MMH Tower Cranes Preliminary Pile Load Schedule GTS Ref 15055

Tower HUH Jib Base Size Working Pile Loads (Unfactored) Ultimate Reinforcement
Crane Ref Tension
Length Width Depth Compression Tension Horizontal

(m) (m) (m) (m) (m) (kN) (kN) (kN) (kN)

TC1 63 47.5 5.00 5.00 1.50 1603 -698 36 -1165

TC2 81 42.5 6.00 6.00 1.50 2119 -942 46 -1562

TC3 63 45.0 5.00 5.00 1.50 1603 -698 36 -1165

TC4 54 50.0 4.35 4.35 1.50 1398 -631 40 -1042

TC5 72 40.0 5.00 5.00 1.50 1971 -1032 39 -1641

TC6 54 42.5 4.35 4.35 1.50 1398 -631 40 -1042

Notes

1. Preliminary base design based upon the use of 450mm diameter piles

2. Tower crane piles positioned not less than 3 x pile diameters from adjacent permanent piles.

3. Refer to GTS drawing 15055/009A for tower crane base locations. T Roberts, GTS, 24/11/15