Você está na página 1de 22

PROJECT PROPOSAL

REBUILD FOR CHANGE (RFC)


A Compassion Based Community Regrowth Program
Pilot Project: Manegaun Village (Burunchuli)
1 - REBUILD FOR CHANGE (RFC)

BACKGROUND
It had long been prophesized that Nepal is susceptible to natural disasters such as earthquakes. When the disaster in the form of an
earthquake struck on 25th April, the entire nation was engulfed in panic and chaos. The buildings, which seemed to touch the sky, were
reduced to rubble. To be quite specific approximately 9,000 people lost their lives and over 23000 people were injured as well as 800,000
houses were destroyed on a nationwide scale. The epicenter of that devastating earthquake was East of Lamjung district, which was
measured with a 7.8 magnitude.

The RFC project was conceived by keeping these tragic events in mind. There were some villages and communities which were very difficult
to get access to, because of poor infrastructures and poorly constructed roads. These places had not reached any relief from government
or any other organizations.

1. Rationale
Rebuild for Change (RFC) is a compassion based community When we describe our program as compassion based, we do not
regrowth program. Rotary International District 3292 Nepal- mean in its original latin root; passio - meaning “I suffer (with)”, but
Bhutan is the main donor and supporter of the program and the defined as the realization of interconnectedness; that all parts are
whole program has been designed and developed by CREASION/ dependent upon each other to form a whole - prompting a natural
Volunteer for Change Nepal (VFC) and Rotary Club of Jawalakhel- empathy and increased awareness in our daily work. Harmony
Manjushree (RCJM). in any of our projects is reflected by the gracefulness of each
particular, connecting every single beneficiary, partner, volunteer
Our vision is clear: to facilitate the growth of self-sustainable, self- and staff. This infusion of the concept of compassion with our
reliant and conscious communities that offer every individual their innovative developmental-models unites joy and fulfillment
universal human rights, and also expands and pushes the very with the standard-index of success, measured in economic and
frontier for human well-being and development. infrastructural terms.

The RFC initiative was born in the aftermath of the major earthquake RFC never considers communities to be a passive beneficiary -
and aftershock that hit Nepal on 25th April and 12th May 2015, on the contrary we see each member of those community as an
respectively. Both caused extensive damage to buildings and active participant in their own rehabilitation. A community to us is
infrastructure while thousands of lives were lost - with many more synonymous with resourcefulness and creativity and we recognize
injured. that every underprivileged community is an untapped potential
unto itself. We aim towards empowering such communities through
To be more exact, and to understand the scope of the situation; traditional means of socio-economic initiatives and infrastructural
around 9,000 people lost their lives and around 800,000 innovation; but also through igniting individual intelligence by
houses were destroyed on a nationwide scale. virtue of education and personal development programs.

RFC realized early on that many villages and communities were Nepal ranked 145th out of 187 countries on the Human
not, and have not yet been reached by either national government Development Index (HDI) 2014. The limited set of parameters and
agencies, or international organizations. premises encircling this conclusion thoroughly disagrees with the
RFC approach. We recognize that such numbers and diagrams
We take it upon ourselves to reach and embrace these ‘forgotten’ does little to justify the bountiful, many-faceted reality that is Nepal.
villages and to bring with us long-term solutions based on our In worst case such a limited definition may distort and cloud a clear
unique approach to rehabilitation. Specifically we endeavor, on a envisioning of what Nepal is and what she can be: a nation with a
community level, to initiate 6 components that we identified as rich heritage inspiring a world torn by extremities.
vital through extensive surveys and post-earthquake assessments:

• Permanent housing
• Education
• Socio-economic development
• Health/sanitation and water
• Energy
• Community based facilities
REBUILD FOR CHANGE (RFC) - 2

2. Previous Experience in Nepal


VFC started its activities in 2010 working as a volunteering platform In addition, VFC helped facilitate a Teacher Training Program (Nawa
based in Nepal. Since our inception we have been providing a Marga) in Nuwakot School in collaboration with another local NGO
variety of internships and volunteering opportunities in the areas of Karkhana.
education, community-work, agriculture and vocational trainings
to many passionate youths from all over the world. As this initial phase of recovery is slowly coming to a transition
point, we are moving all of our resources into the compassion
However, following the earthquake we decided to put our total based regrowing of communities as per our 6 components.
efforts into the newly initiated RFC program. In the first days
we have distributed first aid materials in the locations that were We have decided, upon careful consideration, to launch our
most hit by the catastrophe, and provided temporary shelters for the Rebuild for Change pilot-project in the village of Manegaun,
communities of Burunchili-Lalitpur, Ratatar-Sindhuli, Jeetpur and Burunchili, Karyavinayak-14, Lalitpur, just an hour drive from
Chaling-Bhaktpur. Furthermore, we have rebuilt schools in Nuwakot, Kathmandu.
Ratatar-Sindhuli, Mulbari-Dhading and Aam Dhadha-Dhading
through successful collaborations with different associations.

3. Pilot Project Location: Manegaun (Burunchuli)

Need-assessment and previous VFC engagement in the area

We have chosen Manegaun based on three accounts; first and channel that reaches the farm land, and therefore, the irrigation
foremost because the community here belongs to the Tamang system needs to be improved as well.
people - an often exposed and marginalized ethnic-group.
Secondly, for the population willingness to active participation and In fact, at present time, the main source of income for the
openness towards innovative approaches. Thirdly, for its proximity population seems to stem from informal business, especially the
to Kathmandu that makes it easier to transport materials and keep making of local alcohol (an illegal practice in Nepal), in which we
our presence vivid and alive. have assessed that as many as 30 women are involved.
Our findings further suggest that all of the households own at
According to our recent census data, Manegaun encompasses 55 least 2 animals - mostly goats and chicken, and that many wish to
households, and counts total populations of 395, among which expand this number substantially.
170 are male, 154 are female and 71 are children. All the houses
have been destroyed and the villagers are now residing in the Furthermore, almost all the houses use wood-fuel for cooking
55 temporary metal shelters that RCJM and VFC erected in the (wood from logs, sticks or twigs) which carries with it a number of
aftermath of the earthquake with the help of BVS- Nepal. health-related risks that could be greatly reduced with a switch to
a cooking stoves and other alternatives.
Our need assessment involved a focus group discussion with the
community and a household based survey with each member of Manegaun has still not been declared an open-defecation-free
the village. We quickly learned that the majority of the villagers zone. That means, sanitation is also one of the major issue, which
are involved in agriculture, and that most of them are women (42 cannot be left behind. The most common diseases are water
females versus 10 males). related diseases, as water-purifiers are not usually utilized. We
have also witnessed an increase in skin/eye infections diseases,
A soil assessment has never been done in this village and for related to the general lack of hygiene living in temporary shelters.
this reason the crop production is only sufficient for personal Another concern is street-lighting during night hours.
consumption- with no way of selling excess- production due to a
non-existent market-economy. Moreover, there is not a irrigation There are 71 children who go to 8 different schools in the area.
3 - REBUILD FOR CHANGE (RFC)

5. Strategy
40 of them go to the government school called Shree Bhimsen Our strategy entails three key-points:
Secondary school - which is in bad repair / critical condition.
1. Education and innovation
Having learned all these facts and considering the overall status
of the village, we analyzed the premises and boundaries for We approach education in a distinctive manner where
socio-economic reintegration - with the overall development of the creative ability to analyse and question outweighs
Burunchuli as a community in mind. We are aware that the very traditional methods of memorization. We want to impart
heart of rehabilitation and self-reliance lies in the provision of the values of logic and critical thinking, as well as inspire
economic opportunities - an uplifting of the valley as a whole, a natural curiosity and entrepreneurial spirit. Besides
that we endeavour to facilitate most efficiently. children’s education we also strive to provide the means
by which a community becomes self-reliant; this means
As already stated we have been working with the village community offering training and seminars on how to utilize new
from the very first week after the initial earthquake; focusing on technologies, how to manage business, how to manage
building temporary shelters and sanitation facilities (toilets) and by new ways of farming, seed distribution, how to be
providing each household with solar-lights and mobile chargers. involved in local tourism etc.

RCJM and VFC did organized the first health camp, in partnership 2. Community empowerment - with special emphasis
with Alka Hospital, in which we have conducted a health-screening on women’s empowerment:
and a vision screening, and provided necessary medical support,
as well as an Inner Healing Training for Post Traumatic Stress In our need assessment it resulted clear that women
Disorders (PTSD) - conducted by trained professional from the represent the major work force in Manegaun, it is
‘Hug and Heal’ organization. therefore equally clear that women will play an essential
role in the long-term rehabilitation. We will actively involve
them and the rest of the village in our socio-economic
development initiatives - through the provision of soft
loans and trainings on different vocational skills and

4. Objectives
home based businesses. The community as a whole
will work actively with our staff in all the phases of the
project. Empowering women empowers children and
The overall objective of the project is to provide the community of empowering children empowers society.
Manegaun with the tools to become self-reliant, resourceful and
resilient, by working with them in the following aspects: 3. Eco-sustainability

• Re-building permanent housing in an innovative We strive to create communities that leave as little
earthquake-proof manner and creating community- impact on Earth as possible. We endeavor to find the
based facilities; right balance between what is desirable and what is
• Securing appropriate health-education and viable for a village-community of this size and character.
sanitation, both on a structural and non-structural level; Our structures are created from indigenous, recycled
• Secure a viable flow of water and provide solar materials, and we seek to power our communities
energy; through sustainable energy and green agriculture.
• Enhance overall socio-economic development,
self-sustainability and economic reintegration of In accordance with our need assessment we identified the
the community, through the provision of soft loans and aforementioned 6 critical components, which will actualize these
new technologies in the field of agriculture, livestock key-points:
and small businesses, as well as the promotion of local
tourism.
REBUILD FOR CHANGE (RFC) - 4

Permanent housing Education


After meticulous research into viable housing-models the RFC During our household surveys it became evident that basic
project will introduce Natural Building Principles focusing primarily education is a major point for remedy in Manegaun. The data we
on earthbag construction. The primary reason for this choice collected show a high degree of illiteracy among the population,
is that we have realized that after the earthquakes that affected but also a strong desire to address this issue. For this reason RFC
Nepal of over 50 earthbag constructions built in Nepal every will provide basic literacy classes in conjunction with building/
single one survived the catastrophe. rehabilitating the relevant educational infrastructures.

Moreover, earthbag construction has the tremendous advantage of We will construct a multifunctional centre (see paragraph on
providing either thermal mass or insulation, depending on content. community-based facilities) that will provide Computer classes,
When filled with soil they provide thermal mass, but when filled with Literacy classes and an Early Childhood Development
lighter weight materials, such as crushed stone, or rice hulls, they Center (ECDC). UNESCO defines “early childhood” as the
provide insulation. The bags can even act as natural non-wicking, first 8-years in a child’s life - a time of remarkable cognitive and
somewhat insulated foundations when they are filled with gravel. psychological growth. These essential years lay the very foundation
for subsequent learning and development. It is our estimate that
If the earthbags are stacked in a wide variety of shapes, including an ECDC will serve a noble purpose as both an educational and
domes, they have the potential to virtually eliminate the need for advisory institution.
common tensile materials in the structure, especially the wood and
steel often used for roofs. This not only saves more energy (and We furthermore envision the community-center as an ample setting
pollution), but also helps save our forests, which are increasingly for future programs in support of our ambition for an enlightened
necessary for sequestering carbon. youth. It is VFC’s firm intent to provide long-standing support for the
youth that are undergoing primary education. Our efforts towards
Another aspect of sustainability is found in the economy of this children’s education in this area also extend to a partnership with
method. The fill material is cheap, especially if on-site soil is used. Shree Bhimsen Secondary School - the institution which most
The earthbags themselves can often be purchased as misprints of children from Manegaun village attend. In this respect, we will
or recycled grain sacks, but even when new are not particularly improve the inherent structural facilities and provide pedagogical /
expensive. Rotary International District 3292 Nepal-Bhutan academic trainings for the resident teachers.
through RCJM and VFC will build earthquake-proof homes for
55 families in Manegaun - all based on Natural Building With these points in mind our education initiative will assist in a
Principles. harmonious integration of the community as a whole - also by
providing relevant workshops and trainings needed to enact our
Together with a team of experts, VFC and RCJM will help design socio-economic initiatives (see next paragraph), and offer a space
earthquake-proof structures using natural and recycled indigenous for the newly formed cooperative and its meetings.
materials as described above to reduce the cost. At the same
time, project will try to incorporate other innovative utilities in
accordance with Natural Building Principles such as renewable
Socio-economic development
energy, rainwater harvesting, sewage treatment and “tempered
indoor climate” as additional funds become available.
As per our need assessment agricultural enterprises on a minor
scale is the predominant way of life - this involves but is not limited
Though the size of the family might vary, the houses will be of
to goats, chickens, buffaloes and cow-rearing. As it stands today
standard size comprising 2 rooms for the family and an additional
however, a large portion of the community-income is derived from
room will be provided in order to accommodate tourists for the
alcohol distillation - an activity entirely conducted by the local
homestay programme we will be promoting (see: socio-economic
women.
development).

It is clear from the data we gathered during our household


The community will be provided trainings on earthbag and will be
interviews that almost all the villagers are interested in either
actively engaged with our staff in all the phases of the construction.
improving their current business, or engaging in new ones. Also
the women now engaged in alcohol distillation are open towards
trying new approaches at generating an income.
5 - REBUILD FOR CHANGE (RFC)

With these points in mind we have planned a series of actions that c. Soft loans
will improve both current economic chains such as agriculture and
animal farming, but also promote new types of businesses. We will be providing grants to the newly formed agro-
Furthermore we have established a cooperative composed of based cooperative who will issue soft-loans (with no
selected members of the local community whose responsibility will interest rates) to those members of the community
encompass activities related to these socio-economic components who apply with the purpose of starting new business
- in time, as our project reaches a natural conclusion. This group enterprises or to improve existing ones.
will take full responsibility and ownership of the community-based
facilities. Moreover, we will engage the women that are currently
involved in alcohol making, through home based
a. Agriculture enterprises like candles, incense, pickles making.

For this component we will be partnering with the These activities will be followed by different vocational
District Agriculture Department, which will provide trainings and courses on small enterprise and proper
us with the necessary expertise for soil assessment, the management.
distribution of improved seeds and the introduction of
new green technologies to scale up the crop production.
For those activities the District will cover the 50% of the d. Homestay
expenses.
Given its proximity to Kathmandu and natural beauty,
Since it was a concern raised by the community, we Burunchuli could easily be made to appeal to both
will also improve the existing irrigation canal by using locals, expats and international tourists for short
natural techniques that will prove more sustainable treks and hiking. A potential that would contribute
than the ones built using cement. In relation we are also with both extra work opportunities and a subsequent
introducing improved methods for compost-making. increased income-flow. To actualize this potential we
will organize a series of consultative meetings with
Moreover, we have partnered with Ask Foundation the Nepal Tourism Board, as well as Trekking and
in introducing and promoting their “Agricultural App.”, Travel agencies. (local youth clubs and expat living in
connecting local farmers to the relevant markets Kathmandu). Furthermore we will generate an online
eliminating the need for middle-men. They will also presence by launching a website to promote the village
assist us in providing proper trainings on using the along with our campaigns and events. The community
phone app. will be provided with different types of tourism and
hospitality related trainings to develop their capacity to
b. Animal farming accommodate in this sector.

We will be partnering with the District Livestock


Department and Animal Nepal NGO, and engage Health/Sanitation and Water
in different activities aimed at improving livestock
business - in terms of expansion and improvement of As far as the health and sanitation component is concerned, RCJM
animals shelters, provision of trainings on free range and VFC organized a preliminary health camp, in partnership with
animal farming to the community, a space for animals to the Alka Hospital of Lalitpur, to assess the main causes of illnesses
be able to roam freely outdoor, and individuation of new of the community, and be able to define the type of trainings on
markets. basic health and sanitation that could benefit the community.
We also organized a free eye camp, in collaboration with Tilganga
In this respect, we are creating a livestock bank, that will hospital where 25 people who were diagnosed with cataract
be handled by the cooperative and that will be given a were provided with medical assistance and were given specific
grant to issue to the villagers. The amount of this grant instructions to visit Tilganga Hospital for further medical treatment.
is based on their needs to expand their current cattles The transportation for these patients suffering for cataract was
business (in terms of number/type of cattles owned arranged by RCJM and VFC.
and shelters) that we have gathered during our need
assessment. Throughout the project, 3 additional health camps will be
conducted in the community to monitor the health conditions
and the progress after the several health camps. Moreover, the
REBUILD FOR CHANGE (RFC) - 6

Community based facilities


structure of the health post office of the village will be enhanced. During our need assessment, we realized that the community does
As far as the water component is concerned, we will improve not have any privacy while bathing nor a cohesive gathering place.
the existing water reservoir of the village. The reservoir will be re For this reason we have decided to provide 2 Pandheros (one for
strengthened by using retrofitting and it will be covered from the women and one for men) - which will act as community-based
upper side so that external means do not pollute the water. drinking and washing facilities, that while securing more privacy
would function as important focal points for social interaction.
Each pandhero will be provided with an attached bathroom.
Energy
We will renovate the green area of the village, equipping it with
During the initial need assessment we have realized that a lot of benches in order to transform it into a public garden, or small park,
the health issues of the community were related to the extensive and we will also pave the walking paths of the village as a further
use of firewood for cooking purposes, whose gas emissions are means to integrate the community in the daily life. When designing
very harmful. We will provide all 55 households with innovative, these facilities we keep both tourist and the community in mind -
improved cooking-stoves. We are always researching viable especially children.
options for green alternatives to introduce to the community.
Finally, we have partnered with the District Education Office,
Moreover, in order to address the lack of street lighting during night Lalitpur in constructing a resilient multifunctional community-
time, we will be providing the village with 25 solar street lights, center, based entirely on our Natural Building Principles, complete
that will certainly benefit the community, especially children, during with a library, musical instruments and sporting-goods, where the
night hours. ECCD and all our trainings will take place during our project. (See;
Education.)
7 - REBUILD FOR CHANGE (RFC)

6. Activities
Component 1 Permanent housing
S.No. Activities Sub-Activities Output
1 Assessment i. Organize a meeting with community to introduce the initiative, set out
expectations from the community and make sure they will be effectively
involved in the construction.
ii. Conduct individual household survey to assess everybody’s need.
iii. Conduct engineering assessment of each household.

2 Documentation i. Focal group discussion with the community.


and verification ii. Verification of legal document to build the house.
iii. Demarcation of lands by the VFC engineering team and Govt. officials.
iv. Meeting with the government officials for the design and project approval.
3 Training i. Analysis about debris management and how it can be reused for the building of
the houses.
ii. Trainings on natural building techniques for the community.
iii. Volunteer engagement.
iv. Volunteers training on first-aid and safety

4 Construction i. Hiring of engineers (external consultants).


ii. Volunteers and community engagement in the construction work.
iii. Clearing of site for house construction.
iv. Construction of 55 houses based on Natural Building techniques
v. Final retouch and painting of the houses.
vi. Stone pavement in front of every house.

Component 2 Education
S.No. Activities Sub-Activities Output
1 Assessment i. Conduct a focal group discussion with the community to introduce the
educational aspects of the project and discuss the implementation plan.
ii. Conduct a literacy survey on a household basis to know the exact literacy rate
of the community.
iii. Carry out an engineering assessment of the Shri Bhimsen Mabi school/
classrooms and their maintenance.
2 Early Childhood i. Equipping an ECDC for the children aged below 5 (within the multifunctional
Development centre- see paragraph on community-based facilities).
Centre (ECDC) ii. Recruit and train 2 care takers on child care and education, and provide a
monthly salary for the project duration.
3 Literacy Classes i. Train the volunteers that will conduct the classes through modern teaching
and various methods and curriculum-based trainings and provide literacy classes to the
trainings population.
ii. Develop a curriculum for the literacy classes in order to facilitate the proper
functioning of the program.
iii. Trainings on life skills, civic engagement and environment.
4 Capacity building i. Conduct Instructive and Academic trainings to the teachers.
and training to ii. Improvement of school facilities (furniture, paintings, sports etc) with the help of
the teachers of the volunteers.
Shree Bhimsen
Madhyamik
Vidyalay
5 Computer i. Formulation of a teaching curriculum.
Classes ii. Set up a small computer lab with 2 computers.
iii. Providing Computer trainings to the population .
REBUILD FOR CHANGE (RFC) - 8

Component 3: Socio-Economic Development


S.No. Activities Sub-Activities Output
1 Assessment i. Focal group discussion and assessment on the socio-economic activities to
engage with the members of the community.

2 Agriculture i. Meeting for partnership with the Dist. Agriculture Office for technical
collaboration.
ii. Carry out soil testing to enhance crop production.
iii. Introduction of new technologies to scale up the production and provision of
trainings to the farmers.
iv. Distribution of improved seeds to the farmers.
v. Construction of an irrigation canal.
vi. Trainings on reusing agriculture waste for compost making.
vii. Finding possible markets and trainings on a phone App to connect the
farmers to the markets.

3 Livestock i. Meetings and consultation with the District Livestock office (GoN) on available
grants to facilitate the community.
ii. Provision of trainings to the community on free range animals rearing
methods and provision of an open space for the animals to roam freely.
iii. Creation of a livestock bank managed by the cooperative and deposit of a
fund aimed to expand the livestock owned by the population.
iv. Construction of new animal shelters and improvement of existing ones.
v. Finding out possible markets for this business.

4 Soft Loans i. Establishment of a multipurpose cooperative, set up of an office with a


computer, train on business management and accountancy.
ii. Provision of soft loans and trainings in home based businesses like pickle
making, candle making, tailoring, incense making for the women.
iii. Establishment of 2 grocery stores.

5 Develop Homestays i. Train the community on how to run a homestay.


for tourists ii. Touristic promotion of the the village through different media, website, events,
advertisement, and creation of partnership with tours and travel to bring local
as well as international tourism to the village.
9 - REBUILD FOR CHANGE (RFC)

Component 4: Health, Sanitation & Water


S.No. Activities Sub-Activities Output
1 Assessment i. Focal group discussions/ meeting with the community and household
surveys to assess the status of health, sanitation and water related issues in
the village.
ii. Provision of 1 health camp to screen the health status of the population in
collaboration with Alka hospital.

2 Health Care i. Signature of a MoU with Alka hospital.


ii. Provision of 3 health camps(one every four months, for the duration of the
project), and distribution of discounted Alka Hospital Health cards to the
community.
iii. Improvement of the structural facility of the village health post and medicines
restock.
iv. Provision of trainings on safe child delivery to 2 local midwives.
v. Provision of 6 inner healing sessions on post traumatic stress disorder (PTSD)
to the population.
3 Sanitation i. Provision of 2 trainings and awareness programs on Solid Waste
Management.
ii. Provision on 3 WASH awareness trainings.
iii. Installation of a water plant for safe and clean drinking water.

Component 5: Energy
S.No. Activities Sub-Activities Output
1 Provision of i. Conduct a survey to assess the need of improved cooking stoves.
Improved Cooking ii. Distribution and installation of 55 improved cooking stoves.
Stoves iii. Provision of a training on a household basis on the use of the new improved
cooking stoves.

2 Solar Street Lights i. Set up 25 Solar street lights.

Component 6: Community based facilities


S.No. Activities Sub-Activities Output
1 Multifunctional Halls i. Construction of a multifunctional centre.
ii. Equipping the hall with musical, sports and other needed tools.
2 Pandhero i. Construction of 2 Pandheros.
ii. Construction of Water Channel and Reservoir
3 Recreational Park i. Creation of a park as a gathering

4 Paved Pathways i. Construction of paved walkways


REBUILD FOR CHANGE (RFC) - 10

7. Technical aspect of the Program and Plan


a. Key actors

Main Donors - Rotary International District 3292 Nepal-Bhutan


Developed & Implementation by - CREASION / VFC Nepal
- Rotary club of Jawalakhel-Manjushree (RCJM)
Partners - District Agriculture Office, Dist. Livestock Office, (Govt. of Nepal), Animal Nepal,
BVS Nepal
Supporters - Ecoprise, Ask Foundation, NERA

b. Project beneficiaries

The direct beneficiaries of the project are the 395 inhabitants The evaluation process will include all stakeholders and will be
of Manegaun, and the 20 teachers and 325 students of the carried out to gain multiple perspectives on project activities
Shree Bhimsen Secondary School. and to enhance the community ownership of the project. The
evaluation component will assess the program in terms of
c. Project location relevance, efficiency, effectiveness, impact and sustainability.

Manegaun, Burunchuli, Karyavinayak Municipality, ward no.-


14, Lalitpur District. f. Funding provision, roles and responsibilities of
PARTNERS:
d. Project management
Implementing Partner/ Main Donor: Rotary International
The overall management and accountability of the project will District 3292 Nepal-Bhutan
be a responsibility of and RCJM and CREASION/VFC Nepal.
However, the community’s active participation is a prerequisite Rotary International District 3292 Nepal-Bhutan being the
of the programme in order to mobilize and motivate local main donor of the project, will be responsible for:
people to stand up for themselves and be self-reliant in the
occurrence of an emergency. Therefore, the local RCC will • providing the financial assistance to the RFC
play an active role in executing most of the activities. project for 55 Permanent Housing, Multi-
Functional Hall and project operations through
e. Monitoring and Evaluation RCJM.
• helping in leveraging funds from other agencies and
Project Steering Committee: different Rotary Clubs.
• providing inputs and advice for the success of
A project steering committee comprising of members from project.
RCJM and VFC will be formed and will meet every months • helping in coordinating with the GoN agencies if
during the project period to make sure that the project required.
is running smoothly. Similarly, in order to monitor project • helping promote the project and its activities in
progress, the project envisages a formal reflection and review public events, ceremonies, social media, etc, locally
of the milestones after 6 months from inception, based on the and globally.
experiences made by then. Detailed MIS systems will be put
into place and periodic external inputs will also be taken.

RCJM and VFC will submit a report on six monthly basis to


its partners, co-partners and donors to assess the progress
of the project.

Once the project will be completed, the steering committee


will carry out the final evaluation and monitoring.
11 - REBUILD FOR CHANGE (RFC)

EXECUTING PARTNERS:

1. Rotary Club of Jawalakhel-Manjushree: • Promote the project and its activities in public
events, ceremonies, social media, etc, locally and
Rotary Club of Jawalakhel-Manjushree being the partner of globally.
the project will be responsible for: • Provide project completion report along with
pictures, videos one week after the project is
• Providing the financial assistance for 2 Padhero, completed.
water mgmt system and project operations.
• Helping in leveraging funds from different Rotary
Clubs, will also look for additional funding sources
for the smaller components of the project through
social media campaign, crowdfunding, local and
international grants etc..
8. Assumptions and risks
• Providing input, advice on the ground (Manegaun,
Stated below are assumptions about risk factors that could
Burunchuli), provide volunteer support through
obstruct the effective implementation of the planned activities
different rotaract clubs.
and/or the achievement of the program’s objectives, but that
• Helping in coordinating, taking permissions with the
are not under the control of RCJM and VFC. These factors will
GoN agencies whenever required.
be monitored throughout the project and efforts will be made to
• Promoting the project and its activities in public
ensure favourable outcomes. The achievement of the objectives
events, ceremonies, social media, etc, locally and
largely depends on the successful implementation of the activities,
globally.
but there are still other factors to take into consideration: t

2. Creasion/ VFC Nepal
In order to carry out activities:

CREASION/ VFC Nepal being the designer of the project will


• Adequate level of security is maintained in the area
be responsible for implementing the project and for:
• No major natural catastrophe affects the operational
area
• Conducting need assessment before starting
• The community, including the women, will be
the project and share the survey report to all the
actively involved the construction work as the
concern parties and partners.
RFC program has been designed that way. Active
• Providing financial, technical and in kind
participation is a must
assistance for need assessment, trainings,
• Effective collaboration will come from our partners
stone paved walkways, app development,
• Cost of materials will not increase significantly due
healthcare, sanitation, and project operation
to market forces
cost.
• Providing the needful procurements for the project
In order to achieve program objectives:
activities once the funds are available.
• Providing Human Resources (volunteers and staffs),
• The key actors of the community (school teachers,
technical expertise and project management
members of the cooperative, will evolve as partners
oversight for the activities and projects as mutually
and not remain a passive beneficiary
agreed.
• Cultural sensitivity and traditional beliefs will not
• Look for additional funding sources for the smaller
hamper the program activities
components of the project through social media
• Increased awareness of the community will translate
campaign, crowdfunding, local and international
into actions (behavioral change)
grants etc.
• Women will take part in the activities and trainings
• Keep up to date all the financial details of the project
carried out throughout the project
activity from incoming resources to the outgoing
• The village will approve of women being organized
resources. Will share the financial details to Rotary
receiving trainings on new businesses and
Club and other partner, donor on regular basis.
enhancing agriculture
REBUILD FOR CHANGE (RFC) - 12

9. Sustainability
Sustainability is a core-principle at RFC - as detailed in previous c. introduce new technologies that will aim to scale
paragraphs. All our efforts go towards creating a confident, self- up the crop production, improve the current animal
reliant and resourceful community. In this respect our strategy farming structures and methods, and connect the
aims towards actively involving the population in each and every farmers to the possible markets, in order to allow
of our activities, and provide necessary technologies, skills and them to sell their products without the need of a
economic support to enhance both living conditions and financial middle man;
stability upon completion of the project.
d. equip each household with an additional room
Specifically, in order to ensure the social and financial sustainability that will be used to accommodate tourists for the
of our project, we are going to implement the following course-of- homestay program, that will be promoted through
action: a website, social media and travel agencies, and
consequently provide extra income to the families;

a. create a cooperative with the help of local RCC that e. ensure the active participation of the community
will receive the necessary accountancy/business in all activity-areas and provide specific capacity-
management trainings and who will be in charge of building trainings for each of the 6 components -
soft loans provided to the community, maintenance so that each inhabitant will acquire a set of abilities
of the provided community based-facilities, and in different areas of expertise, and consequently be
ensure the ability of the community to properly, and more resourceful in overcoming potential difficulties
independently, function in accessing new markets or natural catastrophes.
and sharing profits by the end of the project;

b. provide soft loans through local RCC aimed at


expanding the current businesses in agriculture,
livestock or small shops, and at creating new ones,
in order to ensure the financial security of each
household, that upon project completion will not
have to rely on the illegal practice alcohol making in
order to secure an income;
Component: 1 Permanent Housing

VFC Donors and


Total
Unit Contribution others
S.No. Activities Sub Activities Unit Rate (USD) Budget (In
Number in USD (In Cash contribution in
USD)
& Kind) USD
Focal Group discussion Number $50 5 $250 250
1 Assessment Individual Household Survey Number $500 2 $1,000 1,000
Engineering assessment Number $1,000 2 $2,000 2,000
Focal Group Meeting Number $50 7 $350 350
Legal paper verification L/S $1,000 $1,000 1,000
Documentation Demarcation of the land by Number $1,000 1 $1,000 1,000
2 & officals
Verification Meeting with government Number $100 1 $100 100
bodies for approval of design
and project
Debris management and Days $200 2 $400 400
reuse
3 Training Natural buliding techniques Days $250 4 $1,000 1,000
First Aid and Safety Number $300 1 $300 300
Volunteer engagement Days $200 4 $800 800
A consulting group Months $1,000 12 $12,000 12,000
(engineers) will be hired
4 Construction Volunteer engagement Months $50 12 $600 600
House Construction Number $5,746 55 $316,030 316,030
Stone pavements L/S $2,000 1 $2,000 2,000
Total $338,830 6,800 332,030
1 15% Project cost $50,825 $1,020 $49,805
2 Sub total $389,655 $7,820 $381,835
3 6% Contingency $23,379 $469 $22,910
cost
4 Grand total $413,034 $8,289 $404,745
13 - REBUILD FOR CHANGE (RFC)
Component: 2 Education

Total VFC Contribution in Donors and


Unit
S.No. Activities Sub Activities Unit Rate (USD) Budget (In USD others contribution
Number
USD) (In Cash & Kind) in USD
FGD with community and school Number $200 1 200 200
1 Assessment Literacy rate survey - 200 200
Engineering assesment of the school Number $1,000 1 1,000 1,000
Early Childhood Establishment of ECDC Number $2,000 1 2,000 2,000
2 Development Teachers and care takers training Number $250 1 250 250
Centre Allowance for 2 teachers/ caretakers Number $100 13 1,300 1,300
REBUILD FOR CHANGE (RFC) - 14

Establishment of ALC Number $1,000 1 1,000 1,000


Curriculum development Number $250 1 250 250
Adult Literacy Teachers training to the volunteers and teaching classes to Number $550 12 6,600 6,600
3
Class the population
Training realted to life skills, civic engagement, environment Number $1,000 1 1,000 1,000
etc
Capacity building Capacity building of the teachers Number $500 1 500 500
and training to the Enhancing school facilities (furnitures, paintings, sports Number $5,000 1 5,000 5,000
teachers of Sri etc)
4
Bhimsen Volunteer engagement cost for school construction Number $500 1 500 500
Madhyamik
Vidyalay
Basic curriculum development Number $500 1 500 500
Computer Literacy
5 Computers and other electric appliances Number $2,000 1 2,000 2,000
Classes
Volunteer Engagement cost Number $500 1 500 500
Total $22,800 $3,650 $19,150
1 15% Project cost $3,420 $548 $2,873
2 Sub total $26,220 $4,198 $22,023
3 6% Contingency $1,573 $252 $1,321
cost
4 Grand total $27,793 $4,449 $23,344
Component: 3 Socio-economic development

Total Budget VFC Contribution


Unit Donors and others
S.No. Activities Sub Activities Unit Rate (USD) (In in USD (In Cash &
Number contribution in USD
USD) Kind)
Focal Group Meetings Number $100 5 500 500
1 Assessment Assessment by experts Number $100 5 500 500
Volunteer engagement L/S $500 - 500 500
Meeting with District Agriculture Office Number $25 10 250 250
Soil test by experts Number $100 3 300 300
Training on different modern agriculture Number $300 5 1,500 1,500
techniques
2 Agriculture
Improved seeds distribution Times $700 2 1,400 1,400
Construction of canal for irrigation Number $3,000 2 6,000 6,000
Training on compost making Number $350 2 700 700
Market outreach, phone app training L/S $2,000 1 2,000 2,000
Meeting with District Livestock office Number $25 5 125 125
Training on different kinds of livestock Number $500 2 1,000 1,000
rearing
3 Livestock
Livestock bank setup Number $100 50 5,000 5,000
Animal Shelters L/S $4,000 4,000 4,000
Market outreach L/S $100 5 500 500
Establish a multipurpose co-operative L/S $3,000 1 3,000 3,000
(setting up their office, computers ,
4 Soft loans training (business mgmt, accoutancy)
Home based business for women Number $500 5 2,500 2,500
Grocery stores Number $500 2 1,000 1,000
Homestay training to the community Number $100 50 5,000 5,000
Promoting of the place through L/S $5,000 1 5,000 5,000
5 Homestay
different media, website, events,
advertisement
Total $40,775 $1,875 $38,900
1 15% Project cost $6,116 $281 $5,835
2 Sub total $46,891 $2,156 $44,735
3 6% Contingency $2,813 $129 $2,684
cost
4 Grand total $49,705 $2,286 $47,419
15 - REBUILD FOR CHANGE (RFC)
Component: 4 Health and sanitation

Donors and
Total VFC Contribution in
others
S.No. Activities Sub Activities Unit Rate (USD) Unit Number Budget USD (In Cash &
contribution in
(In USD) Kind)
USD
Focus Group Discussion Month $200 12 2,400 2,400
awareness meetings
1 Assessment Household Survey Number $200 3 600 600
Health Screening by Number $500 1 500 500
specialists
REBUILD FOR CHANGE (RFC) - 16

MoU with Hospitals


Health Camp Number $300 3 900 300 600
Cataract treatment
Distribution of medicines Number $500 3 1,500 1,500
2 Health Care Enhacement of existing Number $1,000 1 1,000 1,000
health posts
Local midwife volunteers Number $200 2 400 400
training
Stress management Number $200 6 1,200 1,200
Solid Waste management Number $500 2 1,000 1,000
awareness & training
3 Sanitation WASH awareness training Number $300 3 900 900
Safe drinking water plant Number $2,000 1 2,000 2,000
set up
Total $12,400 $2,700 $9,700
1 15% Project $1,860 $405 $1,455
cost
2 Sub total $14,260 $3,105 $11,155
3 6% Contingency $856 $186 $669
cost
4 Grand total $15,116 $3,291 $11,824
Component: 5 Energy

Donors and
Total VFC Contribution in
Sub others
S.N. Activities Unit Rate (USD) Unit Number Budget (In USD (In Cash &
Activities contribution in
USD) Kind)
USD
Need Number $100 1 100 100
assessment of Improved
cooking stove
Distribution of Distribution & Number $50 55 2,750 2,750
1 Improved Installation of
cooking stoves stoves
Training on Times $200 1 200 200
improved
stoves
Solar Street Solar Streetlights Number $700 25 17,500 17,500
2
Lights installation
Total $20,550 $300 $20,250
1 15% Project cost $3,083 $45 $3,038
2 Sub total $23,633 $345 $23,288
3 6% Contingency $1,418 $21 $1,397
cost
4 Grand total $25,050 $366 $24,685
17 - REBUILD FOR CHANGE (RFC)
Component: 6 Community based facilities

VFC
Donors and
Contribution
Total Budget others
S.No. Activities Sub Activities Unit Rate (USD) Unit Number in USD (In
(In USD) contribution in
Cash &
USD
Kind)
Construction of Hall Number $11,000 1 11,000 11,000
1 Multifunctional Hall
Resources for hall L/S $3,500 1 3,500 3,500
Construction of Number $3,100 2 6,200 6,200
Padheros
REBUILD FOR CHANGE (RFC) - 18

2 Padhero Construction of L/S $3,000 1 3,000 3,000


water channel
and reservoir
Construction of L/S $4,000 1 4,000 4,000
3 Recreational park
parks
4 Stone paved walkways Paving the walkways L/S $3,000 1 3,000 3,000
Total $30,700 $3,000 $27,700
1 15% Project cost $4,605 $450 $4,155
2 Sub total $35,305 $3,450 $31,855
3 6% Contingency $2,118 $207 $1,911
cost
4 Grand total $37,423 $3,657 $33,766
C/O CREASION
P.O. Box: 11772

Neel Saraswoti Marg, Lazimpat


Kathmandu, Nepal

Phone No.: +977-1- 4004069


Email: info@vfcnepal.org

For more information, log in to :

www.vfcnepal.org
Follow Us on : www.facebook.com/volunteer4change

Joint Initiative of VFC Nepal and RCJM


(Rotary Club of Jawalakhel, Manjushree)

Você também pode gostar