Você está na página 1de 195

Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Operation of Distributed Networks with


Distributed Generations Under the Impact of
Load and Generation Uncertainties

Soumyabrata Barik

Indian Institute of Technology Kharagpur

May 14 2019

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
1 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Objectives

I The purpose of this thesis is to develop different strategies


for the effective operation of distribution network in
presence of different DGs by considering the uncertainties.
I To develop a new meta-heuristic optimization technique for
placement of DGs, that mimics the athletes in a
tournament.
I To develop a economic operation of distribution network in
presence of renewable DGs and shunt capacitors based on
seasonal variation of load demand.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
2 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Objectives

I To propose a new strategy to boost and maintain the


voltage of the remotely located buses by placing DGs with
using the concept of novel Q − P QV bus pair method.
I To develop a strategy to consider a predefined contracted
amount of power exchange between the upstream grid and
the distribution networks, by using the concept of
P QV δ-zero bus concept.
I Proposal of a strategy to analyze the effect of FFC DGs in
presence of uncertainties caused by renewable sources and
the load demand.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
3 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Load Demand and Renewable Generation


Along with Uncertainty Modelling

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
3 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Load Demand and Renewable DGs


Load modelling

I Average time varying load demand profiles are considered.


I Load data are collected from the load dispatch centre and
normalized based on the peak load.
I The per unit load patterns are considered, and the loads
connected to each bus at each load level is modified
according to
P Li (t)=P Lpeak
i ×Loadpu (t)
(1)
QLi (t)=QLpeak
i ×Loadpu (t)

for {i∈N|2≤i≤N B} and t represents number of load hours.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
4 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Load Demand and Renewable DGs


Load modelling

I Load growth is a natural phenomena in the distribution


network which is modelled as
P Li (t)=P Lbase
i (t)×(1+gr)nLG
(2)
QLi (t)=QLbase
i (t)×(1+gr)nLG

I The uncertainty in the load demand is modelled as Normal


distribution  2
x−µload (t)
−1
2
t
fload (x)= 1 √
σload (t) 2π
e σload (t)
(3)
I The mean or the expected value of the active and the
reactive power loads
peak
µP pu
i (t)=Load (t)P Li
(4)
µQ pu peak
i (t)=Load (t)QLi

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
5 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Load Demand and Renewable DGs


Solar modelling

I Solar units convert the solar irradiation into usable power.


I The power generation from solar PV plant at every instant
depends on the solar irradiance and the ambient
temperature.
S(t)
Psolar (t)=PST C S
ST C
(1+Ki (T (t)−TST C )) (5)
I The average solar irradiation and the solar power patterns
are collected from the 100kWp solar plant installed at the
rooftop of IIT Kharagpur.
I The power generation pattern of the solar plant is
normalized w.r.t the peak power produced.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
6 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Load Demand and Renewable DGs


Solar modelling

I The intermittent nature of the solar power generation is


modelled by Beta distribution as

Γ(α(t)+β(t))
t (S)=
fsol Γ(α(t))Γ(β(t))
(S(t))α(t)−1 (1−S(t))β(t)−1 (6)
I α and β are shape factors given as
 
µsol (t)(1+µsol (t))
β(t) =(1−µsol (t)) −1
(σsol (t))2
(7)
α(t) = µ(sol
1−µ
(t)βsol (t)
(t))
sol

I The mean value of solar power generation with solar DG


rating
rating Psolar is
rating
µsol (t)=αsolar
pu (t)Psolar (8)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
7 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Load Demand and Renewable DGs


Wind modelling

I Wind speed is converted to usable power by the wind


turbines. Power extracted from the wind is
PW ind = 12 ρAV 3 Cp (λ,θ) (9)
I The unpredictable behavior of the wind speed can be well
fitted in Weibull distribution. The wind velocity v t (m/s) at
time instant t is given by
 
v(t)
kw (t)

v(t)
kw (t)−1 −
t
fwind (v)= c(t) c(t)
e c(t)
(10)
I The mean value of the wind power generation with wind
rating
DG rating Pwind is
rating
µwind (t)=αwind
pu (t)Pwind (11)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
8 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Load Demand and Renewable DGs


Wind modelling

I c(t) is the scale factor at time t that depends on the shape


factor kw (t)(> 0).
Scale factor at time t is given by

µ (t)
c(t)=  wind  (12)
Γ 1+ 1
kw (t)

I Shape factor can be calculated by solving the non-linear


equation as
 
 2 Γ 1+ 2
σwind (t) kw (t)
µwind (t)
−  2 +1=0 (13)
Γ 1+ 2
kw (t)

I However, the shape factor can also be approximated as

σwind (t) −1.086


 
kw (t)= µwind (t)
(14)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
9 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test and Objective Functions With Equality


and Inequality Constraints

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
9 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Optimization Problem

I Optimization methods seek the best possible/optimal


solution for a problem.
I An optimization problem can be expressed as a
minimization problem as

minimize
n
f (X)
X∈<
subject to gk (X) ≤ 0, k = 1, . . . , K (15)
hl (X) = 0, l = 1, . . . , L
I The penalty method is used to transform the constrained
optimization to unconstrained optimization problem
PK PL
f mod (X)=f (X)+ k=1 φk gk2 (X)+ l=1 ψk h2l (X) (16)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
10 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test Functions
Schwefel’s Function

I This test function is a multimodal and seperable in nature


and expressed as
Pn √
f (X)= i=1 −xi sin( |xi | ) (17)
n×418.9829

I n is an integer number and the unknown variables are in


the range of −500≤xi ≤500.
I The minimum value of the objective function to be
obtained is f (X ∗ )=−1, for the optimum values of
x∗ (i) = 420.9687, ∀i = 1, 2, · · · , n.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
11 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test Functions
Schwefel’s Function

0.5

-0.5

-1
500
500
400
300
0 200
100
0
-100
-200
-300
-500 -400
-500

Figure – 3D plot of Schwefel’s function

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
12 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test Functions
Michalewicz Function

I Michalewicz function is a multimodal test function with d!


number of local minima. The function is mathematically
expressed as

ix2
 
Pd
f (X)=− i=1 sin(xi )sin2m π
i (18)
I The parameter m gives an idea about the steepness.
I This test function is evaluated on 0 ≤ x1 , x2 , · · · , xd ≤ π
and for n = 2, the minima is f (X ∗ )=−1.8013 and for n = 5,
the minima is f (X ∗ )=−0.4687.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
13 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test Functions
Michalewicz Function

0.5

-0.5

-1

-1.5

-2
4
3.5
3 4
2.5 3.5
2 3
2.5
1.5 2
1 1.5
0.5 1
0.5
0 0

Figure – 3D plot of Michalewicz function

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
14 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test Functions
Goldstein-Price’s Function

I Goldstein Price Function is multimodal and non-scalable


function. The mathematical expression is

f (X)=fa (X)×fb (X) (19)


where
fa (X)=1+(x1 +x2 +1)2 (19−14x1 +3x21 −14x2 +6x1 x2 +3x22 )
(20)
fb (X)=30+(2x1 −3x2 )2 (18−32x1 +12x21 +48x2 −36x1 x2 +27x22 )

I The two input variables defined as x1 ∈ [−2, 2] and


x2 ∈ [−2, 2]. The global optima is f (X ∗ )=3 at x∗1 = 0 and
x∗2 = −1.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
15 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test Functions
Goldstein-Price’s Function

×105

10

0
2
1.5
1 2
0.5 1.5
0 1
0.5
-0.5 0
-1 -0.5
-1.5 -1
-1.5
-2 -2

Figure – 3D plot of Goldstein-Prices’s function

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
16 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test Functions
Six Hump Camel Back Function

I This function is multimodal and non-seperable. It has total


six minima, among which two are global. The mathematical
expression of the test function is

f (X)=(4−2.1x21 + 31 x41 )x21 +x1 x2 +(−4+4x22 )x22 (21)


I The two input variables are x1 ∈ [−2, 2] and x2 ∈ [−3, 3].
The global optima is f (X ∗ )=−1.0316 at x∗1 = −0.0898, 0.0898
and x∗2 = 0.7126, −0.7126.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
17 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test Functions
Six Hump Camel Back Function

400

300

200

100

-100
3
2 3
2.5
1 2
1.5
0 1
0.5
0
-1 -0.5
-1
-2 -1.5
-2

Figure – 3D plot of Six Hump Camel Back function

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
18 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test Functions
Schaffer’s Function

I This is a unimodal, non-seperable and non-convex function


in nature. The mathematical expression is
cos2 sin |x2
( ( 2
))
1 −x2 | −0.5
f (X)=0.5+ 2 (22)
(1+0.001 x2(
1 +x2
2
))
I The two input variables are −100 ≤ x1 , x2 ≤ 100. The
global optima is f (X ∗ )=0.292579 at the minima points x∗1 = 0
and x∗2 = 1.253115.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
19 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test Functions
Schaffer’s Function

0.8

0.6

0.4

0.2
100
50 100
0 50
0
-50 -50
-100 -100

Figure – 3D plot Schaffer’s function

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
20 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Practical Engineering Problems


Spring Design

I The weight of the spring is minimized.


I It has three design variables namely diameter of the wire
0.05 ≤ x1 ≤ 2, mean diameter of the coil (0.25 ≤ x2 ≤ 1.3),
and the active coil numbers 2 ≤ x3 ≤ 15.
I The objective function is
f (X)=(x3 +2)x2 x21 (23)
x32 x3 ≤0
g1 (X)=1−
71785x41
4x2
2 −x1 x2 1
g2 (X)= + −1≤0
(
12566 x2 x3 4
) 5108x2
1 −x1 1 (24)
140.45x
g3 (X)=1− 2 1 ≤0
x2 x3

x1 +x2
g4 (X)= 1.5
−1≤0

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
21 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Practical Engineering Problems


Pressure Vessel Design

I The fabrication cost is to be minimized.


I The four design variables are thickness of shell 0≤ x1 ≤ 99,
head 0 ≤ x2 ≤ 99, the inner radius 10 ≤ x3 ≤ 200 and the
length of the cylindrical section 10 ≤ x4 ≤ 200.
I The objective function is

f (X)=0.6224x1 x3 x4 +1.7781x2 x23 +3.1661x21 x4 +19.84x21 x3 (25)

g1 (X) =−x1 +0.0193x3 ≤0


g2 (X) =−x3 +0.00954x3 ≤0
(26)
g3 (X) =−πx23 x4 − 34 πx33 +1296000≤0
g4 (X) =x4 −240≤0
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
22 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Objective Functions

I The operation of the distribution networks in presence of


DGs and capacitors needs the the proper sizing and siting
strategies.
I The wrongly sized and placed DGs and the capacitors may
lead to the detrimental effect on the distribution network
and causes maloperation.
I The different combinations (weightage approach) of active
power loss, voltage deviation, and the DG cost are
considered as the objective functions.
I The weighting factors are selected such as
PNobj
0≤wi ≤1 and i=1 wi =1 (27)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
23 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Objective Functions
Function-1

I The active power loss in the distribution network in the


presence of DGs and (or) capacitors is considered as the
primary objective function to reduce the burden of the
network. P LIF is defined as the factor of base case loss
mod
Ploss
(min)J1 =P LIF =
P base
(28)
loss

I The power loss Ploss is defined as the


N BN B
Ploss = 12 [<{Yij }][|Vi |2 +|Vj |2 −2|Vi ||Vj |cosδij ] (29)
P P
i=1 j=1

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
24 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Objective Functions
Function-2

I Along with the active power loss, the voltage deviation of


the network can also be considered as the other essential
objective function to improve the voltage profile of the
distribution network.
I The objective function is constructed with different
combinations of weighting factors.

min J2 =w1 (P LIF )+w2 (V DIF ) (30)

I V DI is the voltage deviation index of the system defined as


mod
V DIF = V Dbase
VD
(31)
and
PN B 2
V D= N1B i=1 (Vi −1.0) (32)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
25 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Objective Functions
Function-3

I This objective function includes the active power loss,


voltage deviation and the operation cost of the DGs.
I With the weighting factors, the objective function can be
constructed as
min J3 =w1 P LIF +w2 V DIF +w3 CF (33)
CF is the cost factor of the DGs and can be defined as
PN DG
i=1 fcosti (PDG )
CF = (34)
( ) fcost P max
i DG

I The cost function fcosti depends on the amount of active


power injected by the DG, and is defined as
2
fcost (PDG )=a+bPDG +cPDG (35)
I The a, b, c are the three cost coefficients.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
26 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Operational Constraints
Equality Constraints

I The objective functions are used to solve under the


consideration of some equality and inequality constraints.
I The active and the reactive power balance should be
maintained as
peak P DG P BR
sgnP grid (t)− N
P B
i=2 P Li Loadpu (t)+ N
l=1 PDGl (t)− N
j=1 Plossj (t)=0
PN DG P BR
QLpeak
PN B
sgnQgrid (t)− i=2 i Loadpu (t)+ l=1 QDGl (t)− N
j=1 Qlossj (t)=0

(36)
I sgn defines the mode of the power exchange with the main
grid, i.e. 



 +1 when the power is imported from the grid

sgn= −1
 when the power is exported to the grid (37)


0

when no power is exchanged with the grid
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
27 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Operational Constraints
Inequality Constraints

I The DGs and (or) capacitor are placed with the bus
voltages maintained within lower and upper voltage levels
as
Vmin ≤Vi (t)≤Vmax ∀i∈N B (38)
I Power supplied by the DGs at any bus should be less than
the total load demand
P Lpeak
PN B
PDG (t)≤ i=2 i Loadpu (t) (39)
I DG size should be always within the lower and the upper
limit as
min ≤P
PDG max
DG ≤PDG (40)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
28 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Operational Constraints
Inequality Constraints

I The power exchanged from the main grid is decided by the


utility and the time of use tariff (TOU) and should be kept
within certain pre-specified limits
grid grid
Pmin ≤P grid (t)≤Pmax (41)
where
grid PN B
Pmin =contmin
pu i=2 P LP
i
eak

grid PN B (42)
Pmax =contmax
pu i=2 P LP
i
eak

I The current flowing through any branch of the modified


distribution network should be always within
rated
max|(Iij orIji )|≤Iij i,j∈N B|i6=j (43)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
29 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test Systems Considered


33 Bus Distribution Network

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
30 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Test Systems Considered


69 Bus Distribution Network

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
31 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

A Novel Athlete Run Based Optimization


Method (ARBO)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
31 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Athlete Run Based Optimization (ARBO)


Optimization method

I ARBO is a novel meta-heuristic population based (swarm


based) optimization algorithm where the key inspiration
comes from finding out the best athlete in a tournament.
I The quality of the athletes is judged as per their
performance in the race.
I Athletes can improve their performance (fitness) only after
hard practices.
I Initially, the athletes are chosen according to their best and
worst performance as
X=rangemin +rand1 ×(rangemax −rangemin ) (44)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
32 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Athlete Run Based Optimization (ARBO)


Optimization method

I After the competition in each group, one best candidate is


chosen and denoted by Xbest .
I Within these all Xbest s, one will be best of all and is
lgroup
denoted by Xbest .
lgroup
I All the Xbest s will try to achieve Xbest by more practice,
and as a result, some Xbest s may be even better qualified
lgroup
than Xbest .
I This can happen for each group denoted by the variable i
by the following relation
 
new =X old +C×rand × X lgroup −X old
Xbest (45)
i best i
2 best best W (k) i

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
33 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Athlete Run Based Optimization (ARBO)


Optimization method

I W is the weighting factor which is used to vary from


iteration to iteration by
iter
W (iter)=Wmax ×e− M AXIT ER (46)
Wmax is the maximum value of the weighting factor and
considered as 1.2.
Some situations may arise in the relation of Xbest in (45)
new old
1. When rand = 0, then Xbest = Xbest i.e., no improvement.
1 new lgroup
2. When rand = 2 , then Xbest = Xbest , i.e., due to the
practice this athlete has achieved the best position.
new lgroup old
3. When rand = 1, then Xbest = 2 × Xbest − Xbest , means,
due to hard practice this athlete has reached a better
lgroup
position than the best i.e., Xbest .
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
34 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Athlete Run Based Optimization (ARBO)


Optimization method

lgroup
I After practice, the athletes will be updated and Xbest will
be modified.
lgroup sup
I The new Xbest after the practice is denoted by Xbest .
I After the final competition the best athlete shall be
emerged and for the next tournament the athletes will try
to follow the performance record of the champion of the
previous tournament and update themselves.
I The selection of the athletes for the next tournament
(iteration) is done

X=rangemin +rand3 ×(f inal−rangemin )+rand4 ×(rangemax −f inal)


(47)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
35 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Athlete Run Based Optimization (ARBO)


Flow Chart

Find the best among the


updated values of X best
and termed as sup
X best
Start

Read input data No Yes


iter 1
?
Generate random
populations
No
sup sup fitness (iter - 1) fitness (iter )
iter = 1 3 X bestprev ← X best ? Yes

1
sup
final ← X best

Yes No
iter MAXITER
sup sup Update
X bestprev ← X best
? X sup
best

Store the final


Calculate the solutions Generate new
athletes Check the limits
fitness value
X best
Fitness for the
final solutions
iter = iter + 1
fitness (iter ) ¬ fitness (iter 1)
Find out the best
for each group
STOP

Calculate the sup sup


X best ← X bestprev
weighting factor
3 Check the limits Update
X sup
best
1

Find best among all


the X best
and termed as
Xlgbestroup

Check the limits of


X best

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
36 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Application of ARBO in Test Functions


Comparison of Schwefel’s Function

I Minimum value by ARBO technique is f (X) = −1 for


xi = 420.96. After 30 runs the mean and standard deviation
are -0.9955 and 0.002345 respectively.
0

-0.1

-0.2
PSO
-0.3 TLBO
ARBO
-0.4
Fitness Value

-0.5

-0.6

-0.7

-0.8

-0.9

-1
0 50 100 150 200 250 300 350 400 450 500
Number of Iterations

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
37 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Application of ARBO in Test Functions


Comparison of Langermann’s Function

I Minimum value by ARBO technique is f (X) = −1.0809 for


x1 = 9.6817 and x2 = 0.6681. After 30 runs the mean and
standard deviation are -1.0807 and 1.9 × 10−9 respectively.
-0.85

-0.9
PSO
TLBO
ARBO
Fitness Value

-0.95

-1

-1.05

-1.1
0 50 100 150 200 250 300 350 400 450 500
Number of Iterations

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
38 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Application of ARBO in Test Functions


Comparison of Michalewicz Function

I Minimum value by ARBO technique is f (X) = −4.585 for


x1 = 2.207, x2 = 1.558, x3 = 1.295, x4 = 1.113 and
x5 = 1.708 for d = 5. After 30 runs the mean and standard
deviation are -4.425 and 0.081 respectively.
-1.5

PSO
-2
TLBO
ARBO
-2.5
Fitness Value

-3

-3.5

-4

-4.5

-5
0 50 100 150 200 250 300 350 400 450 500
Number of Iterations

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
39 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Application of ARBO in Test Functions


Comparison of Goldstein-Price’s Function

I Minimum value by ARBO technique is f (X) = 3 for x1 = 0


and x2 = −1. After 30 runs the mean and standard
deviation are 3.0013 and 0.0019 respectively.
12

11

10
PSO
9 TLBO
ARBO
Fitness Value

2
0 50 100 150 200 250 300 350 400 450 500
Number of Iterations

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
40 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Application of ARBO in Test Functions


Comparison of Six Hump Camel Back Function

I Minimum value by ARBO technique is f (X) = −1.0316 for


x1 = 0.089, −0.089 and x2 = −0.7126, 0.7126. After 30 runs
the mean and standard deviation are -1.03167 and
7.86975 × 10−6 respectively.
-0.96

-0.97

-0.98
PSO
TLBO
-0.99 ARBO
Fitness Value

-1

-1.01

-1.02

-1.03

-1.04

-1.05
0 50 100 150 200 250 300 350 400 450 500
Number of Iteratioins

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
41 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Application of ARBO in Test Functions


Comparison of Schaffer’s Function

I Minimum value by ARBO technique is f (X) = 0.29258 for


x1 = 0 and x2 = 1.255. After 30 runs the mean and
standard deviation are 0.29259 and 1.57 × 10−5 respectively.
0.48

0.46

0.44 PSO
TLBO
0.42 ARBO
Fitness Value

0.4

0.38

0.36

0.34

0.32

0.3

0.28
0 50 100 150 200 250 300 350 400 450 500
Number of Iterations

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
42 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Application of ARBO in Engineering Problems


Comparison of Spring Design

I Minimum value by ARBO technique is f (X) = 0.01295 for


x1 = 0.0516, x2 = 0.3529, and x3 = 11.7673. After 30 runs
the mean and standard deviation are 0.013 and 0.00021
respectively.
0.25

0.2
PSO
TLBO
ARBO
Fitness Value

0.15

0.1

0.05

0
0 50 100 150 200 250 300 350 400 450 500
Number of Iterations

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
43 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Application of ARBO in Engineering Problems


Comparison of Pressure Vessel Design

I Minimum value by ARBO technique is f (X) = 6613.75 for


x1 = 0.8458, x2 = 0.4669, x3 = 43.140 and x4 = 178.4323.
After 30 runs the mean and standard deviation are 8053
and 553.545 respectively.
×105
4

3.5

3 PSO
TLBO
2.5 ARBO
Fitness Value

1.5

0.5

0
0 50 100 150 200 250 300 350 400 450 500
Number of Iterations

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
44 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Application of ARBO in Engineering Problems


Comparison of Welded Beam Design

I Minimum value by ARBO technique is f (X) = 1.8328 for


x1 = 0.2064, x2 = 3.5724, x3 = 8.8914 and x4 = 0.2215.
After 30 runs the mean and standard deviation are 1.9493
and 0.0592 respectively.
30

25
PSO
TLBO
ARBO
20
Fitness Value

15

10

0 50 100 150 200 250 300 350 400 450 500


Number of Iterations

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
45 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Sizing of DGs and Shunt Capacitors With


Seasonal Load Variation

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
45 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Load Pattern
I An average hourly load profile for one year is considered.
I The four seasons are considered in a year mainly Winter
(1 − 8th and 44 − 52nd week), Spring (9 − 17th week),
Summer (18 − 30th week) and Fall (31 − 43rd week).

0.95
Normalized Load Demand Pattern (pu)

0.9

0.85

0.8

0.75 Winter Spring Summer Fall

0.7

0.65

0.6

0.55
1 10 20 30 40 50 60 70 80 90 96
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
46 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Optimal Sizes of Renewable DGs


Solar DG

I The peak solar power is generated during Fall season at


12.00 (noon), i.e. t = 85 hours.
I Therefore, the equation (1) is written as
P Li (t=85)=P Lpeak
i ×0.6962
(48)
QLi (t=85)=QLpeak
i ×0.6962

0.9
Normalized Solar Power Generation Pattern (pu)

0.8

0.7

0.6

0.5 Winter Spring Summer Fall

0.4

0.3

0.2

0.1

0
1 10 20 30 40 50 60 70 80 90 96
Hour
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
47 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Optimal Sizes of Renewable DGs


Solar DG (33 Bus)

I Optimum solar power injection is determined by minimizing


the objective function which is the combination of active
power loss and voltage deviation with w1 = w2 = 0.5.
0.5

0.45

0.4
Objective Function J

0.35

0.3 Minimum size of


Solar DG

0.25

0.2

0.15
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Solar DG size

I The solar power injection is Psolar


30 30
=1457≈1460kW =Psolarmax .
I For all the other load hours (t 6= 85)
30
Psolar 30
(t)=Psolarmax αpu
solar (t) (49)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
48 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Optimal Sizes of Renewable DGs


Solar DG (69 Bus)

I Optimum solar power injection is determined by minimizing


the objective function which is the combination of active
power loss and voltage deviation with w1 = w2 = 0.5.
0.5

0.45

0.4
Objective Function J

0.35

0.3

0.25

Minimum size
0.2 of Solar DG

0.15

0.1
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Solar DG size

I The solar power injection is Psolar


61 61
=1548≈1550kW =Psolarmax .
I For all the other load hours (t 6= 85)
61
Psolar 61
(t)=Psolarmax αpu
solar (t) (50)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
49 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Optimal Sizes of Renewable DGs


Panel Generating Factor (PGF)

I The actual size of the solar PV depends on the locations


and the climate condition and can be taken care of by the
term PGF defined as
PGF= Peak Energy in kWh
power in kW (kWp)
(51)
I The PGF is calculated from the average yearly solar power
generation.
I From the data obtained from rooftop installed 100kWp
solar plant, the PGF is obtained as 3.52.
I The actual size of the solar plant using PGF is
avg
E (pu) 30
Ssolar (kW p)= solar Psolarmax (kW )
P GF
E
avg
(pu) 61
(52)
Ssolar (kW p)= solar
P GF
Psolarmax (kW )

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
50 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Optimal Sizes of Renewable DGs


Average Annual Solar Generation Profile

avg
I The average annual solar production Esolar (pu) is
calculated from the generation profile
Yearly Average Solar Power (IIT KGP 100 kW Plant)

60

50

40

30

20

10

0
12AM 1AM 2AM 3AM 4AM 5AM 6AM 7AM 8AM 9AM 10AM 11AM 12PM 1PM 2PM 3PM 4PM 5PM 6PM 7PM 8PM 9PM 10PM 11PM
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
51 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Optimal Sizes of Renewable DGs


Wind DG

I The peak wind power is generated at t = 14 & t = 17 hour


with load 0.8416 pu and 0.7974 pu during Winter.
I Therefore, the equation (1) is written as
P Li (t=85)=P Lpeak
i ×0.8416
(53)
QLi (t=85)=QLpeak
i ×0.8416

0.9
Normalized Wind Power Generation Pattern (pu)

0.8

0.7

0.6

0.5 Winter Spring Summer Fall

0.4

0.3

0.2

0.1

0
1 10 20 30 40 50 60 70 80 90 96
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
52 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Optimal Sizes of Renewable DGs


Wind DG (33 Bus)

I Optimum wind power injection is determined by minimizing


the objective function which is the combination of active
power loss and voltage deviation with w1 = w2 = 0.5.
0.7

0.65

0.6
Objective Function J

0.55

0.5

0.45
Minimum size
0.4 of Wind DG

0.35

0.3

0.25

0.2
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Wind DG size

I The wind power injection is 13 =1362≈1370kW =P 13


Pwind windmax

I For all the other load hours (t 6= 85)


pu
13 (t)=P 13
Pwind windmax αwind (t) (54)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
53 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Optimal Sizes of Renewable DGs


Wind DG (69 Bus)

I Optimum wind power injection is determined by minimizing


the objective function which is the combination of active
power loss and voltage deviation with w1 = w2 = 0.5.
0.7

0.65
Objective Function J

0.6

Minimum size
0.55
of Wind DG

0.5

0.45
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Wind DG size

I The wind power injection is windmax .


17 =948≈950kW =P 17
Pwind
I For all the other load hours (t 6= 85)
pu
17 (t)=P 17
Pwind windmax αwind (t) (55)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
54 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Placement of the Capacitors


Fixed and Switched Capacitors

I The installation of shunt capacitors as the source of


reactive power is popular method for improving voltage
profile and power factor.
I Along with the DGs, optimal placement,and sizing of fixed
and switched shunt capacitors for varying load level is
considered for better voltage profile.
I The capacitor sizes obtained by the method at an average
low load level are considered as fixed capacitors which will
remain connected throughout the year.
I With the increment in load level, the switched capacitors
are opted to add as per the requirements.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
55 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Placement of the Capacitors


Selection of Average Load Levels

I Different load levels are considered to reduce the


computational time for obtaining fixed and switched
capacitors.
I The pu load pattern is subdivided into four types of average
load levels such as low, medium, high and very high.
1

Very High
0.95 Load Level
Normalized Load Demand Pattern (pu)

0.9

0.85 High Load


Level

0.8
Medium
Load Level
0.75

0.7

0.65
Low Load
Level
0.6

0.55
1 10 20 30 40 50 60 70 80 90 96
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
56 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Placement of the Capacitors


Fixed and Switched capacitors in 33 bus

I The locations of the shunt capacitors are obtained as bus-7,


bus-30 and bus-15 for the 33 bus distribution network.
0.45
Determination of first capacitor
Determination of second capacitor
Determination of third capacitor
0.4
Objective Function J

0.35

0.3

0.25

0.2
2 5 10 15 20 25 30 33
Bus number

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
57 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Placement of the Capacitors


Fixed and Switched capacitors in 69 bus

I The locations of the shunt capacitors are obtained as


bus-61, bus-12 and bus-56 for the 69 bus distribution
network.
0.4
Determination of first capacitor
Determination of second capacitor
0.38 Determination of third capacitor

0.36

0.34
Objective Function J

0.32

0.3

0.28

0.26

0.24

0.22
2 7 12 17 22 27 32 37 42 47 52 57 62 67 69
Bus number

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
58 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Cost-Benefit (CB) Analysis for DGs and Capacitors


Placement
I Investment for extension or modification of a system is
viable if it is economically sound.
I Capital costs, operation and maintenance costs have been
considered for CB analysis.
I The annual installment cost is defined as
Cinst =(Csolar Ssolar +Cwind Swind )CRFDG +
Nf ixed
!
Nswitched
f ixed P f ixed switched
P switched CRF
CCap Scap i
+CCap Scap j Cap
i=1 j=1

(56)
I The capital recovery factor for the DGs and the capacitors
k(1+k)n
CRF = (1+k)n −1 (57)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
59 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Cost-Benefit (CB) Analysis for DGs and Capacitors


Placement
I The annual operation and maintenance cost is defined as
96
(OMsolar Ssolar αpu pu
solar (t)+OMwind Swind αwind (t)) (58)
P
OM =91.25
j=1

I The amount of energy saved annually is given by


96  ∗ base ∗ DGcap

<(V˜s I˜s ) −<(V˜s I˜s ) (59)
P
Esavings =91.25 ∆t
j=1

I To get the profit


Ke Esavings −(AI+OMDG )>0
AI+OMDG
Ke > Esavings
(60)

I Net profit can be expressed as


P rof it=Esavings (Keconsidered −Kecalculated ) (61)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
60 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
Case Studies

Four different scenarios are considered


I Scenario-1 : Base Case
I Scenario-2 : Both Solar and Wind DGs
I Scenario-3 : Switched and Fixed Capacitors
I Scenario-4 : Solar and, wind DGs and Shunt Capacitors

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
61 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
33 Bus

Cost of the electricity Keconsidered is taken as 0.18$/kWhr. The


costs of the fixed and the switched capacitors are considered as
$3/kVAr and $9/kVAr

Case E save Kecalculated profit/hr V min V max


(MWhr) ($/kWh) ($) (pu) (pu)
Scenario-1 0 - - 0.913 1.0
Scenario-2 7340.4 0.116 57.27 0.94 1.0
Scenario-3 6248.0 0.0222 1.125 0.957 1.02
Scenario-4 7383.7 0.111 58 0.98 1.02

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
62 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
Active Power Loss Profile (33 Bus)

220

200
Summer Fall
Winter Spring
180 Bare Condition
With DGs only
160 With Caps only
Power Loss (kW)

With DGs and Caps


140

120

100

80

60

40
1 10 20 30 40 50 60 70 80 90 96
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
63 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
Peak Load Voltage Profile (33 Bus)

1.01

0.99 Bare Condition


With DGs only
0.98 With Caps only
Voltage magnitude (in pu)

With DGs and Caps


0.97

0.96

0.95

0.94

0.93

0.92

0.91
1 5 10 15 20 25 30 33
Bus number

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
64 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
69 Bus

Cost of the electricity Keconsidered is taken as 0.18$/kWhr. The


costs of the fixed and the switched capacitors are considered as
$3/kVAr and $9/kVAr.

Case E save Kecalculated profit/hr V min V max


(MWhr) ($/kWh) ($) (pu) (pu)
Scenario-1 0 - - 0.909 1.0
Scenario-2 6441.4 0.1157 47.28 0.953 1.0
Scenario-3 157.3 0.01154 3.019 0.94 1.0
Scenario-4 6576.3 0.1136 49.48 0.982 1.0

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
65 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
Active Power Loss Profile (69 Bus)

250

Bare Condition
With DGs only
With Caps only
200 With DGs and Caps
Power Loss (kW)

150

100

50

Winter Spring Summer Fall

0
1 10 20 30 40 50 60 70 80 90 96
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
66 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
Peak Load Voltage Profile (69 Bus)

1.01

0.98
Voltage magnitude (in pu)

0.96

0.94 Bare Condition


With DGs only
With Caps only
With DGs and Caps
0.92

0.9
1 5 10 15 20 25 30 35 40 45 50 55 60 65 69
Bus number

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
67 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Power Loss Profile with Load Growth (7%)


33 Bus

I After 10 years, the active power loss reduces from 937.12


kW to 347 kW.
I After 5 years, the minimum voltage remains at 0.9465 pu.
1000
Bare Condition
900
With DGs only
With Caps only
800
With DGs and Caps
700
Active Power Loss

600

500

400

300

200

100

0
0 1 2 3 4 5 6 7 8 9 10
Year

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
68 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Power Loss Profile with Load Growth (7%)


69 Bus

I After 10 years, the active power loss reduces from 1083 kW


to 336.8 kW.
I After 5 years, the minimum voltage remains at 0.945 pu.
1200

Bare Condition
1000 With DGs only
With Caps only
With DGs and Caps
Active Power Loss

800

600

400

200

0
0 1 2 3 4 5 6 7 8 9 10
Year

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
69 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Novel Q − P QV Bus Pair Method of DG


Placement to Maintain the Volatge of
Remotely Located Bus

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
69 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

A Novel Q − P QV Bus Pair Method

I A novel method of finding out the locations and sizes of


DGs based on the concept of Q and P QV bus pair is
developed.
I The P QV bus is the remotely located bus where the
voltage is to be improved.
I The Q is the bus, at which the DG is to be placed.
I In Q bus, only the reactive power is known, whereas the
active power, the voltage magnitude, and the voltage angle
are unknown.
I In P QV bus, only the voltage angle is unknown, whereas
all the other quantities are known.
I Active power injection at Q bus plus the load demand is
the expected size of the DG placed at Q bus.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
70 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

A Novel Q − P QV Bus Pair Method


Modification of Jacobian Matrix

I This new pair of buses modify the Jacobian Matrix in the


load flow technique.
I In a distribution network, assume that except the slack bus,
Q bus (mth )and P QV bus (nth ) all the other buses are of
P Q type.
I The complex power injection at the bus-i is
Sipow =Vi
PN B
j=1 Yij∗ Vj∗ (62)
I The real power mismatch (∆Pi ) of the ith bus is given as

∂Pi P B ∂Pi
∆Pi = N
P B
j=2 ∂δj
∆δj + N
j=2 ∂|Vj | ∆|Vj | (63)
j6=n

This is valid for i∈{2,3,··· ,N B}\{m}.


Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
71 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

A Novel Q − P QV Bus Pair Method


Modification of Jacobian Matrix

I The reactive power mismatch (∆Qi ) of the ith bus is given


as
P B ∂Qi PN B ∂Qi
∆Qi = N
j=2 ∂δj ∆δj + j=2 ∂|Vj | ∆|Vj | (64)
j6=n
This is valid for i∈{2,3,··· ,N B}.
I For the sake of clarity a 5 bus sample network is selected as


 


     



Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
72 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

A Novel Q − P QV Bus Pair Method


Modification of Jacobian Matrix

The relation between the power mismatch matrix and the state
variable matrix is given by

 ∂P3 ∂P3 ∂P3 ∂P3 ∂P3 ∂P3 ∂P3



  ∂δ2 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V5 |  
∆P3  ∂P4 ∂P4 ∂P4 ∂P4 ∂P4 ∂P4 ∂P4  ∆δ2
 ∆P4   ∂δ2
 ∂P5 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V5 |   ∆δ3 
  ∂P5 ∂P5 ∂P5 ∂P5 ∂P5 ∂P5   
∆P5 ∂|V2 | ∂|V3 | ∆δ4
 ∂δ ∂δ3 ∂δ4 ∂δ5 ∂V5  

   2 
   ∂Q2 ∂Q2 ∂Q2 ∂Q2 ∂Q2 ∂Q2 ∂Q2   

 ∆Q2 =
  ∂δ2 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V5 |  
 ∆δ5 

 ∂Q3 ∂Q3 ∂Q3 ∂Q3 ∂Q3 ∂Q3 ∂Q3  
∆Q3 ∆|V2 |
   
∂|V2 | ∂|V3 | ∂|V5 |  
 ∂δ ∂δ3 ∂δ4 ∂δ5
   2 
 ∆Q4   ∂Q4 ∂Q4 ∂Q4 ∂Q4 ∂Q4 ∂Q4 ∂Q4   ∆|V3 | 
 ∂δ2 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V5 | 
∆Q5 ∂Q5 ∂Q5 ∂Q5 ∂Q5 ∂Q5 ∂Q5 ∂Q5 ∆|V5 |
∂δ2 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V5 |
(65)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
73 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Load Profile and Objective Function

I The minimization of the active power loss given in (28) is


selected as the objective function.
I The load demand profile given in Figure-46 with four
different season winter, spring, summer and fall is
considered.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
74 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Flow Chart of Q − P QV bus Pair Method


Start

Read network data , Hr=1


load data

Run the load flow Set voltage of PQV


bus to Vmin

Find bus with


minimum voltage Run the load flow
Increase the
Consider this as PQV voltage of
bus PQV bus in
Find out loss
a step of
0.01 pu
Select the
corresponding lateral Hr=Hr+1
branch
Voltage of PQV
bus < Vmax
Find the buses in the NO YES
lateral branch Consider this bus as
Q bus
Consider one bus at a Find out the
time as Q bus minimum loss

Run load flow


Find out bus with Select corresponding
minimum loss optimal value of the
Find out loss voltage of PQV bus

Find out DG size by


All buses proposed method
NO YES
considered
?
NO
YES
Hr<96
?
Terminating
Include the DG in the
conditions meet
network
?
NO
YES

Draw all the graphs

Stop
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
75 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Q − P QV Bus Pair Method


Evaluation Indices

I Line power transfer capability index (LPTCI) is defined as


∗ base ∗ DG base −P DG
<(V˜s I˜s ) −<(V˜s I˜s ) +Ploss
LP T CI=
˜ ˜ ∗ base
loss (66)
<(Vs Is )

I Active power loss reduction index (APLRI) is defined as


base −P DG
Ploss
AP LRI=
P base
loss (67)
loss
I Reactive power loss reduction index (APLRI) is defined as
Qbase DG
loss −Qloss
RP LRI=
Q base (68)
loss
I Voltage deviation index (VDI) is defined as
PN B 2
V DI= i=1 (Viideal −ViDG ) (69)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
76 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
33 bus

DG No. Selection of DG locations UPF Lag


Selected P QV bus 18 18
Voltage to be boosted at P QV bus 0.95 0.95
1st DG Selected Q bus (DG location) 6 6
Minimum voltage after first DG 0.95 0.9632
Selected P QV bus 18 18
Voltage to be boosted at P QV bus 0.98 0.99
2nd DG Selected Q bus (DG location) 11 11
Minimum voltage after first DG 0.9604 0.9752

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
77 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
Selection of Voltage for 33 bus

400

350
Active power loss (kW)

300

Voltage to select for PQV bus with upf DG


250 Voltage to select for PQV bus with lpf DG

200

150

100

50
0.9 0.92 0.94 0.96 0.98 1 1.02 1.04 1.05
Voltage (pu)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
78 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
33 bus

DG Size Loss (kW) % Less Power V18 (pu)


Drawn
1 UPF DG 2700 kW 104.21 64 0.950
2 UPF DGs 570 kW 95.57 79 0.968
1 LPF DG 3180 kVA 62.27 65 0.963
2 LPF DGs 610 kVA 51.65 80 0.985

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
79 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
DG Impact Evaluation Indices 33 bus

Eval Index 1 UPF DG 2 UPF DGs 1 LPF DG 2 LPF DGs


LPTCI 0.6732 0.8175 0.6946 0.8117
APLRI 0.4858 0.5284 0.6927 0.7452
RPLRI 0.4466 0.4992 0.6397 0.7024
VDI 0.0325 0.0148 0.0145 0.00403

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
80 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
Active Power Loss Profile for 33 bus

250
Bare condition
With upf DG at bus 6
With lpf DG at bus 6
200 With upf DGs at bus 6 and 11
With lpf DGs at bus 6 and 11
Power Loss (kW)

150

Winter Spring Summer Fall


100

50

0
1 10 20 30 40 50 60 70 80 90 96
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
81 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
Active Power Loss Profile for 33 bus

1.01

0.99
Voltage magnitude (in pu)

0.98

0.97

0.96

0.95

0.94 Bare condition


With upf DG at bus 6
0.93 With lpf DG at bus 6
With upf DGs at bus 6 and 11
0.92 With lpf DGs at bus 6 and 11

0.91
1 5 10 15 20 25 30 33
Bus number

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
82 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
69 bus

DG No. Selection of DG locations UPF Lag


Selected P QV bus 65 65
Voltage to be boosted at P QV bus 0.98 0.98
1st DG Selected Q bus (DG location) 60 60
Minimum voltage after first DG 0.9675 0.9716
Selected P QV bus 27 27
Voltage to be boosted at P QV bus 0.99 0.99
2nd DG Selected Q bus (DG location) 19 19
Minimum voltage after first DG 0.9731 0.9883

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
83 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
Selection of Voltage for 69 bus

300

250
Active power loss (kW)

200
Voltage to select for PQV bus with upf DG
Voltage to select for PQV bus with lpf DG
150

100

50

0
0.9 0.92 0.94 0.96 0.98 1 1.02 1.04 1.05
Voltage (pu)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
84 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
69 bus

DG Size Loss (kW) % Less Power V65 (pu)


Drawn
1 UPF DG 2000 kW 91.88 47 0.970
2 UPF DGs 520 kW 80.21 61 0.973
1 LPF DG 2350 kVA 36.34 49 0.985
2 LPF DGs 505 kVA 20.42 60 0.988

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
85 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
DG Impact Evaluation Indices 69 bus

Table – DG impact evaluation indices for 69 bus distribution network

Eval Index 1 UPF DG 2 UPF DGs 1 LPF DG 2 LPF DGs


LPTCI 0.5114 0.6461 0.539 0.6512
APLRI 0.5916 0.6434 0.8446 0.9134
RPLRI 0.5592 0.6061 0.7995 0.8601
VDI 0.02324 0.00738 0.01293 0.00125

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
86 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
Active Power Loss Profile for 69 bus

250
Bare conditioin
With upf DG at bus 60
With lpf DG at bus 60
200
With upf DGs at bus 60 and 19
With lpf DGs at bus 60 and 19
Power Loss (kW)

150

Summer
100
Winter
Spring
Fall

50

0
1 10 20 30 40 50 60 70 80 90 96
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
87 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
Active Power Loss Profile for 69 bus

1.01

0.99

0.98
Voltage magnitude (in pu)

0.97

0.96

0.95
Bare condition
0.94
With upf DG at bus 60
0.93 With lpf DG at bus 60
With upf DGs at bus 60 and 19
0.92 With lfp DGs at bus 60 and 19
0.91

0.9
1 5 10 15 20 25 30 35 40 45 50 55 60 65 69
Bus number

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
88 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Integration with FFC and UPC DGs


under three different power contract
scenarios using MDPSO algorithm

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
88 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

P QV δ-Zero Bus Pair Method

I With rapid load growth the amount of active and reactive


power exchanged with the main grid increases.
I A pre-contracted active and reactive power from the main
grid, and the rest of the power can obtain from biomass
DGs to gain profit.
I As the main grid active and reactive power are known a
priory, load flow is to be modified.
I Concept of P QV δ-zero bus pair is adopted.
I Three different scenarios are considered as
1. Zero power exchange with the main grid.
2. Fixed amount of power exchange between the main grid and
the distribution network.
3. Power exchange based on Time of Use (TOU) tariff rate.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
89 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

P QV δ-Zero Bus Pair Method


Modification of Jacobian Matrix

I Introduction of P QV δ-zero bus pair modifies the load flow


method.
I In a distribution network, assume that except the P QV δ
(bus-1) and zero bus (dth ), all the other buses are of P Q
type.
I For P QV δ bus, all the quantities are known.
I For zero bus, all four quantities (voltage magnitude, voltage
angle, active and reactive power) are unknown, and hence
the name.
I The active power mismatch (∆Pi ) and reactive power
mismatch (∆Qi ) for ith bus are given as

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
90 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

P QV δ-Zero Bus Pair Method


Modification of Jacobian Matrix

I
∂Pi P B ∂Pi
∆Pi = N
P B
j=2 ∂δj
∆δj + N
j=2 ∂|Vj | ∆|Vj |

∂Qi P B ∂Qi (70)


∆Qi = N
P B
j=2 ∂δj
∆δj + N
j=2 ∂|Vj | ∆|Vj |

This is valid for i∈{1,2,··· ,N B}\{d}.


I For the sake of clarity, a sample 5 bus distribution network
is given as

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
91 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

P QV δ-Zero Bus Pair Method


Modification of Jacobian Matrix

The relation between the power mismatch matrix and the state
variable matrix is given by
   ∂P1 ∂P1 ∂P1 ∂P1 ∂P1 ∂P1 ∂P1 ∂P1 
∂δ2 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V4 | ∂|V5 | 
∂P2 ∂P2 ∂P2 ∂P2 ∂P2 ∂P2 ∂P2 ∂P2  ∆δ2
 ∆P1   ∂δ2 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V4 | ∂|V5 |  
   ∆δ3
 ∆P2   ∂P3
 ∂P3 ∂P3 ∂P3 ∂P3 ∂P3 ∂P3 ∂P3  
  ∂δ2 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V4 | ∂|V5 |  
  ∆δ4
 ∆P3   ∂P4 ∂P4 ∂P4 ∂P4 ∂P4 ∂P4 ∂P4 ∂P4  
   ∂δ2 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V4 | ∂|V5 |   ∆δ5
 ∆P4  =  ∂Q ∂Q1 ∂Q1 ∂Q1 ∂Q1 ∂Q1 ∂Q1 ∂Q1  

   1 ∆|V2 |
 ∆Q1   ∂δ2 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V4 | ∂|V5 | 

   ∂Q2 ∂Q2 ∂Q2 ∂Q2 ∂Q2 ∂Q2 ∂Q2 ∂Q2   ∆|V3 |
 ∆Q2   ∂δ2 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V4 | ∂|V5 |  
   ∂Q
  3 ∂Q3 ∂Q3 ∂Q3 ∂Q3 ∂Q3 ∂Q3 ∂Q3 
 ∆|V4 |
 ∆Q3 ∂δ2 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V4 | ∂|V5 | 
∂Q4 ∂Q4 ∂Q4 ∂Q4 ∂Q4 ∂Q4 ∂Q4 ∂Q4 ∆|V5 |
∆Q4
∂δ2 ∂δ3 ∂δ4 ∂δ5 ∂|V2 | ∂|V3 | ∂|V4 | ∂|V5 |
(71)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
92 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Objective Function

I The objective functions given in (28) and (30) are


considered. For multi-objective function, the weighting
factors are selected as w1 = w2 = 0.5.
I For both of the objective functions, the decision variables
vector [X] contains the locations and the sizes of the DGs,
 [X] =
i.e., 
locDG1 , locDG2 , · · · , locDGn , PDG1 , PDG2 , · · · , PDGn−1 .
I For the FFC DG, the size depends on the UPC DGs and
the amount of power contract.
I Therefore, in the optimization problem number of decision
variables are reduced to (2n − 1).

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
93 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Daily Load Profile


A daily average load profile (24 Hours) is considered to find out
the DG sizes using P QV δ-zero technique.

0.98

0.96

0.94
Load Levels (pu)

0.92

0.9

0.88

0.86

0.84

0.82

0.8
1 5 10 15 20 24
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
94 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Hourly Power Contract


For Scenario-3, the 24 hours of power exchange in between main
grid and the distribution network is given as

0.7

0.6
Energy Contract (pu)

0.5

0.4

0.3

0.2

0.1
1 5 10 15 20 24
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
95 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Profile of Time of Use Tariff (TOU)


The profile of hourly basis price of electricity ($/kWhr) is given
as

0.25

0.2
TOU Tariff ($/kWh)

0.15

0.1

0.05

0
1 5 10 15 20 24
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
96 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Mixed Discrete Particle Swarm Optimization (MDPSO)


I MDPSO is a modified version of PSO that can handle both
continuous as well as the discrete variables.
I The optimization strategy for continuous variables are same
as normal PSO.
I The locations of the discrete variables are expressed in
terms of hypercube which are the sets of ordered pairs as
Hd ={(xL
id ,xid )|x∈X,d∈m+1,m+2,...,N |m<N }
U (72)
I xL U
id and xid are lower and the upper bound of discrete
variables that bound the hypercube.
I The upper and lower bounds are given as

xL +
id =bxid c=max{nid ∈Z |nid 6xid }
(73)
xU +
id =dxid e=min{nid ∈Z |nid 6xid }

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
97 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Mixed Discrete Particle Swarm Optimization (MDPSO)

I The locations of the discrete particles are determined by


the Nearest Vertex Approach (NVA)
(
dis xL
id if |xid − xL U
id | 6 |xid − xid |
xid = (74)
xU
id if |xid − xL U
id | > |xid − xid |
I To prevent the tendency of the particle to escape from the
search space, a confinement mechanism is introduced for
both types of variables

xid
 if xmin
d < xid < xmax
d
xid = xmind if x id 6 x min
d (75)

 max
xd if xid > xd max

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
98 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Mixed Discrete Particle Swarm Optimization (MDPSO)


Flow Chart

Start

Read data such as


swarm, dimension,
iterations

Initialize the particles


positions and velocity

Find out fitness fi(iter-1)


and fi(iter) for ith particle

If
fi(iter-1)<fi(iter)
?

Pbest=fi(iter-1) Pbest=fi(iter)

i=i+1

Yes If No
i =<N
?

Determine the global best


Max(Pbesti)

Yes Convergence
criteria meets
? Confinement
criteria

Optimal output
No No
results
Nearest Vertex
Update velocity Approach

Stop Variables are


discrete
Yes ?
Update position

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
99 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Economic Analysis of DG Placement


I Investment for extension or modification of a system is
viable if it is economically sound.
I The Net Annual Profit (NAP) obtained from the less
energy drawn from the upstream grid.
I The NAP with the TOU tariff scheme is
P24 grid
P rof it=365 t=1 {PBase (t)−P
grid }×∆t×C
T OU (t) (76)
I The annual instalment cost is given by
PNDG rating r(1+r)yr
InstDG = k=1 PDGk CDGk (1+r)yr −1 (77)
I Per hour profit obtained by the utility for DGs placement
and the TOU is
P24 PNDG
P rof it−InstDG −365 t=1 k=1 PDGk (t)OMDG (t)
P rof itN et/hr = 8760
(78)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
100 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Assumptions

I Bus-1 is selected as the location of P QV δ bus.


I Load power factors for all buses have kept unchanged, i.e.
this is independent on the variation of the load demand.
I Voltage of the P QV δ bus (bus-1) is assumed as 1.0∠0 pu.
I Only a single DG is allowed to place at a particular bus i.e
locDG
i 6= locDG
j .
I Flat voltage profile is considered for the initiation of the
load flow.
I For MDPSO swarm size is considered as 20 and maximum
iterations are considered as 200.
I The inertia weight varies in the range of w ∈[0.4,0.9].

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
101 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results
I The different combinations of active power loss and the
voltage deviation given in (28) and (30) are considered.
I In scenario-1, zero power is taken from the substation.
I In scenario-2, 50% of the total load demand at any load
level is supplied by substation and rest of the load is
supplied by DGs.
I In scenario-3, the load demand to be supplied by the
substation is set according to the TOU tariff.
I For 33 bus system, DGs are placed at bus-14 (FFC), bus-3
(UPC) and bus-30 (UPC) which are determined by
MDPSO.
I For 69 bus system, DGs are placed at bus-61 (FFC), bus-17
(UPC) and bus-49 (UPC) which are determined by
MDPSO.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
102 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Case-1 (Power Loss), Scenario-1 (Zero Power Intake)

I The determined size of the biomass DGs at bus-14 is


14 = 670 kW, at bus-3 is P 3 = 1900 kW and at bus-30
PDG DG
30 = 1170 kW.
is PDG
I After the placement of the biomass DGs, the active power
loss is reduced to 21.32 kW at peak load level.
I The minimum voltage of the system has been improved to
0.9884 pu.
I The voltage of the bus-18 has been improved to 0.9973 pu.
I The voltage deviation index of the system has been reduced
to 0.000476.
I The average profit obtained after the placement of the DGs
for this scenario is $114 per hour.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
103 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Case-1 (Power Loss), Scenario-2 (Half Power Intake)

I The determined size of the biomass DGs at bus-14 is


14 = 700 kW, at bus-3 is P 3 = 300 kW and at bus-30 is
PDG DG
30 = 1200 kW.
PDG
I After the placement of the biomass DGs, the active power
loss is reduced to 32.35 kW at peak load level.
I The minimum voltage of the system has been improved to
0.9794 pu.
I The voltage of the bus-18 has been improved to 0.9900 pu.
I The voltage deviation index of the system has been reduced
to 0.0033.
I The average profit obtained after the placement of the DGs
for this scenario is $62.8 per hour.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
104 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Case-1 (Power Loss), Scenario-3 (TOU Based Power Intake)

I The determined size of the biomass DGs at bus-14 is


14 = 540 kW, at bus-3 is P 3 = 1330 kW and at bus-30
PDG DG
30 = 1220 kW.
is PDG
I After the placement of the biomass DGs, the active power
loss is reduced to 33.98 kW at peak load level.
I The minimum voltage of the system has been improved to
0.9791 pu.
I The voltage of the bus-18 has been improved to 0.9888 pu.
I The voltage deviation index of the system has been reduced
to 0.00392.
I The average profit obtained after the placement of the DGs
for this scenario is $11.6 per hour.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
105 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Case-1 (Plot for Active Power Loss)

250
Bare case
0% power exchange with upstream grid
50% power exchange with upstream grid
Power exchange according to TOU tariff
200
Active power loss (kW)

150

100

50

0
1 5 10 15 20 24
Hours

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
106 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Case-1 (Plot for Voltage)

1.01

0.99
Voltage magnitude (in pu)

0.98

0.97 Bare case


0% power exchange with upstream grid
0.96 50% power exchange with upstream grid
Power exchange according to TOU tariff
0.95

0.94

0.93

0.92

0.91
1 5 10 15 20 25 30 33
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
107 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Case-2 (Power Loss+Voltage), Scenario-1 (Zero Power Intake)

I The determined size of the biomass DGs at bus-14 is


14 = 690 kW, at bus-3 is P 3 = 1870 kW and at bus-30
PDG DG
30 = 1200 kW.
is PDG
I After the placement of the biomass DGs, the active power
loss is reduced to 21.35 kW at peak load level.
I The minimum voltage of the system has been improved to
0.9884 pu.
I The voltage of the bus-18 has been improved to 0.9984 pu.
I The voltage deviation index of the system has been reduced
to 0.000428.
I The average profit obtained after the placement of the DGs
for this scenario is $113 per hour.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
108 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Case-2 (Power Loss+Voltage), Scenario-2 (Half Power Intake)

I The determined size of the biomass DGs at bus-14 is


14 = 730 kW, at bus-3 is 0 kW and at bus-30 is
PDG
30 = 1180 kW.
PDG
I After the placement of the biomass DGs, the active power
loss is reduced to 32.45 kW at peak load level.
I The minimum voltage of the system has been improved to
0.9794 pu.
I The voltage of the bus-18 has been improved to 0.9900 pu.
I The voltage deviation index of the system has been reduced
to 0.00317.
I The average profit obtained after the placement of the DGs
for this scenario is $70.5 per hour.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
109 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Case-2 (Power Loss+Voltage), Scenario-3 (TOU Based Power Intake)

I The determined size of the biomass DGs at bus-14 is


14 = 700 kW, at bus-3 is P 3 = 1280 kW and at bus-30
PDG DG
30 = 1300 kW.
is PDG
I After the placement of the biomass DGs, the active power
loss is reduced to 32.02 kW at peak load level.
I The minimum voltage of the system has been improved to
0.9799 pu.
I The voltage of the bus-18 has been improved to 0.9888 pu.
I The voltage deviation index of the system has been reduced
to 0.00196.
I The average profit obtained after the placement of the DGs
for this scenario is $6.6 per hour.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
110 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Case-2 (Plot for Active Power Loss)

250
Bare case
0% power exchange with upstream grid
50% power exchange with upstream grid
Power exchange according to TOU tariff
200
Active power loss (kW)

150

100

50

0
1 5 10 15 20 24
Hours

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
111 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Case-2 (Plot for Voltage)

1.01

0.99
Voltage magnitude (in pu)

0.98

0.97 Bare case


0% power exchange with upstream grid
0.96 50% power exchabge with upstream grid
Power exchange according to TOU tariff
0.95

0.94

0.93

0.92

0.91
1 5 10 15 20 25 30 33
Bus number

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
112 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Case-1 (Power Loss), Scenario-1 (Zero Power Intake)

I The determined size of the biomass DGs at bus-61 is


61 = 670 kW, at bus-17 is P 17 = 1900 kW and at bus-49
PDG DG
49 = 1170 kW.
is PDG
I After the placement of the biomass DGs, the active power
loss is reduced to 7.535 kW at peak load level.
I The minimum voltage of the system has been improved to
0.9945 pu.
I The voltage of the bus-65 has been improved to 0.9983 pu.
I The voltage deviation index of the system has been reduced
to 0.000262.
I The average profit obtained after the placement of the DGs
for this scenario is $119 per hour.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
113 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Case-1 (Power Loss), Scenario-2 (Half Power Intake)

I The determined size of the biomass DGs at bus-61 is


61 = 1550 kW, at bus-17 is P 17 = 450 kW and at bus-49
PDG DG
is 0 kW.
I After the placement of the biomass DGs, the active power
loss is reduced to 10.925 kW at peak load level.
I The minimum voltage of the system has been improved to
0.9872 pu.
I The voltage of the bus-65 has been improved to 0.9872 pu.
I The voltage deviation index of the system has been reduced
to 0.00360.
I The average profit obtained after the placement of the DGs
for this scenario is $73.5 per hour.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
114 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Case-1 (Power Loss), Scenario-3 (TOU Based Power Intake)

I The determined size of the biomass DGs at bus-61 is


61 = 1680 kW, at bus-17 is P 17 = 560 kW and at bus-49
PDG DG
49 = 1030 kW.
is PDG
I After the placement of the biomass DGs, the active power
loss is reduced to 9.018 kW at peak load level.
I The minimum voltage of the system has been improved to
0.9909 pu.
I The voltage of the bus-65 has been improved to 0.9909 pu.
I The voltage deviation index of the system has been reduced
to 0.00171.
I The average profit obtained after the placement of the DGs
for this scenario is $71 per hour.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
115 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Case-1 (Plot for Active Power Loss)

250
Bare case
0% power exchange with upstream grid
50% power exchange with upstream grid
200 Power exchange according to TOU tariff
Active power loss (kW)

150

100

50

0
1 5 10 15 20 24
Hours

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
116 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Case-1 (Plot for Voltage)

1.02

1
Voltage magnitude (in pu)

0.98

0.96

Bare case
0% power exchange with upstream grid
0.94 50% power exchange with upstream grid
Power exchange according to TOU tariff

0.92

0.9
1 5 10 15 20 25 30 35 40 45 50 55 60 65 69
Bus number

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
117 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Case-2 (Power Loss+Voltage), Scenario-1 (Zero Power Intake)

I The determined size of the biomass DGs at bus-61 is


61 = 1740 kW, at bus-17 is P 17 = 580 kW and at bus-49
PDG DG
49 = 1700 kW.
is PDG
I After the placement of the biomass DGs, the active power
loss is reduced to 7.542 kW at peak load level.
I The minimum voltage of the system has been improved to
0.9956 pu.
I The voltage of the bus-65 has been improved to 0.9956 pu.
I The voltage deviation index of the system has been reduced
to 0.000253.
I The average profit obtained after the placement of the DGs
for this scenario is $113.5 per hour.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
118 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Case-2 (Power Loss+Voltage), Scenario-2 (Half Power Intake)

I The determined size of the biomass DGs at bus-61 is


61 = 1500 kW, at bus-17 is P 17 = 450 kW and at bus-49
PDG DG
is 0 kW.
I After the placement of the biomass DGs, the active power
loss is reduced to 11.142 kW at peak load level.
I The minimum voltage of the system has been improved to
0.9856 pu.
I The voltage of the bus-65 has been improved to 0.9856 pu.
I The voltage deviation index of the system has been reduced
to 0.00333.
I The average profit obtained after the placement of the DGs
for this scenario is $74.7 per hour.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
119 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Case-2 (Power Loss+Voltage), Scenario-3 (TOU Based Power Intake)

I The determined size of the biomass DGs at bus-61 is


61 = 1680 kW, at bus-17 is P 17 = 560 kW and at bus-49
PDG DG
49 = 1000 kW.
is PDG
I After the placement of the biomass DGs, the active power
loss is reduced to 9.086 kW at peak load level.
I The minimum voltage of the system has been improved to
0.9899 pu.
I The voltage of the bus-65 has been improved to 0.9899 pu.
I The voltage deviation index of the system has been reduced
to 0.00162.
I The average profit obtained after the placement of the DGs
for this scenario is $72 per hour.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
120 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Case-2 (Plot for Active Power Loss)

250
Bare case
0% power exchange with upstream grid
50% power exchange with upstream grid
Power exchange according to TOU tariff
200
Active power loss (kW)

150

100

50

0
1 5 10 15 20 24
Hours

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
121 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Case-2 (Plot for Voltage)

1.02

1
Voltage magnitude (in pu)

0.98

0.96
Bare case
0% power exchange with upstream grid
50% power exchange with upstream grid
0.94
Power exchange according to TOU tariff

0.92

0.9
1 5 10 15 20 25 30 35 40 45 50 55 60 65 69
Bus number

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
122 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Assessment of FFC DG Impact


MDPSO Based PEM with Load
and Renewable Uncertainties

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
122 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

MDPSO Based PEM Method


I Point estimate based method is used to analyze the
uncertainties in the distribution network.
I Distribution network is power independent on the main
grid, i.e. no power exchange is taken place though it is
connected to main grid.
I Uncertainties due to renewable sources and load demand
(Industrial, Commercial, Residential) are considered.
I Concept of P QV δ-zero bus is used.
I The locations of DGs and the zero bus are determined by
MDPSO.
I Expected values of DGs, and shunt capacitors are found
out by MDPSO based PEM method.
I Results are compared with TLBO method.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
123 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Objective Functions

I Different combinations of active power loss, voltage


deviation and the DG cost as objective functions.
I In Objective Function-1 (28), only power loss is considered
as the prime objective function.
I In Objective Function-2 (30), power loss and voltage
deviation are considered as objective function. The choice
of w1 = w2 = 0.5 for Case-1, and w1 = 0.3 and w2 = 0.7 for
33 bus and w1 = 0.2 and w2 = 0.8 for 69 bus for Case-2.
I In Objective Function-3 (33), power loss, voltage deviation
and DG cost are considered as the objective function. The
choice of w1 = w2 = w3 = 31 for Case-1, and w1 = 0.10,
w2 = 0.45 and w3 = 0.45 for 33 bus and w1 = 0.15,
w2 = 0.425 and w3 = 0.425 for 69 bus in Case-2.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
124 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Hong’s Point Estimation Method


Overview

I Hong’s PEM is an approximate method to model the


uncertainty of an output variable Z.
I The statistical information of the output variable Z is
provided in terms of the moments as
P unc PN
E[Z n ]=hZ n i≈ N
l=1
n
k=1 wl,k Z (l,k) (79)
Here Z(l,k)=F (hx1 ihx2 i···pl,k ···hxm i) and N unc is the number of
uncertain i.e. random variables, where
N unc =2(N B−1)+N DG −N0act −N0react −N0DG (80)
I In Hong’s PEM the location of the k th concentration of lth
random variable can be determined by
pl,k =hxl i+ξl,k σxl (81)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
125 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Hong’s Point Estimation Method


Order of PEM Used

I Higher PEM schemes consider more detailed probabilistic


information in terms of the higher order central moments.
I Positions in N m scheme highly depend on the number of
uncertain variables.
I For the system with Wiebull distributed uncertain variable
N m + 1 method is effective, as for (N ≥ 3) the PEM
method yields complex concentration.
I Hence instead of using N m, N m + 1 PEM methods are
used.
I The 2m + 1 and 4m + 1 schemes of PEM is considered.
I 3m + 1 PEM scheme gives non real values of concentrations
and hence discarded.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
126 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Hong’s Point Estimation Method


Methodology

I For N m + 1 scheme of PEM, the standard locations ξl,k are


determined by solving N th order polynomial
PN
N (ξ)=ξ N +
fpol i=1 PN −i ξ N −i (82)
I The coefficients of the polynomial (82) are found out by
[P]N ×1 =−[A]−1
N ×N [λ]N ×1 (83)
I aij is an element of the matrix [A] and aij =λl,i+j−1 .
I The λl,k is the k th standard central moment.
I The weights of the N points are obtained by solving
[W ]N ×1 =[L]−1 ∗
N ×N [λ ]N ×1 (84)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
127 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

MDPSO Based Point Estimate Method


Flow Chart

Select Hr=1 Start

Read solar, wind, load Read network data, load


uncertainty data, Nunc levels, solar and wind pu
data
in
P=1
Select DG locations and
peak values of UPC DGs
Read MDPSO data such as variables for MDPSO
Find out mean as swarm, dimension, no
and standard of iteratioins
deviation

Randomly in
Compute central moments generate particles
and standard locations out

Generate the
Yes swarm
P<Nunc
?
No Find out fitness for all particles Confinement
based on the objective function criteria
I=0, L=1 minimization
Hr=Hr+1
No
I=I+1 Find global and Variables are
local best Nearest vertex Yes
approach discrete
?
Compute the
concentrations
L=L+1 Convergence No Update the
Update the
criteria meets velocity of the
out positions
? particles
Yes in

Calculate Yes
L<Npoint
moments for
?
output variables Best solution

Yes
No
I<Nunc
out
?
No
Find out GCE Find out CDF and
coefficients PDF
Yes
Hr<24
?
No Note down the
FFC DG and Stop
Capacitor size

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
128 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Gram Charlier Expansion (GCE)


I The PDF and CDF of probabilistic output variables can be
approximately expressed by a known distribution function.
I GCE Type-A method which is given by
F (x)=[1+ ∞ k
k=3 (−1) Ck Hk (x;µ,σ)]ψ(x;µ,σ) (85)
P

f (x)=[1+ ∞ k
k=3 (−1) Ck Hk (x;µ,σ)]φ(x;µ,σ) (86)
P

I φ(x;µ,σ) is the kernel of the PDF, considered as the Normal


Distribution.
I Hk is the k th order Chebycheff–Hermite probabilistic
polynomial
Hk (x;µ,σ)=(−1)k φ−1 (x;µ,σ)Dk [φ(x;µ,σ)] (87)
I Ck are the coefficients of GCE as
R∞
Ck = −∞ Hk (x;µ,σ)f (x)dx=hHk (x;µ,σ)i (88)
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
129 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Comparison of DGs and capacitors by MDPSO and TLBO

Mean value of Solar Mean Value of Wind


Obj Func Case
power (kW) power (kW)
MDPSO TLBO MDPSO TLBO
J1 1 995.30 994 998.70 1165.40
J2 1 989.50 996.20 1168.70 1165.40
J2 2 982.20 975.50 1264.20 1267.90
J3 1 1471.80 1473 1581 1594.70
J3 2 1380 1224.30 1095 1370.30

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
129 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-1

I 33 = 1900kW p and the size of


The size of solar DG placed Psol
wind DG placed Pwin11 = 1300kW p.

I After PEM the shunt capacitor to be connected is


Q30
cap = 1200kV Ar by both 2m + 1 and 4m + 1.
I After PEM the FFC DG to be connected is
Pf3f c = 2400kV A by 2m + 1 and Pf3f c = 2350kV A by
4m + 1.
I The minimum voltage is improved to 0.979pu by both
2m + 1 and 4m + 1.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
130 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-1 (PDF)

0.14

2m+1 PEM by MDPSO


0.12 2m+1 PEM by TLBO
4m+1 PEM by MDPSO
4m+1 PEM by TLBO
0.1

0.08
Probability

0.06

0.04

0.02

0 5 10 15 20 25 30 35 40 45 50 55 60
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
131 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-2, Case-1

I 33 = 1900kW p and the size of


The size of solar DG placed Psol
11
wind DG placed Pwin = 1300kW p.
I After PEM the shunt capacitor to be connected is
Q30 30
cap = 1200kV Ar by 2m + 1 and Qcap = 1150kV Ar by
4m + 1.
I After PEM the FFC DG to be connected is
Pf3f c = 2200kV A by 2m + 1 and Pf3f c = 2230kV A by
4m + 1.
I The minimum voltage is improved to 0.984pu both by
2m + 1 and 4m + 1.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
132 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-2, Case-1 (PDF)

0.16

2m+1 PEM by MDPSO


0.14 2m+1 PEM by TLBO
4m+1 PEM by MDPSO
4m+1 PEM by TLBO
0.12

0.1
Probability

0.08

0.06

0.04

0.02

0 5 10 15 20 25 30 35 40 45 50 55 60
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
133 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-2, Case-2

I 33 = 1850kW p and the size of


The size of solar DG placed Psol
11
wind DG placed Pwin = 1400kW p.
I After PEM the shunt capacitor to be connected is
Q30 30
cap = 1400kV Ar by 2m + 1 and Qcap = 1550kV Ar by
4m + 1.
I After PEM the FFC DG to be connected is
Pf3f c = 2050kV A by 2m + 1 and Pf3f c = 1970kV A by
4m + 1.
I The minimum voltage is improved to 0.9869pu by 2m + 1
and 0.9885pu by 4m + 1.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
134 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-2, Case-2 (PDF)

0.3
2m+1 PEM by MDPSO
2m+1 PEM by TLBO
4m+1 PEM by MDPSO
4m+1 PEM by TLBO

0.2
Probability

0.1

0 5 10 15 20 25 30 35 40 45 50 55 60
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
135 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-3, Case-1

I 33 = 2770kW p and the size of


The size of solar DG placed Psol
11
wind DG placed Pwin = 1760kW p.
I After PEM the shunt capacitor to be connected is
Q30 30
cap = 1450kV Ar by 2m + 1 and Qcap = 1550kV Ar by
4m + 1.
I After PEM the FFC DG to be connected is
Pf3f c = 1450kV A by 2m + 1 and Pf3f c = 1410kV A by
4m + 1.
I The minimum voltage is improved to 0.9884pu both by
2m + 1 and 4m + 1.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
136 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-3, Case-1 (PDF)

0.04

2m+1 PEM by MDPSO


0.035
4m+1 PEM by TLBO
2m+1 PEM by MDPSO
0.03 4m+1 PEM by TLBO

0.025
Probability

0.02

0.015

0.01

0.005

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
137 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-3, Case-2

I 33 = 2600kW p and the size of


The size of solar DG placed Psol
wind DG placed Pwin11 = 1220kW p.

I After PEM the shunt capacitor to be connected is


Q30
cap = 1200kV Ar by bboth 2m + 1 and 4m + 1.
I After PEM the FFC DG to be connected is
Pf3f c = 2030kV A by 2m + 1 and Pf3f c = 2020kV A by
4m + 1.
I The minimum voltage is improved to 0.9853pu both by
2m + 1 and 4m + 1.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
138 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-3, Case-2 (PDF)

0.08

0.07
2m+1 PEM by MDPSO
2m+1 PEM by TLBO
4m+1 PEM by MDPSO
4m+1 PEM by TLBO
0.05
Probability

0.03

0.01

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
139 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Comparison of DGs and capacitors by MDPSO and TLBO

Mean value of Solar Mean Value of Wind


Obj Func Case
power (kW) power (kW)
MDPSO TLBO MDPSO TLBO
J1 1 550.33 555 2033.20 2031.80
J2 1 665.62 663.77 1843 1866.01
J2 2 714.42 714.06 1806.20 1794
J3 1 686.76 698.82 2055.70 2051.20
J3 2 652.87 674.15 1893.10 1921.02

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
139 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-1

I 18 = 1050kW p and the size of


The size of solar DG placed Psol
2
wind DG placed Pwin = 2250kW p.
I After PEM the shunt capacitor to be connected is
Q2cap = 1100kV Ar by 2m + 1 and Q2cap = 1600kV Ar by
4m + 1.
I After PEM the FFC DG to be connected is
Pf61f c = 2200kV A by 2m + 1 and Pf61f c = 1900kV A by
4m + 1.
I The minimum voltage is improved to 0.984pu by 2m + 1
and 0.977pu by 4m + 1.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
140 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-1 (PDF)

0.18

0.16 2m+1 PEM by MDPSO


2m+1 PEM by TLBO
0.14 4m+1 PEM by MDPSO
4m+1 PEM by TLBO
0.12
Probability

0.1

0.08

0.06

0.04

0.02

0 5 10 15 20 25 30 35
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
141 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-2, Case-1

I 18 = 1250kW p and the size of


The size of solar DG placed Psol
wind DG placed Pwin2 = 2100kW p.
I After PEM the shunt capacitor to be connected is
Q2cap = 1500kV Ar by 2m + 1 and Q2cap = 1550kV Ar by
4m + 1.
I After PEM the FFC DG to be connected is
Pf61f c = 2000kV A by both 2m + 1 and 4m + 1.
I The minimum voltage is improved to 0.9858pu by 2m + 1
and 0.9855pu by 4m + 1.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
142 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-2, Case-1 (PDF)

0.35

2m+1 PEM by MDPSO


0.3
2m+1 PEM by TLBO
4m+1 PEM by MDPSO
0.25 4m+1 PEM by TLBO
Probability

0.2

0.15

0.1

0.05

0 5 10 15 20 25 30
Expected value of active power loss

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
143 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-2, Case-2

I 18 = 1350kW p and the size of


The size of solar DG placed Psol
2
wind DG placed Pwin = 2000kW p.
I After PEM the shunt capacitor to be connected is
Q2cap = 850kV Ar by 2m + 1 and Q2cap = 1150kV Ar by
4m + 1.
I After PEM the FFC DG to be connected is
Pf61f c = 2500kV A by 2m + 1 and Pf61f c = 2250kV A by
4m + 1.
I The minimum voltage is improved to 0.9910pu by 2m + 1
and 0.9900pu by 4m + 1.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
144 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-2, Case-2 (PDF)

0.14
2m+1 PEM by MDPSO
0.12 2m+1 PEM by TLBO
4m+1 PEM by MDPSO
4m+1 PEM by TLBO
0.1
Probability

0.08

0.06

0.04

0.02

0 5 10 15 20 25 30 35
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
145 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-3, Case-1

I 18 = 1300kW p and the size of


The size of solar DG placed Psol
wind DG placed Pwin2 = 2300kW p.
I After PEM the shunt capacitor to be connected is
Q2cap = 1700kV Ar by 2m + 1 and Q2cap = 1550kV Ar by
4m + 1.
I After PEM the FFC DG to be connected is
Pf61f c = 1800kV A by both 2m + 1 and 4m + 1.
I The minimum voltage is improved to 0.9840pu by 2m + 1
and 0.9800pu by 4m + 1.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
146 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-3, Case-1 (PDF)

0.08

2m+1 PEM by MDPSO


0.07
2m+1 PEM by TLBO
4m+1 PEM by MDPSO
4m+1 PEM by TLBO
0.06

0.05
Probability

0.04

0.03

0.02

0.01

0 5 10 15 20 25 30 35 40
Expected values of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
147 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-3, Case-2

I 18 = 1300kW p and the size of


The size of solar DG placed Psol
wind DG placed Pwin2 = 2300kW p.
I After PEM the shunt capacitor to be connected is
Q2cap = 1700kV Ar by 2m + 1 and Q2cap = 1550kV Ar by
4m + 1.
I After PEM the FFC DG to be connected is
Pf61f c = 1800kV A by both 2m + 1 and 4m + 1.
I The minimum voltage is improved to 0.9840pu by 2m + 1
and 0.9800pu by 4m + 1.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
148 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-3, Case-2 (PDF)

0.3

2m+1 PEM by MDPSO


0.25 2m+1 PEM by TLBO
4m+1 PEM by MDPSO
4m+1 PEM by TLBO

0.2
Probability

0.15

0.1

0.05

0 5 10 15 20 25 30 35
Expected values of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
149 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Conclusion

I Different strategies of operation of distribution networks by


placement of DGs are discussed.
I A new meta-heuristic type swarm based optimization
method ARBO is developed and compared with PSO and
TLBO for different test functions and practical engineering
problems.
I A new strategy for the placement of renewable DGs based
on the seasonal variation of the load demand is discussed.
I To improve the power factor of the networks, average load
level method is developed for the placement of fixed and
switched capacitors.
I The load growth of the networks are considered and it is
taken care of by the DGs and the capacitors.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
150 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Conclusion
I To improve the voltage of the remotely located bus, a novel
Q − P QV bus pair concept is developed to place the
biomass DGs at Q bus.
I The techno-economic analysis is also performed which
shows that the technique is economically sound.
I For the predefined power exchange between main grid and
the distribution network, a P QV δ−zero bus pair method is
adopted.
I Results show that, the zero power exchange is more cost
effective but tough to implement whereas power exchange
according to TOU tariff less cost effective but popular
method and easy to implement.
I The effect of the random behavior of the renewable
resources and the load demand is analyzed using the PEM
method.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
151 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Future Work

I Extend the concept of Q − P QV bus to place the renewable


DGs and the effect of the uncertainties caused by renewable
resources and load demand.
I Extend the work of MDPSO based PEM method used in
P QV δ-zero bus concept, considering correlation
uncertainties.
I Use the concept of ARBO method for finding out battery
charging and discharging strategy in presence of renewable
sources.
I Effect of hybrid electric vehicles in the microgrid in
presence of loads and renewable uncertainties.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
152 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Papers Published From the Thesis

[1] S. Barik and D. Das, “Determining the Sizes of Renewable DGs


Considering Seasonal Variation of Generation and Load and Their
Impact on System Load Growth,” IET Renewable Power
Generation, vol. 12, no. 10, pp. 1101–1110, 2018
[2] S. Barik, D. Das, “Impact of Feeder Flow Control Distributed
Generation in a Distribution Network in Presence of Renewable
and Load Uncertainties by Mixed Discrete Particle Swarm Based
Point Estimate Method”, IET Renewable Power Generation,
doi-10.1049/iet-rpg.2018.5834, 2019.
[3] S. Barik, and D. Das, “MDPSO Based Q–PQV Bus Pair
Technique–A Novel Method to Maintain the Voltage of Remotely
Located Buses with Renewable DGs,” IEEE PES Asia–Pacific
Power and Energy Engineering Conference (APPEEC), IEEE,
2018.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
153 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

References

I Al-Rashidi, Mohammed R., and Mohamed E. El-Hawary, “A survey of particle swarm


optimization applications in electric power systems,” IEEE transactions on
evolutionary computation, vol. 13, no. 4, pp. 913-918, 2009.
I Shi, Yuhui, “Particle swarm optimization : developments, applications and resources,”
Proceedings of the 2001 congress on evolutionary computation (IEEE Cat. No.
01TH8546), Vol. 1, 2001.
I Kennedy, James, “Particle swarm optimization,” Encyclopedia of machine learning,
pp. 760-766, 2010.
I Trelea, Ioan Cristian, “The particle swarm optimization algorithm : convergence analysis
and parameter selection,” Information processing letters, vol. 85, no. 6, pp. 317-325,
2003.
I Lu, Qiang, Qing-Long Han, and Shirong Liu, “A finite-time particle swarm optimization
algorithm for odor source localization,” Information Sciences, vol. 277, pp. 111-140,
2014.
I Wu, Jui-Yu, “Real-coded genetic algorithm-based particle swarm optimization method
for solving unconstrained optimization problems,” International Conference on
Electronics and Information Engineering, Vol. 1, 2010.
I Parsopoulos, Konstantinos E., and Michael N. Vrahatis, “Particle swarm optimization
method in multiobjective problems,” Proceedings of the 2002 ACM symposium on
Applied computing, pp. 603-607, 2002.
I Bratton, Daniel, and James Kennedy, “Defining a standard for particle swarm
optimization,” IEEE swarm intelligence symposium, pp. 120-127, 2007.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
154 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

References

I Elbeltagi, Emad, Tarek Hegazy, and Donald Grierson, “Comparison among five
evolutionary-based optimization algorithms,” Advanced engineering informatics, vol.
19, no. 1, pp. 43-53, 2005.
I Hassan, Rania, et al, “A comparison of particle swarm optimization and the genetic
algorithm,” 46th AIAA/ASME/ASCE/AHS/ASC structures, structural dynamics
and materials conference, pp. 1897, 2005.
I Zhang, Haopeng, and Qing Hui, “Hybrid multiagent swarm optimization : Algorithms,
evaluation, and application,” IEEE Conference on Decision and Control, pp.
5699-5704, 2012.
I HA, Mahmoud Pesaran, Phung Dang Huy, and Vigna K. Ramachandaramurthy, “A
review of the optimal allocation of distributed generation : Objectives, constraints,
methods, and algorithms,” Renewable and Sustainable Energy Reviews, vol. 75,pp.
293-312, 2017.
I Atwa, Y. M., et al., “Optimal renewable resources mix for distribution system energy
loss minimization,” IEEE Transactions on Power Systems, vol. 25, no. 1, pp. 360-370,
2010.
I Thomson, Murray, and David G. Infield, “Network power-flow analysis for a high
penetration of distributed generation,” IEEE Transactions on Power Systems, vol. 22,
no. 3, pp. 1157-1162, 2007.
I Rahmani-andebili, Mehdi, “Simultaneous placement of DG and capacitor in distribution
network,” Electric Power Systems Research, vol. 131, pp. 1-10, 2016.
I Gholami, R., M. Shahabi, and M-R. Haghifam, “An efficient optimal capacitor allocation
in DG embedded distribution networks with islanding operation capability of micro-grid
using a new genetic based algorithm,” International Journal of Electrical Power &
Energy Systems, vol. 71, pp. 335-343, 2015.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
155 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

References

I Zeinalzadeh, A., Mohammadi, Y., & Moradi, M. H., “Optimal multi objective placement
and sizing of multiple DGs and shunt capacitor banks simultaneously considering load
uncertainty via MOPSO approach,” International Journal of Electrical Power &
Energy Systems, vol. 67, pp. 336-349, 2015.
I Ramadan, H. S., A. F. Bendary, and S. Nagy, “Particle swarm optimization algorithm
for capacitor allocation problem in distribution systems with wind turbine generators,”
International Journal of Electrical Power & Energy Systems, vol. 84, pp. 143-152,
2017.
I El-Fergany, A. A., & Abdelaziz, A. Y., “Artificial bee colony algorithm to allocate fixed
and switched static shunt capacitors in radial distribution networks,” Electric Power
Components and Systems, vol.42, no. 5, pp. 427-438, 2014.
I García, J. A. M., & Mena, A. J. G., “Optimal distributed generation location and size
using a modified teaching–learning based optimization algorithm,” International
journal of electrical power & energy systems, vol. 50, pp. 65-75, 2013.
I Kanwar, Neeraj, et al., “Improved meta-heuristic techniques for simultaneous capacitor
and DG allocation in radial distribution networks,” International Journal of Electrical
Power & Energy Systems, vol. 73, pp. 653-664, 2015.
I Lasseter, Robert H., “Microgrids and distributed generation,” Journal of Energy
Engineering, vol. 133, no. 3, pp. 144-149, 2007.
I Chowdhury, S., Tong, W., Messac, A., & Zhang, J., “A mixed-discrete particle swarm
optimization algorithm with explicit diversity-preservation,” Structural and
Multidisciplinary Optimization, vol. 47, no. 3, pp. 367-388, 2013.
I Chowdhury, S., Zhang, J., Messac, A., & Castillo, L., “Exploring key factors influencing
optimal farm design using mixed-discrete particle swarm optimization,”
Multidisciplinary Analysis Optimization Conference, pp. 9280, 2010.
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
156 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

References

I Alavi, S. A., Ahmadian, A., & Aliakbar-Golkar, M., “Optimal probabilistic energy
management in a typical micro-grid based-on robust optimization and point estimate
method,” Energy Conversion and Management, vol. 95, pp. 314-325, 2015.
I Zhang, P., & Lee, S. T, “Probabilistic load flow computation using the method of
combined cumulants and Gram-Charlier expansion,” IEEE transactions on power
systems, vol. 19, no. 1, pp. 676-682, 2004.
I Xiao, Q., He, Y., Chen, K., Yang, Y., & Lu, Y., “Point estimate method based on
univariate dimension reduction model for probabilistic power flow computation,” IET
Generation, Transmission & Distribution, vol. 11, no. 14, pp. 3522-3531, 2017.
I Delgado, C., and J. A. Domínguez-Navarro, “Point estimate method for probabilistic
load flow of an unbalanced power distribution system with correlated wind and solar
sources,” International Journal of Electrical Power & Energy Systems, vol. 61, pp.
267-278, 2014.
I Ma Xi-Yuan, Yuan-Zhang Sun, and Hua-Liang Fang, “Scenario generation of wind power
based on statistical uncertainty and variability,” IEEE Transactions on Sustainable
Energy, vol. 4, no. 4, pp. 894–904, 2013.

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Backup Slides for Chapter-5

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Sizing of DGs and shunt capacitors


Fixed and Switched Capacitors Sizes (33 Bus)

I The fixed and switched capcitors sizes for 33 bus DNR are

Load level Shunt Caps 7th bus 30th bus 15th bus
types types (kVAr) (kVAr) (kVAr)
Low Fixed 1750 650 300
Medium Switched 0 150 50
High Switched 0 50 50
Very High Switched 0 0 0

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Sizing of DGs and Shunt Capacitors


Fixed and Switched Capacitors Sizes (33 Bus)

3500
Capacitor Sizes in kVAr of bus no 7, 30 and 15

Cap size for bus no 15 Cap size for bus no 30 Cap size for bus no 7
3000

2500

2000

1500

1000

500

0
1 10 20 30 40 50 60 70 80 90 96
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Sizing of DGs and Shunt Capacitors


Comparison of DGs and Fixed and Switched Capacitor Sizes (33 Bus)

DG and Caps Proposed ARBO PSO TLBO


sizes Method
Solar DG (30th bus) 1460 1456.5 1456.8 1456.7
Wind DG (13th bus) 1370 1361.6 1361.8 1361.9
Fixed Caps (7th bus) 1750 1772.3 1772.1 1772.1
Switched Caps (7th bus) 0,0,0 0,0,0 0,0,0 0,0,0
Fixed Caps (30th bus) 650 663.6 663.8 663.8
Switched Caps 150, 159.4, 159.35, 159.35,
(30th bus) 50, 0 15.91, 0 15.84, 0 15.78, 0
Fixed Caps (15th ) bus 300 278.71 278.38 278.37
Switched Caps at 50, 79.88, 79.98, 79.97,
(15th bus) 50, 0 21.51, 0 21.47, 0 21.49, 0
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Sizing of DGs and Shunt Capacitors


Fixed and Switched Capacitors Sizes (69 Bus)

I The fixed and switched capacitors sizes for 69 bus DNR are

Load level Shunt Caps 61st bus 12th bus 56th bus
types types (kVAr) (kVAr) (kVAr)
Low Fixed 1200 850 600
Medium Switched 200 100 50
High Switched 50 0 0
Very High Switched 0 0 0

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Sizing of DGs and Shunt Capacitors


Fixed and Switched Capacitors Sizes (69 Bus)

3500
Cap size for bus no 56 Cap size for bus no 12 Cap size for bus no 61

3000
Capacotor Sizes in kVar of bus no 61, 12 and 56

2500

2000

1500

1000

500

0
1 10 20 30 40 50 60 70 80 90 96
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Sizing of DGs and Shunt Capacitors


Comparison of DGs and Fixed and Switched Capacitor Sizes (69 Bus)

DG and Caps Proposed ARBO PSO TLBO


sizes Method
Solar DG (61st bus) 1547 1546.87 1547.83 1547.88
Wind DG (17st bus) 947 947.58 947.55 947.54
Fixed Caps (61st bus) 1200 1209.53 1209.62 1209.63
Switched Caps 200, 221.43, 221.52, 221.49,
(61st bus) 50, 0 55.14,0 55.15, 0 55.149, 0
Fixed Caps (12th bus) 850 845.87 846.63 846.62
Switched Caps 100, 112.40, 112.32, 112.33,
(12th bus) 0, 0 0, 0 0, 0 0, 0
Fixed Caps (56th bus) 600 619.20 619.149 619.151
Switched Caps 50,0,0 72.50,0,0 72.47,0,0 72.46,0,0
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Sizing of DGs and Shunt Capacitors


Comparison of Energy Imported from the Substation (33 Bus)

4000
Bare Condition
With DGs only
3500 With Caps only
Energy imported from the grid

With DGs and Caps


3000

2500

2000

1500

1000 Winter Spring Summer Fall

500
1 10 20 30 40 50 60 70 80 90 96
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Sizing of DGs and Shunt Capacitors


Comparison of Energy Imported from the Substation (69 Bus)

4500

4000 Base Condition


With DGs only
With Caps only
Energy imported from the grid

3500 With DGs and Caps

3000
Summer

2500 Winter Spring Fall

2000

1500

1000

500
1 10 20 30 40 50 60 70 80 90 96
Hours

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Backup Slides for Chapter-6

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

DG Placement Using Q-PQV Bus Pair Method


Comparison of Energy Imported from the Substation (33 Bus)

4000

3500
Energy improted from the grid

3000

2500
Bare condition
2000 With upf DG at bus 6
With lpf DG at bus 6
With upf DGs at bus 6 and bus 11
1500 With lpf DGs at bus 6 and bus 11

1000

500
Winter Spring Summer Fall
0
1 10 20 30 40 50 60 70 80 90 96
Hours

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

DG Placement Using Q-PQV Bus Pair Method


Comparison of Energy Imported from the Substation (69 Bus)

4500
Bare condition
With upf DG at bus 60
4000 With lpf DG at bus 60
With upf DGs at bus 60 and 19
Energy improted from the grid

With lpf DGs at bus 60 and 19


3500

3000

2500

Winter Spring Summer Fall


2000

1500

1000
1 10 20 30 40 50 60 70 80 90 96
Hours

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Backup Slides for Chapter-7

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Case-1 (Loss)

2000
DG at bus 14 scenario-1
1800 DG at bus 14 scenario-2
DG at bus 14 scenario-3
DG at bus 3 scenario-1
1600 DG at bus 3 scenario-2
DG at bus 3 scenario-3
1400 DG at bus 30 scenario-1
DG at bus 30 scenario-2
DG at bus 30 scenario-3
DG sizes (kW)

1200

1000

800

600

400

200

0
1 5 10 15 20 24
Hour

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Case-2 (Loss+Voltage)

2000
DG at bus 14 scenario-1
DG at bus 14 scenario-2
1800 DG at bus 14 scenario-3
DG at bus 3 scenario-1
DG at bus 3 scenario-2
1600
DG at bus 3 scenario-3
DG at bus 30 scenario-1
1400 DG at bus 30 scenario-2
DG at bus 30 scenario-3
DG sizes (kW)

1200

1000

800

600

400

200

0
1 5 10 15 20 24
Hours

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Backup Slides for Chapter-8

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Expected Values at Peak Load Level after PEM

Objective Case PEM FFC DG Cap Ploss Vmin


Function Method (kVA) (kVAr) (kW) (pu)
J1 1 2m + 1 2383.32 1193.13 29.02 0.979
J1 1 4m + 1 2340.25 1178.97 29.08 0.979
J2 1 2m + 1 2212.08 1168.47 29.91 0.984
J2 1 4m + 1 2226.64 1140.75 29.87 0.984
J2 2 2m + 1 2039.95 1372.12 31.64 0.987
J2 2 4m + 1 2223.14 1540.78 32.16 0.988
J3 1 2m + 1 1445.5 1453.57 45.28 0.988
J3 1 4m + 1 1407.91 1515.30 44.70 0.988
J3 2 2m + 1 2024 1172.28 34.01 0.985
J3 2 4m + 1 2018.92 1181.05 33.94 0.985
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
157 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-1 (CDF)

2m+1 PEM by MDPSO


0.9
2m+1 PEM by TLBO
4m+1 PEM by MDPSO
0.8
4m+1 PEM by TLBO

0.7
Cumulative distribution

0.6

0.5

0.4

0.3

0.2

0.1

0 5 10 15 20 25 30 35 40 45 50 55 60
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
158 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-2, Case-1 (CDF)

0.9 2m+1 PEM by MDPSO


2m+1 PEM by TLBO
4m+1 PEM by MDPSO
0.8 4m+1 PEM by TLBO

0.7
Cumulative distribution

0.6

0.5

0.4

0.3

0.2

0.1

0 5 10 15 20 25 30 35 40 45 50 55 60
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
159 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-2, Case-2 (CDF)

0.9 2m+1 PEM by MDPSO


2m+1 PEM by TLBO
0.8 4m+1 PEM by MDPSO
4m+1 PEM by TLBO

0.7
Cumulative distribution

0.6

0.5

0.4

0.3

0.2

0.1

0 5 10 15 20 25 30 35 40 45 50 55 60
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
160 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-3, Case-1 (CDF)

0.9 2m+1 PEM by MDPSO


2m+1 PEM by TLBO
0.8 4m+1 PEM by MDPSO
4m+1 PEM by TLBO

0.7
Cumulative distribution

0.6

0.5

0.4

0.3

0.2

0.1

0 5 10 15 20 25 30 35 40 45 50 55 60
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
161 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (33 Bus)


Objective Function-3, Case-2 (CDF)

0.9 2m+1 PEM by MDPSO


2m+1 PEM by TLBO
4m+1 PEM by MDPSO
0.8 4m+1 PEM by TLBO

0.7
Cumulative distribution

0.6

0.5

0.4

0.3

0.2

0.1

0 5 10 15 20 25 30 35 40 45 50 55 60
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
162 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Expected Values at Peak Load Level after PEM

Objective Case PEM FFC DG Cap Ploss Vmin


Function Method (kVA) (kVAr) (kW) (pu)
J1 1 2m + 1 2196.16 1085.04 16.88 0.984
J1 1 4m + 1 1873.01 1566.58 17.25 0.977
J2 1 2m + 1 1987.67 1487.84 15.19 0.986
J2 1 4m + 1 1974.20 1514.53 14.75 0.986
J2 2 2m + 1 2470.47 807.91 24.74 0.991
J2 2 4m + 1 2223.14 1138.89 18.95 0.990
J3 1 2m + 1 1723.83 1665.63 16.96 0.984
J3 1 4m + 1 1789.71 1541.80 17.76 0.981
J3 2 2m + 1 2100.36 1272.80 16.93 0.984
J3 2 4m + 1 2141.49 1214.72 17.14 0.984
Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
162 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-1 (CDF)

0.9 2m+1 PEM by MDPSO


2m+1 PEM by TLBO
0.8 4m+1 PEM by MDPSO
4m+1 PEM by TLBO
Cumulative distribution

0.7

0.6

0.5

0.4

0.3

0.2

0.1

0 5 10 15 20 25 30
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
163 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-2, Case-1 (CDF)

1
2m+1 PEM by MDPSO
2m+1 PEM by TLBO
4m+1 PEM by MDPSO
0.8
Cumulative distribution

4m+1 PEM by TLBO

0.6

0.4

0.2

0 5 10 15 20 25 30
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
164 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-2, Case-2 (CDF)

0.9 2m+1 PEM by MDPSO


2m+1 PEM by TLBO
0.8 4m+1 PEM by MDPSO
4m+1 PEM by TLBO
Cumulative distribution

0.7

0.6

0.5

0.4

0.3

0.2

0.1

0 5 10 15 20 25 30 35 40 45 50
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
165 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-3, Case-1 (CDF)

1.0

0.9 2m+1 PEM by MDPSO


2m+1 PEM by TLBO
0.8 4m+1 PEM by MDPSO
4m+1 PEM by TLBO
Cumulative distribution

0.7

0.6

0.5

0.4

0.3

0.2

0.1

0 5 10 15 20 25 30
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
166 / 167 IIT KGP
Ch-1 Ch-2 Ch-3 Ch-4 Ch-5 Ch-6 Ch-7 Ch-8 Ch-9 Back Up

Simulation Results (69 Bus)


Objective Function-3, Case-2 (CDF)

1.1 2m+1 PEM by MDPSO


2m+1 PEM by TLBO
1
4m+1 PEM by MDPSO
0.9 4m+1 PEM by TLBO
Cumulative distribution

0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1

0 5 10 15 20 25 30
Expected value of active power loss (kW)

Operation of Distributed Networks with Distributed Generations Under the Impact of Load and Generation U
167 / 167 IIT KGP

Você também pode gostar