1.1. BACKGROUND

The project named “Cileunyi – Sumedang – Dawuan (Cisumdawu) Toll Road Project”,
the location of the whole project is in 3 (three) districts, such as Bandung district, Sumedang
district and Majalengka district. The project started from Cileunyi to Dawuan (Majalengka).

Cisumdawu Toll Road Project itself have divided into 6 Sections, namely :
o Section I Sta.-2+245 – 9+750 (IC Cileunyi – IC Ranca Kalong) (L=11,99 Km)
o Section II Sta.9+750 – 27+100 (IC Ranca Kalong – IC Sumedang) (L=17,35 Km)
o Section III Sta.27+100 – 30+850 (IC Sumedang – IC Cimalaka) (L=3,75 Km)
o Section IV Sta.30+850 – 38+050 (IC Cimalaka – IC Legok) (L=7,2 Km)
o Section V Sta.38+050 – 53+950 (IC Legok – IC Ujung Jaya) (L=15,9 Km)
o Section VI Sta.53+950 – 58+326.987 (IC Ujung Jaya – IC Dawuan) (L=4,23 Km)

Cisumdawu Section II divided by 2 stage. Section II stage II, will be executed only for
10,7 Km from the total of 17,35 Km which is (Sta.12+000 – Sta.13+.100 and Sta.17+200 –
Sta.26+800), with the following description for Scope of Work :

PACKAGE NAME
NO (PROVINCE NAME) SCOPE OF WORK

1. Toll Road Development of


Cileunyi – Sumedang – Main Road Location : 10.1 Km
Dawuan Phase II (West Jawa Rancakalong - Sumedang
Province
Bridge Location : 2 locations
Rancakalong - Sumedang

Tunnel Section : 1 locations :


a. Main Road Main Road length 628 m
b. Twin Tunnel Tunnel length 472 m
Location : (Twins Tubes)
Rancakalong - Sumedang

Access Road : 2 locations (1.9 Km) :


a. Rancakalong 0.9 Km
b. Sumedang 1.0 Km

Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 1


Location :
Rancakalong - Sumedang

Overpass Locations : 5 locations


Rancakalong - Sumedang

Underpass Locations : 5 locations


Ciherang - Sumedang

Interchange Locations : 1 locations


Sumedang

Toll Gate Locations : 2 locations


Rancakalong - Sumedang

Pedestrian Bridge 3 locations


Locations :
Rancakalong - Sumedang
(by : Contract Agreement, Number : KU.03.01/PJBHCP-II/16)

a. Scope of Tunnel Work


i. Tunnel work for twin tunnel (L = 472m) including excavation of soil to rock
condition, mucking, disposal, support, grouting, structure work, water
management, drainage, pavement, monitoring and site management.
ii. Tunnel portal work (temporary & permanent works) including earthwork, slope
protection, structure, and landscaping.
iii. Disaster prevention, electrical work (temporary & permanent, including
engineering), lighting work (temporary & permanent), water supply
(temporary), and ventilation work (temporary).

b. Scope of Tunnel Work


The road construction works consist of earthworks, subgrade improvement, sub-drain
installment (if necessary), rigid-concrete pavement with granular drainage layer,
crossing drain structure, overpass/ underpass and retaining wall.
i. The new road is designed with dual separated carriageway : 2 way 4 lanes
@3.60 meter width, with 1.50 meter inner shoulder and 3.00 meter outer
shoulder and 2.50 meter width of median.
ii. Rigid Pavement : thickness of 30 cm, Wet Lean Concrete t = 10 cm.
iii. Flexible Pavement : for outer shoulder.
iv. Earthworks : common excavation and embankment (re-inforce if needed).

Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 2


c. Scope of Structures
1 interchange, 2 main bridges, 5 overpass, and 5 underpass with sub-structures types
bore pile/ spun pile and upper structures with pre-stress concrete I girder.

d. Scope of Stoll Facilities


Toll Gate : 2 @5 lanes – 4 island (3 reversible)

The purpose and benefits of "Construction of Toll Road Cileunyi - Sumedang - Dawuan
(Cisumdawu)" project are :
1. To integrate Bandung city and Cirebon with planning of international airport in Majalengka
and Port in Cirebon as inlet/ outlet of West Java Province.
2. To increase the economic growth in the area around the toll road.
3. To encourage the development of the eastern province of West Java that relatively less
developed than the West.
4. As an alternative way for Cadas Pangeran street

Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 3


1.2. PROJECT ADMINISTRATIVE DATA

No. DESCRIPTION EXPLANATION


A ADMINISTRATIVE DATA OF SUPERVISION AND DESIGN
1. Project Owner Directorate General of Highways
2. Package Name The Implementation of Cisumdawu Toll Road
Phase 2
3. Sub Project Managers Andi Bustami, ST
(PPK) name
Sub Project Manager of Supervision and Design
4. Position
of The Implementation of Cisumdawu Toll Road
Project
5. Address Jl. Winaya Mukti No. 01 Komplek ITB – Kab.
Sumedang
6. Phone/ Fax/ Email Telp. (022) 7795597 Email
ppk_ppjbhc@yahoo.com

B ADMINISTRATIVE DATA OF THE IMPLEMENTATION


1. Pemilik Kegiatan Directorate General of Highways
2. Package Name The Implementation of Cisumdawu Toll Road
Phase 2
3. Sub Project Managers Yusrizal Kurniawan, ST., M.Eng.
(PPK) name
4. Position Sub Project Manager of The Implementation of
Cisumdawu Toll Road Project
5. Address Jl. Winaya Mukti No. 01 Komplek ITB – Kab.
Sumedang
6. Phone/ Fax/ Email Telp. (022) 7795597 Email
cisumdawuphase2@gmail.com

C ADMINISTRATIVE DATA OF SUPERVISION CONSULTANT


1. Supervision Consultant CECI (China Engineering Consultant,Inc.)
Cooperates with :
PT. Ciriatama Nusawidya Consultant, PT. Daya
Creasi Mitrayasa, PT. Indra Karya (Persero), PT.
Parama Karya Mandiri, PT. Seecons.

Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 4


No. DESCRIPTION EXPLANATION
2. Representative Director Van Go
3. Address Wolter Monginsidi 122-124 Tendean Square No.
27, Kelurahan Petogogan, Kecamatan Kebayoran
Baru, Jakarta Selatan
4. Phone/ Fax Telp. (021) 72784046 –– Fax. (021) 72786905
5. Contract No. HK.02.03/PK-P2JBHC/I/2016/20
6. Contract Date 22th January 2016
7. Amandment No. 01 18th August 2016
8. Contract Price Rp. 65.196.021.000,00 (including VAT)
(Original Contract) (Sixty Five Billion One Hundred Ninety Six
Million Twenty One Thousand Rupiah)
9. Contract Price Rp. 65.196.021.000,00 (termasuk PPN)
(Amandment No. 01) (Sixty Five Billion One Hundred Ninety Six
Million Twenty One Thousand Rupiah)
10. SPMK No. HK.02.03/PK-P2JBHC/VIII/2016/188
11. SPMK Date 22th August 2016
12. Maintenance Period 36 (Thirty Six) months

D ADMINISTRATIVE DATA OF THE CONTRACTOR


1. Contractor Metallurgical Corporation of China Ltd.
Consortium PT. Wika – PT. Nindya Karya - PT.
Waskita joint operation
2. General Superintendent Hu Yinglin
3. Address Jalan Dangdeur Dusun Ciawi Larangan Desa
Ciherang - Sumedang Regency, West Java
Province
4. Phone/ Fax Telp. (022) Fax. (022)
5. Contract No. KU.03.01/PJBHCP-II/16
6. Contact Date 15th September 2015
7. Contract Price Rp. 3.485.999.660.965,00 (termasuk PPN)
(Original Contract) (Three Trillions Four Hundred Eighty Five
Billions Nine Hundred Ninety Nine Millions Six
Hundred and Sixty Thousand Nine Hundred
Sixty Five Rupiah)
8. SPMK No. KU.03.01/PJBHC/II/31
9. SPMK Date 18th August 2016

Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 5


No. DESCRIPTION EXPLANATION
th
10. End of Original Contract September 12 2019
11. Maintenance Period 730 (Seven Hundred and Thirty) Calendar Days

E DATA TEKNIS
1. Length of Main Road 10.1 Km
2. Handling Treatment :

- Main Road 10,1 km


(Sta. 12+000 - 12+628 & Sta. 17+200 – 26+800)
- Tunnel 472 m (Sta. 12+628 – 13+100)
3. Speed Plan 80 km/jam (main road)
4. Band width 2 X 3,60 m
5. Outside Road Width 3,00 m
6. Inside Road Width 1,50 m
7. Median Width 2,50 m
8. Pavement Traffic Road Rigid Pavement
9. Pavement Road Flexible Pavement

D Location Kabupaten Sumedang Provinsi Jawa Barat


E Source of Funds Loan China

Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 6


1.3. SITE LOCATION

The site location of toll road Cileunyi – Sumedang – Dawuan (Cisumdawu) is located in
the province of West Java. For more information can be seen on a map location :

Picture 1.1 Site Location

Picture 1.2a Plan Profile of Cisumdawu Phase II

Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 7


Picture 1.2b Plan Profile of Cisumdawu Phase II

Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 8