PROGRAMME MANAGEMENT UNIT,

(PIPIP), AGRICULTURE DEPARTMENT

Annual Report
Punjab Irrigated Agriculture Productivity
Improvement Project (PIPIP),

2016-17
41-A Lawrence Road, Lahore
Phone# 042-99200835
http://pipip.punjab.gov.pk
Annual Report
2016 – 17
ACKNOWLEDGMENT
With the objective to provide a summary of overall

performance of the province under PIPIP, the Program

Management Unit, PIPIP has been preparing the Annual

Report at the end of each financial year as one of its

monitoring functions. This report contains district wise

detail of the executed civil works under Punjab Irrigated

Agriculture Productivity Improvement Project (PIPIP),

during the year 2016-17 in Punjab. It is expected that this report will be a source of

authentic information for all those who are directly or indirectly related to this

project.

Collection of information and analysis of data for a program spread over the
entire province, does involve dedicated efforts on the part of PMU team. In the
preparation of this edition I have been fortunate in being able to count on the
support of all the colleagues of the PMU. Their team spirit, enriched with
commitment and devotion has made this report a presentable document. I am
especially appreciative of Mr. Riaz Ahamed, Deputy Project Director and Mr. Tariq
Mahmood, Deputy Director Technical for their professional contributions. I hope
that the whole PMU team will keep up the same professional approach with the
same zeal & zest in future.

(DR. AYESHA SAEED)


Project Director

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) i


Annual Report
2016 - 17

CONTENTS
Page
SECTION
No.
1 Acknowledgements i

2 Contents Ii

3 Project Location Map Iii

4 Executive Summary iv-vii

4 Physical Performance for the year 2016-17 1-3

5 Punjab Summary 4-5

6 Bahawalpur Region 6-11

7 Dera Ghazi Khan Region 12-19

8 Faisalabad Region 20-27

9 Sargodha Region 28-35

10 Multan Region 36-47

11 Lahore Region 48-57

12 Gujranwala Region 58-69

13 Rawalpindi Region 70-73

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) ii


Annual Report
2016 – 17

PROJECT LOCATION MAP

PMU, HEAD OFFICE

PUNJAB PROVINCE

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) iii


Annual Report
2016 - 17

EXECUTIVE SUMMARY
Each project is unique in its nature. It involves the individuals who are new to it
and the circumstances which are most of the time different than the overall working
environment. In development projects things often turn out differently than expected.
Projects even with a good planning, adequate organizational machinery and sufficient
flow of resources cannot automatically achieve the desired results. There must be some
warning mechanism, which can alert the organization about its possible successes and
failures, off and on. Constant watching not only saves wastage of scarce resources but
also ensure speedy execution of the project. Hence, an affective and dynamic monitoring
system has proved to be the linchpin for success of a project. Monitoring is systematic
collection and analysis of information to identify and measure progress over a period of
time. It enables a continuing critique of the project implementation. The PMU, PIPIP is
one of the few successful examples of such interventions in Punjab. It has been
affectively performing the function of continuous monitoring and has been
providing the required warning mechanism for the NPIW & PIPIP during the last
thirteen years of the PMU life.

After the successful completion of National Program for Improvement of


Watercourses in Pakistan, Punjab Component (NPIW), Punjab Irrigated Agriculture
Productivity Improvement Project (PIPIP) was launched in the year 2011-12
encompassing five components. A new intervention of High Efficiency Irrigation System
(HEIS) was included as core component to persuade farmers for adopting newly evolved
techniques to irrigate their crops rather than sticking to traditional methods. The object
was to increase the production of more profitable crops through HEIS in order to meet
increasing domestic needs and enhancing exports. Other four components of the
project were Improvement of Unimproved (Regular) Watercourses, Additional
Lining of Partially Improved Watercourses, Rehabilitation of Irrigation System in Non-
Canal Commanded Area and Provision of LASER Units to Farmers/ Service Providers.

Year 2011-2012 was the pilot phase of the project and the regular project is for a
period of five years from July, 2012 to June, 2017. This mega initiative envisages
installation of Drip and Sprinkler Irrigation Systems on 1,20,000 acres, improvement

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) iv


Annual Report
2016 – 17
of 5500 unimproved watercourses, completion of lining on 1500 partially improved
watercourses, installation of 2000 irrigation schemes in non-canal commanded area
and provision of 3000 LASER units to farmers/ service providers in the province at a
total cost of 36,000.705 million bifurcated into Rs. 21,249.997 million and Rs. 14,750.708
million as Govt. Share and farmers’ contribution respectively.

This Annual Report, which is 13th in a row, pertains to the financial year 2016-17.
Like previous few, this year also proved to be a bit difficult. During the year under
review, component wise achievement of targets is as under: -

A. Improvement of Regular (Unimproved) Watercourses: A target of 1760


watercourses was assigned for the year 2016-17, against which, upto 30-06-2017, 2066
(117%) ICR-I, 1949 (111%) ICR-II and only 1700 (97%) FCR were verified by the
consultants (PSC). Muzaffar Garh (93%), Multan (57%), Khanewal (89%), Vehari
(83%), Jhang (90%), Sahiwal (90%), Pakpattan (93%), Okara (76%), Nankana Sahib
(82%), Hafizabad (93%), Sargodha (86%), Bhakkar (97%) and Mianwali (96%) are the
districts who failed to achieve 100% targets. Other districts achieved 100% or more.

B. High Efficiency Irrigation System: Against the target of installation HEIS at


15,000 acres, commissioning was certified at 10095 acres (67%). Issuance of Work
Order and Verification of Material remained 11120 (74%) and 10256 acres (68%)
respectively. Layyah (114%), Narowal (111%), Sialkot (100%), Gujrat (108%), Attock
(110%) and Chakwal (111%) are the districts who achieved 100% or more. Other all
districts failed to achieve 100% targets. Verification of Commissioning in these
districts remained 12% to 97%. Lowest Commissioning (12%) was verified in
Khanewal district.

C. Provision of LASER Land Levelling Units: Target of 2970 unit was assigned
to the province, against which, 3833 (129%), units were booked, 2990 (101%) Work
Order were issued and 2500 (84%) units were delivered to farmers/ service
providers. Pakpattan (119%), Okara (130%), Lahore (103%) and Sheikhupura (104%)
are the districts, where delivery of units was 100% or more. Other districts achieved
67% to 94% delivery of LASER units.

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) v


Annual Report
2016 - 17
New Interventions
Punjab Growth Strategy (PGS) 2018 envisages “better use of energy in
Agriculture” and provides exploring means of harnessing renewable and alternate
energy sources to supplement conventional energy sources that are limited and
expensive. National Climate Change Policy (2012) provides use of solar energy and
modern climate resilient irrigation technologies like drip irrigation and tunnels for
enhancing agricultural productivity.
To achieve the objectives of PGS, Chief Minister (CM) Punjab approved Rs. 100
billion “Khadim-e-Punjab Kissan Package” to stimulate growth in the agriculture
sector by providing Climate Smart Technology Package for High Value Agriculture.
Pursuant to above as a Pilot Phase of the Project Promotion of High Value
Agriculture Through Provision of Climate Smart Technology Package, during 2016-17
in addition to activities under PIPIP, some more activities were performed by On
Farm Water Management. PMU, PIPIP also monitored these activities. The detail of
these activities is as under: -
a. Provision of Solar System on HEIS Sites: Under this component a target of
provision of solar systems at 1500 acres was assigned, against which, achievements
were Issuance of Work Order at 3030 acres (202%), Material Supplied at 2526 acres
(168%) and Final Commissioning at 2225 acres (148%).
b. Installation of Tunnels at HEIS Sites: Under this component a target of
installation of tunnels at 300 acres was assigned, against which, achievements were
Allotment/ Booking of Tunnels at 671 acres (224%), Installation of Tunnels by
Farmers at 316 acres (105%) and Inspection by Designated Committee/ Consultant at
316 acres (105%).
c. Rainwater Management in Cotton Fields: This Project has been started in
seven districts of southern Punjab. As a pilot phase during 2016-17 under different
components detail of targets and achievement is as below: -

Target %
Name of Component Achieved
(Nos.) age
Construction of Rainwater Harvesting Ponds 35 68 194

Development of Sunken Fields 15 26 173

Provision of Portable Water Pumping Unit 70 119 170

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) vi


Annual Report
2016 – 17
The Program Management Unit continued to play its positive and effective
role in keeping the programme activities smooth through its coordination,
facilitation and monitoring functions. As per mandate of the PMU, where ever
required, necessary help was extended to OFWM staff in all programme matters for
achieving the desired goals. Role of PMU Regional Offices was substantial in all the
PIPIP targets achieved during the year.

During 2016-17, PMU, Head Office generated weekly, quarterly, annualy


reports and letters addressed to various stakeholders most of them were related to
rectification of shortfalls in civil works, pointed out by the officers of PMU Regional
Offices and Head Office during their site visits. The PIPIP website, established and
being maintained by PMU kept providing live data about all components, completed
during the year under report as well as work done during the previous years.

In addition to above mentioned tasks under PIPIP, PMU was assigned an


additional duty of consultancy for ADP funded project “Optimizing Watercourse
Conveyance EfficiencyThrough Enhancing lining Length” as interim arrangement
uptill the regular consultants are not hired. Under this project during 2016-17,
against the target of 600 watercourses, 971 (162%), ICR-I, 717 (120%) ICR-II and 620
(103%) FCRs were certified by Regional Managers of PMU. Regional Managers
checked 100% FCRs offerred to them, out of which 620 were certified and remaining
were referred back with certain observations inorder to maintain prescribed
standard and quality.

In view of the achievements for the year 2016-17, which was comparatively a
difficult year, it is expected that during the coming years when the Punjab Irrigated
Agriculture Productivity Improvement Project, envisaging multiple modern
challenging initiatives will be under implementation, the same good performance will
be repeated by the PIPIP staff as well as the PMU.

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) vii


Annual Report
2016-17
PHYSICAL PERFORMANCE
IMPROVEMENT OF REGULAR WATERCOURSES IN
CANAL IRRIGATED AREAS (Unimproved Watercourses)
for the year 2016-17

FCR
Name of District Target ICR-I ICR-II
Verified % age
Bahawalpur 61 80 77 75 123
R.Y Khan 125 140 139 139 111
Bahawalnagar 34 46 40 40 118
D.G Khan 63 86 81 65 103
MuzaffarGarh 113 154 146 105 93
Layyah 11 12 12 12 109
Rajanpur 68 85 82 82 121
Faisalabad 23 23 23 23 100
Jhang 42 43 40 38 90
Chiniot 15 19 18 15 100
T.T Singh 1 1 1 1 100
Sargodha 97 95 91 83 86
Khushab 27 28 27 27 100
Bhakkar 70 77 68 68 97
Mianwali 26 30 29 25 96
Multan 134 150 144 76 57
Khanewal 98 113 110 87 89
Vehari 99 107 106 82 83
Lodhran 88 101 99 97 110
Sahiwal 29 41 37 26 90
Pakpattan 42 48 40 39 93
Okara 119 140 121 90 76
Lahore 9 12 12 10 111
Sheikhupura 77 83 82 78 101
Nankana Sahib 11 12 12 9 82
Kasur 106 128 117 117 110
Gujranwala 86 108 98 98 114
Hafizbad 43 49 43 40 93
Narowal 2 2 2 2 100
Sialkot 17 22 21 21 124
M.B Din 23 28 28 27 117
Gujrat 1 3 3 3 300
Total: - 1760 2066 1949 1700 97

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 1


Annual Report
2016-17
PHYSICAL PERFORMANCE
INSTALLATION OF HIGH EFFICIENCY
IRRIGATION SYSTEM (HEIS)
For the year 2016-17

Work Order Material Commissioning


Name of District Target %age
Issued Shifted Verified

Bahawalpur 400 350 377 317 79


R.Y Khan 525 347 428 313 60
Bahawalnagar 525 290 289 296 56
D.G Khan 400 310 384 389 97
MuzaffarGarh 475 274 335 363 76
Layyah 325 320 375 371 114
Rajanpur 250 142 147 142 57
Faisalabad 400 319 357 377 94
Jhang 400 309 172 175 44
Chiniot 250 306 99 116 46
T.T Singh 400 369 360 350 88
Sargodha 600 223 231 211 35
Khushab 400 287 264 278 70
Bhakkar 550 279 210 284 52
Mianwali 250 215 158 125 50
Multan 275 125 90 100 36
Khanewal 275 56 39 53 19
Vehari 275 33 24 45 16
Lodhran 275 69 38 33 12
Sahiwal 350 269 182 154 44
Pakpattan 300 252 241 277 92
Okara 450 333 429 417 93
Lahore 200 100 60 92 46
Sheikhupura 400 349 296 335 84
Nankana Sahib 250 71 54 35 14
Kasur 500 337 314 270 54
Gujranwala 385 401 189 131 34
Hafizbad 265 161 96 106 40
Narowal 150 169 179 167 111
Sialkot 300 206 291 300 100
M.B Din 325 285 181 194 60
Gujrat 325 350 349 351 108
Rawalpindi 900 623 570 461 51
Attock 900 1039 824 988 110
Chakwal 875 938 1107 969 111
Jhelum 875 614 516 511 58
Total: - 15000 11120 10255 10096 67

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 2


Annual Report
2016-17
PHYSICAL PERFORMANCE
PROVISION OF LASER LAND LEVELLING UNITS 2016-17

Work Order No. of Units %


Name of District Target Booking
Issued Delivered age
Bahawalpur 156 204 155 123 79
R.Y Khan 85 111 83 79 93
Bahawalnagar 162 213 161 143 88
D.G Khan 74 108 84 63 85
MuzaffarGarh 169 201 165 125 74
Layyah 89 105 84 61 69
Rajanpur 83 92 84 73 88
Faisalabad 148 194 149 115 78
Jhang 150 190 149 115 77
Chiniot 63 84 63 45 71
T.T Singh 72 94 71 54 75
Sargodha 122 156 121 87 71
Khushab 29 28 19 20 69
Bhakkar 96 123 96 64 67
Mianwali 71 76 64 57 80
Multan 83 111 84 65 78
Khanewal 121 161 123 114 94
Vehari 141 187 141 117 83
Lodhran 85 112 86 67 79
Sahiwal 85 111 86 77 91
Pakpattan 48 69 57 57 119
Okara 53 69 69 69 130
Lahore 30 39 31 31 103
Sheikhupura 124 156 129 129 104
Nankana Sahib 69 93 70 51 74
Kasur 106 140 106 87 82
Gujranwala 124 162 123 109 88
Hafizbad 87 114 87 82 94
Narowal 62 74 61 56 90
Sialkot 85 124 85 80 94
M.B Din 63 90 70 55 87
Gujrat 35 42 34 30 86
Total: - 2970 3833 2990 2500 84

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 3


Annual Report
2016-17
PUNJAB SUMMARY
A. Regular Watercourses:
During 2016-17, in Punjab, against the target of 150
1760watercoures, 1700 (97%) watercourses were ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3
100
compare the actual work pace (ICR-I, ICR-II & FCR)
viz-a-viz TBAP on quarterly basis. The figures show
TBAP
that in case of ICR-I &ICR-II, actual achievement 50
remained below TBAP in the begining while, in case Actual
of FCRs, actual achievement commensurated with 0
TBAP throughout the year. Resultantly 97%targets Sep-16 Dec-16 Mar-17 June-17
could be achieved within stipulated period.
Fig-A1
120
120 ICR-II 100 FCR
100
TBAP 80
80 TBAP
Actual 60 Actual
60
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)

In Punjab, during 2016-17, against the target of 120


15000 acres, commissioning was verified at only Work Order Issued
100
10096 (60%) acres upto 30-06-2017. Figures B1, B2 &
80
B3 compare the actual work pace (Work Order
Issued, Material Verified and Commissioning 60
Verified) viz-a-viz TBAP on quarterly basis. The 40
TBAP
figures show that actual achievement did not 20
commensurate with TBAP throughout the year.
Actual
0
Resultantly 67% commissioning could be got
Sep-16 Dec-16 Mar-17 June-17
verified within stipulated period.
Fig-B1
120
120
Material Verified Commissioning Verified
100 100

80 80
TBAP TBAP
60 60
Actual Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 4


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:
During 2016-17, against the target of 2970 LASER 150
Units, 2500 (84%) units were delivered in Punjab
Booking
upto 30-06-2017. Figures C1, C2 & C3 compare the
100
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis.
The figures show that achievement regarding all 50 TBAP
Key Performance Indicators continued fluctuating
Actual
around TBAP. In the end, though, Booking and
0
Issuance of Work Order were 100% but Delivery of
Sep-16 Dec-16 Mar-17 June-17
Units could not be achieved within stipulated
period. Fig-C1

120 Work Order 120


Issued 100 Unit Delivered
100
80 80
60 60
TBAP 40 TBAP
40
Actual 20 Actual
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
1500 3030 202 2526 168 2225 148

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
300 671 224 316 105 316 105

F. Rainwater Management in Cotton Field

Name of Component Target (Nos.) Achieved %age


Construction of Rainwater
35 68 194
Harvesting Ponds
Development of Sunken
15 26 173
Fields
Provision of Portable Water
70 119 170
Pumping Unit

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 5


Annual Report
2016-17
BAHAWALPUR
A. Regular Watercourses:
During 2016-17, in district Bahawalpur, against the 150
target of 61watercoures, 75 (123%) watercourses ICR-I
were completed upto 30-06-2017. Figures A1, A2 &
100
A3 compare the actual work pace (ICR-I, ICR-II &
FCR) viz-a-viz TBAP on quarterly basis. The figures
show that in case of ICR-I, ICR-II & FCR actual 50 TBAP
achievement commensurated with Actual
TBAP.Hencetargets were achieved within stipulated 0
period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
150 150
ICR-II -
FCR
100 100 TBAP
Actual
50 TBAP 50
Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)

During 2016-17, in district Bahawalpur, against the 120


Work Order Issued
target of 400 acres, commissioning was verified at 100
only 317 acres (79%) upto 30-06-2017. Figures B1, B2
80
& B3 compare the actual work pace (Work Order
Issued, Material Verified and Commissioning 60
Verified) viz-a-viz TBAP on quarterly basis. The 40
TBAP
figures show that actual achievement did not 20 Actual
commensurate with TBAP. Resultantly 100%
0
commissioning could not be got verified within
Sep-16 Dec-16 Mar-17 June-17
stipulated period.
Fig-B1
120 120
Material Verified Commissioning Verified
100 100
80 TBAP 80 TBAP
60 Actual 60 Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 6


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Bahawalpur, against the 150


Booking
target of 156 LASER Units, 123 (79%)were delivered
upto 30-06-2017. Figures C1, C2 & C3 compare the
100
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis.
The figures show that actual achievement remained 50 TBAP
fluctuating around TBAP. Resultantly 100% delivery Actual
of units could not be achieved within stipulated
0
period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1
120 Work Order Issued 120
Unit Delivered
100 100
80 80
60 60
TBAP
40 40 TBAP
Actual
20 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
40 205 513 175 438 97 243

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 10 100 0 0 0 0

F. Rainwater Management in Cotton Field

Name of Component Target (Nos.) Achieved %age


Construction of Rainwater
5 7 140
Harvesting Ponds
Development of Sunken
3 5 167
Fields
Provision of Portable Water
10 13 130
Pumping Unit

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 7


Annual Report
2016-17
RAHIM YAR KHAN
A. Regular Watercourses:
During 2016-17, in districtRahimYar Khan, against 120
the target of 125watercoures, 139 (111%) ICR-I
100
watercourses were completed upto 30-06-2017.
80
Figures A1, A2 & A3 compare the actual work pace
(ICR-I, ICR-II & FCR) viz-a-viz TBAP on quarterly 60
basis. The figures show that in case of ICR-II, actual 40 TBAP
achievement remained below TBAP during 2nd& 20 Actual
3rdquarters while, in case of ICRs-I and FCRs, actual 0
achievementscommensurated with TBAP Sep-16 Dec-16 Mar-17 June-17
throughout the year. Resultantly the district could
get them verified within stipulated period. Fig-A1
120 120
100
ICR-II 100 FCR
80 80 TBAP
60 60 Actual
40 TBAP 40
20 Actual 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)

During 2016-17, in districtRahimYar Khan, against 120


the target of 525 acres, commissioning was verified
Work Order Issued
100
at only 313 (60%) upto 30-06-2017. Figures B1, B2 &
80 TBAP
B3 compare the actual work pace (Work Order
60 Actual
Issued, Material Verified and Commissioning
Verified) viz-a-viz TBAP on quarterly basis. The 40
figures show that actual achievement did not 20
commensurate with TBAPthroughout the year.
0
Resultantly 100% commissioning could not be got
Sep-16 Dec-16 Mar-17 June-17
verified within stipulated period.
Fig-B1
120 120 Commissioning Verified
100 Material Verified 100
80 TBAP 80 TBAP
60 Actual 60 Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 8


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:
During 2016-17, in districtRahimYar Khan, against 150
the target of 85LASER Units, Booking
79(93%)weredeliveredupto 30-06-2017. Figures C1,
100
C2 &C3 compare the actual work pace (Booking,
Work Order Issued, and Units Delivered) viz-a-viz
TBAP on quarterly basis. The figures show that 50 TBAP
actual achievement in case of Work Order Issuance Actual
and Delivery of Units did not commensurate with
0
TBAP during 2nd& 3rdquarters. Resultantly 100%
Sep-16 Dec-16 Mar-17 June-17
delivery of units could not be achieved within
stipulated period. Fig-C1
120 Work Order 120
Unit Delivered
100 Issued 100
80 80
60 60
40 TBAP 40 TBAP
20 Actual 20
Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
53 130 245 130 245 113 213

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 10 100 9 90 9 90

F. Rainwater Management in Cotton Field

Name of Component Target (Nos.) Achieved %age


Construction of Rainwater
5 11 220
Harvesting Ponds
Development of Sunken
2 3 150
Fields
Provision of Portable Water
10 18 180
Pumping Unit

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 9


Annual Report
2016-17
BAHAWALNAGAR
A. Regular Watercourses:
During 2016-17, in district Bahawalnagar, against 150
the target of 34watercoures, 40 (118%) watercourses ICR-I
were completed upto 30-06-2017. Figures A1, A2 & 100
A3 compare the actual work pace (ICR-I, ICR-II &
FCR) viz-a-viz TBAP on quarterly basis. The figures TBAP
50
show that actual achievements commensurated with Actual
TBAP throughout the year. Resultantly 100% targets 0
could be achieved within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
150 150
ICR-II FCR
100 100 TBAP
Actual
50 TBAP 50
Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Bahawalnagar, against 120
the target of 525 acres, commissioning was verified 100 Work Order Issued
at only 296 (56%) upto 30-06-2017. Figures B1, B2 &
80 TBAP
B3 compare the actual work pace (Work Order
Issued, Material Verified and Commissioning 60 Actual
Verified) viz-a-viz TBAP on quarterly basis. The 40
figures show that actual achievement did not 20
commensurate with TBAP throughout the year.
0
Resultantly 100% commissioning could not be got
Sep-16 Dec-16 Mar-17 June-17
verified within stipulated period.
Fig-B1
120
Material Verified
120 Commissioning Verified
100 100
80 TBAP 80 TBAP
60 Actual 60
Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 10


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Bahawalnagar, against 150


the target of 162 LASER Units, 143(88%)were Booking
delivered upto 30-06-2017. Figures C1, C2 & C3
100
compare the actual work pace (Booking, Work
Order Issued, and Units Delivered) viz-a-viz TBAP
TBAP
on quarterly basis. The figures show that though 50
actual achievementscommensurated with TBAP but Actual
100% delivery of units could not be achieved within
0
stipulated period as the pace of work during last
Sep-16 Dec-16 Mar-17 June-17
quarter remained slow
Fig-C1
120 Work Order 120
Unit Delivered
100 Issued 100
80 80
60 60
TBAP
40 40 TBAP
Actual
20 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
40 39 98 39 98 39 98

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 0 0 0 0 0 0

F. Rainwater Management in Cotton Field

Name of Component Target (Nos.) Achieved %age


Construction of Rainwater
5 13 260
Harvesting Ponds
Development of Sunken
2 5 250
Fields
Provision of Portable Water
10 22 220
Pumping Unit

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 11


Annual Report
2016-17
MULTAN
A. Regular Watercourses:
During 2016-17, in district Multan, against the target 120
of 134 watercoures, 76 (57%) watercourses were 100
ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 80
compare the actual work pace (ICR-I, ICR-II & FCR) 60
viz-a-viz TBAP on quarterly basis. The figures show 40 TBAP
that though actual achievements in case of ICR-I & 20 Actual
ICR-II was 100% but in case of FCR 100% targets 0
couldnot be achieved within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100
TBAP 80 TBAP
80
Actual Actual
60 60
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Multan, against the target 120
of 275 acres, commissioning was verified at only 100 100
Work Order Issued
(36%) upto 30-06-2017. Figures B1, B2 & B3 compare
80 TBAP
the actual work pace (Work Order Issued, Material
Verified and Commissioning Verified) viz-a-viz 60 Actual
TBAP on quarterly basis. The figures show that 40
actual achievement did not commensurate with 20
TBAP throughout the year. Resultantly 100%
0
commissioning could not be got verified within
Sep-16 Dec-16 Mar-17 June-17
stipulated period.
Fig-B1

120 120 Commissioning Verified


Material Verified 100
100
80 80
TBAP 60 TBAP
60
Actual Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 12


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Multan, against the target 150


of 83 LASER Units, 65 (78%) were delivered upto30- Booking
06-2017. Figures C1, C2 & C3 compare the actual
100
work pace (Booking, Work Order Issued, and Units
Delivered) viz-a-viz TBAP on quarterly basis. The
TBAP
figures show that actual achievements did not 50
commensurat with TBAP but 100% delivery of units Actual
could not be achieved within stipulated period as
0
the pace of work during last quarter remained slow
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued 120


100
Unit Delivered
100
80 80
60 60
40 TBAP 40 TBAP
Actual 20 Actual
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
45 30 67 24 53 24 53

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 10 100 0 0 0 0

F. Rainwater Management in Cotton Field

Name of Component Target (Nos.) Achieved %age


Construction of Rainwater
5 9 180
Harvesting Ponds
Development of Sunken
2 2 100
Fields
Provision of Portable Water
10 13 130
Pumping Unit

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 13


Annual Report
2016-17
KHANEWAL
A. Regular Watercourses:
During 2016-17, in district Khanewal, against the 150
target of 98watercoures, 87 (89%) watercourses were ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 100
compare the actual work pace (ICR-I, ICR-II & FCR)
viz-a-viz TBAP on quarterly basis. The figures show 50 TBAP
that actual achievements in case of ICR-I & ICR-II Actual
was 100% but in case of FCR 100% targets could not 0
be achieved within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100
80 TBAP
80
60
Actual
60
TBAP 40
40
Actual 20
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3
B. Installation of High Efficiency Irrigation System (HEIS)
During 2016-17, in district Khanewal, against the 120
target of 275 acres, commissioning was verified at Work Order Issued
100
only 53 (19%) upto 30-06-2017. Figures B1, B2 & B3
80
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60 TBAP
a-viz TBAP on quarterly basis. The figures show 40 Actual
that actual achievement did not commensurate with 20
TBAP throughout the year. Resultantly 100%
0
commissioning could not be got verified within
Sep-16 Dec-16 Mar-17 June-17
stipulated period.
Fig-B1
120
120
Material Verified Commissioning Verified
100 100

80 80 TBAP
TBAP
60 60 Actual
Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 14


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Khanewal, against the 150


target of 121 LASER Units, 114 (94%) were delivered Booking
upto 30-06-2017. Figures C1, C2 & C3 compare the
100
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis.
The figures show that actual achievements did not 50 TBAP
commensurate with TBAP. Resultantly 100% Actual
delivery of units could not be achieved within
0
stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued 120


100
Unit Delivered
100
80 80
60 60
TBAP 40 TBAP
40
Actual 20 Actual
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
38 26 68 16 42 16 42

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 5 50 0 0 0 0

F. Rainwater Management in Cotton Field

Name of Component Target (Nos.) Achieved %age


Construction of Rainwater
5 10 200
Harvesting Ponds
Development of Sunken
2 5 250
Fields
Provision of Portable Water
10 13 130
Pumping Unit

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 15


Annual Report
2016-17
VEHARI
A. Regular Watercourses:
During 2016-17, in district Vehari, against the target 120
of 99watercoures, 82 (83%) watercourses were 100
ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 80
compare the actual work pace (ICR-I, ICR-II & FCR) 60
viz-a-viz TBAP on quarterly basis. The figures show 40 TBAP
that actual achievements in case of ICR-I & ICR-II Actual
20
was 100% but in case of FCR 100% targets could not 0
be achieved within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120 120
100 ICR-II 100 FCR
80 80
60 60 TBAP
Actual
40 TBAP 40
20 Actual 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3
B. Installation of High Efficiency Irrigation System (HEIS)
During 2016-17, in district Vehari, against the target 120
of 275 acres, commissioning was verified at only 45
Work Order Issued
100
(16%) upto 30-06-2017. Figures B1, B2 & B3 compare
80
the actual work pace (Work Order Issued, Material
Verified and Commissioning Verified) viz-a-viz 60 TBAP
TBAP on quarterly basis. The figures show that 40 Actual
actual achievement did not commensurate with 20
TBAP throughout the year. Resultantly 100%
0
commissioning could not be got verified within
Sep-16 Dec-16 Mar-17 June-17
stipulated period.
Fig-B1

120 120 Commissioning Verified


Material Verified 100
100
80 TBAP 80 TBAP
60 Actual 60 Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 16


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Vehari, against the target 150


of 141 LASER Units, 117 (83%) were delivered upto Booking
30-06-2017. Figures C1, C2 & C3 compare the actual
100
work pace (Booking, Work Order Issued, and Units
Delivered) viz-a-viz TBAP on quarterly basis. The
figures show that actual achievements did not 50 TBAP
commensurate with TBAP. Resultantly 100%
Actual
delivery of units could not be achieved within
0
stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1
120
120 Work Order Unit Delivered
100 100
Issued
80 80
60 60
40
TBAP 40 TBAP
Actual 20 Actual
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
38 0 0 0 0 0 0

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 0 0 0 0 0 0

F. Rainwater Management in Cotton Field

Name of Component Target (Nos.) Achieved %age


Construction of Rainwater
5 6 120
Harvesting Ponds
Development of Sunken
2 4 200
Fields
Provision of Portable Water
10 25 250
Pumping Unit

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 17


Annual Report
2016-17
LODHRAN
A. Regular Watercourses:
During 2016-17, in district Lodhran, against the 150
target of 88watercoures, 97 (110%) watercourses ICR-I
were completed upto 30-06-2017. Figures A1, A2 & 100
A3 compare the actual work pace (ICR-I, ICR-II &
FCR) viz-a-viz TBAP on quarterly basis. The figures 50 TBAP
show that actual achievements commensurated with Actual
TBAP and resultantly 100% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100 TBAP Actual
80 TBAP
80
60 60
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3
B. Installation of High Efficiency Irrigation System (HEIS)
During 2016-17, in district Lodhran, against the 120
target of 275 acres, commissioning was verified at
Work Order Issued
100
only 33 (12%) upto 30-06-2017. Figures B1, B2 & B3
80
compare the actual work pace (Work Order Issued,
60 TBAP
Material Verified and Commissioning Verified) viz- Actual
a-viz TBAP on quarterly basis. The figures show 40
that actual achievement did not commensurate with 20
TBAP throughout the year. Resultantly 100%
0
commissioning could not be got verified within
Sep-16 Dec-16 Mar-17 June-17
stipulated period.
Fig-B1

120 Material Verified


120 Commissioning Verified
100 100

80 TBAP 80
TBAP
60 Actual 60 Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 18


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Lodhran, against the 150


target of 85 LASER Units, 67 (79%) were delivered Booking
upto 30-06-2017. Figures C1, C2 & C3 compare the
100
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis.
The figures show that actual achievements did not 50
TBAP
commensurate with TBAP. Resultantly 100%
Actual
delivery of units could not be achieved within
0
stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued 120


Unit Delivered
100 100

80 80
60 60
TBAP 40 TBAP
40
Actual Actual
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
38 41 108 30 79 30 79

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 0 0 0 0 0 0

F. Rainwater Management in Cotton Field

Name of Component Target (Nos.) Achieved %age


Construction of Rainwater
5 12 240
Harvesting Ponds
Development of Sunken
2 2 100
Fields
Provision of Portable Water
10 10 100
Pumping Unit

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 19


Annual Report
2016-17
DERA GHAZI KHAN
A. Regular Watercourses:
During 2016-17, in district Dera Ghazi Khan, against 150
the target of 63watercoures, 65 (103%) watercourses ICR-I
were completed upto 30-06-2017. Figures A1, A2 & 100
A3 compare the actual work pace (ICR-I, ICR-II &
FCR) viz-a-viz TBAP on quarterly basis. The figures 50 TBAP
show that actual achievements commensurated with Actual
TBAP and resultantly 100% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
150 120
ICR-II 100 FCR
TBAP
100 80 TBAP
Actual
60 Actual
50 40
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Dera Ghazi Khan, against 120 Work Order Issued
the target of 400 acres, commissioning was verified 100
at only 389 (97%) upto 30-06-2017. Figures B1, B2 &
80
B3 compare the actual work pace (Work Order
Issued, Material Verified and Commissioning 60
Verified) viz-a-viz TBAP on quarterly basis. The 40 TBAP
figures show that actual achievement commensurated 20 Actual
with TBAP and97% commissioning could be got
0
verified within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1
120 120
Material Verified Commissioning Verified
100 100
80 TBAP 80
60 Actual 60
40 40 TBAP
20 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 20


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Dera Ghazi Khan, against 200


the target of 74 LASER Units, 63 (85%) were Booking
delivered upto 30-06-2017. Figures C1, C2 & C3 150
compare the actual work pace (Booking, Work
Order Issued, and Units Delivered) viz-a-viz TBAP 100
on quarterly basis. The figures show that though TBAP
50
actual achievements commensurated with TBAP,but Actual
100% delivery of units could not be achieved within
0
stipulated period as the same became slow during
Sep-16 Dec-16 Mar-17 June-17
last quarter.
Fig-C1
120 Work Order Issued 120 Unit Delivered
100 100
80 80
60 60
40 TBAP 40 TBAP
20 Act… 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
40 76 190 55 138 55 138

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 11 157 11 157 11 157

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 21


Annual Report
2016-17
MUZAFFAR GARH
A. Regular Watercourses:
During 2016-17, in district MuzaffarGarh, against
150
the target of 113watercoures, 105 (93%) ICR-I
watercourses were completed upto 30-06-2017.
100
Figures A1, A2 & A3 compare the actual work pace
(ICR-I, ICR-II & FCR) viz-a-viz TBAP on quarterly TBAP
basis. The figures show that actual achievements 50
Actual
commensurated with TBAP butin the end 100%
FCRscould not begot verified within stipulated 0
period as the pace of work became slow in last Sep-16 Dec-16 Mar-17 June-17
quarter .
Fig-A1
120
150 ICR-II 100 FCR
TBAP TBAP
100 80
Actual Actual
60
50 40
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district MuzaffarGarh, against 120 Work Order Issued
the target of 475 acres, commissioning was verified 100
at only 363 (76%) upto 30-06-2017. Figures B1, B2 &
80 TBAP
B3 compare the actual work pace (Work Order
60
Actual
Issued, Material Verified and Commissioning
Verified) viz-a-viz TBAP on quarterly basis. The 40
figures show that actual achievement did not 20
commensurate with TBAP and100% commissioning
0
could not be got verified within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 120 Commissioning Verified


Material Verified 100
100
80 TBAP 80 TBAP
60 Actual 60 Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 22


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district MuzaffarGarh, against 150


the target of 169 LASER Units, 125 (74%) were Booking
delivered upto 30-06-2017. Figures C1, C2 & C3
100
compare the actual work pace (Booking, Work
Order Issued, and Units Delivered) viz-a-viz TBAP
on quarterly basis. The figures show that though 50 TBAP
actual achievements commensurated with TBAP, Actual
but 100% delivery of units could not be achieved
0
within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued 120


Unit Delivered
100 100

80 80
60 60
40 TBAP 40
TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
53 145 274 132 249 132 249

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 9 129 0 0 0 0

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 23


Annual Report
2016-17
LAYYAH
A. Regular Watercourses:
During 2016-17, in district Layyah, against the target 120
of 11watercoures, 12 (109%) watercourses were 100
ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 80
compare the actual work pace (ICR-I, ICR-II & FCR) 60
viz-a-viz TBAP on quarterly basis. The figures show 40 TBAP
that actual achievements commensurated with 20 Actual
TBAP and resultantly 100% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1

120 120
ICR-II 100 FCR
100
80 TBAP
80
60 Actual
60
TBAP
40 40
Actual
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Layyah, against the target 120 Work Order
of 325 acres, commissioning was verified at only 371 100 Issued
(114%) upto 30-06-2017. Figures B1, B2 & B3
80
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60
a-viz TBAP on quarterly basis. The figures show that 40 TBAP
actual achievement commensurated with TBAP 20 Actual
and100% commissioning could be got verified
0
within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1
120
150
Material Verified Commissioning
100
Verified
100 TBAP 80
Actual 60
50 40 TBAP
20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 24


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Layyah, against the target 150


of 89 LASER Units, 61 (69%) were delivered upto30- Booking
06-2017. Figures C1, C2 & C3 compare the actual
100
work pace (Booking, Work Order Issued, and Units
Delivered) viz-a-viz TBAP on quarterly basis. The
figures show that in case of unit deliveryactual 50
TBAP
achievements did not commensuratewith TBAP Actual
during 3rd& 4th quarter, hence100% delivery of units
0
could not be achieved within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1
120
120 Work Order Issued Unit Delivered
100 100

80 80
60 60
40 TBAP 40 TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
30 73 243 72 240 72 240

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 7 100 7 100 7 100

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 25


Annual Report
2016-17
RAJANPUR
A. Regular Watercourses:
During 2016-17, in district Rajanpur, against the 150
target of 68watercoures, 82 (121%) watercourses ICR-I
were completed upto 30-06-2017. Figures A1, A2 & 100
A3 compare the actual work pace (ICR-I, ICR-II &
FCR) viz-a-viz TBAP on quarterly basis. The figures 50 TBAP
show that actual achievements commensurated with Actual
TBAP and resultantly 100% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
150
150 ICR-II FCR
TBAP 100 TB…
100

50 50

0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Rajanpur, against the 120 Work Order
target of 250 acres, commissioning was verified at 100 Issued
only 142 (57%) upto 30-06-2017. Figures B1, B2 & B3
80
compare the actual work pace (Work Order Issued, TBAP
Material Verified and Commissioning Verified) viz- 60
a-viz TBAP on quarterly basis. The figures show that 40
actual achievement did not commensurate with TBAP 20
and100% commissioning could not be got verified
0
within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 Material 120 Commissioning


100 Verified 100 Verified
80 80
TBAP 60 TB…
60
40 Ac…
40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 26


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Rajanpur, against the 120


target of 83 LASER Units, 73 (88%) were delivered Booking
100
upto 30-06-2017. Figures C1, C2 & C3 compare the
80
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis. 60
The figures show that actual achievements did not 40 TBAP
commensurate with TBAP, resultsntly 100% 20 Actual
delivery of units could not be achieved within
0
stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1
120 Unit Delivered
120 Work Order Issued
100 100

80 80 TBAP
60 Actual
60
40 TBAP 40
20
Actual 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
38 78 205 63 166 43 113

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 5 71 0 0 0 0

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 27


Annual Report
2016-17
FAISALABAD
A. Regular Watercourses:
During 2016-17, in district Faisalabad, against the 120
target of 23watercoures, 23 (100%) watercourses 100
ICR-I
were completed upto 30-06-2017. Figures A1, A2 & 80
A3 compare the actual work pace (ICR-I, ICR-II & 60
FCR) viz-a-viz TBAP on quarterly basis. The figures 40 TBAP
show that actual achievements commensurated with 20 Actual
TBAP and resultantly 100% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100 TBAP
80 TBAP
80 Actual Actual
60 60
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Faisalabad, against the 120 Work Order
target of 400 acres, commissioning was verified at 100 Issued
only 377 (94%) upto 30-06-2017. Figures B1, B2 & B3
80
4compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60
a-viz TBAP on quarterly basis. The figures show that 40 TBAP
actual achievement commensurated with TBAP and 20 Actual
94% commissioning could be got verified within
0
stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1
120
120 Material Verified Commissioning Verified
100 100

80 TBAP 80 TBAP
60 Actual 60 Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 28


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Faisalabad, against the 150


target of 148 LASER Units, 115 (78%) were delivered Booking
upto 30-06-2017. Figures C1, C2 & C3 compare the
100
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis.
The figures show that actual achievements 50 TBAP
remained fluctuating arround TBAP, but 100% Actual
delivery of units could not be achieved within
0
stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1
120 Work Order Issued 120
Unit Delivered
100 100
80 80
60 60
40 TBAP 40 TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
38 50 132 50 132 50 132

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 76 760 34 340 34 340

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 29


Annual Report
2016-17
JHANG
A. Regular Watercourses:
During 2016-17, in district Jhang, against the target 120
of 42watercoures, 38 (90%) watercourses were 100
ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 80
compare the actual work pace (ICR-I, ICR-II & FCR) 60
viz-a-viz TBAP on quarterly basis. The figures show 40 TBAP
that actual achievements commensurated with 20 Actual
TBAP in case of ICR-I & FCR but94% targets could 0
be achieved within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100 TBAP
80 TBAP
80 Actual Actual
60 60
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Jhang, against the target 120 Work Order
of 400 acres, commissioning was verified at only 175 100 Issued
(44%) upto 30-06-2017. Figures B1, B2 & B3 compare
80
the actual work pace (Work Order Issued, Material
Verified and Commissioning Verified) viz-a-viz 60
TBAP on quarterly basis. The figures show that 40 TBAP
actual achievement did not commensurate with 20 Actual
TBAP.Resultantly 44% commissioning could be got
0
verified within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 Material 120 Commissioning


100 Verified 100 Verified
80 80
TBAP TBAP
60 60
Actual Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 30


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Jhang, against the target 150


of 150 LASER Units, 115 (77%) were delivered upto Booking
30-06-2017. Figures C1, C2 & C3 compare the actual
100
work pace (Booking, Work Order Issued, and Units
Delivered) viz-a-viz TBAP on quarterly basis. The
figures show that actual achievements remained 50
fluctuateingarond TBAP, but 100% delivery of units TBAP
could not be achieved within stipulated period.
0
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order 120


Unit
100 Issued 100
Delivered
80 80
60 60
40 40
TBAP TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
38 75 197 75 197 66 174

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 103 1471 40 571 40 571

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 31


Annual Report
2016-17
CHINIOT
A. Regular Watercourses:
During 2016-17, in district Chiniot, against the target 150
of 15 watercoures, 15 (100%) watercourses were ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 100
compare the actual work pace (ICR-I, ICR-II & FCR)
viz-a-viz TBAP on quarterly basis. The figures show 50 TBAP
that actual achievements commensurated with Actual
TBAP and resultantly 100% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
150 ICR-II 100 FCR
TBAP
100 Actual 80 TBAP
60 Actual
50 40
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Chiniot, against the target 150
Work Order
of 250 acres, commissioning was verified at only 116
(46 %) upto 30-06-2017. Figures B1, B2 & B3 compare Issued
100
the actual work pace (Work Order Issued, Material
Verified and Commissioning Verified) viz-a-viz
TBAP on quarterly basis. The figures show that 50 TBAP
actual achievement did not commensurate with TBAP Actual
and 100% commissioning could not be got verified
0
within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 120 Commissioning


Material Verified
100 100 Verified
80 TBAP 80
TBAP
60 Actual 60
Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 32


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Chiniot, against the target 150


of 63 LASER Units, 45 (71%) were delivered upto Booking
30-06-2017. Figures C1, C2 & C3 compare the actual
100
work pace (Booking, Work Order Issued, and Units
Delivered) viz-a-viz TBAP on quarterly basis. The
figures show that though actual achievements 50 TBAP
commensurated with TBAP, but 100% delivery of Actual
units could not be achieved within stipulated period
0
as the same became slow during last quarter.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued 120


Unit Delivered
100 100

80 80
60 60
TBAP 40 TBAP
40
Actual Actual
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
23 37 161 15 65 15 65

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 3 30 3 30 3 30

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 33


Annual Report
2016-17
TOBA TEK SINGH
A. Regular Watercourses:
During 2016-17, in district Toba Tek Singh, against 120 ICR-I
the target of 1 watercoures, 1 (100%) watercourses 100
were completed upto 30-06-2017. Figures A1, A2 & 80
A3 compare the actual work pace (ICR-I, ICR-II & 60
TBAP
FCR) viz-a-viz TBAP on quarterly basis. The figures 40 Actual
show that actual achievements commensurated with 20
TBAP and resultantly 100% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100
80 80
60
TBAP
60
Actual
40 TBAP 40
Actual 20
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Toba Tek Singh, against 120 Work Order Issued
the target of 400 acres, commissioning was verified 100
at only 350 (88%) upto 30-06-2017. Figures B1, B2 &
80
B3 compare the actual work pace (Work Order
Issued, Material Verified and Commissioning 60
Verified) viz-a-viz TBAP on quarterly basis. The 40 TBAP
figures show that actual achievement did 20 Actual
otcommensurate with TBAP and 100%
0
commissioning could nobe got verified within
Sep-16 Dec-16 Mar-17 June-17
stipulated period.
Fig-B1

120 Material Verified 120 Commissioning Verified


100 100

80 TBAP 80
TBAP
60 Actual 60
Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 34


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Toba Tek Singh, against 150


the target of 72 LASER Units, 54 (75%) were Booking
delivered upto 30-06-2017. Figures C1, C2 & C3
100
compare the actual work pace (Booking, Work
Order Issued, and Units Delivered) viz-a-viz TBAP
on quarterly basis. The figures show that though 50
actual achievements commensurated with TBAP, TBAP
but 100% delivery of units could not be achieved
0
within stipulated period as the same became slow
Sep-16 Dec-16 Mar-17 June-17
during 3rd& 4th quarters.
Fig-C1
120
120 Work Order Issued Unit Delivered
100 100

80 80
60 60
40 TBAP 40
TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
30 106 353 106 353 85 283

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 67 670 24 240 24 240

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 35


Annual Report
2016-17
SARGODHA
A. Regular Watercourses:
During 2016-17, in district Sargodha, against the 120
target of 97 watercoures, 83 (86%) watercourses 100
ICR-I
were completed upto 30-06-2017. Figures A1, A2 & 80
A3 compare the actual work pace (ICR-I, ICR-II & 60
FCR) viz-a-viz TBAP on quarterly basis. The figures 40 TBAP
show that actual achievements did not 20 Actual
commensurate with TBAP and resultantly 100% 0
targets could not be achieved within stipulated Sep-16 Dec-16 Mar-17 June-17
period.
Fig-A1
120
120 ICR-II 100 FCR
100
80 TBAP 80 TBAP
60 Actual 60 Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Sargodha, against the 120 Work Order Issued
target of 600 acres, commissioning was verified at 100
only 211 (35%) upto 30-06-2017. Figures B1, B2 & B3
80 TBAP
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60 Actual
a-viz TBAP on quarterly basis. The figures show that 40
actual achievement did not commensurated with 20
TBAP and 100% commissioning could not be got
0
verified within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

Material Verified 120


120 Commissioning Verified
100 100

80 80
TBAP TBAP
60 Actual 60 Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 36


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Sargodha, against the 150


target of 122 LASER Units, 87 (71%) were delivered Booking
upto 30-06-2017. Figures C1, C2 & C3 compare the
100
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis.
The figures show that actual achievements 50 TBAP
fluctuatedaround TBAP, but 100% delivery of units Actual
could not be achieved within stipulated period.
0
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued 120


100
Unit Delivered
100
80 80
60 60
40 TBAP 40 TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
45 78 173 53 118 53 118

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 7 100 0 0 0 0

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 37


Annual Report
2016-17
KHUSHAB
A. Regular Watercourses:
During 2016-17, in district Khushab, against the 120
target of 27 watercoures, 27 (100%) watercourses ICR-I
100
were completed upto 30-06-2017. Figures A1, A2 & 80
A3 compare the actual work pace (ICR-I, ICR-II & 60
FCR) viz-a-viz TBAP on quarterly basis. The figures 40 TBAP
show that actual achievements commensurated with 20
Actual
TBAP and resultantly 100% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100
80 TBAP 80
60 Actual 60
TBAP
40 40 Actual
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Khushab, against the 120 Work Order
target of 400 acres, commissioning was verified at 100 Issued
only 278 (70%) upto 30-06-2017. Figures B1, B2 & B3
80
compare the actual work pace (Work Order Issued, TBAP
Material Verified and Commissioning Verified) viz- 60
Actual
a-viz TBAP on quarterly basis. The figures show that 40
actual achievement did not commensurated with 20
TBAP and 100% commissioning could not be got
0
verified within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1
120
120 Material Verified Commissioning Verified
100 100

80 80
TBAP TBAP
60 60
Actual Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 38


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Khushab, against the 120


target of 29 LASER Units, 20 (69%) were delivered 100
Booking
upto 30-06-2017. Figures C1, C2 & C3 compare the
80
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis. 60
The figures show that actual achievements did not 40 TBAP
commensurate with TBAP, resultantly 100% 20 Actual
delivery of units could not be achieved within
0
stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued 120 Commissioning Verified


100 100

80 80
TBAP
60 60
Actual
40 TBAP 40
20 Actual 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
30 93 310 39 130 39 130

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 7 100 0 0 0 0

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 39


Annual Report
2016-17
BHAKKAR
A. Regular Watercourses:
During 2016-17, in district Bhakkar, against the 120
target of 70 watercoures, 68 (97%) watercourses 100
ICR-I
were completed upto 30-06-2017. Figures A1, A2 & 80
A3 compare the actual work pace (ICR-I, ICR-II & 60
FCR) viz-a-viz TBAP on quarterly basis. The figures 40 TBAP
show that actual achievements commensurated with 20 Actual
TBAP and resultantly97% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II FCR
100 100
80 TBAP
80 Actual
60 60

40 TBAP 40

20 Actual 20
0
0
Sep-16 Dec-16 Mar-17 June-17
Sep-16 Dec-16 Mar-17 June-17
Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Bhakkar, against the 120 Work Order
target of 550 acres, commissioning was verified at 100 Issued
only 284 (52%) upto 30-06-2017. Figures B1, B2 & B3
80
compare the actual work pace (Work Order Issued, TBAP
Material Verified and Commissioning Verified) viz- 60 Actual
a-viz TBAP on quarterly basis. The figures show that 40
actual achievement did not commensurate with TBAP 20
and 100% commissioning could nobe got verified
0
within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 Material Verified 120


Commissioning Verified
100 100

80 80
TBAP TBAP
60 60
Actual Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 40


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Bhakkar, against the 150


target of 96 LASER Units, 64 (67%) were delivered
Booking
upto 30-06-2017. Figures C1, C2 & C3 compare the
100
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis.
The figures show that actual achievements 50
TBAP
remained fluctuatingaround TBAP, but 100%
Actual
delivery of units could not be achieved within
0
stipulated period as the same became slow during
Sep-16 Dec-16 Mar-17 June-17
last quarter.
Fig-C1

120 Work Order Issued 120 Unit Delivered


100 100

80 80
60 60
40 TBAP 40 TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
38 204 537 132 347 132 347

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 7 100 0 0 0 0

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 41


Annual Report
2016-17
MIANWALI
A. Regular Watercourses:
During 2016-17, in district Mianwali, against the 150
target of 26watercoures, 25 (96%) watercourses were ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 100
compare the actual work pace (ICR-I, ICR-II & FCR)
viz-a-viz TBAP on quarterly basis. The figures show 50 TBAP
that actual achievements commensurated with Actual
TBAP and resultantly96% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A3
120
120 ICR-II 100 FCR
100
80 TBAP
80
Actual
60 60
40 TBAP 40
20 Actual 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Mianwali, against the 120 Work Order Issued
target of 250 acres, commissioning was verified at 100
only 125 (50%) upto 30-06-2017. Figures B1, B2 & B3
80
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60
a-viz TBAP on quarterly basis. The figures show that 40
TBAP
actual achievement did not commensurate with TBAP 20 Actual
and only 50% commissioning could be got verified
0
within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 Material Verified 120 Commissioning Verified


100 100

80 80
TBAP TBAP
60 60
Actual Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 42


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Mianwali, against the 120


target of 71 LASER Units, 57 (80%) were delivered Booking
100
upto 30-06-2017. Figures C1, C2 & C3 compare the
80
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis. 60
The figures show that actual achievements did not 40 TBAP
commensurate with TBAP, and 100% delivery of 20 Actual
units could not be achieved within stipulated period
0
as the same became slow during last quarter.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1
Work Order Issued 120
120 Unit Delivered
100 100

80 80
60 60
40 TBAP 40 TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
23 123 535 78 339 78 339

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 7 100 0 0 0 0

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 43


Annual Report
2016-17
SAHIWAL
A. Regular Watercourses:
During 2016-17, in district Sahiwal, against the 150
target of 29 watercoures, 26 (90%) watercourses
ICR-I
were completed upto 30-06-2017. Figures A1, A2 & 100
A3 compare the actual work pace (ICR-I, ICR-II &
FCR) viz-a-viz TBAP on quarterly basis. The figures 50
TBAP
show that actual achievements commensurated with Actual
TBAP and resultantly90% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
150 ICR-II 100 FCR
100 80
60 TBAP
50 TBAP 40 Actual
Actual 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Sahiwal, against the 120
target of 350 acres, commissioning was verified at
Work Order Issued
100
only 154 (44%) upto 30-06-2017. Figures B1, B2 & B3
80
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60
a-viz TBAP on quarterly basis. The figures show that 40
actual achievement did notcommensurate with TBAP TBAP
20
and only 44% commissioning could be got verified
Actual
0
within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 Material Verified 120 Commissioning Verified


100 100

80 TBAP 80
TBAP
60 Actual 60
Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 44


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Sahiwal, against the 150


target of 85 LASER Units, 77 (91%) were delivered Booking
upto 30-06-2017. Figures C1, C2 & C3 compare the
100
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis.
The figures show that though actual achievements 50
TBAP
commensurated with TBAP, but 100% delivery of
Actual
units could not be achieved within stipulated
0
period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued 120


Unit Delivered
100 100

80 80
60 60
40 40 TBAP
TBAP
20 20 Actual
Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
38 75 197 75 197 56 153

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 28 280 28 280 28 280

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 45


Annual Report
2016-17
PAKPATTAN
A. Regular Watercourses:
During 2016-17, in district Pakpattan, against the 120
target of 42 watercoures, 39 (93%) watercourses ICR-I
100
were completed upto 30-06-2017. Figures A1, A2 & 80
A3 compare the actual work pace (ICR-I, ICR-II & 60
FCR) viz-a-viz TBAP on quarterly basis. The figures 40 TBAP
show that actual achievements commensurated with 20 Actual
TBAP and resultantly93% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100
80 80
60 TBAP
60 TBAP Actual
40 Actual 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Pakpattan, against the 120
target of 300 acres, commissioning was verified at
Work Order Issued
100
only 277 (92%) upto 30-06-2017. Figures B1, B2 & B3
80
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60
a-viz TBAP on quarterly basis. The figures show that 40
TBAP
actual achievement commensurated with TBAP 20 Actual
and92% commissioning could be got verified within
0
stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 120 Commissioning Verified


Material Verified 100
100
80 80
TBAP
60 60 Actual
40 TBAP 40
20 Actual 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 46


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Pakpattan, against the 200


target of 48 LASER Units, 57 (119%) were delivered Booking
upto 30-06-2017. Figures C1, C2 & C3 compare the 150
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis. 100
The figures show that actual achievements
50 TBAP
commensurated with TBAP, and 119% delivery of
Actual
units was achieved within stipulated period.
0
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

150 Work Order Issued 150


Unit Delivered
100 100

50 TBAP 50 TBAP
Actual Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
34 34 100 34 100 34 100

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 20 200 20 200 20 200

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 47


Annual Report
2016-17
OKARA
A. Regular Watercourses:
During 2016-17, in district Okara, against the target 150
of 119watercoures, 90 (76%) watercourses were ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 100
compare the actual work pace (ICR-I, ICR-II & FCR)
viz-a-viz TBAP on quarterly basis. The figures show 50
TBAP
that actual achievements did not commensurate
Actual
with TBAP and resultantly 100% targets could not 0
be achieved within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100
80 80
60 TBAP
60
TBAP 40
Actual
40
Actual 20
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Okara, against the target 120 Work Order Issued
of 450 acres, commissioning was verified at only 417 100
(93%) upto 30-06-2017. Figures B1, B2 & B3 compare
80
the actual work pace (Work Order Issued, Material
Verified and Commissioning Verified) viz-a-viz 60
TBAP on quarterly basis. The figures show that 40
TBAP
actual achievement did not commensurate with TBAP 20 Actual
and93% commissioning could be got verified within
0
stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 120 Commissioning Verified


Material Verified
100 100

80 80 TBAP
TBAP
60 Actual
60 Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 48


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Okara, against the target 150


of 53 LASER Units, 69 (130%) were delivered upto Booking
30-06-2017. Figures C1, C2 & C3 compare the actual
100
work pace (Booking, Work Order Issued, and Units
Delivered) viz-a-viz TBAP on quarterly basis. The
figures show that actual achievements 50
TBAP
commensurated with TBAP, and 130% delivery of
Actual
units could not be achieved within stipulated
0
period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1
150 Unit Delivered
150 Work Order
Issued
100 100

50 TBAP 50 TBAP
Actual Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
50 144 288 117 234 117 234

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 41 410 41 410 41 410

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 49


Annual Report
2016-17
LAHORE
A. Regular Watercourses:
During 2016-17, in district Lahore, against the target 150
of 9 watercoures, 10 (111%) watercourses were ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 100
compare the actual work pace (ICR-I, ICR-II & FCR)
viz-a-viz TBAP on quarterly basis. The figures show 50 TBAP
that actual achievements commensurated with Actual
TBAP and resultantly 111% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
150 ICR-II 100 FCR
100 80
60 TBAP
TBAP 40 Actual
50
Actual
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Lahore, against the target 120 Work Order Issued
of 200 acres, commissioning was verified at only 92 100
(46%) upto 30-06-2017. Figures B1, B2 & B3 compare
80 TBAP
the actual work pace (Work Order Issued, Material
Verified and Commissioning Verified) viz-a-viz 60 Actual
TBAP on quarterly basis. The figures show that 40
actual achievement did not commensurate with TBAP 20
and 100% commissioning could not be got verified
0
within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 120 Commissioning Verified


Material Verified 100
100
80 80
TBAP TBAP
60 60
Actual Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 50


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Lahore, against the target 150


of 30 LASER Units, 31 (103%) were delivered upto
Booking
30-06-2017. Figures C1, C2 & C3 compare the actual
100
work pace (Booking, Work Order Issued, and Units
Delivered) viz-a-viz TBAP on quarterly basis. The
figures show that actual achievements 50 TBAP
commensurated with TBAP, but 103% delivery of
Actual
units could not be achieved within stipulated period
0
as the same became slow during last quarter.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued


120
100
100
Unit Delivered
80 80
60 60
40
40 TBAP TBAP
20 Actual
20 Actual
0
0 Sep-16 Dec-16 Mar-17 June-17
Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
23 22 96 22 96 22 96

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 9 129 0 0 0 0

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 51


Annual Report
2016-17
SHEIKHUPURA
A. Regular Watercourses:
During 2016-17, in district Sheikhupura, against the 120
target of 77 watercoures, 78 (101%) watercourses 100
ICR-I
were completed upto 30-06-2017. Figures A1, A2 & 80
A3 compare the actual work pace (ICR-I, ICR-II & 60
FCR) viz-a-viz TBAP on quarterly basis. The figures 40 TBAP
show that actual achievements commensurated with Actual
20
TBAP and resultantly 100% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100 TBAP
80 TBAP
80 Actual
Actual
60 60
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Sheikhupura, against the 120
target of 400 acres, commissioning was verified at
Work Order Issued
100
only 335 (84%) upto 30-06-2017. Figures B1, B2 & B3
80
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60
a-viz TBAP on quarterly basis. The figures show that 40 TBAP
actual achievement did not commensurate with TBAP 20 Actual
and 84% commissioning could be got verified
0
within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 120 Commissioning Verified


Material Verified
100 100

80 80
TBAP
60 60
Actual
40 TBAP 40
Actual 20
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 52


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Sheikhupura, against the 150


target of 124 LASER Units, 129 (104%) were Booking
delivered upto 30-06-2017. Figures C1, C2 & C3
100
compare the actual work pace (Booking, Work
Order Issued, and Units Delivered) viz-a-viz TBAP
on quarterly basis. The figures show that actual 50 TBAP
achievements commensurated with TBAP, and Actual
resultantly 104% delivery of units could not be
0
achieved within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1
120
120 Work Order Issued Unit Delivered
100 100
80 80
60 60
40 TBAP 40
TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
38 82 216 56 147 41 108

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 36 360 10 100 10 100

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 53


Annual Report
2016-17
NANKANA SAHIB
A. Regular Watercourses:
During 2016-17, in district Nankana Sahib, against 120
the target of 11 watercoures, 9 (82%) watercourses 100
ICR-I
were completed upto 30-06-2017. Figures A1, A2 & 80
A3 compare the actual work pace (ICR-I, ICR-II & 60
FCR) viz-a-viz TBAP on quarterly basis. The figures 40 TBAP
show that actual achievements did 20 Actual
notcommensurate with TBAP and resultantly82% 0
targets were achieved within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100
80 80 TBAP
60 Actual
60
40 TBAP 40
20 Actual 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Nankana Sahib, against 120
the target of 250 acres, commissioning was verified
Work Order Issued
100
at only 35 (14%) upto 30-06-2017. Figures B1, B2 &
80 TBAP
B3 compare the actual work pace (Work Order
Issued, Material Verified and Commissioning 60 Actual
Verified) viz-a-viz TBAP on quarterly basis. The 40
figures show that actual achievement did not 20
commensurate with TBAP and only 14%
0
commissioning could be got verified within
Sep-16 Dec-16 Mar-17 June-17
stipulated period.
Fig-B1

120 Material Verified 120 Commissioning Verified


100 100

80 80
TBAP TBAP
60 Actual 60 Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 54


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Nankana Sahib, against 150


the target of 69 LASER Units, 51 (74%) were Booking
delivered upto 30-06-2017. Figures C1, C2 & C3
100
compare the actual work pace (Booking, Work
Order Issued, and Units Delivered) viz-a-viz TBAP
on quarterly basis. The figures show that actual 50
TBAP
achievements did not commensurate with TBAP,
Actual
and 100% delivery of units could not be achieved
0
within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued 120


Unit Delivered
100 100

80 80
60 60
40 40 TBAP
TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
18 22 122 22 122 22 122

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 82 1171 0 0 0 0

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 55


Annual Report
2016-17
KASUR
A. Regular Watercourses:
During 2016-17, in district Kasur, against the target 150
of 106 watercoures, 117 (110%) watercourses were
ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 100
compare the actual work pace (ICR-I, ICR-II & FCR)
viz-a-viz TBAP on quarterly basis. The figures show 50 TBAP
that actual achievements commensurated with Actual
TBAP and resultantly 110% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100
80 80
60 60 TBAP
40 TBAP 40 Actual
Actual 20
20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Kasur, against the target 120
Work Order Issued
of 500 acres, commissioning was verified at only 270 100
(54%) upto 30-06-2017. Figures B1, B2 & B3 compare
80
the actual work pace (Work Order Issued, Material
Verified and Commissioning Verified) viz-a-viz 60
TBAP on quarterly basis. The figures show that 40
actual achievement did not commensurate with TBAP 20
TBAP
and only 54 % commissioning could be got verified Actual
0
within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1
120 Commissioning Verified
120 Material Verified
100 100

80 80
TBAP TBAP
60 60
Actual Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 56


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Kasur against the target 150


of 106 LASER Units, 87 (82%) were delivered upto Booking
30-06-2017. Figures C1, C2 & C3 compare the actual
100
work pace (Booking, Work Order Issued, and Units
Delivered) viz-a-viz TBAP on quarterly basis. The
figures show that actual achievementsdid 50
TBAP
notcommensurate with TBAP, resultantly 100%
Actual
delivery of units could not be achieved within
0
stipulated period as the same became slow during
Sep-16 Dec-16 Mar-17 June-17
last quarter.
Fig-C1

120 Work Order Issued 120 Unit Delivered


100 100

80 80
60 60
40 40 TBAP
TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
50 73 146 73 146 73 146

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 10 100 9 90 9 90

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 57


Annual Report
2016-17
GUJRANWALA
A. Regular Watercourses:
During 2016-17, in district Gujranwala, against the 150
target of 86 watercoures, 98 (114%) watercourses ICR-I
were completed upto 30-06-2017. Figures A1, A2 & 100
A3 compare the actual work pace (ICR-I, ICR-II &
FCR) viz-a-viz TBAP on quarterly basis. The figures 50 TBAP
show that actual achievements commensurated with Actual
TBAP and resultantly 114% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100
80 80
TBAP
60 60 TBAP
Actual
40 40 Actual
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Gujranwala, against the 120
target of 385 acres, commissioning was verified at Work Order Issued
100
only 131 (34%) upto 30-06-2017. Figures B1, B2 & B3
80
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60
a-viz TBAP on quarterly basis. The figures show that 40
TBAP
actual achievement did not commensurate with TBAP 20 Actual
resultantly only 34% commissioning could be got
0
verified within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1
120
120
Material Verified Commissioning Verified
100 100

80 80
TBAP TBAP
60 60 Actual
Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 58


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Gujranala, against the 150


target of 124 LASER Units, 109 (88%) were delivered Booking
upto 30-06-2017. Figures C1, C2 & C3 compare the
100
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis.
The figures show that actual achievements dd not 50
TBAP
commensurate with TBAP, and88% delivery of units
Actual
could be achieved within stipulated period.
0
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued


120 Unit Delivered
100 100

80 80
60 60
40 40 TBAP
20 TBAP 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
38 47 124 42 111 42 111

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 18 180 4 40 4 40

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 59


Annual Report
2016-17
HAFIZABAD
A. Regular Watercourses:
During 2016-17, in district Hafizabad, against the 120
target of 43watercoures, 40 (93%) watercourses were 100
ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 80
compare the actual work pace (ICR-I, ICR-II & FCR) 60
viz-a-viz TBAP on quarterly basis. The figures show 40 TBAP
that actual achievements commensurated with Actual
20
TBAP and resultantly93% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100
80 80
60 60 TBAP
40 TBAP 40 Actual
20 Actual 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Hafizabad, against the 120 Work Order Issued
target of 265 acres, commissioning was verified at 100
only 106 (40%) upto 30-06-2017. Figures B1, B2 & B3
80 TBAP
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60 Actual
a-viz TBAP on quarterly basis. The figures show that 40
actual achievement did notcommensurate with TBAP 20
and only 40% commissioning could be got verified
0
within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 Material Verified 120 Commissioning Verified


100 100

80 80
TBAP TBAP
60 60
Actual Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 60


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Hafizabad, against the 150


target of 87 LASER Units, 82 (94%) were delivered Booking
upto 30-06-2017. Figures C1, C2 & C3 compare the
100
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis.
The figures show that actual achievements did not 50
TBAP
commensurate with TBAP, and94% delivery of units Actual
could be achieved within stipulated period.
0
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued 120


Unit Delivered
100 100

80 80
60 60
40 TBAP 40
TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
25 12 48 12 48 12 48

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 5 71 5 71 5 71

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 61


Annual Report
2016-17
NAROWAL
A. Regular Watercourses:
During 2016-17, in district Narowal, against the 120
target of 2 watercoures, 2 (100%) watercourses were
ICR-I
100
completed upto 30-06-2017. Figures A1, A2 & A3 80
compare the actual work pace (ICR-I, ICR-II & FCR) 60
viz-a-viz TBAP on quarterly basis. The figures show 40 TBAP
that actual achievements commensurated with Actual
20
TBAP and resultantly 100% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120 ICR-II 100 FCR
100
80 80
60 60
TBAP TBAP
40 40 Actual
Actual
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Narowal, against the 120
target of 150 acres, commissioning was verified at
Work Order Issued
100
only 167 (111%) upto 30-06-2017. Figures B1, B2 &
80
B3 compare the actual work pace (Work Order
Issued, Material Verified and Commissioning 60
Verified) viz-a-viz TBAP on quarterly basis. The 40 TBAP
figures show that actual achievement commensurated 20 Actual
with TBAP and 111% commissioning could be got
0
verified within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

150 120 Commissioning Verified


Material Verified 100

100 TBAP 80
Actual 60
50 40 TBAP
20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 62


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Narowal, against the 150


target of 62 LASER Units, 56 (90%) were delivered Booking
upto 30-06-2017. Figures C1, C2 & C3 compare the
100
actual work pace (Booking, Work Order Issued, and
Units Delivered) viz-a-viz TBAP on quarterly basis.
The figures show that actual achievements 50 TBAP
commensurated with TBAP, but 100% delivery of Actual
units could not be achieved within stipulated period
0
as the same became slow during last quarter.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1
120
120 Work Order Issued Unit Delivered
100 100

80 80
60 60
40 40
TBAP TBAP
20 20 Actual
Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
15 54 360 40 267 31 207

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 7 100 `7 100 7 100

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 63


Annual Report
2016-17
SIALKOT
A. Regular Watercourses:
During 2016-17, in district Sialkot, against the target 150
of 17 watercoures, 21 (124%) watercourses were
ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 100
compare the actual work pace (ICR-I, ICR-II & FCR)
viz-a-viz TBAP on quarterly basis. The figures show 50
TBAP
that actual achievements commensurated with Actual
TBAP and resultantly 124% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
150
150 ICR-II FCR
100 100
TBAP
50 TBAP 50 Actual
Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Sialkot, against the target 120
Work Order
of 300 acres, commissioning was verified at only 300 100
(100%) upto 30-06-2017. Figures B1, B2 & B3 Issued
80
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60
a-viz TBAP on quarterly basis. The figures show that 40
actual achievement commensurated with TBAP and TBAP
20
100% commissioning could be got verified within Actual
0
stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 Material Verified 120 Commissioning Verified


100 100

80 80
TBAP
TBAP 60
60 Actual
Actual 40
40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 64


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Sialkot, against the target 200


of 85 LASER Units, 80 (94%) were delivered upto
Booking
30-06-2017. Figures C1, C2 & C3 compare the actual 150
TBAP
work pace (Booking, Work Order Issued, and Units
100 Actual
Delivered) viz-a-viz TBAP on quarterly basis. The
figures show thatactual achievements
50
commensurated with TBAP, but 100% delivery of
units could not be achieved within stipulated
0
period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1

120 Work Order Issued 120


Unit Delivered
100 100

80 80
60 60
40 40
TBAP TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
25 13 52 13 52 13 52

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
10 4 40 4 40 4 40

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 65


Annual Report
2016-17
MANDI BAHA-UD-DIN
A. Regular Watercourses:
During 2016-17, in district Mandi Baha-ud-Din, 150
against the target of 23watercoures, 27 (117%)
ICR-I
watercourses were completed upto 30-06-2017. 100
Figures A1, A2 & A3 compare the actual work pace
(ICR-I, ICR-II & FCR) viz-a-viz TBAP on quarterly 50 TBAP
basis. The figures show that actual achievements Actual
commensurated with TBAP and resultantly 117% 0
targets were achieved within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
150
150 ICR-II FCR
TBAP
100 Actual 100
TBAP
50 Actual
50

0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Mandi Baha-ud-Din, 120
against the target of 325 acres, commissioning was Work Order Issued
100
verified at only 194 (60%) upto 30-06-2017. Figures
80
B1, B2 & B3 compare the actual work pace (Work
Order Issued, Material Verified and Commissioning 60
Verified) viz-a-viz TBAP on quarterly basis. The 40
TBAP
figures show that actual achievement did not 20 Actual
commensurate with TBAP and only 60%
0
commissioning could be got verified within
Sep-16 Dec-16 Mar-17 June-17
stipulated period.
Fig-B1
120
120 Material Verified Commissioning Verified
100 100

80 TBAP 80
Actual 60 TBAP
60
Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 66


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Mandi Baha-ud-Din, 200


against the target of 63 LASER Units, 55 (87%) were Booking
delivered upto 30-06-2017. Figures C1, C2 & C3 150
compare the actual work pace (Booking, Work
Order Issued, and Units Delivered) viz-a-viz TBAP 100
on quarterly basis. The figures show that actual TBAP
50
achievements commensurated with TBAP, but 100% Actual
delivery of units could not be achieved within
0
stipulated period as the same became slow during
Sep-16 Dec-16 Mar-17 June-17
last quarter.
Fig-C1

120 Work Order Issued 120


Unit Delivered
100 100

80 80
60 60
40 40 TBAP
TBAP
20 Actual
20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
34 29 85 29 85 29 85

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 5 71 5 71 5 71

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 67


Annual Report
2016-17
GUJRAT
A. Regular Watercourses:
During 2016-17, in district Gujrat, against the target 400
of 1 watercoures, 3 (300%) watercourses were ICR-I
completed upto 30-06-2017. Figures A1, A2 & A3 300

compare the actual work pace (ICR-I, ICR-II & FCR) TBAP
200
Actual
viz-a-viz TBAP on quarterly basis. The figures show
100
that actual achievements commensurated with
TBAP and resultantly300% targets were achieved 0
within stipulated period. Sep-16 Dec-16 Mar-17 June-17

Fig-A1
400
400 ICR-II FCR
300 300
TBAP
Actual 200 TBAP
200
Actual
100 100

0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Gujrat, against the target 120 Work Order
of 325 acres, commissioning was verified at only 351 100 Issued
(108%) upto 30-06-2017. Figures B1, B2 & B3
80
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60
a-viz TBAP on quarterly basis. The figures show that 40 TBAP
actual achievement commensurated with TBAP and 20 Actual
108% commissioning could be got verified within
0
stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-B1

120 120 Commissioning


Material
100 100 Verified
Verified 80
80
60 60
40 TBAP
40 TBAP
20 Actual
20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-B2 Fig-B3

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 68


Annual Report
2016-17
C. Provision of LASER Land Levelling Units:

During 2016-17, in district Gujrat, against the target 150


of 35 LASER Units, 30 (86%) were delivered upto Booking
30-06-2017. Figures C1, C2 & C3 compare the actual
100
work pace (Booking, Work Order Issued, and Units
Delivered) viz-a-viz TBAP on quarterly basis. The
figures show that actual achievements did not 50 TBAP
commensurate with TBAP, and 100% delivery of Actual
units could not be achieved within stipulated
0
period.
Sep-16 Dec-16 Mar-17 June-17

Fig-C1
120
120 Work Order Unit Delivered
100
100 Issued
80 80
60 60
40 TBAP 40 TBAP
20 Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-C2 Fig-C3
D. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
23 28 122 28 122 28 122

E. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 6 86 6 86 6 86

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 69


Annual Report
2016-17
RAWALPINDI

A. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Rawalpindi, against the 120 Work Order Issued
target of 900 acres, commissioning was verified at 100
only 461 (51%) upto 30-06-2017. Figures A1, A2 &A3
80 TBAP
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz- 60 Actual
a-viz TBAP on quarterly basis. The figures show that 40
actual achievement did not commensurate with TBAP 20
and resultantly100% commissioning could not be
0
got verified within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120
Material Verified Commissioning
100
100 Verified
80 80
TBAP TBAP
60 60
Actual Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3
B. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
104 135 130 115 111 85 82

C. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 19 271 19 271 19 271

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 70


Annual Report
2016-17
ATTOCK

A. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Attock, against the target 150
of 900 acres, commissioning was verified at only 988 Work Order Issued
(110%) upto 30-06-2017. Figures A1, A2 &A3
100
compare the actual work pace (Work Order Issued,
Material Verified and Commissioning Verified) viz-
a-viz TBAP on quarterly basis. The figures show that 50 TBAP
actual achievement commensurated with TBAP Actual
andtargets were achieved within stipulated period.
0
Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
120
Material Verified Commissioning
100 100
Verified
80 80
60 60
40 TBAP 40 TBAP
20
Actual 20 Actual
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3
B. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
89 276 310 221 248 156 175

C. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 7 100 0 0 0 0

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 71


Annual Report
2016-17
CHAKWAL

A. Installation of High Efficiency Irrigation System (HEIS)


During 2016-17, in district Chakwl, against the 120
target of 875 acres, commissioning was verified at Work Order
100
only 969 (111%) upto 30-06-2017. Figures A1, A2 Issued
80
&A3 compare the actual work pace (Work Order
Issued, Material Verified and Commissioning 60
TBAP
Verified) viz-a-viz TBAP on quarterly basis. The 40
Actual
figures show that actual achievement commensurated 20
with TBAP andtargets were achievedwithin
0
stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-A1
120
150
Material Verified Commissioning
100
Verified
100 TBAP 80
Actual 60
50 40 TBAP
20 Actual

0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3
B. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
89 260 292 228 256 228 256

C. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 22 314 22 314 22 314

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 72


Annual Report
2016-17
JHELUM

A. Installation of High Efficiency Irrigation System (HEIS)

During 2016-17, in district Jhelum, against the target 120 Work Order Issued
of 875 acres, commissioning was verified at only 511 100
(58%) upto 30-06-2017. Figures A1, A2 &A3 compare TBAP
80
the actual work pace (Work Order Issued, Material
60 Actual
Verified and Commissioning Verified) viz-a-viz
TBAP on quarterly basis. The figures show that 40
actual achievement did not commensurate with TBAP 20
and resultantly100% commissioning could not be
0
got verified within stipulated period.
Sep-16 Dec-16 Mar-17 June-17

Fig-A1

120 120 Commissioning Verified


Material Verified 100
100
80 TBAP 80 TBAP
60 Actual 60 Actual
40 40
20 20
0 0
Sep-16 Dec-16 Mar-17 June-17 Sep-16 Dec-16 Mar-17 June-17

Fig-A2 Fig-A3

B. Provision of Solar System on HEIS Sites

Work Order Material Final


Target
Issued Supplied Commissioning
(Acres)
Achieved % age Achieved % age Achieved % age
89 115 129 115 129 95 107

C. Installation of Tunnels at HEIS Sites

Allotment/ Booking Installation of Inspection by Designated


Target
of Tunnels Tunnels by Farmers Committee / Consultant
(Acres)
Achieved % age Achieved % age Achieved % age
7 8 114 8 114 8 114

Punjab Irrigated Agriculture Productivity Improvement Project (PIPIP) 73