Escolar Documentos
Profissional Documentos
Cultura Documentos
ENGINEERING DESIGN
Civil 409 – Lecture 2:
Infrastructure Planning Components
CHRIS JOHNSTON
2
THE FIRST WATER AND SEWER SYSTEMS
• 3000 BCE: Our Earliest archaeological records date back about 5000 years to the City
of Nippur, Sumeria (Iraq). Water was drawn by wells and cisterns and waste was
conveyed through and extensive system of arched stone drains.
• 2000 BCE: Earliest record of water treatment is in Egypt. Boil, sunlight, charcoal filter,
then cool
• 1440 BCE: First system for clarifying liquids is also in Egypt using a siphon to separate
water from settled solids
• 98 CE: First Engineering Report on water supply, conveyance, and treatment was in
Rome by Julius Frontinus
• Not much happened from the Roman time to the middle of the 1850s!
• 1842 CE: First modern day sewer collection system was in Hamburg Germany
• London and Paris then followed after major outbreaks of Cholera in London from 1848
to 1854 and a connection was made between water supply and sanitation.
(Source: Water Supply and Pollution Control. W. Viessman et al, 8th Edition 2009)
3
EARLY WATER AND SEWER SYSTEMS
4
LANDMARK BENEFITS OF MUNICIPAL INFRASTRUCTURE
“some” (mostly engineers) feel that the greatest increase in the life expectancy from
1860 to the 1920s was due to the widespread adoption of modern day sanitary
sewer systems! In this period, life expectancy rose roughly 30 years”.
5
METRO VANCOUVER’S WATER SUPPLY AND FEEDER SYSTEM
Seymour
Water
Treatment
Plant
6
SEYMOUR WATER FILTRATION PLANT
7
METRO VANCOUVER’S WASTEWATER COLLECTION SYSTEM
8
METRO VANCOUVER’S WASTEWATER TREATMENT PLANT (1/5)
(ANNACIS ISLAND SECONDARY TREATMENT PLANT)
9
MANY MUNICIPAL UTILITIES IN ROAD RIGHT-OF-WAYS
10
MANY MUNICIPAL UTILITIES IN ROAD RIGHT-OF-WAYS
(Same area showing utilities below Ground)
11
UTILITIES THAT CAN BE FOUND IN ROAD R/W AND
EASEMENTS
• Watermains
• Oil and gas pipelines
• Gravity sewer mains
• Major water feeder mains
• Storm sewers
• Sewer forcemains
• Electrical ducts
• Transportation tunnels
• Signal cables
• Rain Gardens
• Street lighting electrical ducts
• Vaults
• Gas mains
• Sewer / Water / Drainage
• Cable TV lines
service connections
• Telephone cables
• Others
• Fiber optic cables
• District heating mains
• Abandoned utilities
• Oil and gas pipelines
12
TYPICAL ROAD CROSS-SECTION WITH UTILITY RESERVATION
13
OUTLINE
14
EVERY PIECE OF PROPERTY HAS A ZONING
The Zoning tell the owner what they can or can’t do on that property. It also provides
Engineers, Planners, potential buyers, 3rd parties, etc. what can happen on the property
in the future.
15
TYPES OF LAND USE PLANNING HORIZONS
Build-out /
Official Saturation /
Existing Approved
Community Urban
Land Use Zoning
Plan Containment
10 – 100 years?
5 – 20 years?
5- 30 years?
Population
Now
Time
16
TYPES OF LAND USES
17
EXISTING LAND USE – VERNON, BC
18
EXAMPLE OF ZONING LAND USE
19
EXAMPLE OF OFFICIAL COMMUNITY PLAN (OCP) LAND USE
20
EXAMPLE OF HOW CHANGES TO LAND USE ARE CHANGED
21
EXAMPLE HOW ZONING IS THEN APPLIED TO INFRASTRUCTURE
22
THE LAND DEVELOPMENT AND REDEVELOPMENT PROCESS
23
OUTLINE
24
CITY OF SURREY’S ON-LINE GIS DATABASE
25
CITY OF VANCOUVER’S ON-LINE GIS DATABASE
26
DISTRICT OF NORTH VANCOUVER’S ON-LINE GIS DATABASE
27
DISTRICT OF NORTH VANCOUVER’S ON-LINE GIS DATABASE
28
DISTRICT OF NORTH VANCOUVER’S ON-LINE GIS DATABASE
29
DISTRICT OF NORTH VANCOUVER’S ON-LINE GIS DATABASE
30
THE GIS “INTERSECTION” PROCESS
31
GIS SUMMARY
• City of Vancouver
http://vanmapp.vancouver.ca/pubvanmap_net/default.aspx
http://cosmos.surrey.ca/external/
http://geoweb.dnv.org/properties/
33
OUTLINE
34
METRO VANCOUVER POPULATION PROJECTIONS
35
POPULATION PROJECTIONS
36
POPULATION PROJECTION METHODS (EXAMPLES)
POPULATION PROJECTIONS:
METHODS AVAILABLE:
• Arithmetic growth rate: Assumed to follow some logical math relationship in which
population growth is a function of time
• Uniform percentage growth rate: based on past short term or longer term trends
• Curvilinear method (eye-ball extrapolation!)
• Logistical method: if saturation population known or urban containment boundary has
been reached and land use constrains future growth.
• Comparison method: a comparison with similar, larger communities
• Ratio Method: population growth rate is assumed to be related to that of the larger
region
37
PROJECTING SATURATION POPULATION LEVEL - SECHELT
38
CENSUS CANADA POPULATION COUNTS
39
USING “CENSUS” GIS INFORMATION
40
INTERSECT CENSUS LAYER WITH LOT (PARCEL) LAYER TO
DETERMINE EXISTING RESIDENTIAL PEOPLE / LOT Census Canada
Population
Layer
Intersect
with Parcel
Layer to
determine
people / lot
41
OUTLINE
42
CENSUS POPULATIONS AND POPULATION EQUIVALENTS
44
(MAGNIFIED VERSION PART 1)
45
(MAGNIFIED VERSION PART 2)
46
EXAMPLE CALCULATIONS
Method 1: New Residential Development
and ICI zonings: The density for RM15
times its lot area, will provide the maximum
allowable residential population for that lot
(see zoning tables).
• Engineering planners and modelers develop infrastructure models based on land use
scenarios:
• Population Projections are then used to estimate when some of these scenarios are
likely to be reached (e.g. In what year). Keeping in mind it can be a chicken and egg
procedure if land use constrains growth.
48
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 3:
Introduction to Municipal Water Systems
CHRIS JOHNSTON
2
YOUR MINI WATER USE ASSIGNMENT
3
MY WATER USE ASSIGNMENT
4
CLASS SURVEY
5
OUTLINE
6
OUTLINE
7
DEFINITIONS
8
EXAMPLE OF A MUNICIPAL WATER DISTRIBUTION SYSTEM –
WHITE ROCK
9
10
SOME BASICS
P = Pressure
Column H = Head (= Pressure)
HGL = Hydraulic Grade Line
HGL of a body of water is the surface
1m
W.C. = Water Column
Indicates elevation of a free water surface m = meters
(May refer to meters of elevation or water column)
Water
0m
Elevation
(0 m elev. is commonly ‘the datum’, although datum can be non-zero)
11
DESIGN CRITERIA - PRESSURES
Normal demands:
28 - 35 m WC (40 – 50 psi min.)
105 m WC max (150 psi)
Fire demands:
14-21 m WC residual (20 to 30 psi)
14 m WC zone constraint
12
DELIVERY OF REQUIRED WATER FLOWRATES (DEMAND)
13
ESTIMATING WATER DEMANDS
“Friday Lecture”
“Wednesday’s Lecture”
14
DEMAND TERMINOLOGY
15
Typical Design Criteria* in B.C.
500
0
Su
r re
y
Sq
u am
M is
ap h
le
R
id
g e
N
an
ai
m
o
C
hi
lliw
ac
Ab k
b ot
sf
or
d
Ve
r no
n
Ka
m
lo
o ps
Ke
G lo
le w
nm na
or
e-
MDD DESIGN CRITERIA (L/ca/day)
E
llis
W on
ill
ia
m
s
La
ke
Tr
ai
l
DAILY DIURNAL PATTERN
18
MDD DIURNAL PATTERN
19
DESIGN CRITERIA – HYDRANT FIRE PROTECTION
Required duration
• 1.5 SFR to 3 hours Industrial
Hydrant Spacing
• 150 m typ. SFR, 75 m or less higher density evaluated on MDD
20
DESIGN CRITERIA – SPRINKLER FIRE PROTECTION
• Fireflows – NFPA
• 2.6 L/s (2 sprinkler heads) SFR – 13D
• Up to 60 L/s – to NFPA 13
• Required duration
• Typ. Not an issue
• Evaluated on PHD
21
EXAMPLE OF FIREFLOW ANALYSIS RESULTS
22
MINIMUM VELOCITIES
23
DESIGN CRITERIA – WATER QUALITY
24
DESIGN CRITERIA – REDUNDANCY
• Looping
• Valve clusters at intersections, hydrants, mid-block spacing
• Length of cul-de-sacs
• Standby power at booster pump stations
• Spare pump at p.s.’s
• Reservoir storage
25
DESIGN CRITERIA – RELIABILITY
26
MORE BASICS
HGL (dynamic)
87 m
HGL (static)
13 m House
10 m
River / Lake 0m
(Datum)
27
SOME EQUATIONS
(Darcy-Weisbach)
(Hazen-Williams)
28
PUMP AND SYSTEM CURVES
HL = 16 m
Ht = 90 m
Hs = 74 m
30 m
0 Q
0 80 L/s 120 L/s
29
Simple System
HGL UNDER A SMALLER FLOW
HGL (dynamic)
87 m
35 m
13 m House
10 m
0m
(Datum)
30
Simple System
HGL WITH A LARGER FLOW
HGL (dynamic)
87 m
Storage Reservoir
- AKA Tank
- Elevations
Model it!
- Geometry
Entrance / Exit
(minor losses)
Static Head (Hs)
(87–13=) 74 m W.C. Bends, Valves & Other Fittings
(minor losses)
35 m Pipeline (friction loss)
- Material, Diameter
Pump
- Elevation
- Pump Curve Demands
- AKA Junctions or Nodes
13 m House - Demand amount and pattern
10 m
River / Lake Bends (minor losses)
0m
- AKA Reservoir - AKA Junctions or Nodes
(Datum)
- Elevation - Elevation
31
EXAMPLE OF A WATER SYSTEM SCHEMATIC
32
EXAMPLE OF AREAS OF PRACTICE WITHIN THE WATER
PRACTICE
33
DESIGN STANDARDS
34
OUTLINE
35
Water System Planning Case
Study
Albion Area
District of Maple Ridge
RULES OF THUMB
Pressure Zoning –
• 50 to 60 m between zones is good
• Top of zone 35m below TWL of tank
42
RULES OF THUMB
43
RULES OF THUMB
44
RULES OF THUMB
Water Quality
• Don’t oversize pipes
• Rechlorinate for reservoirs
Redundancy
• Max. unlooped length 150m
45
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 4:
Calculation of Fireflows, Irrigation Demands, and
Thrust Restraints
CHRIS JOHNSTON
2
PROVIDING WATER FOR FIRE PROTECTION
As a municipal engineer (consultant or working for a city), your job is to ensure that you
have done a proper analysis on the water distribution system to identify what flow rate
can be supplied to any point in the city and for how long.
You also have to identify what is going to happen in the future and plan for it (i.e. review
fireflows under the various development scenarios).
If there is a deficiency, the fire department and long term planning staff must know
about it so they can plan accordingly.
You also have to anticipate what can go wrong. Power outages, mechanical failures,
maintenance, hot weather, cold weather, etc. are considered normal and not special
events. Redundancy, proper design, and specification of the right equipment are part
of what’s required.
3
GUIDING DOCUMENTS
4
HOW MUCH WATER DO YOU NEED TO FIGHT A FIRE IN THIS
SITUATION?
The FUS
calculations use
building area,
material type,
exposure
distance to
adjacent
structures, and
fire suppression
systems to
estimate how
much water a fire
department would
typically require
to fight a fire.
5
THE FIREFLOW FORMULA
6
CALCULATION PROCEDURE
7
HOW MUCH WATER DO YOU NEED TO FIGHT A FIRE IN THIS
SITUATION?
Q = 220 C √ A
8
SURREY FIREFLOW REQUIREMENTS
Many cities
provide
minimum fireflow
requirements
9
DETERMINE HYDRANT SPACING AND FIREFLOW STORAGE
REQUIREMENTS
10
EXAMPLE OF FIREFLOW ANALYSIS RESULTS
11
RESERVOIR SIZING
12
DESIGN CRITERIA – SPRINKLER FIRE PROTECTION
• Fireflows – NFPA
• 2.6 L/s (2 sprinkler heads) SFR – 13D
• Up to 60 L/s – to NFPA 13
• Required duration
• Typ. Not an issue
• Evaluated on PHD
13
APPLICATION OF FORMULA ACROSS LAND USES
Average fireflow calcualtions for “typical properties” within a particular land use are usually
performed to derive required fireflows. However, for larger structures, older areas, or
structures in dense areas manually calculations are sometimes performed.
14
CITY OF WHITE ROCK FIRE EXAMPLE A– MAY 15, 2016
15
AFTER THE FIRE
This is a worst case scenario and goes beyond the FUS calculations as the fire
suppression systems, fire walls, and other measure are typically not in place while the
building is under construction. The strong wind that was blowing that day aggravated the
situation and spread the fire from the wooden building under construction to the existing
multi-family complex nearby.
17
COMPARISON TO SURREY FIREFLOW REQUIREMENTS
18
OUTLINE
19
Terminology
500
0
Su
r re
y
Sq
u am
M is
ap h
le
R
id
g e
N
an
ai
m
o
C
hi
lliw
ac
Ab k
b ot
sf
or
d
Ve
r no
n
Ka
m
lo
o ps
Ke
G lo
le w
nm na
or
e-
MDD DESIGN CRITERIA (L/ca/day)
E
llis
W on
ill
ia
m
s
La
ke
Tr
ai
l
Population-Based Criteria
PROBLEMS:
Criteria assumes that irrigation usage is
also proportional to population
Overestimation of Overestimation of
MDD in high-density future demands,
residential areas no credit for infill
Underestimation of
MDD in low-density
residential areas
Average Water Use in the GVRD
800
700
600
ADD L/ca/day
500
400
300
0
1984 1986 1988 1990 1992 1994 1996 1998 2000
Year
*GVRD Regional Water Demand by Sector , 2001
Existing Criteria Summary
• Population Based
• Use of ADD not appropriate
• MDD values range from 900 – 3000 L/ca/
day
• Does not address irrigation adequately
Better Way
Osoyoos
Castlegar
Kelowna
Vernon
Vancouver
Maple Ridge
Surrey
0 5 10 15 20 25 30
Frequency & Lot Coverage
• Sprinkling frequency, S
– GVRD allows 4 days/wk, Vernon 7 days/wk
• Lot coverage, rc
– Varies 10% to 65% depending on land use
– typ. range for mixed density 40 - 50 %
Sprinkling Efficiency
• Sprinkling Efficiency, ns
– “good” value - 70% (IIABC)
– Burnaby, Surrey, Maple Ridge range from 25 - 65%
– design value 30 %
Method for Estimating Outdoor
Usage
Demand = Irrig. Rate • Area
Qo = qo • A
= (IRt / (S • ns)) • (rc • A)
• S = 4 days / week
• ns = 30 %
• rc = 40%
• A = 600 m2 Old
• 3 people/lot Qmdd = 3,000 L/lot
• IRt = 9 mm/week
• S = 4 days / week © CITY OF VANCOUVER
Data quality not guaranteed
• ns = 30 %
• rc = 65%
• A = 1000 m2 Old
• 3 people/lot Qmdd = 3,000 L/lot
• S = 4 days / week
• ns = 30 %
• rc = 30% Old
• A = 2500 m2 Qmdd = 48,600 L/lot
• 18 units, 2.7 cap/lot
New
• Design Criteria: qi = 300 L/cap/d, Qo = 5,625 L/lot
mdd = 1000 L/cap/d Qi = qi *18*2.7 = 14,580 L/lot
Qmdd = 22,205 L/lot
• Qmdd = 1000 L/cap *2.7*18
• Qo = (9 / (4 * 0.3)) *(0.3 *2500) =
5,625 L/lot
Summary
• Population-based design criteria not
appropriate for assigning MDD
• Penalizes high-density development
• May result in undersized facilities for large
lot areas
• Area-weighting of outdoor use component
more accurate
• However, City may still require the use
of one number (Example Surrey: 1000
L/day/capita)
OUTLINE
40
THE NEED FOR THRUST RESTRAINT
41
THRUST CALCULATIONS
Where:
AT = the thrust
area required
P = the maximum
operating
pressure
a* = the internal
pipe diameter
q all = the
bearing strength
of the soil
Missing:
Normally there is
a factor of safety
in the calculation
42
43
BEARING CAPACITY OF UNDISTURBED SOILS
City of Surrey
Criteria for the
bearing strength of
soil:
44
EXAMPLE OF THRUST BLOCK REQUIREMENTS
45
THIS IS NOT THE WAY YOU DO IT.
46
RESTRAINT PHILOSOPHIES
• Fully Restrained
• vs.
• Locally Restrained
RESTRAINT PHILOSOPHIES
• Tie-rods:
COMPARISON OF METHODS
• Tie-rods:
- not a complete restraint system, connection to
pipe must be designed
- corrosion vulnerability (esp. if not coreten)
+ versatile when used in conjunction with other
methods
COMPARISON OF METHODS
• Serrated
split-ring
restraints
COMPARISON OF METHODS
• Locking gasket:
+ supply cost similar to WAR
+ normal installation simple
- use limited to Tyton rubber gaskets
- disassembly
COMPARISON OF METHODS
• Boltless Pipe:
COMPARISON OF METHODS
• Boltless Pipe:
+ option for fully restrained pipelines
+ installation advantages over WAR
harnesses
- supply costs
- delivery
- special fittings
- not practical for local restraint only
- field cut pipe requires special sol’n
local excavation
Installation Cost
L – Low
failure due to
M – Medium
Vulnerability
Potential for
Potential for
vulnerability
Acceptance
Supply Cost
installation
H – High
Corrosion
improper
Industry
Seismic
LOCALLY RESTRAINED SYSTEMS
Concrete Thrust Blocks H M None H H L L
Concrete Gravity Blocks H M None M H L+ L
Rodding M M L-H M M M M
Wedge Action Restraints (WAR) M M L M–H M M- L
Locking Gasket M M ? M–H M M L
Boltless Pipe L-M M L- M–H M M+ L
Serrated split-ring restraints L H L M– H M M- L
FULLY RESTRAINED SYSTEMS
WAR only M L L L L H M+
Boltless pipe with WAR at fittings M L L L L H M
Boltless pipe and fittings M M L- L L H+ H
MJ/TJ pipe and fittings M- M L L L H+ NI
Locking Tyton gasket pipe and
fittings L M M L L NI NI
WATER USE & DEMAND
TOPICS
• Design Criteria
• Water Use Trends
• Indoor End Use Calculations
2
DEFINITIONS
ADD Average Day Demand
BD Base demand = indoor water use
ICI Industrial, Commercial, Institutional
L/c/d Liters per capita per day
MDD Maximum Day Demand
NRW Non-revenue water – water that is lost from the system through leakage
and or meter inaccuracies
PE Population Equivalents (used for ICI demands)
PHD Peak Hour Demand
SD Seasonal Demand
3
DESIGN CRITERIA
• Design criteria are established by either associations (e.g. MMCD, FUS)
and/or municipalities/regional districts to ensure an adequate level of
service and to protect human health.
4
DESIGN CRITERIA
Example - Residential Demand Design Criteria
Sources:
(1) Master Municipal Construction Document – Design Guideline, 2005
5
DESIGN CRITERIA
Example – ICI Demand Design Criteria
Sources:
(1) Master Municipal Construction Document – Design Guideline, 2005
6
DESIGN CRITERIA
Examples - Residential Demand Design Criteria (L/c/d)
District of
City of City of City of
MMCD(1) North
Vancouver(3) Surrey(4) Kelowna(5)
Vancouver(2)
BDD
300
(L/c/d)
450
ADD (300 for
600 metered)
320 500 900
(L/c/d)
MDD
1200 1000 512 1000 1800
(L/c/d)
PHD
1800 2000 672 2000 4000
(L/c/d)
Sources:
(1) Master Municipal Construction Document – Design Guideline, 2005
(2) The District of North Vancouver DEVELOPMENT SERVICING BYLAW - BYLAW 8145
(3) City of Vancouver Engineering Design Manual, 2018
(4) Design Criteria Manual, July 11, 2016 7
(5) Design Standards, Bylaw 7900
DESIGN CRITERIA
What do design criteria affect?
• Infrastructure Size (pipes, pump stations, PRVs, reservoirs)
• Costs (Capital & O&M)
• Leakage/Water Loss
• Energy Consumption
• Water Quality
• Source Water Capacity
8
DESIGN CRITERIA VS. WATER USE
9
LOWER MAINLAND - WATER USE
10
WATER SYSTEM AVERAGE ANNUAL
(METRO VANCOUVER)
11
WATER SYSTEM PER CAPITA
(METRO VANCOUVER)
PHD
MDD
ADD
12
WATER SYSTEM PER CAPITA
(METRO VANCOUVER)
PHD
MDD
ADD
13
WATER SYSTEM PER CAPITA
(METRO VANCOUVER)
PHD
MDD
ADD
14
WATER SYSTEM PER CAPITA
(METRO VANCOUVER)
4000
PHD
MDD
ADD
15
WATER USE
16
WATER USE
17
WATER USE
Source:
Water Research
Foundation,
Residential end uses
of water, 2016
18
WATER USE
• Education (e.g. turn off the faucet while you brush your teeth)
• Conservation Programs
• Demographics
19
WATER USE
High efficiency fixtures
• Toilets
22 L/flush
20
WATER USE
Conservation Programs
• Rebate programs
21
WATER USE
Demographics
• Transient Populations
• Specific to Location
Example:
Both demands were metered and were based on existing populations. But
approximately half of the strata residence left for the winter.
22
WATER SYSTEM DESIGN
How does reduced water use effect our water system design?
23
WATER SYSTEM DESIGN
Water Use Demands
BD • used for understanding low flows
• pump station design
• water quality
ADD • used for benchmarking
• water supply (i.e. water licenses)
MDD • infrastructure design
24
WATER SYSTEM DESIGN
Water Use Components
Seasonal
Demand Non-Revenue
Base Demand (irrigation) Water
(Indoor Usage) Average over ADD
(System
Year Leakage)
Seasonal
Demand on Non-Revenue
Base Demand Water
(Indoor Usage) MDD MDD
(irrigation) (System
Leakage)
25
WATER DEMANDS
NRW/Water Losses
Demand
Time
26
WATER DEMANDS
NRW/Water Losses + Base Demand
Demand
Time
27
WATER DEMANDS
NRW/Water Losses + Base Demand + Irrigation
Demand
Time
28
WATER DEMANDS
GREATER VANCOUVER WATER DISTRICT
2003 Peak Week Vs. Winter Week Demand
Totals for GVRD
Winter Week Demand Peak Week Demand
3000
2500
2000
Total Flow (ML/d)
1500
1000
500
NRW
0
24 6 12 18 24 6 12 18 24 6 12 18 24 6 12 18 24 6 12 18 24 6 12 18 24 6 12 18
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
29
WATER DEMANDS
GREATER VANCOUVER WATER DISTRICT
2003 Peak Week Vs. Winter Week Demand
Totals for GVRD
Winter Week Demand Peak Week Demand
3000
2500
2000
Total Flow (ML/d)
1500 ADD
1000
500
NRW
0
24 6 12 18 24 6 12 18 24 6 12 18 24 6 12 18 24 6 12 18 24 6 12 18 24 6 12 18
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
30
WATER DEMANDS
450,000
400,000
350,000 2016
m3/day
2017
2018
300,000
250,000
200,000
Jan
Nov
Mar
Aug
Apr
Dec
May
Oct
Feb
Jun
Sep
Jul
Month
31
WATER SYSTEM DESIGN
Water Use Components
Seasonal
Demand Non-Revenue
Base Demand (irrigation) Water
(Indoor Usage) Average over ADD
(System
Year Leakage)
Seasonal
Demand on Non-Revenue
Base Demand Water
(Indoor Usage) MDD MDD
(irrigation) (System
Leakage)
32
WATER SYSTEM DESIGN
Calculating NRW/Water Losses
• Previously used 10% to 15% of total demand as NRW estimate
• Present day practice is to calculate losses based on infrastructure
Source: Design Guidelines for Rural Residential Community Water Systems, 2012
33
WATER DEMANDS – RESIDENTIAL
Base Demand– Fixture Calculation water efficient fixtures
Demand
End Use Fixture use Use /day Duration Notes
(L/ca/day)
House
29.9 L/c/d 29.9
Leaks
Note: this does
Other AWWA
not include
9.5 L/c/d 9.5
Indoor Use Residential End irrigation usage
Use report, 2016 and municipal
Baths 4.9 L/c/d 4.9
watermain
Dish
2.7 L/c/d 2.7 leakage
Washing
Total
157.2
Indoor Use
WATER SYSTEM DESIGN
Demand Calculations
• Benchmark data
• Fixture calculations
35
WATER SYSTEM DESIGN
Demand Calculations
36
WATER DEMANDS
Analysis of Water Use in New Single Family Homes (3 people / home)
Source: Analysis of Water Use in New Single Family Homes, Aquacraft for EPA, 2011
37
WATER DEMANDS
Residential Indoor Use Vs. Number of Residents
Source: Analysis of Water Use in New Single Family Homes, Aquacraft for EPA, 2011
38
WATER DEMANDS
ICI Demands
• PE
• Fixture counts
39
DESIGN CRITERIA
Example – ICI Demand Design Criteria
Sources:
(1) Master Municipal Construction Document – Design Guideline, 2005
40
WATER DEMANDS – HEATED FLOOR AREA
ICI
41
WATER DEMANDS
ICI - Fixture Count
ICI water demands based on fixture count, have to be developed based on the
specific operation.
42
DESIGN CRITERIA
Fire Flows
• Generally the dependent criteria for sizing water mains
• Can be calculated a number of ways, which can vary
significantly
• Many Lower Mainland municipalities use:
• Water Supply for Public Fire Protection – A Guide to
Recommended Practice, published by Fire Underwriters
Survey; and
• Tables of typical fire flows
44
WATER DEMANDS
(262 L/c/d)
(222 L/c/d)
(139 L/c/d)
45
WATER
• Rainwater Harvesting
46
47
Water Use
at Fixtures
Underground
Cistern
47
March 11, 2011
QUESTIONS
48
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 8: Disinfection and Pipe Hydraulics
CHRIS JOHNSTON
2
KEY TEXT FOR THIS LECTURE (SAVED ON CANVAS)
3
Disinfection 4
Focus of this
discussion
5
IMPORTANCE OF DISINFECTION
6
Objectives of Primary Disinfection 7
Important !
(hint)
9
What Can We Use for Primary 10
Disinfection?
25 97 0.48 11 750
Example CT achieved
reservoir
Water Water
Source Treatment
dedicated line
chlorine Disinfection
sufficient
residual
sufficient
contact time
distribution
system
Flow rate =
10 L/s
chlorine Disinfection
500 m of
200 mm diameter pipe
distribution
system
CT achieved
reservoir
Surface Water Water
Source Treatment
For 500 m
long pipe,
Contact Time
of 26 min
chlorine Disinfection
10 6 1.0
13 > 12 Therefore OK 25.1
for Viruses 1491
20
CT Table, 3-log Inactivation of Giardia
Temperature Free Ozone Chlorine Chloramines
(°C) Chlorine (mg/L * min) Dioxide (mg/L * min)
(mg/L * min) (mg/L * min)
0.5 552 2.9 63 3900
25 97 0.48 11 750
21
A Baffling Revelation 22
The scenario…
• A water system at a mine site
uses two wells to provide
domestic and process water to
several buildings.
• Domestic water use occurs in
one building.
• The challenge: achieve 4-log
virus inactivation.
System Schematic
reservoir
Building where
domestic use
takes place
wells
distribution
system
chlorine Residual = 1
mg/L
reservoir
Building where
domestic use
takes place
wells
distribution
CT not met system
CT achieved
chlorine
reservoir
Building where
domestic use
takes place
wells
distribution
system
CT achieved
chlorine
reservoir
wells
distribution
system
reservoir
chlorine
contact pipe
CT achieved
wells
distribution
Building where system
domestic use
takes place
The scenario…
• Small residential community
water system.
• No treated water storage.
• One chlorine contact tank
installed.
• The challenge: achieve 4-
log virus inactivation.
System Schematic
raw water
storage
contact tank
surface water
source
distribution system
March 11, 2011
System Retrofit Example # 2 32
contact tank
chlorine
surface water
source
Residual = 1 mg/L
CT not met
distribution system
March 11, 2011
System Retrofit Example # 2 33
contact tank
chlorine
surface water
source
Residual = 1 mg/L
CT achieved
distribution system
distribution system
March 11, 2011
Reservoirs 35
Conflicting priorities
• Quantity
Fire
Storage
important
• Stagnation
Emergency
Storage
• Primary
• For drinking
Balancing
Contact
function or Storage • Freshness
Time
byproduct? important
• Avoid conflict
short-
circuiting March 11, 2011
Summary 36
37
SECONDARY DISINFECTION – DISTRIBUTION SYSTEMS
38
BACKFLOW PREVENTION – HIGH WATER USAGE
39
BACKFLOW PREVENTION – ACCIDENTAL OPERATIONS
40
BACKFLOW PREVENTION – DOUBLE CHECK VALVES
41
OUTLINE
42
Simple System
HGL WITH FLOWS
HGL (dynamic)
87 m
Storage Reservoir
- AKA Tank
- Elevations
Model it!
- Geometry
Entrance / Exit
(minor losses)
Static Head (Hs)
(87–13=) 74 m W.C. Bends, Valves & Other Fittings
(minor losses)
35 m Pipeline (friction loss)
- Material, Diameter
Pump
- Elevation
- Pump Curve Demands
- AKA Junctions or Nodes
13 m House - Demand amount and pattern
10 m
River / Lake Bends (minor losses)
0m
- AKA Reservoir - AKA Junctions or Nodes
(Datum)
- Elevation - Elevation
43
SOME EQUATIONS – FROM PREVIOUS PRESENTATION
(Energy Equation)
(Darcy-Weisbach)
(Hazen-Williams)
44
AND MANNING’S EQUATION FOR HEADLOSS
45
FRICTION LOSSES: HAZEN-WILLIAMS, MANNINGS
46
RELATIVE ROUGHNESS AND FRICTION: DARCY-WEISBACH
47
NOMOGRAPHS
48
THE “FAMOUS” MANNING’S WHEEL
49
MINOR LOSSES
HL = K ( V2 / 2g)
50
EQUIVALENT PIPE LENGTHS
51
EXAMPLE – HEAD LOSS CALCULATION
Extra Question:
• Hazen – Williams
• Darcy – Weisbach
• Chezy – Manning
Length = 12 miles
Storage Reservoir
(220 –100) 120 ft W.C.
Static Head
Model it!
- Geometry
(plus fitting losses)
Entrance / Exit
(minor losses)
Bends, Valves & Other Fittings
(minor losses)
53
RELATIVE ROUGHNESS AND FRICTION: DARCY-WEISBACH
54
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 9:
Water System Components Including Valves,
Pipelines, Pump Stations, and Reservoirs
CHRIS JOHNSTON
2
FROM WEDNESDAY’S PUMP LECTURE – PUMP SIZING
3
FROM GRUNDFOS PUMP SIZING WEB SITE – ENTER DESIGN
CRITERIA
4
ENTER DESIGN CRITERIA – SELECT PUMP WITH BEST
EFFICIENCY
5
ENTER DESIGN CRITERIA – REVIEW RESULTS
6
ENTER DESIGN CRITERIA – REVIEW RESULTS
7
ENTER DESIGN CRITERIA – REVIEW RESULTS
8
DEFINITIONS
9
EXAMPLE OF A WATER SYSTEM SCHEMATIC
10
WHISTLER’S EXISTING AND PROPOSED WATER DISTRIBUTION
SYSTEM
11
WATER SYSTEM TOUR
12
http://watersupplysensui.blogspot.com
Pump
Station
Pressure
Reducing
Valve
Pressure Zone 13
Boundary
THE TYPICAL UTILITY TRENCH
14
Pipe Zone Fill Placement
Fill Compaction
Pipe Bedding and Trench Dams
Pavement Restoration – MMCD Standard
Placement of Road Base Material
Road Base Compaction
Asphalt Repair
Rock Removal
Trench Crossing Existing Utilities
Concrete Thrust Blocks
Valve Types
• Gate
• Globe
• Pinch
• Diaphragm
• Needle
• Plug
• Ball
• Butterfly
• Check
• Relief
• Control
• And others…
Gate Valve
• Body: CI (std.) or DI
Principal Types:
Looking into a
1200mm dia High
Performance
Butterfly Valve
Actuators - Hydraulic
31
Pressure Reducing Valve Stations
Pressure Sustaining Valves
- Valve/pilot remain closed until the inlet pressure exceeds the pilot
setting
Installation
of Lake
Intake near
Hudson
Hope BC
Installation of Well in
Squamish BC
37
Reservoirs
SFU
Water
Tower
Provides gravity
flow and storage
to university
To meet PHD.
Also supplies
water for fire
protection
(supplemented
with fire pumps)
38
Bolted Steel tanks
39
Concrete Water Reservoirs
40
Concrete Reservoirs
41
Concrete Reservoir Construction
Water Pump Stations
43
Water Pump Stations
44
Water Pump Stations – Control Panels
45
Water pump Stations
Fitting in to the
Neighbourhood
46
TRENCH AND SITE SAFETY
47
SAFETY
We’re going to go through some construction photos as part of the review of components.
First though, we need to review some trench safety items and confined spaces.
48
Excavation. Trenching and Backfilling
(extract from WorkSafe BC)
Unshored Trench
Stepped Excavation
Small Shoring Cage
Large Shoring Cage (Cambie St.)
Steel Plate and Plywood Shoring
Site Safety and Groundwater
• https://youtu.be/kluzvEPuAug
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 10:
Municipal Water Design Criteria, Detailed Design
Drawings – Water, Standard Drawings, MMCD
CHRIS JOHNSTON
2
OUTLINE
3
SURREY’S DESIGN CRITERIA MANUAL – WATER, JANUARY 2016
4
OUTLINE
5
DETAILED DESIGN DRAWINGS - WATER
6
DETAILED DESIGN DRAWINGS - WATER
7
DETAILED DESIGN DRAWINGS – PLAN VIEWS
8
DETAILED DESIGN DRAWINGS – PLAN VIEWS
9
DETAILED DESIGN DRAWINGS – PROFILE VIEWS
10
DETAILED DESIGN DRAWINGS – PROFILE VIEWS
11
DETAILED DESIGN DRAWINGS – WATER – STANDARD DETAILS
12
DETAILED DESIGN DRAWINGS – WATER – STANDARD DETAILS
13
DETAILED DESIGN DRAWINGS – WATER – STANDARD DETAILS
14
DETAILED DESIGN DRAWINGS – WATER – STANDARD DETAILS
15
DETAILED DESIGN DRAWINGS – DRAWING NOTES
16
Alternatively – MMCD Standard Drawings
18
BURIED GATE VALVES
19
WATER SERVICE CONNECTIONS – RESIDENTIAL VERSION 1
20
WATER SERVICE CONNECTIONS – RESIDENTIAL VERSION 2
21
WATER METER CHAMBERS
22
AIR VALVE INSTALLATION DETAILS
23
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 11:
Municipal Infrastructure Pumping Systems
ROBIN PARKER
AS A JUNIOR ENGINEER, WORK VERY HARD TO UNDERSTAND
THE DETAILS AND MINUTIA OF YOUR PROBLEMS.
2
PUMP TYPES
3
ANATOMY OF A PUMP
4
ANATOMY OF A PUMP
5
PUMP IMPELLERS
6
PACKING AND SEALS – MECHANICAL SEALS
7
PACKING AND SEALS - STUFFING BOX
8
DRAINAGE PUMPS
9
MINE SITE DEWATERING
10
SEWAGE PUMPS
11
RECIPROCATING POWER PUMP
12
END SUCTION PUMP
13
SPLIT CASE PUMPS
(VERTICAL AND HORIZONTAL)
14
HORIZONTAL SPLIT CASE MULTISTAGE
15
SUBMERSIBLE WELL PUMP
• Multistage Pump
• Submerged Motor
• No shaft
• Good for deep wells
16
VERTICAL TURBINE WELL PUMP
17
VERTICAL TURBINE WELL PUMP
18
VERTICAL TURBINE WELL PUMP
19
VERTICAL TURBINE WELL PUMP
20
PUMP CURVES - COMPONENTS
21
PUMP CURVES
22
VARYING IMPELLER TRIM
23
PUMP CURVES – WORKED EXAMPLE
• Components of a Curve
– Speed
– Impeller Diameter
– Efficiency
– Power
– NPSH Required
• Parallel Pumping
• Series Pumping
24
PUMP CURVES – AFFINITY LAWS
Affinity laws
Q2 RPM 2 D2
= =
Q1 RPM 1 D1
2 2
H 2 ⎛ RPM 2 ⎞ ⎛ D2 ⎞
= ⎜⎜ ⎟⎟ = ⎜⎜ ⎟⎟
H1 ⎝ RPM1 ⎠ ⎝ D1 ⎠
3 3
P2 ⎛ D2 ⎞ ⎛ RPM 2 ⎞
= ⎜⎜ ⎟⎟ = ⎜⎜ ⎟⎟
P1 ⎝ D1 ⎠ ⎝ RPM1 ⎠
25
SYSTEM CURVE
26
SYSTEM CURVE
Basic Components
• Static components
o Suction conditions
o Discharge conditions
• Dynamic components
o Pipe friction
o Fittings
o Valves
27
SYSTEM CURVE
Basic Rules
• Be precise
• Be consistent
• Be real
28
BE PRECISE
K vs Cv
Example: “Conventional plug valve” 400 dia. at 300 L/s
• generic K = 0.23, hl = 0.076 m
• Dezurik Cv = 7300, hl = 0.30 m
• Valmatic Cv = 8050, hl = 0.25 m
Use actual lengths, diameters and fittings
29
BE REAL
• Use actual diameters for piping – important in small diameter, long lengths
• Friction losses
30
DETAILED HYDRAULICS – LINE SHAFT
The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted. Restart your computer, and then open the file again. If the red x still
appears, you may have to delete the image and then insert it again.
31
DETAILED HYDRAULICS – LINE SHAFT
32
DETAILED HYDRAULICS – DISCHARGE HEAD
33
SYSTEM CURVE TABLE
Stellat'en
WTP Detailed Design
System Curve
Flow in
Element I.D. Total Flow Element Length "C" "K" "CV" Velocity Delta H
mm L/s L/s m m/s m
SUBM. PUMP 90-1
Discharge elbow 90-1 50 5 2.5 0.37 1.27 0.03
100 PVC Pipe 50 5 2.5 30 140 1.27 1.12
Discharge elbow 82-1 50 5 2.5 0.37 1.27 0.03
100 dia PVC Pipe 50 5 2.5 10 140 1.27 0.37
Tee (Through) 106 5 5 1.28 0.57 0.02
100 dia PVC Pipe 106 5 5 50 140 0.57 0.17
90 degree elbow 106 5 5 0.37 0.57 0.01
100 PVC Pipe 106 5 5 50 140 0.57 0.17
35
PUMP AND SYSTEM CURVES COMBINED
Worked Example
36
HYDRAULIC GRADE LINES
37
HYDRAULIC GRADE LINES
38
NPSHa CALCULATION
Client: Client
Project: Project
Project No: 0
Reference Data
Vapour Pressures of Water
Temp (C) Vap Press Spec Wt Press
(Deg C) (kPa) (kN/m 3) (m H 20)
0 0.610 9.809 0.06
5 0.872 9.810 0.09
10 1.130 9.807 0.12
15 1.600 9.801 0.16
20 2.340 9.792 0.24
30 4.240 9.768 0.43
40 7.380 9.733 0.76
Barometric Pressures
Reference "Advanced water Distribution, Modelling, and Management" by Haested
Elevation Pressure
(m geo) (m H 20)
0 10.3
305 9.97
610 9.63
914 9.3
1220 8.93
1524 8.59
1829 8.26
2134 7.95
2440 7.65
39
WELL PUMP WATER LEVELS
• Bottom of Screen
40
VARIABLE SPEED DRIVES
• Different Types
– Electrical (frequency) (VFD)
41
VARIABLE SPEED DRIVE – WORKED EXAMPLE
• Avg Flow is Qavg, if pumps are run continuously for same total output
42
RELIABILITY AND REDUNDANCY
• What is reliability?
– Unscheduled maintenance
– Operators Hours
43
RESOURCES
http://www.peerlesspump.com/fire_pumps_prod_brochure.aspx
https://product-selection.grundfos.com/sizing-by-application.html?
qcid=157455764
https://product-selection.grundfos.com/sizing-by-application.html?
qcid=157455764
44
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 11:
Pump Sizing Example, Municipal Water Design
Criteria, Detailed Design Drawings - Water
CHRIS JOHNSTON
46
ENTER DESIGN CRITERIA – SELECT PUMP WITH BEST
EFFICIENCY
47
ENTER DESIGN CRITERIA – REVIEW RESULTS
48
ENTER DESIGN CRITERIA – REVIEW RESULTS
49
ENTER DESIGN CRITERIA – REVIEW RESULTS
50
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 12:
Municipal Sanitary Sewer Collection Systems
CHRIS JOHNSTON
2
SANITARY SEWER COLLECTION SYSTEMS
Showing a
properly
connected
sewer
connection on
the right and a
poorly
connected
connection on
the left
3
EXAMPLE: DISTRICT OF NORTH VANCOUVER SANITARY
SEWER COLLECTION SYSTEM
Wastewater flow is collected by “Metro Vancouver” along the shoreline (trunk sewer not
shown) and conveyed to the Lions Gate Treatment Plant for primary treatment (2017). 4
SANITARY SEWER COLLECTION SYSTEMS CONNECT TO MOST
BUILDINGS
The sanitary sewer collection system is mainly
comprised of collection system pipes, manholes,
trunk and interceptor sewers, pump stations,
hydraulic control structures, clean-outs, and
overflow structures.
5
SANITARY SEWER SERVICE CONNECTIONS
6
GIS drawing on left. “Record Drawing” showing actual constructed location on right.
SANITARY SERVICE CONNECTION
7
PUBLIC AND PRIVATE PORTIONS OF SERVICE CONNECTIONS
Red = public portion of service connection, yellow = private portion of service connection
8
TYPICAL DAILY FLOWS IN SEWER COLLECTION SYSTEM
9
DRY-WEATHER, DAILY SEWER FLOWS ARE QUITE PREDICTABLE
10
TYPICAL DIURNAL PATTERNS FOR DIFFERENT LAND USES
11
GLOSSARY OF SANITARY COLLECTION SYSTEM TERMS
12
DESIGN FLOW DEFINITIONS
13
CALCULATION OF SEWER LOADINGS
• Very similar to WINTER (INDOOR) water loadings (most regions assume they are the
same)
• Be careful to not use water loadings that include irrigation amounts. They are NOT
the same.
• Population Equivalents (PEs) are used in the calculation of sewer loads too. Refer to
previous lectures.
• British Columbia sewer loadings range from 165 L/PE/day (high efficiency fixtures, new
construction) to 455 L/PE/day (old standards). Most use between 300 to 350 L/PE/day
in their design criteria.
14
EXAMPLES OF WASTEWATER LOADINGS - GENERAL
15
OTHER HISTORICAL LOADINGS - DETAILED
16
SANITARY SEWER ACRONYMS FOR DRY WEATHER FLOWS
PSF
BSF = ADWF – GWI (also known as ADF in
Flow
some regions)
(BSF = PE s x unit loading)
ADWF
GWI = 0.85 x minimum night flow in dry periods.
4:00 AM +/-
Different types of
Peaking Factor
Formulas
The Harmon
Peaking Factor
Formula is the
most common.
Note whether PF
is multiplied to
ADWF or BSF !
18
HARMON PEAKING FACTOR VERSUS ACTUAL MEASUREMENTS
19
SANITARY SEWER FLOW RESPONSE TO RAINFALL
Blue line = measured flow, green line = ADWF template, red line = resultant RDI&I flow, blue
20
bars = hourly rainfall
I&I Definitions (will be discussed in detail in
Wednesday’s Lecture)
Groundwater
Infiltration Water
(GWI)
Infiltration
Rainfall - Induced
Infiltration (RII)
Rainfall-Dependent
Extraneous Water Inflow and
(I&I) Infiltration
(RDI&I)
Stormwater Inflow
(SWI)
Inflow
Dry Weather Inflow
(DWI)
SEWERS DETERIORATE OVER TIME AND ALLOW RAINWATER,
SNOWMELT, AND GROUNDWATER TO ENTER
22
I&I ENTERING A SANITARY SEWER
23
SANITARY SEWER OVERFLOWS
Sanitary Sewer Overflows (SSOs) can be harmful to the environment and can also
result in health risks to humans and damage to property.
24
SANITARY SEWER OVERFLOWS IN METRO VANCOUVER - 2014
25
COMBINED SEWERS
26
COMBINED SEWER OVERFLOWS (CSO) IN VANCOUVER
27
OUTLINE
28
MANNING’S FORMULA
- Pipe capacities
- Minimum velocities
- Maximum velocities
- Depth of flow
- Minimum slopes
29
MANNING’S “N” VALUES
30
HYDRAULIC ELEMENTS OF CIRCULAR PIPES
31
PIPE NOMIGRAPHS BASED ON MANNING’S EQUATION
32
CALCULATION OF PARTIAL DEPTHS IN CIRCULAR PIPES
33
OUTLINE
34
SURREY’S DESIGN CRITERIA MANUAL – SEWER, JANUARY 2016
35
TYPICAL DESIGN CRITERIA - DEPTHS
36
TYPICAL DESIGN CRITERIA - VELOCITIES
37
EXISTING SEWERS – ALLOWABLE DEPTHS
38
NEW SEWERS – ALLOWABLE DEPTHS
39
MINIMUM PIPE GRADES
40
OUTLINE
41
EXAMPLE FROM TEXT
42
EXAMPLE FROM TEXT – CALCULATION OF FLOWS
43
EXAMPLE FROM TEXT – SIZING PIPES AND CHECKING
HYDRAULICS
44
CITY OF SURREY CALCULATION SHEET
45
THE SCIENCE OF INFLOW &
INFILTRATION
(RECENT PHOTO)
• Inflow
o Stormwater Inflow (SWI)
• Infiltration
o Groundwater Infiltration (GWI)
o Rainfall Induced Infiltration (RII)
▪ RIIFAST
▪ RIISLOW
• Rainfall-Dependent I&I
o RDI&I=RII+SWI
• Total I&I
o I&I=RDI&I+GWI
2
COMMON I&I CAUSES
3
HOW TO MEASURE I&I – SANITARY FLOW MONITORS
4
5
HOW TO MEASURE RAIN – TIPPING BUCKETS
6
7
8
9
10
11
HOW TO CORRECTLY SPECIFY I&I
Examples:
12
13
14
15
DETERMINATION OF RELATIONSHIP BETWEEN RDII RATE AND
SANITARY SEWER AGE (5 TO 10 YEAR AGE-OF-SEWER)
16
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 15:
Piping Systems
(Types of pipes and materials used in municipal infrastructure)
TED STEELE
2
THE PIPING PROJECT TEAM:
3
REFERENCE STANDARDS AND MANUALS
4
Commonly used AWWA Manuals
(Watermains):
– AWWA M11: Steel
Pipe
– AWWA M23: PVC
Pipe
– AWWA M41: Ductile
Iron Pipe
– AWWA M55:
Polyethylene Pipe
– AWWA M9: Concrete
Pressure Pipe
Handbooks from Manufacturer’s Assoc’s
CLIENT AND CONSULTANT REFERENCES:
• MMCD Specifications
(Master Municipal Construction Document)
• MMCD Design Guidelines
• Municipal Supplementary Specifications
(different for each one)
• Experience
7
MUNICIPAL PIPING APPLICATI0NS:
•Water Mains
•Sanitary Sewers
•Sanitary Sewage Forcemains
•Storm Sewers and Culverts
•Casing Pipes (not covered here)
8
PIPE PARTS I – BASIC PIPE
9
PIPE PARTS II – BELL & SPIGOT JOINT PIPE
10
DUCTILE IRON PIPE – PLAIN BELL AND SPIGOT
11
RESTRAINED BELL AND SPIGOT JOINTS
12
PIPE JOINTS – DUCTILE IRON LOCKING JOINT
13
WELDED JOINTS
14
PIPE JOINTS - BUTT FUSION WELDING (HDPE)
15
FLANGED JOINTS
16
PIPE JOINTS - FLANGES
17
PIPE JOINTS –
BACKING FLANGES ON HDPE (HIGH DENSITY POLYETHYLENE)
18
HISTORICAL DEVELOPMENTS IN MUNICIPAL PIPING
20
WOOD STAVE PIPE
21
FACTORS IN THE EVOLUTION OF PIPE MANUFACTURE
22
TYPES OF SEWER PIPING TYPICAL IN MUNICIPAL
APPLICATIONS (IN BC)
PVC
Concrete and Reinforced Concrete
Corrugated Steel
HDPE and Steel (force mains)
23
PVC SEWER PIPE
24
PVC SEWER PIPE - MANHOLE CONSTRUCTION
25
CONCRETE
SEWER PIPE
26
CSP SEWER PIPE (CORRUGATED STEEL PIPE)
27
CORRUGATED METAL PIPE – STORM SEWER
Hugger Band
Coupling
28
TYPES OF BURIED WATER PIPING TYPICAL IN
MUNICIPAL APPLICATIONS (BC)
Steel
Ductile Iron
PVC
HDPE
Pre-Stressed Concrete Cylinder Pipe
29
‘CURRENT’ PIPING EVOLUTION AND INNOVATION’
30
PIPE LOADS AND STRUCTURAL DESIGN
31
PIPE LOADS AND STRUCTURAL DESIGN
• Internal Pressure
• Design stress for materials:
• Load factor or material safety factor
• Cyclic surge design (reduction) – (PVC)
• Design Internal Pressures
• Working Pressure/Surge Pressure
• Factored Pressure
32
33
PIPE LOADS AND STRUCTURAL DESIGN
34
PIPE LOADS AND STRUCTURAL DESIGN
External Loads
• Trench Fill (light weight is an option)
• Road Base, Road Structure
• Foundation Loads from Nearby Structures
• Traffic Loading
• Future Loads
• These loads must be combined with trench
vacuum and hydro-static loads.
35
TRENCH DESIGN
36
BASIC TYPES OF BURIED PIPE CONSTRUCTION (2/4)
37
TRENCH FACTORS FOR EXTERNAL PIPE LOADING
38
TYPES OF TRENCHES - EMBANKMENT FILL
39
40
41
42
CORROSION AND CORROSION CONTROL - WATERMAINS
Vulnerable Piping:
• Metallic piping:
• Steel (long continuously welded lengths)
• Ductile Iron (less corrosive, shorter lengths)
• Copper & bronze
• Causes of Corrosion (buried utilities) –
• Corrosive Soils
• Corrosive Water
• Mixing of metallic materials – (galvanic series)
• Other utility cathodic protection systems
43
CORROSION CONTROL
Exterior:
• Materials Selection
• Coatings
• Tapes
• Isolation from soils (ie bagging)
• Cathodic Protection (impressed current & passive)
Interior:
• Linings (coatings, ie epoxy paints, cement mortar
lining)
• Water Treatment
44
CORROSION AND CORROSION CONTROL
‘Bagging’ of
Ductile Iron Pipe
45
CORROSION AND CORROSION CONTROL
Cathodic
Protection
Test Station
46
CORROSION AND CORROSION CONTROL – SEWERS AND
FORCEMAINS
Vulnerable Piping:
• Steel
• Ductile Iron
• Concrete
• Causes of Corrosion (buried utilities) –
• Same as water mains plus:
• Hydrogen sulphide attack
• Erosion (high velocities with entrained solids)
47
HYDROGEN SULPHIDE ATTACK
– CONCRETE SEWERS
48
PIPE FITTINGS
Corrugated Steel
PVC
HDPE
49
PIPE FITTINGS
Ductile Iron
Tee
Reducer
Test Cap
Restrained Joint
T.C.I.W.
50
PIPE FITTINGS - FABRICATED HDPE, STUB ENDS, SO FLGS
51
PIPE COUPLINGS
Dresser style
Repair Clamp Type
Restrained Couplings
• To restrain pipe movement from
internal pressure
• To maintain pipeline integrity under
seismic loads
52
BOLTED SLEEVE COUPLINGS
53
RESTRAINED COUPLING
54
RESTRAINED CONNECTIONS: JOINTS – COUPLINGS, JOINTS,
FLANGES
55
RESOURCES (KWL):
• Copy of presentation
• Typical Pipe Selection Outline
• List of References
56
CIVIL 409 – LECTURE 15: PIPING SYSTEMS
Questions?
(time permitting)
57
CIVIL 409 – LECTURE 15: PIPING SYSTEMS
MISC PHOTOS
58
CIVIL 409 – LECTURE 15: PIPING SYSTEMS
Casing Pipes?
(time permitting)
59
CIVIL 409 – LECTURE 15: PIPING SYSTEMS
60
PARIS SEWERS
61
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 15:
Municipal Sanitary Sewer Collection Systems – Calculation Examples
CHRIS JOHNSTON
2
Generalized Steps to Designing a Sanitary Sewer System
• Task 1: Obtain the lot layout, tie-in point, and ground surface contours of the area to be serviced by
a sanitary sewer.
• Task 2: determine the minimum service elevation of each lot
• Task 3: Develop a preliminary layout of a sanitary collection system that follows the natural ground
elevation. Add preliminary manholes at junction points. Add pipe and junction names or numbers.
• Task 4: using the surface contour elevation, determine the surface elevation (Rim Elevation) of each
manhole/junction
• Task 5: Using the contour drawing determine tributary areas to each junction/manhole. Add
additional pipes to suit to service low lying lots.
• Task 6: Develop a “Loading Table” (Table 3 below) to calculate incoming flows to each junction. Start
at “Top of the Tree” and work down adding contributing pipe segments.
• Task 7: Setup a “Hydraulic Table” (Table 4 below) to tabulate the pipe hydraulics (Tasks 6 and 7 can
also be combined into 1 table as shown in the City of Surrey’s Table 4.1.1 below)
• Task 8: Set starting elevation of of first pipe to be able to service minimum service elevation of
connecting lots.
• Task 9: Set elevation of downstream pipes to generally follow contour slope but check that other
minimum service elevations can be reached. Check that minimum/maximum depths and slopes are
met. Adjust alignments where necessary.
• Task 10: Determine pipe slopes, velocities, and partial depths. Ensure that values meet design
criteria. Adjust network as required if modifications are necessary
3
Designing a Sewer System
4
EXAMPLE FROM TEXT – TASK 1 - 5
5
Example from text – Task 6: Loading Table
6
TASK 6: LOADING TABLE (METRIC)
7
DESIGN FLOW DEFINITIONS
8
EXAMPLES OF WASTEWATER LOADINGS - GENERAL
9
(MAGNIFIED VERSION PART 1)
10
CALCULATION OF PEAKING FACTORS
Different types of
Peaking Factor
Formulas
The Harmon
Peaking Factor
Formula is the most
common. Note
whether PF is
multiplied to ADWF
or BSF !
11
Example – Task 6 to 10: sizing pipes and checking hydraulics
12
HYDRAULIC ELEMENTS OF CIRCULAR PIPES
13
CALCULATION OF PARTIAL DEPTHS IN CIRCULAR PIPES
14
CITY OF SURREY CALCULATION SHEET
15
SERVICE LATERAL CONNECTIONS
16
Assignment number 2 – designing a sewer system
Sewer Wye
18
OUTLINE
19
20
PLAN VIEW
21
PROFILE VIEW
22
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 17:
Municipal Sanitary Sewer Collection Systems:
Manholes, Pipes, Pump Stations, Sewer Rehabilitation
CHRIS JOHNSTON
2
Sewers in
the
Context
of Buried
Utilities
Gravity Flow
• Sewer depths will be dictated by several
variables including basement elevations,
minimum depth of cover, and costs.
• Other utilities can go over or under – sewer
grades are pretty closely fixed by the depth of
the services and the profile of the sewer
corridor.
Therefore – Sewers take
precedence over all other
services in determining utility
depths and corridors!!!
Health Considerations
Three key design goals:
• Sewer integrity (as for I&I)
• Locate sewers below water mains
• Locate sewers at least 3 meters clear of
watermains
Health Considerations – Cont’d
Where this cannot be done:
• Tape wrap joints on both pipes to a distance
of at least 3 meters in all directions
(minimum)
Field Guide to Sewer Piping (and
pipe selection)
• Corrosion considerations
• Strength considerations (deep bury)
• Availability
• Std. Practice
• Cost: material and labor
Concrete Pipe and Fittings
Resources:
• Ocean Concrete Pipe Products Catalogue (see
sections on hydraulics and loads in the back)
• Langley Concrete Catalogue
• ASTM Standards
Design Parameters
• N= .013 (Manning)
• Joint Deflection (see table in Ocean
catalogue).
Joint Types:
• Bell & Spigot (to 1200 dia)
• ‘Straight Wall’ (1350 to 3050 dia)
Fittings
• Mitred fittings, fabricated
• Fabricated tees and wyes
Concrete
Manholes
– Standard
Concrete
Manholes
– Standard
Concrete
Manholes
– Standard
Concrete
Manholes
– Standard
PVC Sewer Pipe and Fittings
Resources
• PVC Pipe Handbook (Uni-Bell)
• IPEX Catalogue & Supporting Information
Standards
• CSA B182.2 (Sewer Pipe)
• Strength is governed by DR ratio DR 35, DR28
available in smaller diameters.
• Building sewer pipe is different.
Design Parameters
• N= .013 (Manning)
• N is governed by deposition, not by pipe
material.
Other Piping Systems
Brick and Brick Lined Cast-in-Place
Sewers
Forcemains and Siphons
• Often designed using watermain materials for
pressure applications, ie:
– HDPE
– Steel
– PVC C900
Summary of New Terms
• Forcemains
• Siphons
• Manhole Rim
• Manhole Chimney
• Sewer Invert Elevation
• Mitred Bends
• Sewer Wyes
• Crown of pipe
OUTLINE
26
TYPICAL SEWAGE PUMP STATION DESIGN CONSIDERATIONS
North Bluff
Evolution of Sewage Pump Station
Design in B.C.
• influences on pump station design
• 1960’s & 70’s - the first widespread use of
sewage pumping stations in B.C.
• 1980’s - expansion
• 1990’s - regulation
• 2000’s – LWMPs, return period storms,
data management, SCADA, SSOs, sound,
vibration
Example of Data Management
System
HMI / Data
Source
System Levels
7000
4 5
Reservoir Overflow Level (6800 mm)
6000
5000
Inflow (L/s)
4000
Minimum Reservoir Level for Fire Storage (4000 mm) 2 15
Level
(mm)
3000
2000
1000 0 25
Sun Mon Tue Wed Thu Fri Sat Sun
Feb 01 Feb 02 Feb 03 Feb 04 Feb 05 Feb 06 Feb 07 Feb 08
Wet Well Low Alarm (600 mm)
Date
0 1998 1998/03/31 09:57
Time
C:\email\prmfiles\syslevel.PRM 1999 1999/03/03 23:26
Pump Rooms
55
Pump
Rooms
56
Wet Well
Design
57
Good Neighbour Policy
• Odour control – no
detectable odours
• Acoustic mitigation –
no louder than
background noise
• Aesthetically pleasing
58
Modern Day Pump Stations
59
OUTLINE
60
Age of Sewer Database
Sewer Age vs RDI&I Rate (0-100 years)
DETERMINATION OF RELATIONSHIP BETWEEN RDII RATE AND SANITARY SEWER AGE
5 to 100 Year Age-of-Sewer
350,000
0.0325x
y = 12,355e
2
R = 0.9013
300,000
Peak 1-hour 100-year RDI&I Rate (L/Ha/d)
200,000
150,000
54 Independent Basins
in CRD and GVRD
100,000
50,000
0
0 10 20 30 40 50 60 70 80 90 100
Age (years)
Kerr Wood Leidal Associates Ltd. Catchment Value Expon. (Catchment Value) Figure 3
Sewer Age vs RDI&I Rate (0- 40 years)
S A N I T A R Y S EW ER A G E V ER S U S R A I N F A L L -D EP EN D EN T I & I R A T E
5 to 4 0 Ye a r A g e -o f-S e w e r
200,000
P eak 1-h o u r, 100-year RDI&I (L /Ha/d )
180,000
R e l a ti o n sh i p U si n g A l l D a ta
160,000 0.0325x
y = 12355e
140,000
120,000
100,000
80,000
60,000
40,000 R e l a ti o n sh i p U si n g O n l y D a ta u p to 4 0 Ye a rs
y = 542x + 12,418
20,000 2
R = 0.4177
0
0 10 20 30 40 50 60 70 80 90 100
A g e (y e a rs)
F i g u re 4
Note: the I&I Rate would be the RDI&I rate plus GWI
Estimated I&I Design Rates
OUTLINE
66
Sanitary Sewer Rehabilitation
• ASSESS I&I
• Summary of FIELD work
• REHABilitation to address defects
• MONITOR the response after rehab
• Calculate the REDUCTION in I&I
I&I Reduction - InfraGuide
Flow Monitoring
Identify I&I Sources
Field Investigations:
– CCTV inspection
– MH inspection
– Smoke & dye testing
Status of
Evaluation and
Rehabilitation
Efforts
CCTV: Sewer Condition Rating
Manhole Condition Assessment
Smoke & Dye
Testing
Identifies sources of inflow
(cross-connections,
connected roof leaders, pipe
defects where rainwater may
enter the system)
Field Investigations
CCTV
Smoke/Dye
Lateral Inspections
• Assess condition
• Confirm material
CUES LAMP II
Field Investigation Results
Work Program
Work Program
Sewer System Rehabilitation
Typical Project:
Goal-based Approach
Tier I
Trenchless Technologies:
- Pipe Bursting
Manhole Sealingb
2
Odour Problems
• Odours can be
found anywhere in a
wastewater system!
• Operational
headache and
nuisance:
• odour complaints from the
public.
• potential safety issues to
O&M staff.
Odour Problems
• Combination of:
• High flow rate of air from one section colliding with air in
a downstream section that has a lower air flow rate.
• Storm displacement
Developing Solutions
Measure Odour
Gases Sources
• Odour Control
Treatment
Technology
Identify Odour Understand
Air Flow
and/or System Model
Dynamics and • Size and
Corrosion Geometry and Hydraulics
Displacement Location
Complaints Components
• Geometry and
Configuration
Measure
Pressures
Odour and Air Management Study
0.300
Pressure (inches of
• An effective odour control and air 0.200
management study includes:
Differential
0.100
H2O)
0.000
• Monitoring program (H2S, VOCs, -0.100
differential air pressure).
-0.200
-0.300
• Ventilation modeling (areas of
pressurization, air flow rates,
ventilation dynamics, release 20.0
H2S (ppm)
points).
10.0
• Hydraulic modeling (displacement
effects).
0.0
Development Planning
Odour
Problems
Odour
Problems
27
Background
Proposed Odour Control Facility
• An odour control facility was proposed at this location to
actively draw the air out of the system, treat it, and discharge
it to the atmosphere.
28
Sewer Ventilation Dynamics 29
30
Fan Testing Results - What We Want to See
0.300
0.200
0.100
Differential Pressure (inH2O)
9,000 cfm
0.000
-0.100
3,000 cfm
6,000 cfm
Fan Off
Fan Off
-0.200
-0.300
14:00 16:00
Stephens Scotia Glen 1750 RPM 1500 RPM 1200 RPM
900 RPM 750 RPM 600 RPM 300 RPM 150 RPM Fans Off
31
3,000 cfm
6,000 cfm
11,000 cfm
7,000 cfm
11,000 cfm
8,000 cfm
7,000 cfm
6,000 cfm
3,000 cfm
15,000 cfm
Fan Testing Results - What We Saw
Target
32
Desktop Investigation 33
sdf
34
The Hypotheses
Hypothesis 1
• The sewer separation program is allowing odours from the
interceptor’s to travel into the new storms sewer pipes and
being discharged through the various storm connections
(catch basins, rain water leaders etc.)
Hypothesis 2
• The stormwater component was serving to dilute the
wastewater and increasing its velocity through the system,
thereby decreasing the amount of odour generation.
35
The Questions - Hypothesis
• How is the odour escaping from the sewer system?
• Through the separated storm sewer system.
36
OUTLINE
37
FATS, OILS, AND GREASES (FOG)
38
Courtesy: Gloucester Department of Public Utilities, VA
39
FOG REDUCES CAPACITIES AND CAN CAUSE SSOS AND FLOODING
40
Food Service
Establishment
(FSE)
44
NEW ISSUES: FLUSHABLE WIPES THAT AREN’T FLUSHABLE!
45
46
47
48
49
50
51
52
53
54
OUTLINE
55
PHARMACEUTICALS AND WASTEWATER
56
57
58
59
60
61
62
63
SUMMARY
64
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 19:
Municipal Stormwater Systems – Overview and SWM
Evolution
CHRIS JOHNSTON
3
THE EVOLUTION OF STORMWATER THINKING
4
THE FAMOUS SCARBOROUGH GOLF COURSE
5
SCARBOROUGH (CONT.)
6
7
TIA DEFINITION
• Total Impervious Area (TIA): The total area of all impenetrable surfaces (paved
surfaces, building roofs and areas sealed from the underlying soils) in a
watershed.
• These surfaces force rainwater to runoff into the collection system without
infiltrating into the soil.
8
LET’S LOOK AT ALL OF THE RAINFALL EVENTS!
9
EXAMPLE OF EXCEEDANCE-DURATION-CURVES
COMPARES CHANGE IN FLOWS OVER VARIOUS DEVELOPMENT SCENARIOS
10
INCREASED EROSIVE FORCES
11
WASHINGTON STATE RESEARCH
12
THE TIA – B-IBI RELATIONSHIP!
Linear (%TIA)
45
Expon. (%TIA)
40
35
B-IBI
25
15
10
0 10 20 30 40 50 60 70 80
%TIA
13
NATURAL CONDITIONS
14
Courtesy May, U of W
DEVELOPED CONDITIONS
15
Courtesy May, U of W
ote: no runoff when
N
land is undeveloped
16
IMPERVIOUS AREAS IMPACT AQUATIC HABITAT
17
IMPACT OF IMP. AREAS ON STREAM HEALTH
18
19
WASHINGTON RESEARCH (CONT.)
Impact of Research
Not only is erosion from the full spectrum of all rainfall events important in
reducing downstream property damage, but the increased energy due to land
development is also significantly damaging fish habitat and wild salmon
populations.
20
MAJOR SWM TURNING POINTS - SUMMARY
2 Major Developments:
1. Scarborough Law Suit (1989): Upstream changes in the watershed carry downstream
consequences not only during major storm events, but during all rainfall events. You must
understand the impact of these changes as it relates to the erosive energy being generated.
2. Washington State Research (1997): The changes in watershed impervious cover has a direct
impact on the benthic community in downstream watercourses and streams. With as little
as 10 - 15% TIA, significant impacts can be measured. Land development without source
controls will degrade fish habitat.
21
A SHIFT TO INCORPORATING “SOURCE CONTROLS”
22
RAIN GARDENS
23
ROADS – OLD DESIGN STANDARD
24
ROADS – NEW DESIGN STANDARD
Silver Ridge,
Maple Ridge
25
DISCONNECTED ROOF LEADERS
26
ROOF TOPS – TRADITIONAL DESIGN
27
ROOFTOPS – GREEN ROOFS
28
BARRIERS TO IMPLEMENTATION
The thirst for raised curbs continues to provide a barrier for source
controls on roadways
29
BARRIERS TO SOURCE CONTROL IMPLEMENTATION (2013)
Although the Lower Mainland now has numerous source control examples,
source controls are still not in the mainstream.
Barriers Include:
• Raised curbs with gutters and catch basins: we just can’t seem to let these
things go. They still have their place, but they’re in a minority of applications.
• Rain garden maintenance: we seem to have busted through the cost issue
except when it comes to who pays for the annual maintenance of rain gardens.
30
BARRIERS TO SOURCE CONTROL IMPLEMENTATION (2013)
Barriers (cont.)
• Stormwater re-use regulation: provincial and federal regulation and building /
plumbing codes prohibit the use of stormwater for re-use.
32
OBJECTIVES OF RAINWATER MANAGEMENT
• Route urban runoff safely from upland areas through lowland areas to a
receiving water
33
PLAN COMPONENTS
34
DESIGN CRITERIA – MANAGING RISK
35
WHITE ROCK – JUNE 8, 1999
36
KEY HYDROTECHNICAL ANALYSIS TASKS
• Rainfall
• Runoff
• Routing
• Risk
• Mitigation
37
SUGGESTED DESIGN CRITERIA
Capture
frequently Slow runoff Reduce TSS & Provide Safe
occurring Reduce peak flows contaminants Passage
rainfall
• 72% of 2-year,
• 6-month • 90% Average • 5/10 year
24-hour event
• 2-year Annual Runoff • 100 year
(this is the
• 5-year • 200 year
estimated 6- • 80% of TSS
• (10/100 year) • Climate Change
month storm)
38
RISK AND LEVEL OF SERVICE
• 5/10 year to 100 year return periods: route safely above ground to receiving
waters (overland flow routes, major drainage system components, and
detention ponds)
• Maximum Probable Flood: not used in stormwater, but used for dam design
39
TYPICAL TASKS
2. Flood Conveyance – Minor Systems: Route minor urban runoff safely from site
through existing areas (usually up to the 5 to 10 year storm events)
3. Flow Rate Control: Mitigate post-development flow rates prior to creek
discharge to ensure that flows don’t exceed existing conditions (usually means
developing a detention pond with outlet control scheme)
4. Flood Conveyance: Major Systems: Route major urban runoff safely above
ground through existing areas (usually 100-year storm using roads and
dedicated easements)
40
SOURCE CONTROLS
Design infiltration features into the development that meet the Flow Volume
Reduction target (i.e. rainfall capture target)(example: White Rock: 72% of 2-year,
24-hour duration rainfall = 29 mm rainfall)
41
ROUTING FLOWS – MINOR EVENTS
• Need to route 5-year or 10-year flows into drainage/piping system and check
capacities
42
MAJOR STORM EVENTS
Need to determine the route that every drop of water is taking and ensure that all
flows up to the 100-year return period are safely moved to the receiving waters.
In some cases, a major trunk sewer may be required. Also, additional storage may
be needed to match pre-development conditions
43
OUTLINE
44
DRAINAGE COMPONENT: COURSE CONTENT
45
Civil 409 - Drawings, Specs, and Contracts 1
Outline:
1. Design Drawings
• Essential Components
• Plan & Profile
• Details
2. Specifications
• Standard
• Supplemental
3. Contract Documents
• Contract
• Tender/Contract Documents
Design Drawings
February 2019
Civil 409 - Drawings, Specs, and Contracts 4
Drawing Components
February 2019
Civil 409 - Drawings, Specs, and Contracts 5
Design vs Reality
February 2019
Civil 409 - Drawings, Specs, and Contracts 6
Design vs Reality
February 2019
Civil 409 - Drawings, Specs, and Contracts 7
Drawing Components
February 2019
Civil 409 - Drawings, Specs, and Contracts 8
Location
Basic Information:
Owner
Project
Engineer
Revision
Drawing Components
February 2019
Civil 409 - Drawings, Specs, and Contracts 9
Drawing Components
Survey Control
February 2019
Civil 409 - Drawings, Specs, and Contracts 10
Drawing Components
Existing information such as: topo, buried utilities and
features relevant to constructing the works February 2019
Civil 409 - Drawings, Specs, and Contracts 11
Drawing Components
Proposed information
February 2019
Civil 409 - Drawings, Specs, and Contracts 12
Scales
Drawing
Components February 2019
Civil 409 - Drawings, Specs, and Contracts 14
Dimensioning:
Proposed
Existing
Property Line
Drawing
Components February 2019
Civil 409 - Drawings, Specs, and Contracts 15
Notes:
• Specs, MMCD
• Existing Utilities
• Traffic
• ESC
• Special
Drawing Components
February 2019
Civil 409 - Drawings, Specs, and Contracts 16
Drawing Components
Revisions February 2019
Civil 409 - Drawings, Specs, and Contracts 17
Contract
February 2019
Civil 409 - Drawings, Specs, and Contracts 22
Tender Documents
• What – describe the work
• Who – define the owner, contractor,
engineer/contract administrator
• Price – list quantities, rates, prices, measures of
payment
• When – define schedule, milestones
• How – specifications, traffic management,
access, hours of work, etc.
Tender Documents
February 2019
Civil 409 - Drawings, Specs, and Contracts 23
Tender Documents
February 2019
Civil 409 - Drawings, Specs, and Contracts 24
Common Formats
• Master Municipal
Construction Documents
(MMCD)
• Canadian Construction
Documents Committee
(CCDC)
Invitation to
Tenderers
February 2019
Civil 409 - Drawings, Specs, and Contracts 26
Instructions to
Tenderers February 2019
Civil 409 - Drawings, Specs, and Contracts 27
The Tender
(Bid) February 2019
Civil 409 - Drawings, Specs, and Contracts 29
General Conditions
February 2019
Civil 409 - Drawings, Specs, and Contracts 31
Standard Specifications
February 2019
Civil 409 - Drawings, Specs, and Contracts 33
Questions?
February 2019
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 21:
Municipal Stormwater Systems – IDF Curves, Time of
Concentration, Rational Method, Design Storms
CHRIS JOHNSTON
2
OUTLINE
3
IDF Curves
• Intensity Duration Frequency (IDF) Curves
• Derived from historical data sets of continuous
rainfall data (20 to 100 years…but sometimes less)
• An IDF analysis summarizes the maximum rainfall for
any given year in each duration period then runs a
statistical analysis on the annual maximums to derive
a curve for each return period.
• Typical Distributions include: Gumbel (EV1)(Env.
Canada), Log Pearson Type III (U.S.)(LP3), and
possibly the Generalize Extreme Value (GEV).
Let’s Look at All of the Rainfall Events! 5
Published IDF Curves
(typical of West Coast Canada)
summer
Intensity
winter
Duration
2 hrs
Seasonal IDF Curves
(typical of West Coast Canada)
Winter Data
Intensity
Summer Data
Duration
2 hrs
IDF Statistics
Selecting an Intensity and Return Period
11
Time of Concentration
CALCULATING TC AND FLOW
Q = CIA
Where “I” is the
rainfall intensity Tc Intersection =
@ the current Tc Upstream Tt + To
(To + all Tt s)
Tc Street = Upstream Tc
13
Overland Flow Min and Max Times
OUTLINE
15
Rational Method
• Q = RAIN (or Q=CIA in imperial units)
• where:
– Q is in cms
– R is the runoff coef. (0 to 1)(see table)
– I is the rainfall intensity mm/hr (from IDF curves)
– A is the tributary area in hectares
– N is 0.00278
• typically used for small basins up to 20 ha.
Urban Hydrology
Flow = Surface Runoff + Interflow + Groundwater Flow
Rational Formula
Runoff Coefficients
Rational Formula Example Calculation
Q = CIA
Where “I” is the
rainfall instensity Tc Intersection =
@ the current Tc Upstream To + Tt
Point B
Point A
Point B: QBLOCK = RAIN = (0.6)(15,000/10,000 ha.)(28mm/hour@24 min)(0.00278) = 0.07 cms (70 L/s)
21
A - Lot 0.06 0.6 0.036 0.036 10 10
A B Pipe 1.5 0.6 ? ? 15 25
23
OUTLINE
24
Design Storms
• Design storms are a statistical simplification of
the rainfall patterns that occur at a location
• used in hydrologic modeling
• popular sources:
– AES, Huff, Chicago, SCS distributions
26
Selection of Distribution
• Determine purpose of modeling exercise:
Peak flow? Volume? Velocity-duration
distribution?
• Consider hydrologic nature of area being
modeled (size, land use, etc.)
• Choice of distribution will influence peak flow
and possibly volume estimates
Typical Lower Mainland Design
Storms
• Atmospheric Environment Service:
– published by Federal Gov’t
– 1 hour distribution (also used for 2 hr)
– 12 hour distribution (also used for 6 hr)
– statistically represents >1 return period
• Application:
– run all durations (usually 1, 2, 6, 12, 24) available
through the model and select the ‘worst case’
peak flow or volume for design
SCS Method
n SCS (1973) adopted method similar to DDF to develop dimensionless rainfall
temporal patterns called type curves for four different regions in the US.
n SCS type curves are in the form of percentage mass (cumulative) curves based on
24-hr rainfall of the desired frequency.
n If a single precipitation depth of desired frequency is known, the SCS type curve is
rescaled (multiplied by the known number) to get the time distribution.
n For durations less than 24 hr, the steepest part of the type curve for required
duraction is used
38
DRAINAGE ASSIGNMENT: (ASSIGNMENT NO. 2)
Your group is a consulting engineering team again. You are writing a report to your client who is a
developer in Deep Cove.
You group will develop a Master Drainage Plan (MDP) for an area of Deep Cove in the District of
North Vancouver. You will assume that the existing drainage infrastructure doesn’t exist except
for the Gallant Creek Culvert under Deep Cove Road and under Gallant Ave. The plan should
develop the conceptual layout to convey minor and major storm events, as well as identify the
facilities and source control measures to protect the downstream aquatic habitat. To do this, each
group will need to complete the following:
Task No.1: Select on-site source control measures to the capture lot and road surfaces to the
“Volumetric Reduction Criteria”. In this case, assume the volumetric reduction criteria is 72% of
the 2-year, 24-hour rainfall. Produce a plan drawing showing the location of the on-site control
measures (Note: please develop measure that can relate to “typical” housing configurations and
road widths. Assume that all roads have a cross-fall and drain to one side (your choice)).
39
DRAINAGE ASSIGNMENT: (ASSIGNMENT NO. 2 CONT.)
Task No.2: Develop and size a storm sewer network to convey the minor storms (5-year return
period). Use the rational formula to size the storm sewer. Produce a table similar to Table 5.3.14
in the Surrey Design Criteria Manual (January 2016). Show a plan drawing of the storm sewer
showing manholes, pipes, diameters, contours, and invert elevations. However, in this case, you
will use the climate change IDF curves rather than the historical IDF curves. Use the “Lynn Creek
Task No.3: Develop major overland flow routes and major storm collection trunks (100-year
storm). Show the direction of flow arrows on every street following the contours. Show sufficient
arrows such that the reader can clearly understand where the major flows are going. If the 100-
year storm is to be picked up by a major storm trunk, show the connection and trunk sewer. Show
where the major flow connects with the receiving water. Include the 100-year design flows in the
table described above using the Rational Method.
Task No. 4: Size a detention pond using the EPA SWMM5 model and design rainfall events in the
Surrey Design Manual (January 2016). Use the design criteria laid out in the Surrey Design Manual
(January 2016) Section 5.2.1c. Assume the “pre-development” 5-year flow rate is 0.007 cms/ha (7
L/s/ha). You do not have to model the pre-development flow, just the post-development flow.
Assume that the source controls are full and not functioning under the 5-year post-development
flow. 40
DRAINAGE ASSIGNMENT: (ASSIGNMENT NO. 2 CONT.)
Task No 5: Develop a “Class D” Capital Cost estimate for your “Stormwater Management Plan”.
Include pipes, manholes, detention pond(s), and source controls. Summarize in a table.
Task 6: Undertake the detailed design of a 250 m section of the new drainage pipe. Select a 250
m section of drainage pipe that connects to your detention pond and produce a plan and profile
drawing of the new pipe.
Bonus Task (extra marks): Size the pond assuming the source controls are functioning under the
5-year storm. Can the size of the detention pond be reduced? Are there any other measures that
can be added to the source controls to reduce the size of the detention pond? If the C-factors can
be reduced by 20% and the overland flow component of the Tc increased by 5 minutes as a result
of the source controls, could the size of the storm sewers be reduced? What savings can be
realized by the cost of the source controls?
41
STUDY AREA – DEEP COVE
42
COST ESTIMATING TABLE – USE THIS FORMAT
43
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 22:
Municipal Stormwater Systems – Source Controls: Lot and
Streets
CHRIS JOHNSTON
2
Major SWM Turning Points - Summary 3
Linear (%TIA)
45
Expon. (%TIA)
40
35
B-IBI
25
15
10
0 10 20 30 40 50 60 70 80
%TIA
Impact of Imp. Areas on Stream Health
7
Low Impact Development
An innovative, ecosystem-based
approach to land development and
stormwater management
A Shift to Incorporating “Source Controls”
DEFINITIONS
There are a variety of terms used around the world to describe stormwater practices that try to
mimic pre-development, and more natural hydrology. Below are some of the terms that are
used in B.C.
Low Impact Development:
“The term low impact development (LID) refers to systems and practices that use or mimic natural
processes that result in the infiltration, evapotranspiration or use of stormwater in order to
protect water quality and associated aquatic habitat.” USEPA
Source Controls:
The “systems” can include Source Controls. Source Controls can include absorbent landscapes, bio
retention facilities (including rain gardens), vegetated swales, pervious/porous pavers and
pavements, infiltration trenches, and green roofs. Source controls can also be referred to as on-
site BMPs.
Best Management Practices (BMPs)
The practices can be referred to as Best Management Practices . There are both structural and
non-structural BMPs and can include every stormwater best practice including source controls,
street sweeping, water quality ponds, oil/grit separators,etc. 10
‘Better’ Stormwater Management Practices
To reduce
infrastructure costs
To make our
communities more
attractive
Primary Goal of LID
Amended
Soils Open
Drainage
Rain
Rain Barrel
Gardens
Createa aHydrologically
Create Hydrologically Functional
Functional Lot Lot
Conventional Approach
Centralized
Control
Pond
LID Design
24-hour Rainfall (mm)
0
10
20
30
40
60
50
1999 Jan 01
1999 Jan 17
1999 Feb 02
1999 Feb 18
1999 Mar 06
1999 Mar 22
1999 Apr 07
9
1999 Apr 23
1999 May 09
1999 May 25
1999 Jun 13
Rainfall
1999 Jun 29
Date
1999 Jul 15
1999 Jul 31
1999 Aug 16
less than 36 mm of rain
1999 Sep 01
0% of rainfall events are
24 HOUR RAINFALL TOTALS FOR SOUTH SURREY
1999 Sep 17
1999 Oct 03
1999 Oct 19
1999 Nov 04
1999 Nov 20
1999 Dec 06
1999 Dec 22
Selecting Rainfall Capture Targets
6-Month Storm: 72 % of 2-year 24 hour storm
(covers approx. 90 % of all 24hr. Events)
Silver Ridge,
Maple Ridge
Rain Gardens
Disconnected Roof Leaders
Roof Tops – Traditional Design
Rooftops – Green Roofs
Anticipated Runoff Reductions
Conventional Low Impact
Good Drainage
Conventional Functional Landscape Design
Seattle’s Street Edge Alternatives Program
Disconnectivity
Soil Amendment
Soil aeration
machine
Development at
Redmond Ridge, where
soils were amended to a
depth of 12 inches.
Construction Impacts on Soils
Rain Barrels, Cisterns and Storage Tanks
Permeable Pavement
Terracing
Pervious road boulevards
Pervious driveways
Narrower Roads
Innovative ditches
Innovative ditches
Construction Cost Comparison
51
How Do Rain Gardens Work?
Example
Surface Runoff to
Rain Garden
• Recommended Maximum
Impervious / Pervious (I/
P) Area Ratios
• Source: Metro Vancouver
Source Control Design
Guidelines 2012
How Do I Calculate Capture amount?
Intensity-Duration-Frequency (IDF) Curve • Select local IDF
curve
• Pick intensity at 24-
hour duration for 2-
year storm
Intensity (mm/hr)
Input Volume:
1. Evaporation
• Tributary Area x Capture
Rainfall Amount = Volume
(cu.m.)
2. Growing Medium
Capture Volume (sum):
3. Rock Pit
1. 24 hour evaporation x
surface area
2. Volume of growing
medium x (field capacity –
4. Infiltration wilting point)
Input Volume should equal 3. Volume of rock pit x
available water content
capture volume 4. 24 hour infiltration x
(assume dry soils i.e. moisture surface area
content at wilting point)
Selecting the Soil Type
From www.waterbalance.ca
Example: Port Moody Parking Lot
62
Using Metro Vancouver Design Charts
• Released May
2012. Available on
Metro Vancouver
web site.
www.metrovancouver.org
• Provides a series
of design charts
and guidelines for
design of source
controls
Application of Simplified Design Approach 64
Design Variables:
v Rainfall
v Capture Target
v Subsurface Soil
Infiltration Rate
v Thickness of Growing
Media (Absorbent
Soil)
v I/P Ratio
Using Metro Vancouver Design Charts
I/P ratio = 8
infiltration rate = 1 mm/hr
Result: 57% annual capture
0.5 m rock trench depth
Adding an orifice to
low permeable
soils can increase
the annual
rainfall capture
target by
mimicking
natural
infiltration rates
Adding a Orifice to the Design
I/P ratio = 8
infiltration rate = 1 mm/hr
Result: 96% annual capture
72
Rain Garden Design Considerations
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
1. Design Criteria 74
• Protect water
quality
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
1. Design Criteria - Capturing Rainfall
Rock Pit
4. 24 hour infiltration
x surface area
Size for dry soils
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
Infiltration
1. Design Criteria – Proper Sizing
• Continuous Simulation
Or Typical Year
Rainfall
• SWMM models
• Water balance models
• Simplified Sizing
Charts/Equations
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
2. Impervious/Pervious Ratio
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
2. Impervious/Pervious Ratios
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
3. Distributed In-Flows 80
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
4. Curb Edge 83
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
5. Rain Garden Depth 84
Include sediment
accumulation storage
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
6. Topsoil Selection 85
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
7. Trees & Shrubs
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
Growing Medium
Rock Pit
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
Infiltration
9. Rock Trench Depth & Soil Infiltration Rate
• Water does infiltrate into
rock, clay, and glacial till…
just very slowly.
• focus on small storms
Soil Saturated
Type Hydraulic
Conductivity
(mm/hr)
Evaporation
• Size to capture
design rainfall
depth
• Assume empty
Growing Medium
at start of rain
event
Rock Pit
• Limit drain
Size for dry soils
time to 4 days
Infiltration
10. Flow Direction Of Infiltrated Water 91
Copyright © 2013 Kerr Wood Leidal Associates Ltd. All rights reserved.
93
Proposed SWM Strategy for Lots <5% Slope
Example: Port Moody Residential Lot –
Mitigating the Impervious Surface
21 m
Port Moody 6-month rainfall event
25 m x 76.8 mm (2-yr, 24 hr) = 55mm
72%
Assume dry conditions, and the pervious area does not need to be mitigated
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 23:
Municipal Stormwater Systems – Design Criteria and Flood
Routing, Climate Change
CHRIS JOHNSTON
2
Stormwater Design Criteria
Flow Volume Flow Rate Water Quality
Flood Conveyance
Reduction Control Treatment
4
EXAMPLE OF SURREY STORMWATER CRITERIA
Note Missing Flow Volume Reduction and Water Quality Treatment Criteria
5
Let’s Look at All of the Rainfall Events! 6
Rate Control
Volumetric
Reduction
Control
OUTLINE
7
Example: Port Moody Parking Lot
10
RATE CONTROL CONCEPTS
Design a control
structure and pond
system to mimic
the shape and
peak flows of pre-
development
conditions
11
RATE CONTROL FACILITIES
12
MULTIPLE CONTROLS ARE USUALLY USED
13
Stormwater Design Criteria
Flow Volume Flow Rate Water Quality
Flood Conveyance
Reduction Control Treatment
15
OUTLINE
16
WATER QUALITY TREATMENT
17
STORMWATER QUALITY
18
EXAMPLE OF STORMWATER QUALITY – NON POINT SOURCE
19
TYPICAL MUNICIPAL CONTROLS / SOLUTIONS
21
EXAMPLE: LOST LAGOON WETLAND – STANLEY PARK
24
DEVELOP SUB-CATCHMENTS FOR EACH PIPE LENGTH
25
ANALYZE / DESIGN MINOR/MAJOR PIPE SYSTEM
26
DEVELOP MAJOR OVERLAND DRAINAGE PATHS
27
IDENTIFY AREAS WHERE MAJOR OVERLAND FLOW ROUTES ARE
TRAPPED
28
MAJOR OVERLAND FLOW ROUTES
29
MAJOR OVERLAND FLOW ROUTES (CONT)
30
MAJOR OVERLAND FLOW ROUTES (CONT)
31
Stormwater Design Criteria
Flow Volume Flow Rate Water Quality
Flood Conveyance
Reduction Control Treatment
33
STORMWATER PIPE VELOCITIES AND GRADES
34
SURCHARGING OF SEWERS
35
STORMSEWER DEPTHS
36
PIPE JOINTS AND EXFILTRATION
37
MANHOLES
38
CATCH BASINS
39
CATCH BASIN SPACING
40
SERVICE CONNECTIONS
41
OUTLINE
42
What are the Global Circulation
Models Saying?
• There are many different climate models coupled
with many different model runs under many
different model scenarios.
• Most models can predict seasonal and total
precipitation and changes within a grid cell. Some
can predict maximum daily precipitation difference.
• It is difficult for GCMs to predict changes in
intensities within a 24-hour period
• However, approximations can be used based on
historically based rainfall relationships
Regional Climate Modelling
Results of 2008 Climate Modeling
Estimated Change in • This example uses an
Precip. From Climate older CRCM 4.2.0 driven
Modelling by the CGCM3 using the
Event Avg. Change A2 GHG emission
year 2050 (%) scenario
Avg. Ann.
24-hour
• Study area selected
+ 17%
Precip. were the grids within
Total
the Metro Vancouver
area
Annual + 14%
Precip. • Same analysis can be
Source: Vulnerability to Climate Change done for any region
Report, Metro Vancouver, March 2008
IDF Climate Change Tool
• Western University has developed an online tool that
uses EC IDF curve information and the predicted
precipitation changes from available Global Climate
Models to scale the rainfall intensities and produce
future IDF curve estimates for various greenhouse
gas emission scenarios.
• We seem to be using the RCP 8.5 greenhouse gas
emission scenario
• www.idf-cc-uwo.ca
Historical IDF Curves - National
IDF Under Climate Change Scenarios
Median - 2050
Climate Change Comparisons - 2050
Compares to
276 mm from
Historical IDF
Curve (24%
increase)
IDF Equations
Other
Comparisons:
Abbotsford
What is the Historical Rainfall Data
Saying?
• By analyzing long term rainfall trends, it may be
possible to see if climate change is already
happening
• Two studies were done for Metro Vancouver on this
subject. The first in 2002, and then an update in
2007. (Development of GVRD Precipitation Scenarios,
Metro Vancouver, October 2002 (KWL) and GVRD
Historical and Future Rainfall Analysis Update, Metro
Vancouver, August 2007 (PCIC)
Current Trends in Existing Data Sets
Rainfall Rise in Significant
Trends in
Duration Trends (mm/hr/
century)
Historical
5 min 34-64 Annual Max.
10 min 17-46 Rainfall
15 min 14-38
30 min 5-20 Intensity
1 hour 4-10 Records (PCIC,
2 hour
6 hour
4-7
3
2009)
12 hour 2-3
24 hour 2
Source: Vulnerability to Climate Change Report, Metro
Vancouver, March 2008
Example of IDF Changes - VA28 -
Kent Pump Station (Vancouver)
As intensities
increase, IDF curves
will shift, and
previously infrequent
events will become
more frequent
August 1
3/14, 200
9
Impact on Existing Infrastructure:
Kent Pump Station Vancouver
Surface Runoff to
Rain Garden
CHRIS JOHNSTON
2
OUTLINE
3
Rainfall – Runoff Computer Modelling
Goal: Develop a
computer simulation
model that can
accurately predict
runoff
MAJOR STORMWATER COMPUTER MODELS
Watershed Modelling
Ø XP-SWMM
Ø EPA SWMM 5
Ø Mike Urban
Ø Qualhymo (Water Balance Model)
Ø PCSWMM
Ø HYDSYS
Ø Sewer Gems
Ø Info SWMM
Computer Model Results
Example Model - PCSWMM
Example Model - PCSWMM
OUTLINE
10
THE “SWMM” ENGINE - USEPA
12
THE BASICS OF SWMM MODELING
13
THE NON-LINEAR RESERVOIR AND THE “WIDTH” PARAMETER
14
15
GENERATING RUNOFF AND INTERFLOW
Pervious
Runoff
Interflow - Fast
Interflow - Slow
16
PCSWMM EXAMPLE: NODE
17
PCSWMM EXAMPLE - PIPE
18
PCSWMM EXAMPLE - OUTFALL
19
PCSWMM EXAMPLE – CATCHMENT AREA
20
PCSWMM EXAMPLE – CATCHMENT AREA (CONT)
21
PCSWMM EXAMPLE – CATCHMENT AREA (CONT)
22
IMPORTANT SWMM NOTES – ALWAYS REVIEW OUTPUT FILE
• Always check output file and review water balance continuity and other summaries
• Were the results as expected?
• Is there a continuity error?
• Is the runoff making it to the outfall?
• Is flow leaving the system?
• Are pipes surcharged?
• Does the rainfall amount of the design storm x area = the volume that left the outfall?
23
OUTLINE
24
Stormwater Design Criteria
Flow Volume Flow Rate Water Quality
Flood Conveyance
Reduction Control Treatment
Design a control
structure and pond
system to mimic
the shape and
peak flows of pre-
development
conditions
27
RATE CONTROL FACILITIES
28
DETENTION POND SIZING PROCEDURE
29
Develop Pipe and Node Model
Generate Design Storm
Surrey
Design
Storms
(5-year
Storm
Example)
Produce Hydrograph
Input Hydrographs into Spreadsheet
Build Design Calculations in Spreadsheet
Detention Pond Design 36
37
OUTLINE
38
WHY USE RAINWATER HARVESTING?
OVERVIEW
WHAT IS RAINWATER HARVESTING
AND WHAT ARE PURPLE PIPES?
DESIGN CONSIDERATIONS
SOME EXAMPLES
40
RAINWATER HARVESTING
WHAT IS IT?
IT IS THE COLLECTION OF RAINWATER
AND
STORMWATER MANGEMENT
FOR NON-POTABLE USES
TOILET FLUSHING
LAUNDRY IRRIGATION
41
HOW DOES IT WORK?
Rainwater
Collection
Water Use
at Fixtures
Underground
Cistern
42
Rainwater Harvesting Around the World
DRINKING WATER PROTECTION ACT
44
DRINKING WATER PROTECTION ACT & REGULATION
45
RELEVANT CODES,
REGULATIONS & BYLAWS
47
CROSS CONNECTION BY-LAWS
Why an Air-Gap?
Mostly due to the wording in the Drinking Water Protection Act
Remember: rainwater, grey water and reclaimed water are equal
This means the purple pipe system feeding the toilets and laundry must
be pressurized with a pump even if using potable water
48
RAINWATER HARVESTING SYSTEMS
DESIGN CONSIDERATIONS
OK NOT OK OK
WATER USAGE
49
Water Demands – Residential
BASE DEMAND– FIXTURE CALCULATION WATER EFFICIENT FIXTURES
Demand
End Use Fixture use Use /day Duration Notes
(L/ca/day)
Clothes
56.8 L/Load 0.3 17.0
Efficient Washing Note: this does
Washer Machine
not include
irrigation usage
Showers 7.6 L/min 0.7 7.8 min 40.7 WaterSense and municipal
watermain
leakage
Faucets 5.7 L/min 20 15 s 28.5 WaterSense
House
29.9 L/c/d 29.9
Leaks Current Allowable Usage:
Other
157 – 24 = 133.0 L/c/d
9.5 L/c/d 9.5 AWWA
Indoor Use Residential End
Use report, 2016
Baths 4.9 L/c/d 4.9 Future Allowable Usage?:
133 – 17 – 40.7 = 75.3 L/c/d
Dish
2.7 L/c/d 2.7
Washing
Total
157.2 50
Indoor Use
DESIGN CONSIDERATIONS
ROOF AREA & ROOF TYPE
51
DESIGN CONSIDERATIONS
STREAM BASEFLOWS
53
Theoretical 6 Story Office Building
2500m2 Building Footprint
750 Employees
72% of the 2 Year 24hr Rainfall Depth = 40mm
Total Rainfall Volume = 125m3
Pre-Development Runoff Volume = 90m3
Base Flow Requirement = 5.4 m3/d
4.5 m3/d is Flushed
Minimum Storage Volume Requirement = 35m3
54
Can This Meet the SW Capture Criteria?
Rainwater
Collection
Water Use
at Fixtures
Underground
Cistern
59
OUTLINE
60
Drawing Components
61
Design vs Reality
62
TYPICAL TRENCH BACKFILL - DRAINAGE
63
TYPICAL MANHOLE DETAIL
64
TYPICAL CATCH BASIN STANDARD DRAWINGS
65
TYPICAL RESIDENTIAL CROSS-SECTION
66
TYPICAL RESIDENTIAL DETENTION POND STANDARD DETAIL
67
TYPICAL DETENTION POND CONTROL STRUCTURE
68
UBC Civil 409
Municipal Infrastructure
Cost Estimating
1
Beginning an Estimate
1. PURPOSE: Determine the purpose and
desired accuracy.
(Options, Scoping, Approval, Budgeting, Tender)
2. ACCURACY: Check desired accuracy against
level of project definition.
3. METHODS: Determine an estimating method.
4. DOCUMENT: Complete and document the
estimate.
2
Estimate Classifications
• Once you have the definition complete, select
a class.
• Two typical classification systems
3
Treasury Board of Canada
Cost Estimate Classification System
• Class 'D' (Indicative) Estimate
– to be in unit cost analysis format (such as cost per m² or other measurement unit)
– based upon a comprehensive list of project requirements (i.e. scope) and assumptions
4
AACEi Classification System
5
Variation in Estimate Accuracry
6
Estimating Methods
• Capacity Factored, Parametric
• Equipment Factored, Parametric
• Assembly Level / Developed
• Detailed Unit Costs
7
Equipment Factored Estimate
y = 2.7383x
District Energy Plant Capital Cost Prediction R² = 0.9151
Major Equipment Factor Development
$4,000
$3,500
$3,000
$2,500
Balance of Plant Cost (Thousand CAD)
$2,000
$1,500
$1,000
$500
$0
$0
$200
$400
$600
$800
$1,000
$1,200
$1,400
Major Equipment Cost (Thousand USD)
8
Parametric Capacity Example
• The cost curve function would have a family of
curves
• Adjust for
– Year
– Region (labour costs)
– Power supply type
– Pressure class
– Etc.
9
Parametric Example – Pump Station
10
Assembly Example
• Estimate the cost of pipe per lin.m
• If you don’t have past data, you can build the
estimate from first principles, by each
component
• Build uncertainty into the sum to produce an
assembled value +/- a percent
11
Assembly Example – Pipe Trench
12
Detailed Unit Costs
• Based on quantity take-offs from drawings
13
HDPE Pipe Stored in a Yard
14
Material Supply Quotes
• The budgetary quote from the
supplier is not what the client
will pay. You need to add:
– Freight
– Storage if necessary
– PST (7%)
– Subcontractor markup,
General contractor markup
(5%, 10%)
– Overage (10% of quantity,
material depending)
15
Labour and Construction Equipment
(Construction Crews)
• Common method to cost is to develop daily
crew rates.
16
What Is In a Crew?
17
Traffic Control
18
Trenching Crew
19
HDPE Fusing Crew
20
HDPE Fusing Crew
21
Construction Equipment Costs
• Bare – vehicle only
– Add operator
– Add fuel allowance. Fuel tax for construction
equipment is different than consumer fuel prices
in B.C.
– Servicing allowance - markup to estimate, or built
into the equipment cost
– Remote site may need a mobile shop
• Sum of the above is called the All-Found Rate
22
Trenching Crew
Example
Hrly Daily
CrewC1 TRENCHING Qua Daily Hr Rate Rate
CrewC1 Small Excavator 1 8 $80 $640
23
Equipment Cycle Time
• When building a crew, balance it to minimize idle
and waiting.
Example
• Excavator can load 100 m3/h, based on material,
operator experience, bucket size, excavator size.
• Truck has 5 minute return loop, can hold 10 m3
• How many trucks do you need to balance the
crew?
24
Crew Balance Example
A Excavator Rate 100m3/h
B Truck Capacity 10m3
C Time to Load Truck 6min A/B
D Truck Return Trip 5min
E Total Truck Cycle 11min C+D
0.18hr
F Production Rate/Truck 55m3/hr B/E
G Num Trucks 2
H Total Truck Rate 109m3/hr FxG
25
General Markups / Adders
• Tax
• Currency Effects
• Engineering
• Location
• Mob/demob (indirects)
• Bonding/Insurance
26
Markups
• Engineering (8-25%)
– Pre-design, detailed design, construction management
• Location Factor (depends)
– Difficult access, no services, special treatment (parks)
• Mobilization / Demob (5-10%)
– Major centre, standard equipment vs specialty
equipment
• Bonding & Insurance (5%)
27
Construction Site Indirects
28
29
30
Rebar (ironworker) Crew
31
Formwork Crew
32
Taxes
• Understand the tax regime local to the project
• In Canada/BC G.S.T. is a flow through tax –
exclude it from the estimate.
• In BC P.S.T. is charged on goods purchased to
fulfill a contract: equipment and materials but
not the labour to install it.
33
Currency / Escalation / Inflation
• Always state the currency and year of the
estimate
• Adjust past values for currency
• Adjust past estimate values to current year.
– Bank of Canada consumer price index (simple but not
good for construction)
– RSMeans Construction Cost Index or other trade
publications (better, specific to construction)
• Adjust for expected escalation, or explicitly state
you haven’t (escalation is an economist’s job, you
need one to do it!)
34
Contingency
• Contingency is Expected to be Spent
• It covers the things you don’t know, but you
have a reasonable expectation they will be
there.
• Not a management reserve.
• Not a proxy for accuracy.
35
Contingency
• Contingency items include
– Planning and estimating errors and omissions;
– Minor price fluctuations (other than general
escalation);
– Design and scope changes; and
– Variations in market and environmental
conditions.
36
Recommended Contingency Values
With no better information the following are
typical contingency ranges for civil infrastructure
projects:
38
Estimate Accuracy
• Careful when stating an accuracy. At least give it
bounds (+/-)…Liability
• Be transparent. If you state the accuracy,
describe the method you used to calculate it.
• Methods
– Monte-carlo simulation
– Certainty factors
– Past experience, engineering judgement, guidelines…if
this is your method do not state the accuracy.
39
Basis of Estimate
• This where you document the majority of your
assumptions
• Provides guidance and limitations on the
purpose, use, and classification
• May provide a statement about the accuracy
of the estimate (careful with this)
40
Basis of Estimate Outline
1. Classification, Purpose, and Use of Estimate
2. Estimate Scope (what’s included, excluded)
3. Currency, Escalation, Inflation
4. Estimating Methodology
1. Construction Period and Approach
2. Markups
3. Taxes
4. Labour Rates
5. Equipment Rates
6. Construction Crews
7. Production Rates
8. Freight
9. Insurance and Bonding
10. Mobilization/Demobilization
11. Engineering and Construction Management
5. Contingency and Risk
6. Estimate Accuracy
7. Summary of Costs 41
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 27:
Municipal Stormwater Systems – Working Through a
Practical Example
CHRIS JOHNSTON
2
PRACTICAL EXAMPLE
A house is being tom down and replaced with a larger house. The Impervious
area is increasing dramatically throughout the City.
This increase in impervious area will increase the flows on downstream
infrastructure and eventually cause flooding if not properly addressed.
The city decides that they want to implement detention tanks and source controls
on all new re-developed lots to maintain the hydrologic condition od the existing
conditions. (meaning all new impervious areas will be mitigated)
How big is the storage tank to mitigate the impact for a 10-year storm?
How would you approach this problem?
3
Previous Development
New Development
APPROACH
Assuming a computer model like SWMM is not used, and the Rational Formula
was dictated by the Municipality, the approach would go something like this:
• Use the rational method to determine the flow for each time step based on
design storms.
• Size an orifice and detention tank that is large enough to control the larger
flows from the post-development condition (larger house) to the existing-
development condition and check across all design storm durations.
• How big is the tank? What is the size of the orifice?
6
Runoff Coef. and Areas:
10-year Storm
Compare with Surrey Runoff
Coefficients (FYI)
Lon LaClaire
Director of Transportation 1
Vancouver will be the greenest city
in the world by 2020
2
THE CITY OF VANCOUVER
POPULATION 630,000
SQUARE MILES 45
SQUARE KILOMETERS 112
3
METRO VANCOUVER
MUNICIPALITIES 21 +2
POPULATION 2,500,000
A REGION CONSTRAINED BY
GEOGRAPHY
4
CORPORATE STRATEGIC INITIATIVES
55
THE FREEWAY NEVER BUILT
6
1997
TRANSPORTATION PLAN
No increase in
capacity for cars
Priorities
Walking
Cycling
Transit
Goods Movement
Cars
7
MORE TRIPS CITY DOWNTOWN
FEWER CARS
+18% +75%
POPULATION POPULATION
+16% +26%
JOBS JOBS
-5% -20%
VEHICLES ENTERING
CITY VEHICLES ENTERING
CITY
8
HOW HAVE ADDITIONAL TRIPS BEEN ACCOMODATED?
10
SUCCESS
> 2/3
13
#2 ZERO TRAFFIC-RELATED FATALITIES BY 2040
14
Annual Fatalities Per 10,000 Daily Walk-To-Work Trips
PEDESTRIAN SAFETY COMPARISON
15
:L NAC W PL LN ;N M 2JM LTCB L N 3LNAC 8LM P L :P P P A . & ) & 1 B 1C SSS P PA EA A . & : 1C SSS AC ELR
Annual Fatalities Per 10,000 Daily Bike-To-Work Trips
CYCLING SAFETY COMPARISON
Health
Safety
Accessibility
Affordability
Economy
Public Life
Environment
Resiliency
17
17
LAND USE
support
shorter trips &
sustainable
transportation
choices
18
INTEGRATING LAND USE & STREETS
19
IMPORTANCE OF GOOD URBAN DESIGN
&
WALKING
make walking
safe, convenient
& delightful
support a vibrant
public life
21
CYCLNG
make cycling safe,
convenient,
comfortable & fun for
people of all ages &
abilities
22
Rule of thumb
• Health
• Safety
• Accessibility
• Environment
• Affordability
• Community
Reduce car speeds & Physically separate users
volumes
• Resiliency
2
4 Photo: Ben Johnson
IMPROVING INFRASTRUCTURE, INCREASING RIDERSHIP
One Plan,
Bike volumes acrossMultiple Objectives
the Burrard Bridge jumped 30% to over 1.3 million
annually in the first year after the Burrard-Cornwall improvements
• Health
• Safety
• Accessibility
• Environment
• Affordability
• Community
Cycling is the
fastest
growing
Annual total cycling trips
mode share
in the city
Total cycling
trips
increased
32% from
2014 to 2015
increase capacity
ensure service is
fast, frequent,
reliable &
comfortable
27
PAST INVESTMENTS IN RAPID
TRANSIT : YIELDED BIG DIVIDENDS
Ridership spiked
during the 2010
Olympics…
but growth
continued!
&
PAST GROWTH:
Has Occurred Along Rapid Transit Lines
2011
Source: data from Regional Growth Strategy, 2011, map from Regional Transportation Strategy, 2013
&,
FUTURE GROWTH:
Will Continue Along Rapid Transit Lines
2041
Source: data from Regional Growth Strategy, 2011, map from Regional Transportation Strategy, 2013
OUR TRANSIT
SYSTEM IS FULL
On Broadway,
1000s of people
passed by
overcrowded
buses every day,
despite buses
every 2 minutes
in the peak
31
Broadway subway = 20 lanes
of people-moving capacity on opening day
(Ultimate capacity = 56 lanes)
* If everyone taking the train on opening day instead drove in single occupancy vehicles, it would require an additional 24 lanes.
MOTOR VEHICLES
33
GOODS &
SERVICES
support a thriving
economy & major
port while
reducing impacts
ensure effective
emergency
response
34
MOBI
BIKESHARE
1.5M+ km travelled
(37x around the
world)
35
BIG MOVES
THE EXISTING NETWORK
)
Burrard Inlet
Northeast False Creek – Location
Canada Place
English
Bay
Downtown Gastown
West End
DTES
Rogers Arena
Chinatown
BC Place Strathcona
Science World
Granville Olympic
Island False Creek Village
History of the
viaducts
False Creek: 1890
The Freeway Era: 1971
The Freeway Era: 1971
The Freeway Era – Cut Short: 1972
The Freeway Era – Cut Short: 1972
Pre-Expo: 1980s
Vancouver: 1980s to Today
1982 2012
1979
2003
2011
BIG MOVES
THE PROPOSED NETWORK
()
DRAFT AREA PLAN
(
Andy Livingstone Park / Creekside Park Extension
Draft Concept
Andy Livingstone Park / Creekside Park Extension
Draft Concept
Andy Livingstone Park / Creekside Park Extension
Draft Concept
Dunsmuir Elevated Park
Main Street Blocks
Main Street Blocks
Draft Concept
Other City Projects – Arbutus Greenway
BURRARD BRIDGE
55
GRANVILLE BRIDGE TODAY
56
GRANVILLE BRIDGE WITH TWO LANES
REALLOCATED
Ridership in Metro Vancouver vastly
outperforms cities of similar size
Annual
City Metro Population
Annual
Annual
Boardings
Rides
(thousands)
Boardings / • Ten peer cities
Capita
Denver
DenverVancouver
Metro 2,645,209
2,313,328
2,645,209 363,163
86,659.7
86,660 157/capita
33/capita
of similar size in
Pittsburgh the US and
Pittsburgh
Portland 2,360,733
2,289,800
2,360,733 113,728
65,464.0
65,464 50/capita
28/capita
Vancouver
Canada (±300k)
Metro Vancouver
Denver 2,313,328
2,313,328
2,645,209 363,163.0
363,163
86,660 157/capita
33/capita
Charlotte
Charlotte
Pittsburgh 2,296,569
2,296,569
2,360,733 26,411.6
26,412
65,464 12/capita
28/capita
Portland
Portland
Cleveland 2,289,800
2,289,800
2,063,535 113,727.7
113,728
48,153 50/capita
23/capita
Metro
San Antonio
Vancouver
San Antonio
2,234,003
2,234,003 47,147.1
47,147 21/capita
has higher
Orlando
Orlando
2,223,674
2,223,674 29,364.2
29,364 13/capita ridership than 9
Sacramento
Sacramento
2,196,482
2,196,482 27,280.6
27,281 12/capita of these peer
Cincinnati
Cincinnati
Charlotte 2,128,603
2,128,603
2,296,569 16,356.9
16,357
26,412 8/capita
12/capita
cities
Cleveland
combined
Cleveland
Kansas City 2,063,535
2,063,535
2,038,724 48,152.7
48,153
16,507 23/capita
8/capita
Kansas City
Kansas City
Cincinnati 2,038,724
2,038,724
2,128,603 16,506.5
16,507
16,357 8/capita
Source: American Public Transportation Association 2012 Q4 Ridership Report
Metro Vancouver is the fourth most transit-
oriented region
Annual
City Metro Population
Annual Boardings
(thousands)
Boardings / • Among best in
Capita
Washington,
San FranciscoDC
Bay 5,860,342
6,349,948 456,915
476,219 78/capita
75/capita • 4th in per capita
Boston
Chicago 4,640,802
9,522,434 399,594
658,203 86/capita
69/capita
ridership
behind only
Metro Vancouver
Philadelphia 2,313,328
6,018,800 363,163
336,981 157/capita
56/capita
New York,
Philadelphia
Los Angeles 6,018,800
13,052,921 336,981
620,903 56/capita
48/capita
Montreal and
Source: American Public Transportation Association 2012 Q4 Ridership
Report, CUTA 2012 Transit Fact Book
Toronto
Highest growth in walking, cycling,
and transit trips across Canada
% Growth in Walking, Cycling, and Transit Trips to Work from 2006 to 2016
60%
+12.0% +20.7%
+7.1%
50%
40%
-4.3%
30%
-5.9%
+0.1% -2.4%
20%
-10.3%
10%
0%
Saskatoon Edmonton Winnipeg Calgary Ottawa Toronto Montreal Vancouver
Winston Chou
Traffic & Data Management
City of Vancouver
Background
Background
What is Congestion?
35 600,000
34
Traffic Related Fatalities
32
30
30 500,000
25 26
Population
25 25 25 25
400,000
23
20 21
19 19 300,000
15 16 16
15 15
14
13 13 13 200,000
10
9
5 100,000
0 0
1998
2008
2017
1996
1997
1999
2001
2002
2003
2004
2005
2006
2007
2009
2010
2011
2012
2013
2014
2015
2016
2018
Priority Goals
GOAL 2: Improve Road Safety
Manage congestion by
improving reliability on major
arterial streets to protect
neighbourhoods from
shortcutting
CAMBIE
BROADWAY
Priority Goals
GOAL 3: Efficient & Smart Transportation System
Priority Goals
GOAL 3: Efficient & Smart Transportation System
Congestion Management Strategy
There’s going to be
congestion this
afternoon…
3000
2000
1000
0
2014 2015 2016
Utilities Filming
Priority Goals
GOAL 4: Coordinate Street Use
Motor V ehic le
O c c upants
26 %
P edestrians
Motorc yc lists
11% 59 %
Motor V ehic le
O c c upants
9 7% C yc lists
4%
C o llis io ns F a ta litie s
S ourc es: V P D T raffic F atality D ata ( 20 12- 17) , IC B C C ollision D ata ( 20 12- 17)
S usta ina b le Mo d e S ha re
Tre nd s & Ta rg e ts
75% 6 7%
Transit Walking
12%
50 %
50% 44% 7%
22%
40%
4% 27%
3%
15% 16%
33%
25%
22% 23%
16%
0%
2008 2011 2016 2040 Target
For all t rip s b eg inning or end ing in t he Cit y of Vancouver. Source: 20 0 8 & 20 11 T ranslink T rip D iaries, 20 13- 20 16 C ity of
V anc ouv er P anel S urv ey s ( ex c lud ing rec reational trips) , T ransportation 20 4 0 m od e share targ ets.
R id ing a bic yc le s ho uld
no t re q uire brave ry
11
Image: www.protectedintersection.com
Protected Intersections:
A Design Approach, Not a Template
Image: www.protectedintersection.com
Image: www.protectedintersection.com
Image: www.protectedintersection.com
Image: www.protectedintersection.com
Hornby & Pacific
Routing on red phase
CoV Initiatives …
Burrard Bridge
The Burrard Bridge is a major gateway
between Downtown Vancouver and the
western part of the City.
Pre-2009: Shared Sidewalks
Burrard Bridge
Burrard Bridge – 3 Stages of Improvement
0.8
0.6
Burrard Bridge:
Percent women cycling
0.4
2012 33%
2014 38%
0.2
0
2010 2011 2012 2013 2014 2015
12 Month Rolling Total
Burrard Bridge
Rolling Total
2016/2017 – Bridge Repair and
Burrard Pacific Intersection Upgrade
Burrard Bridge – Addressing a Collision Hotspot
Before Project
Burrard at Pacific
Before Project
Burrard at Pacific
Burrard & Pacific Safety Issues
Reallocating a Vehicle Lane to Pedestrians
Burrard Bridge North End Widening
Vancouver’s Next Protected Intersection
Wayfinding challenging
10 th
10thAve Health
Avenue
Precinct
Corridor
Street Health Precinct:Health Precinct
Challenges and Opportunities
Project
Improvements
…but w hat c an w e do
about it?
W here can w e g et
s pac e?
10th Ave Health
Precinct
Street Emergency Service Implications
Improvements
10th Ave Health
Precinct
Street Emergency Service Implications
Improvements
10th Ave Health
Precinct Developing Concepts:
Street
Improvements
1-way Motor Vehicle Circulation?
Laurel N
Willow
Broadway
10th
Heather
Oak
Cambie
Ash
Laurel S
11th (service)
10th Ave Health
Precinct Developing Concepts: Vehicle Circulation
Street
Improvements
2-way Oak to Willow
Cambie
Willow
Oak
Broadway
10th
Concept #1
(one-way section only)
10th Ave Health
Precinct Developing Concepts:
Street
Improvements
Bi-directional South Side Section
Concept #2
(one-way section only)
10th Ave Health
Precinct Developing Concepts:
Street
Improvements
Uni-directional Section
Concept #3
(one-way section only)
10th Ave Health
Precinct Developing Concepts:
Street
Improvements
Bi-directional – which side?
Nort h Sid e
P otential C onflic ts : 156 0 30 8 0
14 30 310 0
S outh S id e 4 80 + 490 +
P otential C onflic ts :
Laurel N
Willow
Broadway
ER
Cambie
BCCA Res.
11th (service)
Laurel S
Heather
Ash
10th Ave Health
Precinct Developing Concepts:
Street
Improvements
Uni-directional Section
Winner
10th Ave Health
Precinct
Street 10th Avenue Health Precinct Process
Improvements
Seniors,
P ers ons w ith D is abilities ,
V anc ouver C oastal H ealth,
and
B C C anc er
W ere No t On Bo ard
10th Ave Health
Precinct
Street General Feedback
Improvements
10th Ave Health
Precinct
Street 10th Avenue Health Precinct Process
Improvements
10th Ave Health
Precinct
Street 10th Avenue Health Precinct Process
Improvements
Reb oot ,
R eprioritiz e,
R efram e
10th Ave Health
Precinct
Street
Health Precinct Collaborative Process
Improvements
Com p rom ise:
S R W and Trees
10th Ave Health
Precinct
Street
Separate Travel Modes
Improvements
10 Act ions
10th Ave Health
Precinct
Street
10 Actions
Improvements
Laurel N
Willow
Broadway
10th
ER
Oak
Cambie
11th (service)
Laurel S
Heather
Ash
10th Ave Health
Precinct
Street Raised Intersections at Willow and Heather
Improvements
Rendering: NACTO
3. Enhance Pick- up /
D rop- off A reas
10th Ave Health
Precinct
Street Increased / Re-designed Pick-up / Drop-off
Improvements
10th Ave Health
Precinct
Street Passenger Loading & Bus Stops
Improvements
Double
Spaces
10th Ave Health
Precinct Passenger and Bike Volumes at
Street Pick-up / Drop-off Zones
Improvements
10th Ave Health
Precinct
Street Passenger Loading & Bus Stops
Improvements
7th
Heather
Broadway
10th
Cambie
Oak
12th
Yukon
Alder
14th
There w ere 69 vehicle collisions rep ort ed
on 10 th A venue in the H ealth P rec inc t that
involved people w alking or c yc ling in the
past 7 years ( 20 0 9 to 20 15) .
T he re c o m m e nd e d d e s ig n wo uld
have e lim ina te d o r m itig a te d 70 %-
9 0 % o f the s e c o llis io ns , inc luding the
1/4 related to on- street parking and 1/4
related to turn c onflic ts at O ak S t and
10 th A ve.
Based on City of Vancouver analysis of detailed descriptions documented in ICBC data that
records collisions that involved people walking or cycling on 10th Ave in the Health Precinct.
10th Ave Health
Precinct
Street 1st Phase Complete
Improvements
10th Ave Health
Precinct
Street 1st Phase Complete
Improvements
10th Ave Health
Precinct
Street 1st Phase Complete
Improvements
10th Ave Health
Precinct
Street 1st Phase Complete
Improvements
Central Valley Greenway
Quebec Street and W 1st Avenue
Before Project
Quebec at 1st
After Project
Quebec at 1st
Before Project
Quebec at 1st
After Project
Quebec at 1st
10th Ave Policy and Funding
S a fe ty Im p rove m e nts
Safety
Improvements Knight and Marine Drive
Safety
Improvements Knight and Marine Drive
Safety
Improvements Knight and Marine Drive
Access improvement
10th Ave Policy and Funding
U P C O MIN G :
G ra nv ille B rid g e
A B rid g e D e s ig ne d fo r F re ew ay s tha t we re
N eve r B uilt
Mo to r V e hic le V o lum e s ove r F a ls e C re e k B rid g e s
p er lane d uring b usiest t im es
2000
Motor Vehicles per Lane per
750
ext ra cap acit y.
500
250
0
Burrard Granville Cambie
2018 Average AM Peak Hour Northbound
2018 Average PM Peak Hour Southbound
Theoretical Capacity per Lane
Burrard Bridge = 2 lanes in each direction. Granville Bridge = 4 lanes in each direction. Cambie Bridge = 3 lanes
C ha lle ng e s :
Ped est rian Accessib ilit y
C ha lle ng e s :
Uncom fort ab le U ns ig naliz ed P edestrian C ross ing s
C ha lle ng e s :
No B uffer F rom H ig h- S peed & H ig h-V olum e Traffic
C ha lle ng e s :
No Ded icat ed & Prot ect ed Sp ace for Biking
P ro p o s e d G o a ls
• Albert Shamess
– Director – Waste Management and Resource Recovery
– City of Vancouver
• Over 30 years of experience in Solid Waste Management
• Worked in over a dozen countries worldwide
• Only Canadian designated as an International Waste
Manager by the ISWM
• In Vancouver since 2012
• Contact – albert.shamess@vancouver.ca
2
Agenda
• Questions
3
Waste Management in Context
4
Historical Context
Modern Systems
Not so Historic photos
New Delhi
• City of Vancouver
– Collection
– Transfer station and Vancouver Landfill
– Street cleaning
8
Regional Waste System at a Glance
Simplified
City of Vancouver
Vancouver Landfill
(owned and operated by CoV)
~750kT ashes
Waste to Energy
Other municipalities of (Burnaby)
the Region
280kT
USA
~70kT
9
Solid Waste Facilities in Metro Vancouver
10
Collections
11
Garbage and Green Bin
• Utility funded (user fees)
• Labour ~ 60 staff
• Equipment ~ 40 trucks
• 110,000 single family properties
• 34,000 tpy garbage
• 50,000 tpy organics
Collection Costs
• Garbage bins
Bin size 2019 2018 2017
75 L $83 $84 $75
120 L $96 $96 $86
180 L $112 $114 $102
240 L $129 $131 $117
360 L $163 $165 $148
• Green bins
Bin size 2019 2018 2017
120 L $126 $119 $111
180 L $148 $140 $130
240 L $170 $161 $150
360 L $214 $203 $189
13
Recycling
15
Public Realm Cleanliness
https://www.youtube.com/watch?v=aF1V00W3LbI
https://www.youtube.com/watch?v=fZyPKxEWnDM
18
Vancouver South Transfer Station
19
Weigh Scales
• Materials planned:
• Roll-out flexible plastic packaging
• Motor oil and antifreeze
• Hard plastic products
21
Fun Recycling Facts (2017)
• 32,000 mattresses
– if stacked ~ 3 times the height of Whistler
22
Vancouver Landfill
23
Vancouver Landfill
Location: Delta
Began operations: 1966
Total property: 320 hectares
Landfill footprint: 225 hectares
Annual Operating Budget: ~$17.5M
Annual capacity 750,000 TPY
Number of Staff: Approx. 70
24
Landfill Gas Collection System – Jan 2018
25
Landfill Gas Collection
26
Landfill Gas Utilization
27
Fill Phases and Progressive Closure
28
Landfill Progressive Closure
29
Environmental Management - Water
30
Environmental Management - Monitoring
31
Environmental Management - Bird Control
Regulatory requirement
• Raptors
• Whips
• Pyrotechnics
• Pistols firing blanks
• Decoys
32
A Unique Environment
Bird house
33
Zero Waste Strategy
34
Obstacles to Zero Waste
35
Reducing Waste to Disposal
Paper
MIXED
Other Waste 7% Plastic
17%
WASTE
11%
RECOVERY
Compostable
Construction Organics
C&D & Demolition
24%
RECOVERY 40%
Sources: Metro Vancouver 2016 Solid Waste Management Annual Summary; Metro
Vancouver 2017 Multi-family Waste Composition Study; Metro Vancouver 2016 Solid
Waste Composition Report; Metro Vancouver 2015 DLC Waste Composition Report
36
Current Situation
37
Zero Waste 2040
38
Priority Actions
39
Diversion Opportunities
3 streams Current situation (VLF only) Business Cases Underway
Source ?
• ~50kTonnes under contract with • Composting and/or digestion with
Separated Enviro Smart RNG production
Organics
40
Diversion Opportunities
41
Strategic Approach
42
Why a Single-Use Item
Reduction Strategy
43
Areas of focus
44
Questions?
45
MUNICIPAL
ENGINEERING DESIGN
Civil 409 – Lecture 33:
Municipal Stormwater Systems – Culverts
CHRIS JOHNSTON
2
OUTLINE
3
FINAL EXAM
FINAL EXAM
5
OUTLINE
6
Basic Hydraulics: Culverts – I
Example:
D = 42 in.
Q = 120 cfs
Roadway Crest
Inlet Control
Top of Culvert
36
DESIGN OF CULVERTS FOR FISH PASSAGE
37
EXAMPLE OF FISH PASSAGE CRITERIA
38
OUTLET POOL AND TAILWATER
39
BAFFLES
40
BAFFLES (CONT.)
41
CULVERT VELOCITIES AND FISH
42
OUTLINE
43
US MINISTRY OF TRANSPORTATION CULVERT HYDRAULICS
https://www.youtube.com/watch?v=vnXmGyb_hKQ&t=267s
YouTube Video is 45 min long
Outlet Control: 11:30
Inlet Control: 28:38
44
OUTLINE
45
CULVERT AND ROAD COLLAPSE: MAINE, 2008
https://www.youtube.com/watch?v=NTbhyHNA1Vc
46
UBC Civil Engineering
CIVL 409
Resource Recovery in Municipal Systems
April 3, 2019
Outline
2. Circular Economy
What is it?
Integrated Resource Recovery
Energy
+
Solid Waste Liquid Waste
Metro Vancouver and its member municipalities have stated targets for
Climate reducing greenhouse gas emissions. Other climate-related issues include
Action drought, sea level rise and increasing weather intensity.
Liquid and solid waste discharges require permits under the Environmental
Regulatory Management Act and others. Metro Vancouver’s Integrated Solid and Liquid
Waste Resource Management Plans promote resource recovery.
Source: government.nl
Resource Recovery
Resource Streams
Treated
Effluent
Clean CO2
Algal
Process
Sludge Heat
Exchanger District
Ultraviolet Cooling
Wet Organic Waste 17°°C
Anaerobic Or Ozone
Disinfection 4°°C
Digester
Combined
Synthesis Heat & Power
Metals & Ash Gas
Dry Organic Waste
Electricity
Energy Production
Resource Recovery
Organics Recycling
Soil Fabrication
Biosolids
WW Sludge Drying
/ Digestate
Anaerobic
Animal Manure Direct Use
Digestion
WET
Trucked Heat
Liquid Waste Biogas
Power
Food Waste
Biomethane
Yard Waste
DRY
Composting Soil
Wood Waste
Combustion / Heat
Gasification
Power
Resource Recovery
Composting reduces total solids mass by about half, needs about 2:1
ratio of “brown” to “green” biomass (25:1 C to N)
Biofuels
Solids Liquids Gases
Dried Biosolids
18 GJ / dry tonne, but needs about 10 GJ / tonne of
heat to dry
Biogas
25 GJ / 1,000 m3 at standard conditions
Biogas Upgrading:
– Digester gas is about 60-65% methane, 30%
CO2
– Other impurities are siloxanes, water vapour,
hydrogen sulfide
– FortisBC requires 99% pure biomethane
– Biogas from WWTPs is naturally green
– Upgrading to biomethane can displace
natural gas in traditional uses
– Implementation underway at one MV WWTP
Resource Recovery
Water Reclamation
Potential Uses:
• Irrigation
• Toilet Flushing
• Cooling Water
• Dust Control
• Sewer Flushing
http://www.docksidegreen.com/sustainability/environment/
• Industrial Washdown
• Indirect Potable Reuse • Cement Production
• Hydro-excavation
• Spray Parks
• Greater Exposure Potential
• Decorative Ponds
• Moderate Exposure Potential
• Toilet Flushing
– New Toilets 4.8 L / Flush x 5 Flushes / day = 24 L/c/d
– Typical total indoor use in new construction 180-200 L/c/d
– Potential ~12-18% savings for indoor use
• Irrigation
Biomass
Biogas
Energy Transfer
Hydronics
Station
Natural Gas
Sewage Energy
• Use raw
sewage or
treated effluent
• Can be
economically
competitive
heat source
Resource Recovery
6 mm Screens Back to
Chilled Sewage Sewer
Heat Pumps System
(Hot Water 65 ºC to 80 ºC)
Sewage Pumps
Resource Recovery
Hot Water
Return
Warm
Sewage 50 ºC
Expansion Valve
15 ºC
10 ºC Compressor
Hot Water
Cooled Supply
Sewage
Refrigerant (e.g. r134a) 65-80 ºC
Electricity
Benefits Costs
Resource Recovery
• Lifecycle Analysis
– Capital
– O&M
– Input Feedstocks
– Output Products
from Jeff
Carmichael,
Metro
Vancouver
Resource Recovery
Summary
Thanks!
Jeff Carmichael
Division Manager, Utility Research and Innovation
Metro Vancouver
jeff.carmichael@metrovancouver.org