Escolar Documentos
Profissional Documentos
Cultura Documentos
ABSTRACT: Canals are a major source of water for irrigation, particularly in the Indian subcontinent due to
limited number of days with rainfall. Large areas of the Indian subcontinent have expansive soils which can cause
the lining to crack or fail due to repeated swelling/contracting. On the other hand, unlined canals lose large
quantum of water due to seepage, particularly in sandy soil. Geomembranes of various types are available and can
provide some good solution of this problem. The paper discusses this kind of solution by referencing a specific
canal of the Sardar Sarovar Project which was restored effectively.
bonds to the cation in the clay layer, the cation soils, and the leaching of fertilizers and chemicals
becomes hydrated. The newly hydrated cation has below the root zone through desiccation cracks (by
a larger ionic radius and the clay layers expand to pass flow). In these soils horizontal cracks break
accommodate the larger size [3]. capillary flux of water. On the other hand, swelling
clays can be used to seal landfills storing hazardous
Soil shrinkage is generally confined to the upper wastes. This sealing avoids the downward
portions of a soil. As moisture content decreases, migration of contaminants to groundwater.
capillary stress in the void spaces increases due to Bentonite is used for grouting in earthen
the increased surface tension. This increased embankments of dams. In cropped soils, the
surface tension tends to pull adjacent soil particles development of a dense pattern of cracks on drying
closer together resulting in an overall soil volume improves water drainage and soil aeration, and
decrease. As moisture content continues to decreases surface runoff in sloped areas. Soil
decrease, capillary stress continues to increase, cracking is closely related to the recovery of
which continues to reduce overall volume. porosity damages by compaction.
Appearance
Soils containing expansive clays become very
sticky when wet and usually are characterized by
surface cracks or a "popcorn" texture when dry.
Therefore, the presence of surface cracks is usually
an indication of an expansive soil as shown in Fig.
8 and Fig. 9.
SWELLING SOILS – PROS AND CONS Simplest way of identification of swelling soil is
Soil volumetric changes may cause both appearance but it can not easily give an idea about
unfavorable and favorable effects on human extent of swelling. However, experienced people
activities. Unfavorable effects are the destruction may judge from the depth of cracks how much
of buildings, roads and pipelines in uncropped sever is the problem.
V. P. Kapadia
During January 2010, the engineers of the SSNNL the embankment. However, this solution was not
surveyed “Tanchha Distributary”. This distributary satisfactory because of the propensity of the canal
passes by close to the village of “Anor” of Amod embankment to break repeatedly and suddenly.
Taluka. It was observed that it was leaking very
heavily and the agricultural fields in the Piping from canal banks i.e. sides of the canal and
surrounding areas were found to get inundated with leakage from canal siphons both contributed to the
water. This situation has been occurring for the last seepage. These occurrences used to result in water
three years. The overall condition of the canal was inundation of the surrounding areas.
very bad; the bed of the canal was highly uneven;
the brick lining was significantly disturbed. This is Farmers always had a sense of insecurity because
schematically shown in Fig. 16. of this propensity for sudden embankment
destruction which had the potential to destroy
The deteriorated condition of the canal was visible. crops being grown. In these areas, for the purpose
The bed of the canal was also unusually swollen as of irrigation, the only alternative of canal water has
shown in Fig. 17. There were several other issues. been tube well water. However, the ground water
The banks were disbursed and scattered. quality being poor and inappropriate for
agricultural uses, canal water irrigation was and is
critical to sustain cultivation within the area.
operated, it used to give more and more troubles in phenomenon, obviously signals piping as the
the form of various kinds of failures. passage to water through cracked lining and gaps
in the embankment as well, is unobstructed and
DIAGNOSTIC ANALYSIS many such paths are created after some time in the
How canal embankments in swelling soil fail is embankment which not only saturate the
interesting to understand. Soil of canal embankment very soon but also raise the position
embankments made up of swelling soils tends to of the phreatic line.
swell when comes in to contact of water. Because
concrete or brick lining becomes saturated or some Moreover, at the entry point of piping which is
fine cracks give way to water, soil of embankment really as hollow tubular way through the
can not remain dry for a long time after embankment as visibly shown in Fig. 19, the lining
commissioning of the canal. When the soil comes behaves as if an unsupported slab under heavy load
in contact of water, it swells. During the initial due to water and sagging occurs and the lining
stage of swelling, hogging tendency in lining undergoes failure due to bending and shear. Brick
dominates and concrete or brick lining undergoes lining is more vulnerable than concrete lining due
cracks as it has only little flexural and shear to poor bending strength. This phenomenon finally
strength and then more water seeps through and forms a continuous pipe like mechanism within the
further wetting the soil of embankment takes place. embankment.
Then swelling aggravates gradually. It causes
further upheaval of lining. If the embankment does not have any internal
drainage arrangement, raised phreatic line becomes
a major reason for embankment failure. Heavy
pore pressure in addition to several pipings make
the embankment unstable and it becomes difficult
to judge as to whether disintegration or dispersion
of embankment under pore pressure first takes
place or soil erosion through piping followed by
Fig. 20 Hogging of Lining due to Swelling of Soil crumble or subsidence happens prior to that or both
the kinds of failures are mixed.
GAMUT OF SOLUTIONS
Preliminary engineering work was carried out to
examine possible solutions. Several alternatives
Fig. 21 Sagging of Lining under Load of Water at were considered and benefits and shortcomings of
Mouth of Piping the respective methodologies were examined prior
to deciding on the option of utilizing
geomembranes. Some of the options considered are
discussed in brief. This will allow the reader some
measure of understanding of the comprehensive
nature of the analysis carried out. While, in the
long-run, it is possible that multiple alternatives
Fig. 22 Paths of Piping Through Embankment may be used synergistically and in conjunction at
the same site or at adjacent sites within the canal,
When the canal is closed as per schedule, drying of the discussion below is primarily geared towards
the soil of the embankment results in to shrinking understanding and evaluating the merits of each of
which causes wide cracks and gaps in the the possible alternatives, when utilized
embankment. Subsequent operational phase of the independently.
canal, along with aggravating the swelling
V. P. Kapadia
huge range of possibilities, this usually done by reasons why solution with geomembrane was felt
changes during manufacture. more promising as compared to others.
HDPE has higher perforation resistance and There was a specific stretch of canal which needed
perforation modulus than LDPE which is known as some treatment. This problematic length was
Low Density Poly-Ethylene. Mass density of divided in to three different patches specifically
HDPE can range from 0.93 to 0.97 g/cm3 whereas Ch. 5.65 to 7.17 km, Ch. 7.17 to 7.92 km and Ch.
of LDPE from 0.90 to 0.93 g/cm3. When a pointed 7.92 to 8.67 km. It was decided to use three
object slowly pressed through a polymer different geombranes specifically polyolefins -
membrane at room temperature, then the HDPE HDPE, LDPE, modified polyolefin (IIT Delhi
membrane offers a higher resistance than LDPE innovation) referenced as IITD Polyolefin here
(static load). If a weight from the distance of one onwards. The purpose of going for three materials
meter on a piece of membrane cooled down 0 °C is in three patches of the same canal was to have a
dropped, then the LDPE will may have a higher comparative study and apply the right material in
strength compared to HDPE (dynamical load). The different situations in other canals. These three
ability of LDPE membrane to bend over 90° geomembranes needed to be benchmarked for the
without effecting the performance of the membrane following issues in order to arrive at a suitable
is important when lining hard rock quarries. The techno-commercial comparison:
flexibility of the LDPE compared to the stiffer (1) Critical material properties
HDPE makes a geomembrane follow the contours (2) Ease of application
of the sub-base which again helps to minimize (3) Cost of materials
stress of the installed geomembrane. But at the
same time lower puncture property of LDPE makes A market survey was carried out prior to material
it vulnerable against cropping of vegetation. Mix of procurement. In the process of searching for an
the HDPE and LDPE is also manufactured and effective geomembrane based solution, many
used in some applications and some modified manufacturers of different materials were explored.
polyolefin materials are also designed for specific It was found that HDPE and LDPE geomembrane
purposes. Choosing the right material as sheets with a thickness more than 0.3 mm were
geomembrane depends on the challenges of the very difficult to handle due to weight and bending
problem and sometime some special material is difficulty for the width required. Therefore, 0.3
needed to be developed for better results. mm HDPE and LDPE geomembranes were
selected. The IITD Polyolefin was felt easy to
CONVERGENCE TO FINAL SHAPE OF handle - both weight-wise as well as in its ability to
SOLUTION OF THE CANAL bend and conform to all surfaces. HDPE and LDPE
After a systematic and comprehensive were available with flat surface whereas IITD
consideration of all possible alternatives, the option Polyolefin was having a textured surface. HDPE
of utilizing geomembranes was finally selected. All and LDPE with textured surface could be availed
the options discussed above had been actually in sandwiched form but were found exorbitant
explored on different canals and hence sufficient during market survey.
experience and data of working of each were there.
The canal under consideration i.e. Tanchha (1) Critical Material Properties
Distributary was however, somewhat different in a In evaluating all the geomembranes, a comparison
sense that so many pipings had already taken place of the critical material properties which govern
and all of them were not visible even after removal their water seepage prevention characteristics is of
of lining. Moreover, the canal embankment had primary importance. This comparative exercise
been badly disturbed and was not proper to allow was carried out by IIT, Delhi which sheds light on
direct lining in to the canal section. These were the performance of the respective materials.
V. P. Kapadia
An appropriate method to carry out comparison of unit area was a good determinant of the overall
different geomembranes is to select one critical use costs associated with transportation.
parameter and keep the value of that parameter as a
constant. Then, other parameters can be compared The three materials selected viz. IITD polyolefin,
against each other. HDPE and LDPE had a nearly similar weight per
unit area of 260, 283 and 279 gm/m2 respectively.
Table 1 Comparison of Various Geomembranes The respective thicknesses for these three chosen
(Testing by IIT, Delhi) materials were 0.6, 0.3 and 0.3 mm. Table 1
Property Units IITD HDPE LDPE provides performance comparison of materials
(Test Method) Poly- properties for the above described IITD Polyolefin,
olefin HDPE and LDPE geomembranes based on the
Thickness mm 0.6 0.5 0.25 testing performed at I.I.T. Delhi. Results for very
(ASTM D5199) low thickness of LDPE in the said comparison in
Weight gm/m2 260 470 230 Table 1 can be made comparable with other two
Puncture kN 0.5 0.2 0.06 materials but the difference is large though the
Strength weight is almost equal.
(ASTM D4833)
UV ---- Pass Pass Pass Table 2 Parametric Comparisons of HDPE and
Resistance LDPE (Testing by CIPET, Ahmedabad)
(EN277 HDPE LDPE
For 200 hours) (IS : (IS :
Polymer Type
Breaking kN/m 36 10 2 10889- 2508-
Strength 2004) 1984)
(ASTM D638 Property Units Performance
Type IV)
Thickness mm 0.3 0.3
Breaking % 20 500 100
gm/
Elongation Weight 283 279
m2
(ASTM D638
UV
Type IV) ---- Pass Pass
Resistance
Tear kN 0.20 0.22 0.08
Resistance Tensile Strength
(ASTM D5884) at Break
Water cm/sec 10-6 10-6 Vari- (A) Machine Kg/
(A) 332 (A) 212
Permeability able Direction cm2
(ASTM D1499) (B) Transverse
(B) 272 (B) 189
Direction
In this case, it made sense to keep the weight per
Elongation at
unit area as the parameter of choice and maintain it
Break
as a constant. Weight per unit area was selected
(A) Machine
because this property governed the total amount of % (A) 505 (A) 564
Direction
material used for the project. It also automatically
(B) Transverse
brought to light the inherent intrinsic properties of (B) 543 (B) 696
Direction
the material, which included the most important
Tear Resistance
property of puncture resistance in case of
(A) Machine
geomembranes. Also, it allowed for a direct N/ Not (A) 138
Direction
comparison for other related properties such as mm Provi-
(B) Transverse
breaking strength and tear resistance. Furthermore, ded (B) 161
Direction
from an implementation standpoint, the weight per
Addressing Failure of Canal Embankments in Swelling Soils : A Case Study of Sardar Sarovar Project
could not be expected to avoid bending mechanism this could be achieved without significant
in lining for ever as the grout would tend to slide difficulties. Undulations and edges of the canal
down in the piping with passage of time. Thus, section put challenges against placing of
constructing a new canal was found much different geomembrane.
from restoring an existing canal with many pipings.
This factor perhaps requires much higher tensile At the edges of the canal section, there were two
strength of the geomembrane. possibilities – formation of proper corners in
geomembrane or formation of curved surfaces near
(B) Material Vulnerability the corner edges.
Once the canal section was prepared with proper
profile and longitudinal slope, placing The polyolefin could be bent easily and was found
geomembrane in position became important and to be extremely good for bending ease. With
needed to be done immediately as exposed canal HDPE, the experience was totally opposite. It was
prism was not safe for a long time. Placing of role very difficult to place the HDPE in the canal as it
on site and then putting it in to the canal section, made a chamfered surface at all the edges and
spreading and placing as per the canal section corners in the bed as well as within the key of the
needs some strength of the material itself. One of canal. LDPE was largely unsuitable for this
the advantages of the IITD polyolefin purpose.
geomembrane was that handling was significantly
easier since the material’s inherent properties do
not make it vulnerable to tearing and breakage.
LDPE, in fact, was quite prone to tearing during
laying itself. This phenomenon – ruggedness, was
found not much with the LDPE and it needed
careful handling. HDPE was better that way.
unchanged. The LDPE was found to become softer geomembrane was laid in the canal section, 12 mm
with increase in heat. Brick laying on the placed thick cement mortar layer could not be placed up
geomembrane gave different experiences for on it due to lack of bond. The solution to this issue
different materials. was found in specifying the geometrical lay-out of
the bricks. They were placed frog up i.e. right
(E) Heat Sealing position; and were place closely without joints to
Rolls of 80 to 85 meter length were available for be filled in with cement mortar as pointing. Bricks
all the three materials. Heat sealing was required to were placed to maintain weight balancing on the
be carried out on site. Machine parameters were sides of the canal. Then 18 to 20 mm thick single
optimized for this process. Different machines for mala cement plaster was applied on top of the brick
heat sealing for different materials were used. Even layer. The function of the cement plaster was to
the same machine can be used with different keep proper positioning of the bricks and as well as
parameter settings foe different materials. For all to provide a smooth surface. The inside surface of
three materials, heat sealing on site was a rather the canal was found smoother than the
simple and straightforward process. conventional brick lining.
This testing was carried out by filling water within Further, in construction of new canals, usage of
the upstream and downstream walls and was done geomembranes would be more economical than
for a period of over 60 days. conventional CNS treatment in most cases. Areas
where availability of good soils is a problem, use
In the forthcoming irrigation season i.e. beginning of geomembrane for canal lining can be a boon. In
from 1-10-2011, water flow through the canal was the present time when large infrastructure projects
initiated as is normally done through the canal. No have consumed most of the usable soil mass, canal
seepage or leakage was observed for about a period engineers have hardly any choice for materials for
of two years on either side of the canal. Earlier to designing and constructing new canals; rather, in
the restoration, weed growth inside the canal many cases, only theoretically worked out
through brick lining was a severe problem and the specifications might lead to entanglement in work
bank used to remain saturated and hence outer schedules and contract management owing to
sides of the canal banks remained covered with issues like lead, extra, excess, etc. and hence the
vegetation whereas after restoration with engineers would have to learn to work with locally
geomembrane weed growth inside the section and available soil complemented with necessary
on the outer sides of the bank was also absent when corrections such as geomembranes to be applied to
observed after a year. Since the embankment get the proper performance of the canals.
section was not too wide, a comparative
measurement of hydrostatic pressure in the pre- The most important aspect for any civil
application and post-application scenario was not engineering project is its performance. Canals and
felt useful; only visual observation was resorted to hydraulic structures are practically very difficult to
in order to make assessment of the effectiveness of bring to the required performance level as they
the solutions implemented. involve multidisciplinary issues and need utmost
care in design, selecting the materials and
Flow measurement showed that the roughocity Co- workmanship. Because the surface of the canal
efficient of the canal was close to 0.018. This was a lining could obtain the desired value of roughocity
significant achievement because generally in the co-efficient in the present project, it could attain
canals the roughocity co-efficient taken in the success. That became actually a key factor for the
design consideration is not achieved practically and improved hydraulic performance of the canal.
finally the performance of the canals is affected Changes in conventional practice sometime lead to
whereas in this case, it could be achieved and positive changes if introduced thoughtfully which
hence designed discharge could be flown without could be learnt from this project.
any encroachment in the freeboard.
Some engineering solutions can offer many
Appropriate time-period to make a reliable benefits other than addressing the objective
assessment on comparison of actual performance problem without any additional cost as compared
of the three materials, used in the respective canal to the conventional solutions and save large
sections is three years. However, in this short term maintenance costs which otherwise would have
performance, the results are encouraging. been incurred on the project. Fact that problem of
weed growth and subsequent damage to lining and
CONCLUSION vegetation on outer sides of the canal banks could
Application of geomembrane to canals is a be sorted out has proven this aspect. It was found
promising and viable solution to check the problem that if cost of CNS was compared with the
of swelling of soil and consequent problems geomembrane based solution, conventional
leading to failures of canals. For restoration of solution was not any economy. However, if other
deteriorated condition of the canals, the above benefits and reduction in maintenance cost, etc. are
implementations have demonstrated that they properly counted in the life cycle cost analysis of
afford potential to provide an effective solution. the project, their value addition to the future
V. P. Kapadia
ACKNOWLEDGMENT
Valuable contribution of Dr. B.L. Deopura,
Department of Textile Technology and Dr. B.R.
Chahar, Department of Civil Engineering, IIT,
Delhi to the pilot project of canal restoration with
geomembrane is hereby acknowledged.