Escolar Documentos
Profissional Documentos
Cultura Documentos
Guidelines
A Publication of
READY MIXED CONCRETE ASSOCIATION OF ONTARIO
365 Brunel Road, Unit #3
Mississauga, Ontario
L4Z 1Z5
Phone #: (905) 507-1122 Fax #: (905) 890-8122 Email: rmcao@rmcao.org
2009
Property of Ready Mixed Concrete Association of Ontario
TABLE OF CONTENTS
LIST OF APPENDIX
LIST OF TABLES
The intent of this guideline is to offer assurance to specifying Engineers that all
members of the Association are committed to producing concrete of a consistent
and dependable quality. Furthermore, it will provide the member companies with
the tools necessary to develop a Quality Assurance Plan that will enable them to
have confidence in their daily concrete production methods.
1.1 Background
Portland Cement Concrete (PCC) is subject to numerous factors that influence its
plastic and hardened properties. Included among these are:
1. Raw Material Variations.
2. Concrete Production, Delivery, Placement and Consolidation
Techniques.
3. Curing Method and Duration.
4. Preparation, Handling and Testing of Cylinder Strength Specimens.
Ideally, the design of a concrete mix should consider the variability introduced by
all of the above factors.
Strength Test:
The average of two cylinder specimens cast from a single
load of concrete and tested at the same age. For example,
the 28 day strength of a load is calculated as the average of
two cylinders cast from the same load of concrete, tested at
28 days.
Average Strength:
The average of all individual strength tests cast on a specific
class of concrete from a given plant using similar materials.
For example, the average of fifteen, 28 day Compressive
Strength test results for 30 MPa, MTO concrete is 36.3 MPa.
Range:
The difference between the highest and lowest values in a
data group. For example, the 28 day range for 2
Compressive Strength cylinders tested at 37.6 MPa and 39.2
MPa is 1.6 MPa.
Cement Efficiency:
The average amount of cementitious material, in kg, required
to produce 1 MPa of compressive strength per m3 of
concrete. For example, a concrete of average strength 36.3
MPa designed with 335 kg of cementitious material will have
an efficiency of 9.23 kg/MPa per m3 (335 kg ÷36.3 MPa).
1. Average: The sum of all individual test results divided by the number of tests.
2. Standard Deviation: The sum of the root mean squared differences between
each test result and the sample average divided by the number of samples
less 1.
3. Coefficient of Variation: The Standard Deviation divided by the Average
Strength and expressed as a percentage.
4. Cement Efficiency: The total mass of cementitious material per m3 divided
by the Average Strength.
Important Note:
All tests incorporated in the analysis must be taken within the previous twelve
(12) months of operation, with at least fifteen (15) 28 Day Compressive
Strength Tests performed on each class of concrete during the twelve month
testing period.
When a production facility has less than 30 samples, but has a record based on
15-29 tests, the calculated Standard Deviation must be modified by multiplying
by the appropriate factor from the following table (ACI –318 Clause 5.3.1.2):
CSA A23.1, Clause 4.4.6.6.1 indicates that the strength level of each class of
concrete shall be considered satisfactory if the averages of all sets of three (3)
consecutive strength tests for that class at one age equal or exceed the specified
strength (f’c) and no individual strength test is more than 3.5 MPa below the
specified strength. This criterion can be met with 99% confidence when the
concrete mix is proportioned to produce the following Average Design Strength:
CSA states that individual strength tests from concrete meeting these
requirements can be expected to be below specified strength approximately 10%
of the time. Appendix A provides a detailed list of formulas for determining the
Average Design Strength based upon the maximum percentage of tests the
design Engineer would like to see below the specified strength.
For the purpose of this program, each producing Member must analyze the
following two categories of concrete:
1. For each plant, select the mix design that will be used the most
for each category of concrete to be tested.
2. Obtain the 28 day Compressive Strength test results during the
12 month moving window. At a minimum, 15 tests must
conducted for each class of concrete (Note: Additional test
results will reduce the Standard Deviation Modification Factor
and limit the effects of extreme test results).
3. Members are required to keep on file the Compressive Strength
Test Reports (completed by a CSA certified laboratory or
stamped by a PEO Engineer) for each category of concrete.
4. Review the data as it is collected to confirm that no one
individual test is lower than 3.5 MPa below the specified
strength and that the running average of the last three
compressive strength tests are greater than the specified
strength.
5. Input the data in a summary table to allow for quick inspection
by the Engineer during the Plant Audit and Certification Program
(See samples in Appendix 2 & 3).
6. Calculate the Average Strength and Standard Deviation for a
given class of concrete at a given plant for the current testing
period.
7. Modify the Standard Deviation value as required based upon
the number of 28 Day Compressive Strength Tests used in
program (Table 5.3.1.2).
8. Determine CSA’s recommended Average Design Strength
based upon your specific data.
9. Adjust the design mixes in accordance with the statistical
analysis data. One possible method is to determine the cement
efficiency, as described previously, for the mix design in
question.
As per ACI 214 guidelines, if the within test Coefficient of Variation exceeds
6.0%, it is likely that testing error is influencing the accuracy of test results. It is
important that test results influenced by testing not be used in designing
concrete mixes.
Enclosed are two sample reports for the two categories of concrete included in
the Mix Design Statistical Analysis Program.
Note: In order to highlight the main objectives of the program, both samples
contain data that fails to meet the requirement of CSA A23.1
Clause4.4.6.6.1. These failures do not indicate that the Member has
failed to meet the requirements of Mix Design Statistical Analysis
Program. The only requirement of the Program is that the Member modify
its mix designs to address these issues and continue the monitoring
program to determine the effectiveness of the modifications.
If specifying Engineers require greater assurance that the specified strengths will
be achieved, the factor by which the standard deviation is multiplied may be
increased. ACI-214 provides the following guide:
Any Engineer who, unrealistically, refuses to recognize the variability that exists
and demands that no test falls below the specified strength, must realize that the
required average strength is 3.0 standard deviations above the specified
strength, resulting in over-designed and uneconomical mixes.