Audit Objectives:
To verify the compliance with regulatory requirements such as NCAR Part-145, &
To verify the conformity with approved procedures in CAMMOE.
Audit Scope:
Y12E, 9N-AKU
Audit Criteria:
NCAR Part 145
CAMMOE
Auditors Team:
Team Leader/Auditor : Diwakar Banjara & K.P Bhurtel
Page 1 of 4
Quality Assurance Audit Area
Product (Aircraft) Audit
Audit Plan
Y12E, 9N-AKU
Audit Agenda:
Page 2 of 4
Quality Assurance Audit Area
Product (Aircraft) Audit
Audit Plan
Y12E, 9N-AKU
General Rules:
1) Auditees will be present at all times during the audit except during unavoidable
circumstances with the agreement with auditors. In case auditee is not able to
participate in audit, he should allocate appropriately qualified personnel to be
present during the audit.
2) In case of disagreement between auditors and auditee, lead auditor will be
informed. The lead auditor will discuss the matter with responsible Director for
resolution.
3) If a major non-conformance or non-conformity (Level 1) is encountered, Lead
auditor will be immediately informed. Lead auditor in turn will inform Quality
Manager and responsible Director for necessary and prompt action.
Confidentiality Guidelines:
All the information collected during the audit including the audit report will only be
shared within the Accountable Manager, Engineering Maintenance Department and
Quality Assurance and not with any other unauthorized personnel or Department.
Any distribution of the audit report will occur only through written permission from
the EMD Director.
All the documents and information pertaining the audit will be safely secured in the
office of Quality Assurance for at least 3 years from the closure date of the findings as
per CAMMOE 3.1.2.3.
Audit Report:
As per CAMMOE 3.1.2.2, the audit report will be submitted to the Accountable
Manager, Engineering Maintenance Department, within 10 working days after the
completion of audit.
Page 3 of 4
Quality Assurance Audit Area
Product (Aircraft) Audit
Audit Plan
Y12E, 9N-AKU
Follow-Up Audit:
Follow-up audit will be scheduled once the Corrective Action Plan is received from
responsible Departments. Follow-up report will be submitted to the responsible
Department with the status of Non-compliances and Non-conformances.
Page 4 of 4