23/18 T&C Control # 1
135 Individual Test ‐ Battery and Charger 4 days Mon 9/24/18 Thu 9/27/18 T&C Control # 1
136 Individual Test ‐ Emergency Diesel Genset 2 days Mon 8/13/18 Tue 8/14/18 T&C Control # 2
137 AC DC Power Supply Energized 0 days Thu 9/27/18 Thu 9/27/18 9/27
138 Individual Test ‐ Earthing Trafo 1 day Sat 9/22/18 Sat 9/22/18 T&C Control # 1
139 CONTROL & PROTECTION 73 days Fri 9/28/18 Sun 12/9/18
140 Individual Test ‐ SAS and Relay 7 days Fri 9/28/18 Thu 10/4/18 T&C Control # 1
141 Individual Test ‐ LV Panel 6 days Fri 9/28/18 Wed 10/3/18 T&C Protection # 1
142 Individual Test ‐ Fault Recorder 2 days Thu 10/4/18 Fri 10/5/18 T&C Protection # 1
143 Interlocking & Control 275 KV System Test ‐ Start Up 6 days Wed 11/14/18 Mon 11/19/18 T&C Control # 1,T&C Control # 2,T&C Control # 3
144 Interlocking & Control 150 KV System Test ‐ Start Up 3 days Tue 11/20/18 Thu 11/22/18 T&C Control # 3
145 Alarm Test ‐ Start Up 6 days Fri 11/23/18 Wed 11/28/18 T&C Control # 1,T&C Control # 2,T&C Control
146 Protection Relay Functional Test ‐ Start Up 5 days Thu 11/29/18 Mon 12/3/18 T&C Protection # 1,T&C Protection # 2
147 Primary Current Injection 6 days Mon 11/19/18 Sat 11/24/18 T&C Protection # 1,T&C Protection # 2
148 Stability System Test  ( CCP &  BUSPRO )‐ Start Up 4 days Tue 12/4/18 Fri 12/7/18 T&C Protection # 1,T&C Protection
149 Stability System Test  TR DIFF.‐ Start Up 2 days Sat 12/8/18 Sun 12/9/18 T&C Protection # 1
150 TELEPROTECTION SYSTEM 77 days Fri 9/28/18 Thu 12/13/18
151 Individual Test ‐ Telecommunication 3 days Fri 9/28/18 Sun 9/30/18 T&C Control # 2
152 Digital Teleprotection System Test ‐ Start Up 1 day Mon 10/1/18 Mon 10/1/18 T&C Control # 3
153 SCADA Point to Point System Test ‐ Start Up 4 days Mon 12/10/18 Thu 12/13/18 T&C Protection # 1
154 Intertrip Test ‐ Start Up 1 day Fri 12/14/18 Fri 12/14/18 T&C Control # 1,T&C Contr
155 Ready for Energization ‐ Start Up 0 days Fri 12/14/18 Fri 12/14/18 12/14

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: 275 KV SIGLI Installatio Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Critical

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1