Escolar Documentos
Profissional Documentos
Cultura Documentos
REVISED REPORT
(2nd REVISION)
1
2
TABLE OF CONTENTS
1.1 Introduction...................................................................................................................... 7
2. INTRODUCTION........................................................................................................................ 9
2.1 Introduction...................................................................................................................... 9
5.3.1 Methodology........................................................................................................... 18
6.1 Conclusions..................................................................................................................... 25
ANNEXES ....................................................................................................................................... 27
L. Evacuation Losses……………………………………………………………………………………………… 42
M. Voltage Variation Studies with Solar Generation Simulations with +/- 0.95 pf……42
LIST OF FIGURES
Figure 3-1: Existing project area power network schematic diagram ............................................ 9
LIST OF TABLES
Abbreviation/
Description
Acronym
KPLC Kenya Power and Lighting Company Limited
ACSR Aluminium Conductor, Steel Reinforced
Ssc Short Circuit Level
SCR Short Circuit Ratio
EAPP Eastern Africa Power Pool
EN European Standards
KNTGC Kenya National Transmission Grid Code
IEC International Electrotechnical Commission
6
1. EXECUTIVE SUMMARY
1.1 Introduction
The rAREH Icon Solar PV plant is located in Makueni County in the Republic of Kenya. The
project entails construction of a 30MW PV plant, power collection system including inverters
and the interconnection facilities to integrate the plant to the national grid. The proposed plant
site is 3.5km from the existing Kiboko 132/33kV substation.
As part of the project development process, a grid interconnection study is carried out to assess
the available grid connection options, identify the technically feasible and best interconnection
scheme, and if necessary determine the required network reinforcement to ensure effective
interconnection of the plant. The study is aimed at demonstrating the ability of the grid at the
grid connection point to receive the solar PV power without significant negative impact on the
grid.
An assessment of the existing power system infrastructure has been done and based on the
proposed generation capacity, there are two viable grid interconnection options.
a) There are no thermal or voltage violations arising out of the connection of the proposed
power plant under any of the connection options studied.
b) The fault levels are slightly elevated on commissioning of the plant in all the relevant
buses, however, they do not exceed or approach the ratings of currently installed
network equipment.
c) The system voltage variation and the flicker severity at the proposed connection points
are within the required limits.
d) The expected voltage variation on interconnection for each of the proposed options is
within the required limit of +/- 10% at the 33kV voltage level and +/-5% at the 132kV
voltage level.
Based on the analysis and conclusions made from this study, it is technically possible to connect
the plant to the grid via either of the proposed interconnection options. It is however
recommended that the plant be connected to the grid via Option 2 i.e. by constructing a 3.5kM
33kV, double circuit line in 300mm2 AAAC (Upas) conductor to the Kiboko substation 33kV bus
bar and install one 40MVA, 33/132kV step up transformer between the existing 33kV and
132kV bus bars as shown on the attached single line diagram at Annex E.
9
2. INTRODUCTION
2.1 Introduction
The rAREH Icon Solar PV plant is located in Makueni County in the Republic of Kenya. The
project entails construction of a 30MW PV plant, power collection system including inverters
and the interconnection facilities to integrate the plant to the national grid. The proposed plant
site is 3.5km from the existing Kiboko 132/33kV substation.
The objective of the study will be to assess the available grid connection options, identify the
technically feasible and best interconnection scheme, and if necessary determine the required
network reinforcement to ensure effective interconnection of the plant. The study will also
estimate the network short circuit fault levels in order to determine the impact of the proposed
power plant on the existing network switchgears and aid in interconnection equipment design;
calculate voltage variation and also the flicker severity.
10
The existing grid network in the area near the proposed project site is as shown in the figures 3.1 and 3.2 below.
11
Key:
132kV line
33kV line
The requirements specified in the Kenya National Transmission Grid Code (KNTGC) formed the
basis for the grid impact assessment studies. The relevant chapters of the code are Chapter 6 –
Connections and Chapter 7 – Renewable Power Plant. These chapters contain requirements
specific to both the Eastern Africa Power Pool and East African Community Interconnection
Code (EAPP IC) and the KNTGC. Where there are differences in requirements, the KNTGC
specifies that the more stringent requirement shall hold. Chapter 6 – Connections, specifies the
minimum technical, design and operational criteria of plant and apparatus that must be
complied with by the Transmission System Operator (TSO) and Users at the connection Point.
The Transmission System Performance Characteristics specified by the Code are as follows:
4.1 Frequency
The frequency limits under normal and contingency conditions are shown in Table 4-1. Large
generating units can cause a dip in system frequency on tripping due to the inability of the
remaining generators on the system to pick up the shortfall. In extreme circumstances, this can
cause a complete system collapse. The Makindu Solar PV plant is however relatively small and
will therefore have minimal impact on the system frequency.
4.2 Voltage
The impact of the plant on steady-state voltage levels and in terms of voltage fluctuation or
flicker is assessed in the report. Steady-state voltage limits from the KNTGC are shown below.
For assessment of voltage fluctuation or flicker, the KNTGC quotes IEC 61000-3-7 (1996) and
includes the following general requirements:
15
4.3 Harmonics
The limits for harmonic distortion are as follows.
a) Relevant current international and African Standards, such as IEC, ISO, EN;
b) Relevant current national standards.
Furthermore, Plant and Apparatus shall be designed, manufactured and tested in accordance
with the quality assurance ISO 9000 family or equivalent. The above requirements are to be
complied with during the detailed design phase of the project. The KNTGC also specifies
requirements for electrical protection and telecommunication which are to be adhered to in
the detailed design.
These requirements should form part of the specification of the power plant during the next
stage of the project. At this stage, it is assumed that the plant will be designed with the
capability to comply with these requirements. Further tests/studies may be required to confirm
grid code compliance at a later stage. The list of studies/tests is indicated below at Annex O.
From the table above, it can be seen that a plant of 30MW can be connected to the grid at 33kV
voltage level or above. It is however worth noting that these are just guidelines as suitably sized
33kV lines can evacuate much more than 10MW plants efficiently.
Kiboko 132/33kV
1X23MVA Substation Makindu KPC
33kV Bus
Sultan Hamud 132/33kV station
132kV Bus
1X23MVA Substation
3.2MW Load
132kV Bus
3MW Load
33kV Bus
132kV Bus
2.6MW Load
A fault level study was conducted in PSS/E software using the IEC 60909 to determine the
minimum and maximum three-phase fault levels in the network of interest.
Table 5-2 below is a summary of maximum and minimum short circuit fault levels.
18
Tables 5-3 and 5-4 give per unit voltages at the proposed interconnection points and line
loadings of relevant lines in percentage before the plant is added.
It can be noted that, the voltages at the relevant buses are all within acceptable limits i.e. 0.95-
1.05pu. The fault levels are all below the rated breaking currents for the circuit breakers and no
project relevant line is overloaded.
5.3.1 Methodology
The study considered two grid interconnection options for the proposed plant as outlined here
below. For each of the alternative options, load flow and short circuit fault level studies were
carried out to assess adequacy of the network and strength of the point of connection with
respect to the proposed power plant. Short circuit fault levels were evaluated to determine the
impact of the proposed plant on the fault levels in selected relevant buses and ensure minimum
design short circuit ratings for both the transmission and distribution network in Kenya listed in
Table 5-2 above are not violated. The two interconnection options are analyzed below:
19
Kiboko 132/33kV
1X23MVA Substation Makindu KPC
33kV Bus
Sultan Hamud 132/33kV station
132kV Bus
1X23MVA Substation
3.2MW Load
132kV Bus
3MW Load
33kV Bus
132kV Bus
2.6MW Load
It can be noted that the fault levels are elevated at all the buses, but they are still below the
rated breaking currents for the circuit breakers. The addition of the plant also causes a slight
rise in voltages on the monitored buses and the loadings on the monitored lines.
30MW Rareh
M
Solar Farm
Makindu KPC
33kV Bus
Sultan Hamud 132/33kV station
132kV Bus
1X23MVA Substation
3.2MW Load
132kV Bus
3MW Load
33kV Bus
132kV Bus
2.6MW Load
Kiboko 132/33kV
1X23,40MVA Substation
43km 175sq.mm ACSR
Conductor (Lynx)
15km 175sq.mm ACSR
Conductor (Lynx)
It can be noted that the fault levels are elevated at all the buses, but they are still below the
rated breaking currents for the circuit breakers. The addition of the plant also causes a slight
rise in voltages on the monitored buses and the loadings on the monitored lines.
Power system strength with respect to generation is expressed in terms of system short circuit
ratio, which is defined as the ratio of the system short circuit power at the point of connection
to the Maximum power generation from the plant
i.e. ⁄
The power system is determined to be strong with respect to installed capacity if the short
circuit ratio is above 20 and weak if it is below 10.
SCR was calculated at the proposed connection points to the grid for the two options and
tabulated as shown below.
Table 5-11: Short Circuit Ratios at Connection Points
Plant Short Circuit Fault Level SCR
Option Bus Power maximum minimum
Maximum Minimum
(MW) (MVA) (MVA)
1 Kiboko 132kV 30 339.70 313.07 11.32 10.44
2 Kiboko 33kV 30 243.29 230.53 8.11 7.68
The capacity of the power network to absorb the proposed solar PV power plant at the
alternative points of connection considered can be assessed through calculation of short circuit
fault levels at these points. The calculated short circuit fault levels al so give an indication of
whether the existing network breaking capacity will be adequate for the expected increase in
system short circuit fault levels upon integration of additional generation capacity.
Based on the above criteria, it is shown that Kiboko 132kV bus is a strong point for connecting
the proposed solar PV plant to the grid and the 33kV bus in the same substation is a slightly
weaker point for connecting the plant to the grid.
Short circuit fault analysis results indicate that network short circuit fault levels will be slightly
elevated on commissioning of the plant in all the relevant buses. They will however not exceed
or approach the ratings of currently installed equipment at the considered 132kV and 33kV
points of connection.
Voltage variation,
( ⁄ )
( ⁄ )
Where P and are as defined above, β is the angle of network short circuit impedance and α
is the phase angle of the plant output current.
24
The maximum voltage variation is expected at minimum system short circuit fault level.
Assuming unity power factor for the plant power output current, expected Voltage variation on
interconnection for each of the proposed interconnection option is shown in the table below
The voltage variation is within the allowed limits of +/-5% at 132kV voltage level and +/-10% at
the 33kV voltage level.
( )
Where R is the frequency factor, F is the form factor; r is the repetition rate per minute and
( ) % is the maximum voltage variation in percentage. Typical values for R and F are 0.2 and
1.4 respectively.
Short term flicker planning limits are; Pst< 0.9 for medium voltage systems and Pst< 0.8 for high
voltage systems.
Assuming repetition rate of 10 per minute and the determined voltage variations for both the
interconnection options above, applying the expression in above gives s hort term flicker as in
Table 5-13.
This is less than the short-term flicker planning threshold of 0.9Pst for medium voltage systems
and 0.8Pst for high voltage systems for both interconnection options.
25
6.1 Conclusions
The following conclusions can be drawn from this study:
The results also indicate that connecting the solar PV power plant at any of the two proposed
interconnection options does not result to any thermal or voltage violations for the normal
network configuration.
It is shown that Kiboko 132kV bus is a strong point for connecting the proposed solar PV plant
to the grid and the 33kV bus in the same substation is a slightly weaker point for connecting the
plant to the grid.
6.2 Recommendations
Based on the analysis and conclusions made from this study, it is technically possible to connect
the plant to the grid via either of the proposed interconnection options. It is however
recommended that the plant be connected to the grid via Option 2 i.e. by constructing a 3.5kM
33kV, double circuit line in 300mm2 AAAC (upas) conductor to the Kiboko substation 33kV bus
bar and install one 40MVA, 33/132kV step up transformer between the existing 33kV and
132kV bus bars as shown on the attached single line diagram at Annex E. This proposa l will
avoid purchase of additional land for the extension of 132kV bus bar as proposed in Option 1. It
26
will also ease the way-leave acquisition process as the double circuit line will follow the existing
road reserves.
The studies were done in close consultation with Kenya Power who provided valuable system
data. Their input is acknowledged and appreciated.
ANNEXES
A. Load Flow Diagram before connecting the Plant.
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
312005
KKIBOKO11
312009
SW KMAKINDU
312004 0.0
KSULTAN HA11
1.0
131.1
3.2 3.2 3.2
1
1
1.1 1.1I 1.1
15%
1.0
131.0
1.0
32.6
N/A
312013 1.0
RAREH132KV 135.1
N/A
1
N/A
1
N/A
332011 1.0
RAREH33KV 33.7
95% I
1
28
312005
KKIBOKO11
312009
SW KMAKINDU
312004 0.0
KSULTAN HA11
1.0
135.1
3.2 3.2 3.2
1
1
1.1 1.1I 1.1
14%
29.9
2.9
1.0
135.1
1.0
33.6
22% I
312013 1.0
29.9
3.0
RAREH132KV 135.1
3.0
29.9
N/A
1
N/A
1
73% I
332011 1.0
30.0
0.8
RAREH33KV 33.7
95% I
0.8L
30.0
1
29
312005
KKIBOKO11
312009
SW KMAKINDU
312004 0.0
KSULTAN HA11
2.1 1.4
1.0
135.3
3.2
1
1.1
312013 1.0
RAREH132KV 135.6
332011 1 1.0
15.0
15.0
0.4
0.4
RAREH33KV 34.1
0.8L
30.0
1
30
OPTIONS USED:
- VOLTAGE FACTOR C=1.05 WHEN BUS BASE kV<=1.0 kV and C=1.1 WHEN BUS BASE kV>1.0 kV
VOLTAGE FACTOR C= 1.10, NOMINAL FREQUENCY=50.0 Hz, BREAKING CURRENT at TIME= 0.100 seconds
<-SCMVA-> <-Sym I''k rms--> <-ip(B)-> <-ip(C)-> <DC Ib(C)> <Sym Ib-> <Asym Ib>
X---------- BUS ----------X MVA AMP DEG AMP AMP AMP AMP AMP
312005 [KKIBOKO11 132.00] 3PH 339.70 1485.8 -69.45 3233.6 2865.5 230.8 1485.8 1503.6
---------------------------------------------------------------------------------------------------------------
VOLTAGE FACTOR C= 1.10, NOMINAL FREQUENCY=50.0 Hz, BREAKING CURRENT at TIME= 0.100 seconds
<-SCMVA-> <-Sym I''k rms--> <-ip(B)-> <-ip(C)-> <DC Ib(C)> <Sym Ib-> <Asym Ib>
X---------- BUS ----------X MVA AMP DEG AMP AMP AMP AMP AMP
312009 [KMAKINDU 132.00] 3PH 329.32 1440.4 -69.22 3124.7 2766.4 159.9 1440.4 1449.2
---------------------------------------------------------------------------------------------------------------
VOLTAGE FACTOR C= 1.10, NOMINAL FREQUENCY=50.0 Hz, BREAKING CURRENT at TIME= 0.100 seconds
<-SCMVA-> <-Sym I''k rms--> <-ip(B)-> <-ip(C)-> <DC Ib(C)> <Sym Ib-> <Asym Ib>
X---------- BUS ----------X MVA AMP DEG AMP AMP AMP AMP AMP
392055 [KKIBOKO31 33.000] 3PH 151.96 2658.6 -79.63 5962.8 6016.4 526.6 2658.6 2710.3
OPTIONS USED:
- VOLTAGE FACTOR C=0.95 WHEN BUS BASE kV<=1.0 kV and C=1.0 WHEN BUS BASE kV>1.0 kV
VOLTAGE FACTOR C= 1.00, NOMINAL FREQUENCY=50.0 Hz, BREAKING CURRENT at TIME= 0.100 seconds
<-SCMVA-> <-Sym I''k rms--> <-ip(B)-> <-ip(C)-> <DC Ib(C)> <Sym Ib-> <Asym Ib>
X---------- BUS ----------X MVA AMP DEG AMP AMP AMP AMP AMP
312005 [KKIBOKO11 132.00] 3PH 313.07 1369.3 -69.57 2985.2 2645.2 247.6 1369.3 1391.5
---------------------------------------------------------------------------------------------------------------
VOLTAGE FACTOR C= 1.00, NOMINAL FREQUENCY=50.0 Hz, BREAKING CURRENT at TIME= 0.100 seconds
<-SCMVA-> <-Sym I''k rms--> <-ip(B)-> <-ip(C)-> <DC Ib(C)> <Sym Ib-> <Asym Ib>
X---------- BUS ----------X MVA AMP DEG AMP AMP AMP AMP AMP
34
312009 [KMAKINDU 132.00] 3PH 303.22 1326.2 -69.32 2881.1 2550.4 170.8 1326.2 1337.2
---------------------------------------------------------------------------------------------------------------
VOLTAGE FACTOR C= 1.00, NOMINAL FREQUENCY=50.0 Hz, BREAKING CURRENT at TIME= 0.100 seconds
<-SCMVA-> <-Sym I''k rms--> <-ip(B)-> <-ip(C)-> <DC Ib(C)> <Sym Ib-> <Asym Ib>
X---------- BUS ----------X MVA AMP DEG AMP AMP AMP AMP AMP
392055 [KKIBOKO31 33.000] 3PH 146.45 2562.1 -79.31 5711.7 5763.7 559.2 2562.1 2622.4
---------------------------------------------------------------------------------------------------------------
OPTIONS USED:
- VOLTAGE FACTOR C=1.05 WHEN BUS BASE kV<=1.0 kV and C=1.1 WHEN BUS BASE kV>1.0 kV
VOLTAGE FACTOR C= 1.10, NOMINAL FREQUENCY=50.0 Hz, BREAKING CURRENT at TIME= 0.100 seconds
<-SCMVA-> <-Sym I''k rms--> <-ip(B)-> <-ip(C)-> <DC Ib(C)> <Sym Ib-> <Asym Ib>
X---------- BUS ----------X MVA AMP DEG AMP AMP AMP AMP AMP
312005 [KKIBOKO11 132.00] 3PH 342.60 1498.5 -69.57 3266.8 2921.2 191.6 1498.5 1510.7
VOLTAGE FACTOR C= 1.10, NOMINAL FREQUENCY=50.0 Hz, BREAKING CURRENT at TIME= 0.100 seconds
<-SCMVA-> <-Sym I''k rms--> <-ip(B)-> <-ip(C)-> <DC Ib(C)> <Sym Ib-> <Asym Ib>
X---------- BUS ----------X MVA AMP DEG AMP AMP AMP AMP AMP
312009 [KMAKINDU 132.00] 3PH 331.82 1451.3 -69.32 3153.0 2814.1 127.0 1451.3 1456.9
VOLTAGE FACTOR C= 1.10, NOMINAL FREQUENCY=50.0 Hz, BREAKING CURRENT at TIME= 0.100 seconds
<-SCMVA-> <-Sym I''k rms--> <-ip(B)-> <-ip(C)-> <DC Ib(C)> <Sym Ib-> <Asym Ib>
X---------- BUS ----------X MVA AMP DEG AMP AMP AMP AMP AMP
392055 [KKIBOKO31 33.000] 3PH 246.28 4308.7 -76.11 10418.2 9238.3 816.6 4308.7 4385.4
---------------------------------------------------------------------------------------------------------------
OPTIONS USED:
- VOLTAGE FACTOR C=0.95 WHEN BUS BASE kV<=1.0 kV and C=1.0 WHEN BUS BASE kV>1.0 kV
VOLTAGE FACTOR C= 1.00, NOMINAL FREQUENCY=50.0 Hz, BREAKING CURRENT at TIME= 0.100 seconds
<-SCMVA-> <-Sym I''k rms--> <-ip(B)-> <-ip(C)-> <DC Ib(C)> <Sym Ib-> <Asym Ib>
X---------- BUS ----------X MVA AMP DEG AMP AMP AMP AMP AMP
312005 [KKIBOKO11 132.00] 3PH 313.31 1370.4 -69.52 2985.8 2668.3 176.0 1370.4 1381.6
VOLTAGE FACTOR C= 1.00, NOMINAL FREQUENCY=50.0 Hz, BREAKING CURRENT at TIME= 0.100 seconds
<-SCMVA-> <-Sym I''k rms--> <-ip(B)-> <-ip(C)-> <DC Ib(C)> <Sym Ib-> <Asym Ib>
X---------- BUS ----------X MVA AMP DEG AMP AMP AMP AMP AMP
312009 [KMAKINDU 132.00] 3PH 303.43 1327.2 -69.28 2881.5 2570.2 116.5 1327.2 1332.3
VOLTAGE FACTOR C= 1.00, NOMINAL FREQUENCY=50.0 Hz, BREAKING CURRENT at TIME= 0.100 seconds
<-SCMVA-> <-Sym I''k rms--> <-ip(B)-> <-ip(C)-> <DC Ib(C)> <Sym Ib-> <Asym Ib>
X---------- BUS ----------X MVA AMP DEG AMP AMP AMP AMP AMP
392055 [KKIBOKO31 33.000] 3PH 230.53 4033.2 -75.69 9680.8 8584.9 744.6 4033.2 4101.4
Where:
From the already undertaken short circuit study at Kiboko, the maximum short circuit level at the
33kV bus bar is 3.1kA.
=1.18*1.414*2.5
=4.18N/m
2. 132kV System:
Where:
From the already undertaken short circuit study at Kiboko, the maximum short circuit level at the
33kV bus bar is 1.48kA.
=0.159*1.414*2.5
=0.562N/m
Ith = I’’k(m +n)0.5-----As indicated in ABB Switchgear Manual, 11 th Edition at page 146
and 147
Where:
Where:
m = DC component factor
Therefore,
ip/I’’k = 1.95*20.5
40
= 2.76
It is assumed as it is in practice that the relays are set for 1sec fault clearing time
ip = 1.414*3.1 kA
= 4.38K
ip/I’’k = 2.83
=1.59kA
= 0.52
From the the tables at page 147 of the ABB Switchgear Manual;
m = 0.19
n = 0.95
= 1.65Ka
Therefore,
=4.56A/mm2
COMMENT:
The allowed threshold fault current density for Upas conductor with operating temperature of 75 0C
and maximum ultimate temperature of 2000C is 85A/mm2. Refer to Fig 4.16(b) of ABB Switchgear
From the above calculation Upas has adequate capacity to withstand the fault conditions thermal
It is assumed as it is in practice that the relays are set for 1sec fault clearing time
ip = 1.414*1.48 kA
= 2.09K
ip/I’’k = 2.76
=0.76kA
= 0.51
From the the tables at page 147 of the ABB Switchgear Manual;
m = 0.19
n = 0.97
= 0.82Ka
Therefore,
=3.63A/mm2
COMMENT:
The allowed threshold fault current density for Lynx conductor with operating temperature of 75 0C
and maximum ultimate temperature of 2000C is 85A/mm2. Refer to Fig 4.16(b) of ABB Switchgear
From the above calculation Lynx has adequate capacity to withstand the fault conditions thermal
L. Evacuation Losses
The active power losses of the network from is rAREH Icon Solar Limited substation to each of the
proposed connection points were evaluated by determining the active power loss in the overhead line
used to connect the solar plant to the network.
From the results in the table above, the losses are within the acceptable limits. Losses of less than 6%
in 33kV lines are considered satisfactory and thus losses are not a limiting factor in this study.
M. Voltage Variation Studies with Solar Generation Simulations with +/- 0.95 pf
The voltage variations at various bus bars in the substations nearest and interconnected to the solar
generation plant at Makindu is indicated in the tables below.
Option 1
0.95 Power Factor (Lagging)
Actual
Rated Voltage Actual Voltage (pu) Voltage
Bus Variation (%)
(kV) Base Case (pu) Option
1
Kiboko 132 0.9923 1.0266 3.5%
Sultan
132 0.993 1.019 2.6%
Hamud
Kiboko 33 0.9873 1.0245 3.8%
43
Actual
Rated Voltage Actual Voltage (pu) Voltage
Bus Variation (%)
(kV) Base Case (pu) Option
1
Kiboko 132 0.9923 1.0111 1.9%
Sultan
132 0.993 1.0065 1.4%
Hamud
Kiboko 33 0.9873 1.009 2.2%
Option 2
0.95 Power Factor (Lagging)
Actual
Rated Voltage Actual Voltage (pu) Voltage
Bus Variation (%)
(kV) Base Case (pu) Option
1
Kiboko 132 0.9923 1.0281 3.6%
Sultan
132 0.993 1.0202 2.7%
Hamud
Kiboko 33 0.9873 1.0266 4.0%
Actual
Rated Voltage Actual Voltage (pu) Voltage
Bus Variation (%)
(kV) Base Case (pu) Option
1
Kiboko 132 0.9923 1.0056 1.3%
Sultan
132 0.993 1.0021 0.9%
Hamud
Kiboko 33 0.9873 0.9926 0.5%
COMMENT:
From the above tables, it can be seen that the voltages at the 132kV and 33kV bus bars at the point of supply
at Kiboko are below the required threshold of +/_ 5% and +/_ 10% for 132kV and 33kV voltage levels
respectively.
44
NB: PROPOSED NEW 40MVA TRANSFORMER BAY WITH EQUIPMENT IS INDICATED IN RED.
COMMENT:
There is adequate space at KPLC Kiboko 132/33kV Substation for an additional 40MVA 132/33kV transformer bay which
does not interfere with the future expansion of the substation as shown in the above location drawing. More details
including the elevation drawings shall be indicated during detailed design.
45