Escolar Documentos
Profissional Documentos
Cultura Documentos
Say =Rs.42400/-
4 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR STEEL HAND RAILING AS PER DRAWING I/C PAINTING WITH
ALUMINIUM QUANTITY OF ONE SIDE.
5 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR PIPE RAILING AS PER DRAWING ON BRIDGES.
7. Welding of anchor bar and other. = 1 Job. @ Rs. 500/- P.Job = Rs. 500/-
Total = Rs.19651/-
Add 25% overhead/contractor profit on all items except item No. 5-8. = Rs. 4039/-
Total = Rs. 23690/-
6 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR STEEL RAILING AS PER DRAWING ON BRIDGES.
UNIT = 160 Rft
A. Material.
1- Iron post size 3”x3”x1/4”.
2x24x4-2” = 199.68 Rft
199.68x4.89x0.4536 = 472.91 Kg @ Rs. 35/- P.Kg = Rs. 15502/-
8. Carriage of material to site of work.= 1 Job @ Rs. 500/- P.Job = Rs. 500/-
Total =Rs135050/-
7 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR 3” DIA G.I PIPE RAILING FIXED ON R.C.C BARRIER
COMPRISING OF BASE PLATE WITH U-SHAPED STEEL BARS #6 WITH 4”X8”&3/8”
THICK BASE PLATE AND VERTICLE SUPPORT @ 8’ C/C OF MS PLATE ¾” THICK 12”
HEIGHT FOR FIXING G.I PIPE 3” AND AS APPROVED BY THE ENGINEER INCHARGE.
5 Footing plate in pole foundation with J-bolt Each 1 No. 1490/- 1490/-
and nuts i/c ring of steel bat and PVC pipe
6 Rft.
Executive Engineer,
Sub Divisional Officer,
Provincial Highway Division,
Provincial R.C Sub Division,
Gujrat.
Gujrat
9 /conversion/tmp/scratch/421271195.doc
UNIT RATE ANALYSIS FOR ELECTRICAL WORKS (PROVIDING AND FIXING OF
SINGLE ARM STREET LIGHT POLE COMPLETE IN ALL RESPECT.
5 Footing plate in pole foundation with J-bolt Each 1 No. 1490/- 1490/-
and nuts i/c ring of steel bat and PVC pipe
6 Rft.
Executive Engineer,
Sub Divisional Officer,
Provincial Highway Division,
Provincial R.C Sub Division,
Gujrat.
Gujrat
10 /conversion/tmp/scratch/421271195.doc
RATE ANALYSIS FOR ELECTRICAL WORKS.
Unit = P.No
A. Material.
B. Labour.
11 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR TUBELAR POLE UNIT OF UNIT PER NUMBER.
1. M.S pipe 5 mm thick 5” dia 3.89 Meter @Rs: 1031.25 P-M Rs: 4012/-
Overlap =3” =0.25/3.28 0.076m @Rs: 1031.35 P-M Rs: 78/-
2. M.S pipe 5 mm thick 4” dia 2.439 Meter@Rs: 846.90 P-M Rs: 2066/-
Overlap =2x3” =0.5/3.28 0.152 M @Rs: 846.90 P-M Rs: 129/-
3. M.S pipe 3 mm thick 3” dia 1.829 Meter@Rs: 461.85 P-M Rs: 845/-
Overlap =2x3” =0.25/3.28 0.152 M @Rs: 461.85 P-M Rs: 70/-
4. M.S pipe 3 mm thick 2” dia 2.14 Meter @Rs: 308.95 P-M Rs: 661/-
Overlap =2x3” =0.25/3.28 0.076 M @Rs: 308.95 P-M Rs: 23/-
5. Hot dip galvanizing L-S @Rs: 3000 P-No Rs: 3000/-
6. Base Plate 3/4” thick 1x1 1 Sft @24Lbs P-Sft
24 Lbs / 10.88 Kg 10.88 @Rs: 5171.75% Kg Rs: 563/-
2.204
12 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR FOUNDATION OF POLE UNIT P.NO.
13 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR TUBELAR POLE UNIT OF UNIT PER NUMBER.
1. M.S pipe 5 mm thick 5” dia 3.89 Meter @Rs: 1031.25 P-M Rs: 4012/-
Overlap =3” =0.25/3.28 0.076m @Rs: 1031.35 P-M Rs: 78/-
2. M.S pipe 5 mm thick 4” dia 2.439 Meter@Rs: 846.90 P-M Rs: 2066/-
Overlap =2x3” =0.5/3.28 0.152 M @Rs: 846.90 P-M Rs: 129/-
3. M.S pipe 3 mm thick 3” dia 1.829 Meter@Rs: 461.85 P-M Rs: 845/-
Overlap =2x3” =0.25/3.28 0.152 M @Rs: 461.85 P-M Rs: 70/-
4. M.S pipe 3 mm thick 2” dia 4.28Meter @Rs: 308.95 P-M Rs: 1322/-
Overlap =2x3” =0.25/3.28 0.076 M @Rs: 308.95 P-M Rs: 23/-
14 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR CONSTRUCTION OF P.C.C CHUTES.
15 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR LOAD TEST FOR BRIDGE PILE FOR 1000 TONS.
7). Cost of empty bags @ 1.5Cft per bag.= 11112 Nos. @ Rs. 15/- Each = Rs. 166680/-
16 /conversion/tmp/scratch/421271195.doc
9). P/F steel bars of ½” dia around the corner of plates
and around the bags.
180x20x0.668 = 2405 Lbs
76x36x0.668 = 1828 Lbs
Total = 4233 Lbs
4233x0.4536 = 1920 Kg @ Rs. 5181.55 %Kg = Rs. 99486/-
11). Jack, Micro gauge, magnet stand, pump / delivery pump. = Rs. 50000/-
Total = Rs1350964/-
Add 25% contractor profit/ over head charges on item No. 4,5,7,8,10,12. = Rs. 184616/-
Total =Rs1535580/-
Credit of Material.
17 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF SIDE DRAIN
18 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR CONSTRUCTION OF 2’ SPAN
R.C.C. SLAB CULVERT WITH 44’ ROADWAY.
Gujrat
19 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR CONSTRUCTION OF 4’ SPAN
R.C.C. SLAB CULVERT WITH 44’ ROADWAY
20 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR CONSTRUCTION OF 10’ SPAN CULVERTS
HAVING 44’ CLEAR ROADWAY.
1). Excavation for structure in all type of soil.
1x50x18.50x3’-6” = 3238 Cft
Wing. 4x4x 6x4.50 = 432 Cft
Total = 3670 Cft
@ Rs.1905.75 %0Cft = Rs. 6994/-
2). P.C.C. 1:6:12 in foundation
21 /conversion/tmp/scratch/421271195.doc
Sub Divisional Officer
Provincial R.C Sub Division
Gujrat
Gujrat
22 /conversion/tmp/scratch/421271195.doc
ANALYSIS OF RATE FOR W-BEAM GUARD RAIL
Unit = 100 Rft
A- Fabrication and supply to site.
23 /conversion/tmp/scratch/421271195.doc
Rate P.Rft = 195596/100 = 1955.96
Say = Rs. 1956/- P.Rft
24 /conversion/tmp/scratch/421271195.doc