UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

CALCULO DEL FACTOR CAMIÓN POR AASHTO DE DIFERENTES


VEHICULOS

C2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

|24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.136

∴ = 0.5441+3.136= 3.6801

FACTOR CAMION - PAVIMENTOS 1


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

C3

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441+2.004= 2.5481

FACTOR CAMION - PAVIMENTOS 2


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

C4

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 23 Tn → 50600 lb

50000 → 1.22

50600 → x

52000 → 1.43

52000−50000 1.43−1.22
=
52000−50600 1.433−𝑥
2000 0.21
=
1400 1.43−𝑥

2.042857 – 1.42857x = 0.21

x = 1.2830

∴ = 0.5441+1.2830= 1.8271

8x4

 7 Tn → 15400 lb

14000 → 0.360

FACTOR CAMION - PAVIMENTOS 3


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

FACTOR CAMION - PAVIMENTOS 4


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

∴ = 0.5441+0.5441+2.004 = 3.0922

T2S1

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
= 4.09−𝑥
1800
4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

FACTOR CAMION - PAVIMENTOS 5


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

∴ = 0.5441+3.1360+3.1360= 6.8161

T2S2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

FACTOR CAMION - PAVIMENTOS 6


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441+3.1360+2.004= 5.6841

T2Se2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

FACTOR CAMION - PAVIMENTOS 7


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

FACTOR CAMION - PAVIMENTOS 8


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

∴ = 0.5441+3.1360+3.1360+3.1360= 9.9521

T2S3

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 25 Tn → 55000 lb

54000 → 1.66

FACTOR CAMION - PAVIMENTOS 9


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

55000 → x

56000 → 1.91

56000−54000 1.91 − 1.66


=
56000−55000 1.91 − 𝑥
2000 0.25
=
1000 1.91−𝑥

3.82 – 2x = 0.25

x = 1.785

∴ = 0.5441+3.1360+1.785= 5.4651

T2Se3

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

FACTOR CAMION - PAVIMENTOS 10


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441+3.1360+3.1360+2.004 = 8.8201

T3S1

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

FACTOR CAMION - PAVIMENTOS 11


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441+3.1360+2.004 = 5.6841

T3S2

 7 Tn → 15400 lb

FACTOR CAMION - PAVIMENTOS 12


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

FACTOR CAMION - PAVIMENTOS 13


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

∴ = 0.5441+2.004+2.004 = 4.5521

T3Se2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.136

 11 Tn → 24200 lb

FACTOR CAMION - PAVIMENTOS 14


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441+3.1360+3.1360 + 2.004 = 8.8201


T3S3

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥

FACTOR CAMION - PAVIMENTOS 15


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 25 Tn → 55000 lb

54000 → 1.66

55000 → x

56000 → 1.91

56000−54000 1.91 − 1.66


=
56000−55000 1.91 − 𝑥
2000 0.25
=
1000 1.91−𝑥

3.82 – 2x = 0.25

x = 1.785

∴ = 0.5441 + 2.004+ 1.785 = 4.3331


T3Se3

FACTOR CAMION - PAVIMENTOS 16


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

FACTOR CAMION - PAVIMENTOS 17


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

x = 2.004

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441 + 3.1360+ 2.004+ 2.004= 7.6881


C2R2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

FACTOR CAMION - PAVIMENTOS 18


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

FACTOR CAMION - PAVIMENTOS 19


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

∴ = 0.5441 + 3.1360+ 3.1360+ 3.1360= 9.9521


C2R3

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥

FACTOR CAMION - PAVIMENTOS 20


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441 + 3.1360+ 3.1360+ 2.004= 8.8201


C3R2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

FACTOR CAMION - PAVIMENTOS 21


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

FACTOR CAMION - PAVIMENTOS 22


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

x = 2.004

∴ = 0.5441 + 3.1360+ 3.1360+ 2.004= 8.8201


C3R3

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

FACTOR CAMION - PAVIMENTOS 23


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441 + 3.1360+ 2.004+ 2.004= 7.6881


C3R4

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

FACTOR CAMION - PAVIMENTOS 24


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

FACTOR CAMION - PAVIMENTOS 25


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441 + 2.004+ 2.004+ 2.004= 6.5561


C4R2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

FACTOR CAMION - PAVIMENTOS 26


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 23 Tn → 50600 lb

50000 → 1.22

50600 → x

52000 → 1.43

52000−50000 1.43−1.22
=
52000−50600 1.433−𝑥
2000 0.21
=
1400 1.43−𝑥

2.042857 – 1.42857x = 0.21

x = 1.2830

∴ = 0.5441 + 3.1360+3.1360+1.2830= 8.0991


C4R3

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

FACTOR CAMION - PAVIMENTOS 27


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 23 Tn → 50600 lb

50000 → 1.22

50600 → x

52000 → 1.43

52000−50000 1.43−1.22
=
52000−50600 1.433−𝑥

FACTOR CAMION - PAVIMENTOS 28


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

2000 0.21
=
1400 1.43−𝑥

2.042857 – 1.42857x = 0.21

x = 1.2830

∴ = 0.5441 + 3.1360+2.004+1.2830= 6.9671


8x4R2

7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

FACTOR CAMION - PAVIMENTOS 29


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

FACTOR CAMION - PAVIMENTOS 30


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

10.4 – 5x = 0.38

∴ = 0.5441 + 0.5441 +3.1360+3.1360+2.004 = 9.3642


BA-1

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

FACTOR CAMION - PAVIMENTOS 31


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

∴ = 0.5441+3.1360+0.5441= 4.2242

B4-1

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

FACTOR CAMION - PAVIMENTOS 32


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

 16 Tn → 35200 lb

34000 → 1.095

35200 → x

36000 → 1.38

36000−34000 1.38−1.095
=
36000−35200 1.38−𝑥
2000 0.285
=
800 1.38−𝑥

3.45 – 2.5x = 0.285

x = 1.266

∴ = 0.5441+0.5441+1.266= 2.3542

B3-1

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 16 Tn → 35200 lb

34000 → 1.095

FACTOR CAMION - PAVIMENTOS 33


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

35200 → x

36000 → 1.38

36000−34000 1.38−1.095
=
36000−35200 1.38−𝑥
2000 0.285
=
800 1.38−𝑥

3.45 – 2.5x = 0.285

x = 1.266

∴ = 0.5441+1.266= 1.8101

B2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

FACTOR CAMION - PAVIMENTOS 34


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

4.54444444 – 1.11111x = 1.06

x = 3.1360

∴ = 0.5441+3.1360= 3.6801

T3Se2 S1Se2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

FACTOR CAMION - PAVIMENTOS 35


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

FACTOR CAMION - PAVIMENTOS 36


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

∴ = 0.5441+2.004+(5)(3.1360)= 18.2281

T3S2 S1S2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

FACTOR CAMION - PAVIMENTOS 37


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

1246 – 2000x = 157.8

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥

FACTOR CAMION - PAVIMENTOS 38


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441+3.1360+(3)(2.004)= 9.6921

T3Se2 Se2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

FACTOR CAMION - PAVIMENTOS 39


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

FACTOR CAMION - PAVIMENTOS 40


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

∴ = 0.5441+2.004+(4)(3.1360)= 15.0921

T3S2 S2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

FACTOR CAMION - PAVIMENTOS 41


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 18 Tn → 39600

38000 → 1.70

39600 → x

FACTOR CAMION - PAVIMENTOS 42


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441+(3)2.004= 6.5561

8x4 RB2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

FACTOR CAMION - PAVIMENTOS 43


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = (2)0.5441+2.004+2.004= 5.0962

8x4 RB1

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

FACTOR CAMION - PAVIMENTOS 44


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 11 Tn → 24200 lb

24000 → 3.03

FACTOR CAMION - PAVIMENTOS 45


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

∴ = (2)0.5441+2.004+3.1360= 6.2282

C4RB2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 23 Tn → 50600 lb

50000 → 1.22

50600 → x

52000 → 1.43

52000−50000 1.43−1.22
=
52000−50600 1.433−𝑥
2000 0.21
=
1400 1.43−𝑥

FACTOR CAMION - PAVIMENTOS 46


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

2.042857 – 1.42857x = 0.21

x = 1.2830

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441+1.2830+2.004= 3.8311

C4RB1

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 23 Tn → 50600 lb

50000 → 1.22

50600 → x

52000 → 1.43

FACTOR CAMION - PAVIMENTOS 47


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

52000−50000 1.43−1.22
=
52000−50600 1.433−𝑥
2000 0.21
=
1400 1.43−𝑥

2.042857 – 1.42857x = 0.21

x = 1.2830

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

∴ = 0.5441+1.2830+3.1360= 4.9631

C3RB2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥

FACTOR CAMION - PAVIMENTOS 48


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441+2.004+2.004 = 4.5521
C3RB1

 7 Tn → 15400 lb

FACTOR CAMION - PAVIMENTOS 49


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

FACTOR CAMION - PAVIMENTOS 50


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

∴ = 0.5441+2.004+2.004 = 4.5521
C2RB2

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

FACTOR CAMION - PAVIMENTOS 51


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441+3.1360+2.004 = 5.6841
C2RB1

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

FACTOR CAMION - PAVIMENTOS 52


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

∴ = 0.5441 + 3.1360+ 3.1360 = 6.8161


8x4R4

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

FACTOR CAMION - PAVIMENTOS 53


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 18 Tn → 39600

38000 → 1.70

39600 → x

FACTOR CAMION - PAVIMENTOS 54


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441x2 + 2.004 + 2.004 + 2.004 = 7.1002


8x4R3

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 7 Tn → 15400 lb

14000 → 0.360

15400 → x

FACTOR CAMION - PAVIMENTOS 55


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

16000 → 0.623

16000−14000 0.623−0.360
=
16000−15400 0.623−𝑥
2000 0.263
=
600 0.623−𝑥

1246 – 2000x = 157.8

x = 0.5441

 18 Tn → 39600

38000 → 1.70

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

 11 Tn → 24200 lb

24000 → 3.03

24200 → x

26000 → 4.09

26000−24000 4.09 − 3.03


=
26000−24200 4.09 − 𝑥
2000 1.06
=
1800 4.09−𝑥

4.54444444 – 1.11111x = 1.06

x = 3.1360

 18 Tn → 39600

38000 → 1.70

FACTOR CAMION - PAVIMENTOS 56


UNIVERSIDAD NACIONAL TORIBIO RODRIGUEZ DE MENDOZA

39600 → x

40000 → 2.08

40000−38000 2.08−1.70
=
40000 − 39600 2.08 − 𝑥
2000 0.380
=
400 2.08−𝑥

10.4 – 5x = 0.38

x = 2.004

∴ = 0.5441x2 + 2.004 + 3.1360 + 2.004 = 8.2322