A L A W I T U N S I E S T A B L IS M E N T

Client:Ministry Of Health
JEDDAH NORTH GENERAL HOSPITAL
Consultant:Zuhair Fayez Partnership
500 BED
Contractor:Alawi Tunsi Establishment

Activity Activity Orig % Early/ Early/


ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

500 BED HOSPITAL NORTH JEDDAH


Total 1,952 65 03MAY05A 31JUL11

Main Building
CIVIL WORKS
Mobilize

MBG1100 Mobilize 26 100 04MAY05A 02JUN05A


Mobilize

Earth Works
Basement Floor
MBMCBM1100 Excavate / PCC Basement 27 100 04JUN05A 04JUL05A
Excavate / PCC Basement

MBMCBM2000 Back Fill Basement Sides 4 100 14DEC05A 18DEC05A


Back Fill Basement Sides

Grnd. Floor "4A - 7A"Rear Bldg Works


MBCEG100 Excvt Found. GF 6 100 10OCT06A 16OCT06A
Excvt Found. GF

MBCEG120 B. Fill to Gr. Beam 9 100 07MAR07A 17MAR07A


B. Fill to Gr. Beam

MBCEG140 B. Fill till Gr. Slab 5 100 12JUL07A 17JUL07A


B. Fill till Gr. Slab

MBCEG180 Gravel Gr. Slab 3 100 18JUL07A 21JUL07A


Gravel Gr. Slab

MBCEG160 Pest Cntrl U / Gr. Slab 2 100 22JUL07A 23JUL07A


Pest Cntrl U / Gr. Slab

Grnd Floor "5B - 6B" Rear Bldg Works


MBGD1000FG Excvt Found. 6 100 06DEC06A 12DEC06A
Excvt Found.

MBGD1900FG Back Fill to GB 9 100 31MAR07A 09APR07A


Back Fill to GB

MBGD2500FG B. Fill till Gr. Slab 5 100 17JUN07A 03DEC07A


B. Fill till Gr. Slab

MBGD2700FG Gravel Gr. Slab 2 100 23JUN07A 06DEC07A


Gravel Gr. Slab

MBGD2600FG Pest Cntrl U/ Gr. Slab 3 100 25JUN07A 03DEC07A


Pest Cntrl U/ Gr. Slab

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 1 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
Grnd Floor "4B - 5A" Rear Bldg Works
MBS1000 Excvt Found. 6 100 17OCT06A 23OCT06A
Excvt Found.
MBS1020 Back Fill to GB 9 100 05APR07A 15APR07A
Back Fill to GB
MBS1040 B. Fill till Gr. Slab 5 100 30DEC07A 09JUL08A
B. Fill till Gr. Slab
MBS1080 Gravel G. Slab 3 100 05JAN08A 10JUL08A
Gravel G. Slab
MBS1060 Pest Cntrl Gr. Slab 2 100 10JAN08A 15JUL08A
Pest Cntrl Gr. Slab

Grnd Floor "6A - 7B" Rear Bldg Works


MBCGD1000 Excvt Found. 6 100 24OCT06A 30OCT06A
Excvt Found.
MBCGD1900 Back Fill to GB GF 9 100 12FEB07A 21FEB07A
Back Fill to GB GF
MBCGD2500 B Fill till Gr. Slab 5 100 15JAN08A 06OCT08A
B Fill till Gr. Slab
MBCGD2700 Gravel G. Slab 3 100 23JAN08A 08OCT08A
Gravel G. Slab
MBCGD2600 Pest Cntrl Slab 2 100 27JAN08A 09OCT08A
Pest Cntrl Slab

Concrete Works
Basement Floor
MBMCBM1200 Conc Raft Basment 45 100 28JUL05A 18SEP05A
Conc Raft Basment
MBMCBM1300 Conc Ret. Walls Basement 65 100 19SEP05A 03DEC05A
Conc Ret. Walls Basement
MBMCBM1500 Conc Deck Basement 38 100 19DEC05A 31JAN06A
Conc Deck Basement

Ground Floor Tower


MBMC1100GA Fix Reinf Columns 5 100 05SEP06A 10SEP06A
Fix Reinf Columns
MBMC1400GA Fix Reinf Walls 7 100 05SEP06A 12SEP06A
Fix Reinf Walls
MBMC1200GA Form Columns 7 100 11SEP06A 18SEP06A
Form Columns
MBMC1500GA Form Walls 12 100 13SEP06A 26SEP06A
Form Walls
MBMC1300GA Concrete Columns 1 100 19SEP06A 19SEP06A
Concrete Columns
MBMC1100GC Fix Reinf Columns 5 100 23SEP06A 27SEP06A
Fix Reinf Columns
MBMC1400GC Fix Reinf Walls 8 100 23SEP06A 01OCT06A
Fix Reinf Walls
MBMC1600GA Concrete Walls 1 100 27SEP06A 27SEP06A
Concrete Walls

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 2 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBMC1200GC Form Columns 7 100 28SEP06A 05OCT06A
Form Columns
MBMC1800GA Form Suspended Slab 18 100 28SEP06A 18OCT06A
Form Suspended Slab
MBMC1100GB Fix Reinf Columns 5 100 01OCT06A 05OCT06A
Fix Reinf Columns
MBMC1300GB Fix Reinf walls 7 100 01OCT06A 08OCT06A
Fix Reinf walls
MBMC1400GB Form Walls 15 100 01OCT06A 17OCT06A
Form Walls
MBMC1500GC Form Walls 10 100 02OCT06A 12OCT06A
Form Walls
MBMC1900GA Fix Reinf Slab 10 100 05OCT06A 16OCT06A
Fix Reinf Slab
MBMC1200GB Form Columns 7 100 07OCT06A 14OCT06A
Form Columns
MBMC1300GC Concrete Columns 1 100 07OCT06A 07OCT06A
Concrete Columns
MBMC1600GC Concrete Walls 1 100 14OCT06A 14OCT06A
Concrete Walls
MBMC1250GB Concrete Columns 1 100 15OCT06A 15OCT06A
Concrete Columns
MBMC1800GC Form Ceiling Slab 18 100 15OCT06A 04NOV06A
Form Ceiling Slab
MBMC2000GA Concrete Slab 1 100 17OCT06A 17OCT06A
Concrete Slab
MBMC1500GB Concrete walls 1 100 18OCT06A 18OCT06A
Concrete walls
MBMC1800GB Form Ceiling Slab 18 100 19OCT06A 08NOV06A
Form Ceiling Slab
MBMC1900GC Fix Reinf Ceiling Slab 10 100 21OCT06A 31OCT06A
Fix Reinf Ceiling Slab
MBMC2000GC Conc Slab 1 100 01NOV06A 01NOV06A
Conc Slab
MBMC1900GB Fix Reinf Ceiling Slab 10 100 07NOV06A 18NOV06A
Fix Reinf Ceiling Slab
MBMC2000GB Conc Ceiling Slab 1 100 19NOV06A 19NOV06A
Conc Ceiling Slab

First Floor Tower


MBMC1100FA Fix Reinf Columns 5 100 26OCT06A 31OCT06A
Fix Reinf Columns
MBMC1400FA Fix Reinf Walls 6 100 26OCT06A 01NOV06A
Fix Reinf Walls
MBMC1500FA Form Walls 10 100 29OCT06A 08NOV06A
Form Walls
MBMC1200FA Form Columns 7 100 30OCT06A 06NOV06A
Form Columns
MBMC1100FC Fix Reinf Columns 5 100 07NOV06A 12NOV06A
Fix Reinf Columns

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 3 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBMC1300FA Conc Columns 1 100 07NOV06A 07NOV06A
Conc Columns
MBMC1400FC Fix Reinf Walls 7 100 07NOV06A 14NOV06A
Fix Reinf Walls
MBMC1200FC Form Columns 7 100 09NOV06A 16NOV06A
Form Columns
MBMC1600FA Conc Walls 1 100 09NOV06A 09NOV06A
Conc Walls
MBMC1500FC Form Walls 12 100 11NOV06A 23NOV06A
Form Walls
MBMC1800FA Form Ceiling Slab 18 100 11NOV06A 30NOV06A
Form Ceiling Slab
MBMC1300FC Conc Columns 1 100 18NOV06A 18NOV06A
Conc Columns
MBMC1100FB Fix Reinf Columns 5 100 20NOV06A 25NOV06A
Fix Reinf Columns
MBMC1400FB Fix Reinf Walls 7 100 20NOV06A 27NOV06A
Fix Reinf Walls
MBMC1200FB Form Columns 7 100 22NOV06A 29NOV06A
Form Columns
MBMC1500FB Form Walls 14 100 23NOV06A 09DEC06A
Form Walls
MBMC1600FC Conc Walls 1 100 25NOV06A 25NOV06A
Conc Walls
MBMC1800FC Form Ceiling Slab 18 100 26NOV06A 16DEC06A
Form Ceiling Slab
MBMC1900FA Fix Reinf Ceiling Slab 9 100 28NOV06A 07DEC06A
Fix Reinf Ceiling Slab
MBMC1300FB Conc Columns 1 100 30NOV06A 30NOV06A
Conc Columns
MBMC200FA Conc Ceiling Slab 1 100 09DEC06A 09DEC06A
Conc Ceiling Slab
MBMC1600FB Conc Walls 1 100 10DEC06A 10DEC06A
Conc Walls
MBMC1900FC Fix Reinf Ceiling Slab 9 100 13DEC06A 23DEC06A
Fix Reinf Ceiling Slab
MBMC1800FB Form Ceiling Slab 18 100 17DEC06A 09JAN07A
Form Ceiling Slab
MBMC2000FC Conc Ceiling Slab 1 100 24DEC06A 24DEC06A
Conc Ceiling Slab
MBMC1900FB Fix Reinf Ceiling Slab 9 100 07JAN07A 16JAN07A
Fix Reinf Ceiling Slab
MBMC2000FB Conc ceiling Slab 1 100 17JAN07A 17JAN07A
Conc ceiling Slab

Second Floor Tower


MBMC1100SA Fix Reinf Columns 5 100 10DEC06A 14DEC06A
Fix Reinf Columns
MBMC1400SA Fix Reinf Walls 8 100 10DEC06A 18DEC06A
Fix Reinf Walls

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 4 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBMC1200SA Form Columns 7 100 12DEC06A 19DEC06A
Form Columns
MBMC1500SA Form Walls 14 100 13DEC06A 28DEC06A
Form Walls
MBMC1300SA Conc Columns 1 100 20DEC06A 20DEC06A
Conc Columns
MBMC1100SC Fix Reinf Columns 5 100 25DEC06A 30DEC06A
Fix Reinf Columns
MBMC1400SC Fix Reinf Walls 8 100 25DEC06A 06JAN07A
Fix Reinf Walls
MBMC1200SC Form Columns 8 100 27DEC06A 08JAN07A
Form Columns
MBMC1500SC Form Walls 15 100 28DEC06A 17JAN07A
Form Walls
MBMC1600SA Conc Walls 1 100 30DEC06A 30DEC06A
Conc Walls
MBMC1800SA Form Ceiling Slab 18 100 31DEC06A 23JAN07A
Form Ceiling Slab
MBMC1300SC Conc Columns 1 100 09JAN07A 09JAN07A
Conc Columns
MBMC1100SB Fix Reinf Columns 5 100 18JAN07A 23JAN07A
Fix Reinf Columns
MBMC1400SB Fix Reinf Walls 7 100 18JAN07A 25JAN07A
Fix Reinf Walls
MBMC1600SC Conc Walls 1 100 18JAN07A 18JAN07A
Conc Walls
MBMC1800SC Form Ceiling Slab 18 100 20JAN07A 08FEB07A
Form Ceiling Slab
MBMC1200SB Form Columns 7 100 21JAN07A 28JAN07A
Form Columns
MBMC1900SA Fix Reinf Ceiling Slab 9 100 21JAN07A 30JAN07A
Fix Reinf Ceiling Slab
MBMC1500SB Form Walls 16 100 22JAN07A 08FEB07A
Form Walls
MBMC1300SB Conc Columns 1 100 29JAN07A 29JAN07A
Conc Columns
MBMC2000SA Conc Ceiling Slab 1 100 31JAN07A 31JAN07A
Conc Ceiling Slab
MBMC1800SB Form Ceiling Slab 20 100 03FEB07A 25FEB07A
Form Ceiling Slab
MBMC1900SC Fix Reinf Ceiling Slab 9 100 06FEB07A 15FEB07A
Fix Reinf Ceiling Slab
MBMC1600SB Conc Walls 1 100 10FEB07A 10FEB07A
Conc Walls
MBMC2000SC Conc Ceiling Slab 1 100 17FEB07A 17FEB07A
Conc Ceiling Slab
MBMC1900SB Fix Reinf Ceiling Slab 9 100 22FEB07A 04MAR07A
Fix Reinf Ceiling Slab

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 5 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBMC2000SB Conc Ceiling Slab 1 100 05MAR07A 05MAR07A
Conc Ceiling Slab

Third Floor Tower


MBMC1100TA Fix Reinf Columns 5 100 01FEB07A 06FEB07A
Fix Reinf Columns
MBMC1400TA Fix Reinf Walls 7 100 01FEB07A 08FEB07A
Fix Reinf Walls
MBMC1200TA Form Columns 8 100 04FEB07A 12FEB07A
Form Columns
MBMC1500TA Form Walls 12 100 05FEB07A 18FEB07A
Form Walls
MBMC1300TA Conc Columns 1 100 13FEB07A 13FEB07A
Conc Columns
MBMC1100TC Fix Reinf Columns 5 100 18FEB07A 22FEB07A
Fix Reinf Columns
MBMC1400TC Fix Reinf Walls 7 100 18FEB07A 25FEB07A
Fix Reinf Walls
MBMC1600TA Conc Walls 1 100 19FEB07A 19FEB07A
Conc Walls
MBMC1200TC Form Columns 7 100 20FEB07A 27FEB07A
Form Columns
MBMC1800TA Form Ceiling Slab 18 100 20FEB07A 12MAR07A
Form Ceiling Slab
MBMC1500TC Form Walls 12 100 21FEB07A 06MAR07A
Form Walls
MBMC1300TC Conc Columns 1 100 28FEB07A 28FEB07A
Conc Columns
MBMC1800TC Form Ceiling Slab 18 100 01MAR07A 21MAR07A
Form Ceiling Slab
MBMC1100TB Fix Reinf Columns 5 100 06MAR07A 11MAR07A
Fix Reinf Columns
MBMC1400TB Fix Reinf Walls 7 100 06MAR07A 13MAR07A
Fix Reinf Walls
MBMC1600TC Conc Walls 1 100 07MAR07A 07MAR07A
Conc Walls
MBMC1200TB Form Columns 7 100 08MAR07A 15MAR07A
Form Columns
MBMC1500TB Form Walls 12 100 10MAR07A 22MAR07A
Form Walls
MBMC1900TA Fix Reinf Ceiling Slab 9 100 10MAR07A 19MAR07A
Fix Reinf Ceiling Slab
MBMC1800TB Form Ceiling Slab 18 100 15MAR07A 04APR07A
Form Ceiling Slab
MBMC1300TB Conc Columns 1 100 17MAR07A 17MAR07A
Conc Columns
MBMC1900TC Fix Reinf Ceiling Slab 9 100 19MAR07A 28MAR07A
Fix Reinf Ceiling Slab
MBMC2000TA Conc ceiling Slab 1 100 20MAR07A 20MAR07A
Conc ceiling Slab

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 6 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBMC1600TB Conc Walls 1 100 24MAR07A 24MAR07A
Conc Walls
MBMC2000TC Conc Ceiling Slab 1 100 29MAR07A 29MAR07A
Conc Ceiling Slab
MBMC1900TB Fix Reinf Ceiling Slab 9 100 02APR07A 11APR07A
Fix Reinf Ceiling Slab
MBMC2000TB Conc Ceiling Slab 1 100 12APR07A 12APR07A
Conc Ceiling Slab

Fourth Floor Tower


MBMC11004C Fix Reinf Columns 5 100 31MAR07A 04APR07A
Fix Reinf Columns
MBMC14004C Fix Reinf Walls 7 100 31MAR07A 07APR07A
Fix Reinf Walls
MBMC12004C Form Columns 8 100 02APR07A 10APR07A
Form Columns
MBMC15004C Form Walls 14 100 03APR07A 18APR07A
Form Walls
MBMC11004A Fix Reinf Columns 5 100 04APR07A 09APR07A
Fix Reinf Columns
MBMC14004A Fix Reinf Walls 7 100 04APR07A 11APR07A
Fix Reinf Walls
MBMC12004A Form Columns 8 100 07APR07A 15APR07A
Form Columns
MBMC15004A Form Walls 14 100 08APR07A 23APR07A
Form Walls
MBMC13004C Conc Columns 1 100 11APR07A 11APR07A
Conc Columns
MBMC18004C Form Ceiling Slab 18 100 12APR07A 02MAY07A
Form Ceiling Slab
MBMC11004B Fix Reinf Columns 5 100 14APR07A 18APR07A
Fix Reinf Columns
MBMC14004B Fix Reinf Walls 7 100 14APR07A 21APR07A
Fix Reinf Walls
MBMC12004B Form Columns 7 100 16APR07A 23APR07A
Form Columns
MBMC13004A Conc Columns 1 100 16APR07A 16APR07A
Conc Columns
MBMC15004B Form Walls 16 100 17APR07A 05MAY07A
Form Walls
MBMC18004A Form Ceiling Slab 18 100 17APR07A 07MAY07A
Form Ceiling Slab
MBMC16004C Conc Walls 1 100 19APR07A 19APR07A
Conc Walls
MBMC13004B Conc Columns 1 100 24APR07A 24APR07A
Conc Columns
MBMC16004A Conc Walls 1 100 24APR07A 24APR07A
Conc Walls
MBMC18004B Form Ceiling Slab 18 100 30APR07A 20MAY07A
Form Ceiling Slab

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 7 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBMC19004C Reinf Ceiling Slab 9 100 30APR07A 09MAY07A
Reinf Ceiling Slab
MBMC19004A Fix Reinf Ceiling Slab 9 100 05MAY07A 14MAY07A
Fix Reinf Ceiling Slab
MBMC16004B Conc Walls 1 100 06MAY07A 06MAY07A
Conc Walls
MBMC20004C Conc Ceiling Slab 1 100 10MAY07A 10MAY07A
Conc Ceiling Slab
MBMC20004A Conc Ceiling Slab 1 100 15MAY07A 15MAY07A
Conc Ceiling Slab
MBMC19004B Fix Reinf Ceiling Slab 9 100 17MAY07A 27MAY07A
Fix Reinf Ceiling Slab
MBMC20004B Conc Ceiling Slab 1 100 28MAY07A 28MAY07A
Conc Ceiling Slab
MBMC30804 Form Deck Equipment Rooms 6 100 17JUN07A 23JUN07A
Form Deck Equipment Rooms
MBMC30904 Fix Reinf Deck Equip Rooms 2 100 24JUN07A 25JUN07A
Fix Reinf Deck Equip Rooms
MBMC31004 Conc Deck Equip Room 1 100 26JUN07A 26JUN07A
Conc Deck Equip Room
MBMC32004 Fix Reinf Columns Parapet 8 100 27JUN07A 05JUL07A
Fix Reinf Columns Parapet
MBMC32104 Form Columns Parapet 14 100 07JUL07A 22JUL07A
Form Columns Parapet
MBMC32154 Conc Columns Parapet 1 100 23JUL07A 23JUL07A
Conc Columns Parapet
MBMC30004 Fix Reinf Walls Equip Room 5 100 09OCT07A 14OCT07A
Fix Reinf Walls Equip Room
MBMC30104 Form RC Walls Equipment Room 10 100 16OCT07A 25OCT07A
Form RC Walls Equipment Room
MBMC30604 Conc. RC Walls Equipment Rooms 1 100 27OCT07A 27OCT07A
Conc. RC Walls Equipment Rooms

Pent House
MBMC1100RF Fix Reinf Columns 4 100 29MAY07A 02JUN07A
Fix Reinf Columns
MBMC1400RF Fix Reinf Walls 8 100 29MAY07A 06JUN07A
Fix Reinf Walls
MBMC1600RF Conc Walls 1 100 18JUN07A 18JUN07A
Conc Walls
MBMC1800RF Form Ceiling Slab 16 100 19JUN07A 07JUL07A
Form Ceiling Slab
MBMC1900RF Fix Reinf Ceiling Slab 8 100 01JUL07A 09JUL07A
Fix Reinf Ceiling Slab
MBMC1200RF Form Columns 6 100 11JUL07A 17JUL07A
Form Columns
MBMC2000RF Conc Ceiling Slab 1 100 14JUL07A 14JUL07A
Conc Ceiling Slab
MBPMC30004 Fix Reinf walls Equip Room 5 100 15JUL07A 19JUL07A
Fix Reinf walls Equip Room

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 8 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBMC1300RF Conc Columns 1 100 19JUL07A 19JUL07A
Conc Columns
MBPMC30104 Form RC Walls Equipment Room 10 100 21JUL07A 31JUL07A
Form RC Walls Equipment Room
MBPMC30604 Conc. RC Walls Equipment Rooms 1 100 01AUG07A 01AUG07A
Conc. RC Walls Equipment Rooms
MBMC1500RF Form Walls 14 100 02SEP07A 15SEP07A
Form Walls
MBPMC30804 Form Deck Equip Room 6 100 03FEB08A 31AUG08A
Form Deck Equip Room
MBPMC30904 Fix Reinf Deck Equip Rooms 2 100 10FEB08A 04SEP08A
Fix Reinf Deck Equip Rooms
MBPMC31004 Conc Deck Equip Room 1 100 16FEB08A 10SEP08A
Conc Deck Equip Room

Grnd. Floor "4A - 7A"Rear Bldg Works


MBC1000 PCC Found. 5 100 17OCT06A 22OCT06A
PCC Found.
MBC1020 Fix Reinf Found. 8 100 23OCT06A 31OCT06A
Fix Reinf Found.
MBC1040 Form Found. 6 100 29OCT06A 04NOV06A
Form Found.
MBC1060 Conc Found. 1 100 05NOV06A 05NOV06A
Conc Found.
MBC1080 Reinf Col. Neck 2 100 06NOV06A 07NOV06A
Reinf Col. Neck
MBC1100 Form Col Neck 10 100 08NOV06A 19NOV06A
Form Col Neck
MBC1120 Conc. Col Neck 1 100 20NOV06A 20NOV06A
Conc. Col Neck
MBC1160 Reinf Gr. Beam 12 100 03JUN07A 16JUN07A
Reinf Gr. Beam
MBC1180 Form Gr. Beam 16 100 05JUN07A 23JUN07A
Form Gr. Beam
MBC1220 Conc. Gr. Slab 6 100 24JUL07A 30JUL07A
Conc. Gr. Slab
MBC1260 Fix Reinf Columns GF 12 100 31JUL07A 13AUG07A
Fix Reinf Columns GF
MBC1320 Form Columns 18 100 04AUG07A 23AUG07A
Form Columns
MBC1340 Conc Col GF Sec 1 100 25AUG07A 25AUG07A
Conc Col GF Sec
MBC1380 Form Ceiling Slab 30 100 26AUG07A 29SEP07A
Form Ceiling Slab
MBC1420 Conc Ceiling Slab 1 100 08SEP07A 11SEP07A
Conc Ceiling Slab
MBC1400 Reinf Celing Slab GF 14 100 26SEP07A 11OCT07A
Reinf Celing Slab GF
MBC1140 PCC Gr. Beam 6 100 11NOV07A 15NOV07A
PCC Gr. Beam

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 9 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBC1200 Conc Gr. Beam 1 100 19NOV07A 20NOV07A
Conc Gr. Beam

First Floor "4A - 7A" Rear Bldg Works


MBC3680G Conc Columns 1 100 20SEP07A 18OCT07A
Conc Columns
MBC3720G Form Ceiling Slab 30 100 22SEP07A 10NOV07A
Form Ceiling Slab
MBC3600G Fix Reinf Columns 12 100 13OCT07A 16OCT07A
Fix Reinf Columns
MBC3660G Form Columns 18 100 30OCT07A 24NOV07A
Form Columns
MBC3740G Fix Reinf Ceiling Slab 14 100 30OCT07A 24NOV07A
Fix Reinf Ceiling Slab
MBC3760G Conc Ceiling Slab 1 100 25NOV07A 26NOV07A
Conc Ceiling Slab

Grnd Floor "5B - 6B" Rear Bldg Works


MBGD1100FG PCC Found. 5 100 13DEC06A 18DEC06A
PCC Found.
MBGD1200FG Fix Reinf Found. 8 100 19DEC06A 27DEC06A
Fix Reinf Found.
MBGD1300FG Form Found. 6 100 25DEC06A 31DEC06A
Form Found.
MBGD1400FG Conc Found. 1 100 04JAN07A 04JAN07A
Conc Found.
MBGD1500FG Reinf Col. Neck 2 100 06JAN07A 07JAN07A
Reinf Col. Neck
MBGD1600FG Form Col Neck 10 100 08JAN07A 18JAN07A
Form Col Neck
MBGD1700FG Conc. Col Neck 1 100 20JAN07A 20JAN07A
Conc. Col Neck
MBGD2000FG PCC Gr. Beam 6 100 30JUL07A 05AUG07A
PCC Gr. Beam
MBGD2100FG Reinf Gr. Beam 12 100 06AUG07A 19AUG07A
Reinf Gr. Beam
MBGD2200FG Form Gr. Beam 16 100 08AUG07A 26AUG07A
Form Gr. Beam
MBGD2300FG Conc Gr. Beam 1 100 27AUG07A 27AUG07A
Conc Gr. Beam
MBGD2800FG Conc. Gr. Slab 6 100 26SEP07A 27NOV07A
Conc. Gr. Slab
MBGD2900FG Fix Reinf Columns GF 12 100 11NOV07A 24DEC07A
Fix Reinf Columns GF
MBGD3000FG Form Columns 18 100 11NOV07A 27DEC07A
Form Columns
MBGD3100FG Conc Col GF 1 100 17NOV07A 24DEC07A
Conc Col GF
MBGD3200FG Form Ceiling Slab GF 30 100 17NOV07A 12JAN08A
Form Ceiling Slab GF

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 10 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBGD3300FG Reinf Ceiling Slab GF 14 100 23JAN08A 28JAN08A
Reinf Ceiling Slab GF
MBGD3400FG Conc Ceiling Slab 1 100 23JAN08A 28JAN08A
Conc Ceiling Slab

First Floor "5B - 6B" Rear Bldg Works


MBMC1100FG Reinf Column 12 100 30JAN08A 29MAR08A
Reinf Column
MBMC1200FG Form Columns 18 100 06MAR08A 30MAR08A
Form Columns
MBMC1300FG Conc Columns 1 100 15MAR08A 10APR08A
Conc Columns
MBMC1800FG Form Ceiling Slab 30 100 17MAR08A 24MAY08A
Form Ceiling Slab
MBMC1900FG Fix Reinf Ceiling Slab 8 100 20APR08A 27MAY08A
Fix Reinf Ceiling Slab
MBMC2000FG Conc Ceiling Slab 1 100 31MAY08A 02JUN08A
Conc Ceiling Slab

Grnd Floor "4B - 5A" Rear Bldg Works


MBC1000E PCC Found. 5 100 13DEC06A 18DEC06A
PCC Found.
MBC1020E Fix Reinf Found. 8 100 19DEC06A 27DEC06A
Fix Reinf Found.
MBC1040E Form Found. 6 100 25DEC06A 31DEC06A
Form Found.
MBC1060E Conc Found. 1 100 04JAN07A 04JAN07A
Conc Found.
MBC1080E Reinf Col. Neck 2 100 06JAN07A 07JAN07A
Reinf Col. Neck
MBC1100E Form Col Neck 10 100 08JAN07A 18JAN07A
Form Col Neck
MBC1120E Conc. Col Neck 1 100 20JAN07A 20JAN07A
Conc. Col Neck
MBC1140E PCC Gr. Beam 6 100 11NOV07A 25JUN08A
PCC Gr. Beam
MBC1180E Form Gr. Beam 16 100 14NOV07A 29JUN08A
Form Gr. Beam
MBC1160E Reinf Gr. Beam 12 100 15NOV07A 02JUL08A
Reinf Gr. Beam
MBC1200E Conc Gr. Beam 1 100 19NOV07A 02JUL08A
Conc Gr. Beam
MBC1220E Conc. Gr. Slab 6 100 16JAN08A 16JUL08A
Conc. Gr. Slab
MBC1260E Fix Reinf Columns 12 100 17JAN08A 20JUL08A
Fix Reinf Columns
MBC1320E Form Columns 18 100 19JAN08A 21AUG08A
Form Columns
MBC1340E Conc Col GF 1 100 20JAN08A 31JUL08A
Conc Col GF

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 11 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBC1380E Form Ceiling Slab GF 30 100 20JAN08A 21AUG08A
Form Ceiling Slab GF
MBC1400E Reinf Ceiling Slab GF 14 100 19MAR08A 28AUG08A
Reinf Ceiling Slab GF
MBC1420E Conc Ceiling Slab 1 100 26MAR08A 30AUG08A
Conc Ceiling Slab

First Floor "4B - 5A" Rear Bldg Works


MBC3600E Fix Reinf Columns 12 100 17APR08A 02SEP08A
Fix Reinf Columns
MBC3660E Form Columns 18 100 19APR08A 04SEP08A
Form Columns
MBC3680E Conc Columns 1 100 26APR08A 05OCT08A
Conc Columns
MBC3720E Form Ceiling Slab 30 100 03JUN08A 18SEP08A
Form Ceiling Slab
MBC3740E Fix Reinf Ceiling Slab 14 100 30JUN08A 25SEP08A
Fix Reinf Ceiling Slab
MBC3760E Conc Ceiling Slab 1 100 26JUL08A 05OCT08A
Conc Ceiling Slab

Grnd Floor "6A - 7B" Rear Bldg Works


MBCGD1100 PCC Found. 5 100 23NOV06A 28NOV06A
PCC Found.
MBCGD1200 Fix Reinf Found. 8 100 29NOV06A 07DEC06A
Fix Reinf Found.
MBCGD1300 Form Found. 6 100 05DEC06A 11DEC06A
Form Found.
MBCGD1400 Conc Found. 1 100 12DEC06A 12DEC06A
Conc Found.
MBCGD1500 Reinf Col. Neck 2 100 13DEC06A 14DEC06A
Reinf Col. Neck
MBCGD1600 Form Col Neck 10 100 16DEC06A 26DEC06A
Form Col Neck
MBCGD1700 Conc. Col Neck 1 100 27DEC06A 27DEC06A
Conc. Col Neck
MBCGD2000 PCC Gr. Beam 6 100 29NOV07A 09SEP08A
PCC Gr. Beam
MBCGD2200 Form Gr. Beam 16 100 01DEC07A 10SEP08A
Form Gr. Beam
MBCGD2100 Reinf Gr. Beam 12 100 02DEC07A 13SEP08A
Reinf Gr. Beam
MBCGD2300 Conc Gr. Beam 1 100 08DEC07A 17SEP08A
Conc Gr. Beam
MBCGD2900 Fix Reinf Columns 12 100 22JAN08A 12OCT08A
Fix Reinf Columns
MBCGD2800 Conc. Gr. Slab 6 100 30JAN08A 11OCT08A
Conc. Gr. Slab
MBCGD3000 Form Column GF 18 100 31JAN08A 19OCT08A
Form Column GF

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 12 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBCGD2920 Form Walls 14 100 02FEB08A 11FEB08A
Form Walls
MBCGD3100 Conc Col GF 1 100 04FEB08A 19OCT08A
Conc Col GF
MBCGD2910 Fix Reinf. Walls 10 100 05FEB08A 07FEB08A
Fix Reinf. Walls
MBCGD3200 Form Ceiling Slab 30 100 07FEB08A 29OCT08A
Form Ceiling Slab
MBCGD3300 Reinf Ceiling Slab GF 14 100 10MAR08A 20NOV08A
Reinf Ceiling Slab GF
MBCGD3400 Conc Ceiling Slab GF 1 100 30MAR08A 01DEC08A
Conc Ceiling Slab GF

First Floor "6A - 7B" Rear Bldg Works


MBMC1100DE Fix Reinf Columns 16 100 14APR08A 04DEC08A
Fix Reinf Columns
MBMC1120DE Form Walls 16 100 15APR08A 04MAY08A
Form Walls
MBMC2120DE Form Wall Equip. Room 16 100 15APR08A 10MAY08A
Form Wall Equip. Room
MBMC1200DE Form Columns 18 100 17APR08A 23DEC08A
Form Columns
MBMC1110DE Fix Reinf Core Walls 10 100 20APR08A 29APR08A
Fix Reinf Core Walls
MBMC2100DE Reinf Wall Equipment Room 10 100 20APR08A 29APR08A
Reinf Wall Equipment Room
MBMC1300DE Conc Columns 1 100 26APR08A 24DEC08A
Conc Columns
MBMC1800DE Form Ceiling Slab 30 100 17MAY08A 18JAN09A
Form Ceiling Slab
MBMC2130DE Conc. Walls Equip Room 1 100 31MAY08A 31MAY08A
Conc. Walls Equip Room
MBMC1900DE Fix Reinf Ceiling Slab 14 100 30JUN08A 22JAN09A
Fix Reinf Ceiling Slab
MBMC2000DE Conc Ceiling Slab 1 100 30JUL08A 03FEB09A
Conc Ceiling Slab
MBMC2140DE Form Deck Equip Room 8 100 09JUL09A 17AUG09A
Form Deck Equip Room
MBMC2160DE Reinf. Deck Equip Room 6 100 18JUL09A 24AUG09A
Reinf. Deck Equip Room
MBMC2180DE Conc Deck Equip room 1 100 25AUG09A 25AUG09A
Conc Deck Equip room

Water Proofing & Insulation


Basement Floor
MBMCBM1400 Water Proof Walls Basement 9 100 04DEC05A 13DEC05A
Water Proof Walls Basement

Grnd. Floor "4A - 7A"Rear Bldg Works


MBW0800G Water/Prf Coat Col. Neck 2 100 21NOV06A 22NOV06A
Water/Prf Coat Col. Neck
Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT
Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 13 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBW0810G Water Proof Coat Gr Beam 5 100 25JUN07A 30JUN07A
Water Proof Coat Gr Beam

Grnd Floor "5B - 6B" Rear Bldg Works


MBGD1800FG Water Proof U/Grnd 2 100 23JAN07A 24JAN07A
Water Proof U/Grnd
MBGD2400FG Water Proof Gr. Beam 5 100 28AUG07A 14NOV07A
Water Proof Gr. Beam

Grnd Floor "4B - 5A" Rear Bldg Works


MBW0820E Water Proof Coat U/Grnd 2 100 21JAN07A 22JAN07A
Water Proof Coat U/Grnd
MBW0830E Water Proof Coat Gr Beam 5 100 23NOV07A 06JUL08A
Water Proof Coat Gr Beam

Grnd Floor "6A - 7B" Rear Bldg Works


MBCGD1800 Water Proof U/Gr. 2 100 28DEC06A 30DEC06A
Water Proof U/Gr.
MBCGD2400 Water Proof Gr. Beam 5 100 09DEC07A 20SEP08A
Water Proof Gr. Beam

Electrical works
Basement Floor
MBEBM1000 Fix Cond Raft Basement 4 100 05JUL05A 09JUL05A
Fix Cond Raft Basement

ARCHITECTURAL WORKS
Arch. Materials Submittal

MBWF1250A Get Appvl. Marble Flooring 6 100 01MAR09A 01MAR10A


Get Appvl. Marble Flooring
MBDWB1150 Get Appvl. of Doors 6 100 01JAN10A 01FEB10A
Get Appvl. of Doors
MBDWB1000 Get Appvl. Window 6 100 01FEB10A 01MAR10A
Get Appvl. Window
MBDWB1300 Get Appvl. Door Hardwares 6 100 01FEB10A 01MAR10A
Get Appvl. Door Hardwares
MBFWB920 Get Appvl. Paints 6 100 01FEB10A 01MAR10A
Get Appvl. Paints
MBWF1100A Get Appvl. Porciline Tile 6 100 01FEB10A 01MAR10A
Get Appvl. Porciline Tile
MBWF1400A Get Appvl. tread / Riser 6 100 01FEB10A 01MAR10A
Get Appvl. tread / Riser
MBWF2000A Get Appvl. Epoxy Paint 6 100 01FEB10A 01MAR10A
Get Appvl. Epoxy Paint
MBWF2450A Get Appvl. Anti-Bect.Paint 6 100 01FEB10A 01MAR10A
Get Appvl. Anti-Bect.Paint
MBWF3050A Get App. Toilet Accessories 12 100 01FEB10A 01MAR10A
Get App. Toilet Accessories
MBWF500A Get Appvl. G.Board Ceiling 6 100 01FEB10A 01MAR10A
Get Appvl. G.Board Ceiling

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 14 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBWF650A Get Appvl. Alum.Ceiling. 9 100 01FEB10A 01MAR10A
Get Appvl. Alum.Ceiling.
MBWF800A Get Appvl. Plstr. Board Clng. 6 100 01FEB10A 01MAR10A
Get Appvl. Plstr. Board Clng.
MBWF1850A Get Appvl. Vinyl 6 100 08JUN10A 14JUN10A
Get Appvl. Vinyl
MBWF2150A Get Appvl. Rubber tile 8 100 08JUN10A 17JUN10A
Get Appvl. Rubber tile
MBWF2300A Get Appvl. Carpet 6 100 08JUN10A 14JUN10A
Get Appvl. Carpet

Procure Arch Materials

MBDWB1050 Procurement of Windows 36 100 01FEB10A 17FEB10A


Procurement of Windows
MBDWB1200 Procu.of Doors 36 100 01FEB10A 17FEB10A
Procu.of Doors
MBDWB1350 Procu. of Door Hardwares 78 100 01FEB10A 17FEB10A
Procu. of Door Hardwares
MBFWB940 Procur. of Paints 18 100 01FEB10A 15FEB10A
Procur. of Paints
MBWF1150A Procur. of Porciline Tile 18 100 01MAR10A 10MAR10A
Procur. of Porciline Tile
MBWF1300A Procur. Granite Flooring 26 100 01MAR10A 13MAR10A
Procur. Granite Flooring
MBWF1450A Procur. of Tread/Riser 32 100 01MAR10A 17MAR10A
Procur. of Tread/Riser
MBWF2050A Procur. of Epoxy Paint 18 100 01MAR10A 17MAR10A
Procur. of Epoxy Paint
MBWF2500A Procur. of Anti-Becterial Paint 18 100 01MAR10A 17MAR10A
Procur. of Anti-Becterial Paint
MBWF550A Procur. of Gyp. Board Clng 26 100 01MAR10A 17MAR10A
Procur. of Gyp. Board Clng
MBWF850A Procur.of Plstr. board Clng. 18 100 01MAR10A 17MAR10A
Procur.of Plstr. board Clng.
MBWF2650A Procur.of Texture Paint 18 100 08JUN10A 28JUN10A
Procur.of Texture Paint
MBWF3100A Procure Toilet Accessories 45 100 08JUN10A 14AUG10A
Procure Toilet Accessories
MBWF700A Procur. of Alum. Strip Clng. 28 100 08JUN10A 09JUN10A
Procur. of Alum. Strip Clng.
MBWF1900A Procure Vinyl Flooring 21 0 23NOV10 16DEC10
Procure Vinyl Flooring
MBWF2350A Procure Carpet 18 0 23NOV10 13DEC10
Procure Carpet

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 15 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Masonry Works
Tower Ground Floor-Finishes
MBBWG100 Block Work Ground Floor 20 100 08APR07A 30JAN08A
Block Work Ground Floor

Tower First Floor-Finishes


MBBWF100 Block Work T. Bldg First Floor 20 100 01MAY07A 17JUN07A
Block Work T. Bldg First Floor

Tower Second Floor-Finishes


MBBWB100S Block Work Second Floor 20 100 29MAY07A 23JAN08A
Block Work Second Floor

Tower Third Floor- Finishes


MBBWB100T Block Work Third Floor 20 100 15JUL07A 28AUG07A
Block Work Third Floor

Tower Fourth Floor-Finishes


MBBWB100R Block Work 4th Floor 20 100 07AUG07A 08MAR10A
Block Work 4th Floor
MBB60004 Block Masonry Paparpet 38 100 24NOV07A 31OCT08A
Block Masonry Paparpet

Tower Pent House Finishing Works


MBBWB100P Block Work Pent House 9 100 27DEC07A 07FEB08A
Block Work Pent House

Finish Grnd Floor (4A,7A - 5B,6B) Rear Building


MBMB1100GD Block Work G. Floor Rear Blgd 45 100 28NOV07A 05MAR09A
Block Work G. Floor Rear Blgd

Finish First Floor (4A,7A - 5B,6B) Rear Building


MBBGF100F Block Work First Flr (G-F) 45 100 21JAN08A 17MAR09A
Block Work First Flr (G-F)

Finish Grnd Floor (4B,5A - 6A,7B) Rear Building


MBGBGF100F Block Work Grnd Flr (3-4) 17 100 07JAN09A 26JUN09A
Block Work Grnd Flr (3-4)

Finish First Floor (4B,5A - 6A,7B) Rear Building


MBBED100F Block Work First Flr (E-D) 16 100 28MAY09A 09MAR10A
Block Work First Flr (E-D)

Water Proofing & Insulation


Basement Floor
MBWW300 W. Proof Wet Area Basement 15 19 16OCT10A 06DEC10
W. Proof Wet Area Basement

Tower Ground Floor-Finishes


MBWW300G W. Proof Wet Area 15 0 23NOV10 09DEC10
W. Proof Wet Area

Tower First Floor-Finishes


MBWW300F W. Proof Wet Area Bsmnt 20 100 10DEC09A 11MAR10A
W. Proof Wet Area Bsmnt

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 16 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
Tower Second Floor-Finishes
MBWW300S W. Proof Wet Area 12 100 12DEC09A 04MAR10A
W. Proof Wet Area

Tower Third Floor- Finishes


MBWW300T W. Proof Wet Area 12 100 18NOV09A 02MAR10A
W. Proof Wet Area

Tower Fourth Floor-Finishes


MBWW300R W. Proof Wet Area 12 100 11DEC09A 28FEB10A
W. Proof Wet Area

Tower Pent House Finishing Works


MBWW300P W. Proof Wet Area 3 100 04MAR10A 07MAR10A
W. Proof Wet Area

TOWER BUILDING
MBWW100 Lt. Weight Screed Roof 22 100 09JUN09A 16SEP09A
Lt. Weight Screed Roof
MBWW130 Roof Water Proofing works 20 100 05OCT09A 27OCT09A
Roof Water Proofing works
MBWW160 Lay Roof Insulation 12 100 01NOV09A 05NOV09A
Lay Roof Insulation
MBWW190 Roof Metal Flashing / Exp Joints 15 0 23NOV10 09DEC10
Roof Metal Flashing / Exp Joints

Finish Grnd Floor (4A,7A - 5B,6B) Rear Building


MBW1400 Water Proof Wet Area 18 0 23NOV10 13DEC10
Water Proof Wet Area

Finish First Floor (4A,7A - 5B,6B) Rear Building


MBFGF100F Water Proof Wet Area 15 100 24MAR10A 27MAY10A
Water Proof Wet Area

Finish Grnd Floor (4B,5A - 6A,7B) Rear Building


MBGFGF100F Water Proof Wet Area 14 0 23NOV10 08DEC10
Water Proof Wet Area

Finish First Floor (4B,5A - 6A,7B) Rear Building


MBFFGF100F Water Proof Wet Area 15 100 27MAR10A 31MAY10A
Water Proof Wet Area

REAR BUILDING
MBMW1100 Lt. Weight Foam concrete 18 50 23OCT10A 02DEC10
Lt. Weight Foam concrete
MBMW1200 Lay Water Proofing Membrane 18 0 04DEC10 23DEC10
Lay Water Proofing Membrane
MBMW1250 Lay Roof Insulation 12 0 25DEC10 06JAN11
Lay Roof Insulation
MBMW1300 Roof Metal Flashing / Exp Joints 9 0 08JAN11 17JAN11
Roof Metal Flashing / Exp Joints

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 17 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Doors & Windows


Tower Basement Floor- Finishes
MBDWB120 Install Door Frames 19 62 05JUN10A 30NOV10
Install Door Frames
MBDWB140 Fix Door metal Panels 18 25 10JUN10A 06DEC10
Fix Door metal Panels
MBDB160 Fix Wooden door panels 14 0 23NOV10 08DEC10
Fix Wooden door panels
MBDWB160 Fix Interior Alum Windows frames 12 0 23NOV10 06DEC10
Fix Interior Alum Windows frames
MBDWB100 Fix Door Hard Ware 12 0 09DEC10 22DEC10
Fix Door Hard Ware

Tower Ground Floor-Finishes


MBDWB120G Install Door Frames 19 57 15MAY10A 01DEC10
Install Door Frames
MBDWB140G Fix Door metal Panels 18 40 01JUN10A 05DEC10
Fix Door metal Panels
MBDG160 Fix Wooden door panels 14 0 23NOV10 08DEC10
Fix Wooden door panels
MBDWB160G Fix Interior Alum Windows frames 10 0 23NOV10 04DEC10
Fix Interior Alum Windows frames
MBDWB100G Fix Door Hard Ware 16 0 09DEC10 27DEC10
Fix Door Hard Ware

Tower First Floor-Finishes


MBDWB120F Install Door Frames 19 88 09DEC09A 24NOV10
Install Door Frames
MBDWB140F Fix Door metal Panels 18 55 02JAN10A 02DEC10
Fix Door metal Panels
MBD1F160 Fix Wooden door panels 14 0 04DEC10 19DEC10
Fix Wooden door panels
MBDWB160F Fix Interior Alum Windows frames 10 0 05DEC10 15DEC10
Fix Interior Alum Windows frames
MBDWB100F Fix Door Hard Ware 16 0 20DEC10 06JAN11
Fix Door Hard Ware

Tower Second Floor-Finishes


MBDWB120S Install Door Frames 18 100 19NOV09A 09MAR10A
Install Door Frames
MBDWB140S Fix Door metal Panels 19 81 28DEC09A 27NOV10
Fix Door metal Panels
MBDWB160S Fix Interior Alum Windows frames 10 75 29MAR10A 23NOV10
Fix Interior Alum Windows frames
MBD2F160 Fix Wooden door panels 14 0 28NOV10 13DEC10
Fix Wooden door panels
MBDWB100S Fix Door Hard Ware 16 0 14DEC10 01JAN11
Fix Door Hard Ware

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 18 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
Tower Third Floor- Finishes
MBDWB120T Install Door Frames 28 100 28OCT09A 10MAR10A
Install Door Frames
MBDWB140T Fix Door matel Panels 19 85 01NOV09A 25NOV10
Fix Door matel Panels
MBDWB160T Fix Interior Alum Windows frames 9 75 01APR10A 23NOV10
Fix Interior Alum Windows frames
MBD3F160 Fix Wooden door panels 14 0 27NOV10 12DEC10
Fix Wooden door panels
MBDWB100T Fix Door Hard Ware 16 0 13DEC10 30DEC10
Fix Door Hard Ware

Tower Fourth Floor-Finishes


MBDWB120R Install Door Frames 28 100 01SEP09A 10MAR10A
Install Door Frames
MBDWB140R Fix Door metal Panels 19 85 22OCT09A 25NOV10
Fix Door metal Panels
MBDWB160R Fix Int. Alum Window frame 9 75 04APR10A 23NOV10
Fix Int. Alum Window frame
MBD4F160 Fix Wooden door panels 10 0 27NOV10 07DEC10
Fix Wooden door panels
MBDWB100R Fix Door Hard Ware 16 0 08DEC10 26DEC10
Fix Door Hard Ware

Tower Pent House Finishing Works


MBDWB120P Install Door Frames 6 60 01JUN10A 24NOV10
Install Door Frames
MBDWB160P Fix Interior Alum Windows frames 9 0 24NOV10 04DEC10
Fix Interior Alum Windows frames
MBDWB140P Fix Door metal Panels 9 0 25NOV10 05DEC10
Fix Door metal Panels
MBDP160 Fix Wooden door panels 10 0 06DEC10 16DEC10
Fix Wooden door panels
MBDWB100P Fix Door Hard Ware 7 0 18DEC10 25DEC10
Fix Door Hard Ware

TOWER BUILDING
MBWD140 Fix External Curtain Walls 45 89 01JUN10A 28NOV10
Fix External Curtain Walls

Finish Grnd Floor (4A,7A - 5B,6B) Rear Building


MBMD1200GD Install Door Frames 19 65 06DEC09A 30NOV10
Install Door Frames
MBMD1500GD Fix Door metal Panels 18 25 14DEC09A 08DEC10
Fix Door metal Panels
MBDRG160 Fix Wooden door panels 14 0 09DEC10 25DEC10
Fix Wooden door panels
MBD2020 Fix Interior Alum Windows frames 12 0 10JAN11 23JAN11
Fix Interior Alum Windows frames
MBMD1600GD Fix Door Hard Ware 18 0 24JAN11 13FEB11
Fix Door Hard Ware

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 19 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
Finish First Floor (4A,7A - 5B,6B) Rear Building
MBDGF104F Fix Door metal Panels 19 20 13DEC09A 29DEC10
Fix Door metal Panels
MBDGF100F Install Door Frames 18 62 19FEB10A 30NOV10
Install Door Frames
MBRD1F160 Fix Wooden door panels 14 0 30DEC10 15JAN11
Fix Wooden door panels
MBDGF102F Fix Interior Alum Windows frames 12 0 10JAN11 23JAN11
Fix Interior Alum Windows frames
MBDGF108F Fix Door Hard Ware 18 0 16JAN11 05FEB11
Fix Door Hard Ware

Finish Grnd Floor (4B,5A - 6A,7B) Rear Building


MBGDGF100F Install Door Frames 19 62 14DEC09A 30NOV10
Install Door Frames
MBGDGF104F Fix Door metal Panels 18 20 10JAN10A 29DEC10
Fix Door metal Panels
MBGDGF102F Fix Interior Alum Windows frames 12 0 27DEC10 09JAN11
Fix Interior Alum Windows frames
MBRDG160 Fix Wooden door panels 14 0 30DEC10 15JAN11
Fix Wooden door panels
MBGDGF108F Fix Door Hard Ware 18 0 16JAN11 05FEB11
Fix Door Hard Ware

Finish First Floor (4B,5A - 6A,7B) Rear Building


MBFDGF100F Install Door Frames 19 62 07NOV09A 30NOV10
Install Door Frames
MBFDGF104F Fix Door metal Panels 16 20 01MAR10A 07DEC10
Fix Door metal Panels
MBFDGF102F Fix Interior Alum Windows frames 22 0 01DEC10 26DEC10
Fix Interior Alum Windows frames
MBRD1F1600 Fix Wooden door panels 20 0 30DEC10 22JAN11
Fix Wooden door panels
MBFDGF108F Fix Door Hard Ware 16 0 23JAN11 09FEB11
Fix Door Hard Ware

Pre-Finishing Works Walls


Tower Basement Floor- Finishes
MBFWB110 Fix Metal Studs 18 100 08JAN08A 14JUN08A
Fix Metal Studs
MBFWB120 Fix Dry Board & Insul. 26 100 12JAN08A 17NOV08A
Fix Dry Board & Insul.
MBFWB100 Plaster Works Walls 21 100 06SEP08A 08MAR10A
Plaster Works Walls
MBFWB140 Install Dry Board 2nd. layer 30 100 13DEC08A 09MAR10A
Install Dry Board 2nd. layer
MBFWB180 Putty & Primer Coat Ordinary 25 25 18SEP10A 02JAN11
Putty & Primer Coat Ordinary
MBPWB1234 Putty Primer Anti Bact. Paint 20 0 03JAN11 25JAN11
Putty Primer Anti Bact. Paint

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 20 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBFWB160 Fix Ceramic Wall Tiles 21 0 08JAN11 31JAN11
Fix Ceramic Wall Tiles

Tower Ground Floor-Finishes


MBFWB100G Plaster Works Walls 21 100 08APR07A 08MAR10A
Plaster Works Walls
MBFWB120G Install Dry Board / Insul 42 100 02MAY07A 15SEP09A
Install Dry Board / Insul
MBFWB110G Fix Metal Studs 18 100 01JUL07A 10OCT09A
Fix Metal Studs
MBFWB140G Install Dry Board 2nd Layer 20 100 29DEC07A 11MAR10A
Install Dry Board 2nd Layer
MBFWB180G Putty & Primer Coat Ordinary 38 40 28JAN10A 28DEC10
Putty & Primer Coat Ordinary
MBFWB160G Fix Ceramic Wall Tiles 24 0 11DEC10 06JAN11
Fix Ceramic Wall Tiles
MBFWB170G Putty Primer Anti Bact. Paint 28 0 29DEC10 30JAN11
Putty Primer Anti Bact. Paint

Tower First Floor-Finishes


MBFWB100F Plaster Works Walls 21 100 24MAY07A 01MAR10A
Plaster Works Walls
MBFWB110F Fix Metal Studs 18 100 07JUN07A 31JAN08A
Fix Metal Studs
MBFWB120F Fix Dry Boards & Insul. Dry wall 42 100 11JUL07A 02FEB08A
Fix Dry Boards & Insul. Dry wall
MBFWB140F Install Dry Board 2nd layer 21 100 02APR08A 08MAR10A
Install Dry Board 2nd layer
MBFWB180F Putty & Primer Coat Ordinary 45 100 01NOV09A 22MAR10A
Putty & Primer Coat Ordinary
MBFWB160F Fix Ceramic Wall Tiles 21 98 10MAY10A 24NOV10
Fix Ceramic Wall Tiles
MBFWB170F Putty Primer Anti Bact. Paint 28 0 23NOV10 25DEC10
Putty Primer Anti Bact. Paint

Tower Second Floor-Finishes


MBFWB100S Plaster Works Walls 21 100 29MAY07A 08FEB10A
Plaster Works Walls
MBFWB110S Fix Metal Studs 21 100 16AUG07A 07MAR10A
Fix Metal Studs
MBFWB120S Install Dry Panels & Insul. 48 100 25AUG07A 07MAR10A
Install Dry Panels & Insul.
MBFWB140S Install Dry Board 2nd layer 70 100 31MAY08A 24MAR10A
Install Dry Board 2nd layer
MBFWB180S Putty & Primer Coat Ordinary 48 100 28DEC09A 22MAR10A
Putty & Primer Coat Ordinary
MBFWB160S Fix Ceramic Wall Tiles 21 98 27MAR10A 22NOV10
Fix Ceramic Wall Tiles
MBFWB170S Putty Primer Anti Bact. Paint 28 0 23NOV10 25DEC10
Putty Primer Anti Bact. Paint

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 21 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
Tower Third Floor- Finishes
MBFWB100T Plaster Works Walls 21 100 07AUG07A 19FEB10A
Plaster Works Walls
MBFWB110T Fix Metal Studs 18 100 24OCT07A 08FEB10A
Fix Metal Studs
MBFWB120T Fix Dry Panels & Insulation 42 100 11NOV07A 24FEB10A
Fix Dry Panels & Insulation
MBFWB140T Install Dry Board 2nd layer 21 100 14APR08A 08MAR10A
Install Dry Board 2nd layer
MBFWB180T Putty & Primer Coat Ordinary 45 100 03OCT09A 22MAR10A
Putty & Primer Coat Ordinary
MBFWB160T Fix Ceramic Wall Tiles 21 98 24APR10A 24NOV10
Fix Ceramic Wall Tiles
MBFWB170T Putty Primer Anti Bact. Paint 28 0 23NOV10 25DEC10
Putty Primer Anti Bact. Paint

Tower Fourth Floor-Finishes


MBFWB100R Plaster Work Walls 21 100 30AUG07A 15SEP09A
Plaster Work Walls
MBFWB110R Fix Metal Studs 21 100 10DEC07A 01NOV09A
Fix Metal Studs
MBFWB120R Fix Dry Panels / Insul. 46 100 15DEC07A 04NOV09A
Fix Dry Panels / Insul.
MBFWB140R Install Dry Board 2nd layer 21 100 26OCT08A 08MAR10A
Install Dry Board 2nd layer
MBFWB180R Putty & Primer Coat Ordinary 48 100 19SEP09A 23MAR10A
Putty & Primer Coat Ordinary
MBFWB160R Fix Ceramic Wall Tiles 21 98 08APR10A 22NOV10
Fix Ceramic Wall Tiles
MBFWB170R Putty Primer Anti Bact. Paint 28 0 23NOV10 25DEC10
Putty Primer Anti Bact. Paint

Tower Pent House Finishing Works


MBFWB100P Plaster Work Walls 5 100 10JUN09A 15JUL09A
Plaster Work Walls
MBFWB110P Fix Metal Studs 7 100 10JUL09A 17OCT09A
Fix Metal Studs
MBFWB140P Install Dry Board 2nd 4 100 13JUL09A 07MAR10A
Install Dry Board 2nd
MBFWB120P Fix First Layer Dry Panel / Insul. 9 100 15AUG09A 24OCT09A
Fix First Layer Dry Panel / Insul.
MBFWB180P Putty & Primer Coat Ordinary 18 100 22MAR10A 23MAR10A
Putty & Primer Coat Ordinary
MBFWB160P Fix Ceramic Wall Tiles 10 98 27MAY10A 22NOV10
Fix Ceramic Wall Tiles
MBFWB170P Putty Primer Anti Bact. Paint 8 0 23NOV10 01DEC10
Putty Primer Anti Bact. Paint

TOWER BUILDING
MBWF310 Alum Wall Cladding Main Bldg 45 88 05SEP09A 28NOV10
Alum Wall Cladding Main Bldg

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 22 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
Finish Grnd Floor (4A,7A - 5B,6B) Rear Building
MBMF1585GD Fix Metal Studs 40 100 13NOV07A 11OCT09A
Fix Metal Studs
MBMF1600GD Fix Dry Boards & Insulation 26 100 30AUG08A 10MAR10A
Fix Dry Boards & Insulation
MBMF2000GD Plaster Works Walls 28 100 05MAR09A 05OCT09A
Plaster Works Walls
MBMF1650GD Install Dry Board 2nd layer 35 100 01FEB10A 08JUL10A
Install Dry Board 2nd layer
MBMF3000GD Putty & Primer Coat Ordinary 40 94 25FEB10A 24NOV10
Putty & Primer Coat Ordinary
MBMF2100GD Fix Ceramic Wall Tiles 21 60 26JUN10A 01DEC10
Fix Ceramic Wall Tiles
MBMF170GR Putty Primer Anti Bact. Paint 28 0 25NOV10 27DEC10
Putty Primer Anti Bact. Paint

Finish First Floor (4A,7A - 5B,6B) Rear Building


MBFGF090 Install Metal Studs 40 100 04FEB08A 09MAR10A
Install Metal Studs
MBFGF100 Fix Dry Board & Insulation 48 100 10FEB08A 10MAR10A
Fix Dry Board & Insulation
MBFGF140 Plaster Works Walls 28 100 11AUG09A 08MAR10A
Plaster Works Walls
MBFGF120 Install Dry Board 2nd layer 22 100 20OCT09A 11MAR10A
Install Dry Board 2nd layer
MBFGF180 Putty & Primer Coat Ordinary 40 93 13MAR10A 25NOV10
Putty & Primer Coat Ordinary
MBFGF160 Fix Ceramic Wall Tiles 28 80 27JUN10A 29NOV10
Fix Ceramic Wall Tiles
MBFGF170 Putty Primer Anti Bact. Paint 28 0 27NOV10 28DEC10
Putty Primer Anti Bact. Paint

Finish Grnd Floor (4B,5A - 6A,7B) Rear Building


MBGFGF090 Fix Metal Studs (3-4) 28 100 18AUG08A 03NOV09A
Fix Metal Studs (3-4)
MBGFGF100 Fix Dry Boards & Insul. 38 100 25AUG08A 08MAR10A
Fix Dry Boards & Insul.
MBGFGF140 Plaster Works Walls 21 100 10AUG09A 08MAR10A
Plaster Works Walls
MBGFGF180 Putty & Primer Coat Ordinary 38 95 09SEP09A 24NOV10
Putty & Primer Coat Ordinary
MBGFGF120 Install Dry Board 2nd layer 14 100 23SEP09A 10MAR10A
Install Dry Board 2nd layer
MBGFGF160 Fix Ceramic Wall Tiles 21 60 18MAY10A 01DEC10
Fix Ceramic Wall Tiles
MBGFF170 Putty Primer Anti Bact. Paint 28 0 25NOV10 27DEC10
Putty Primer Anti Bact. Paint

Finish First Floor (4B,5A - 6A,7B) Rear Building


MBFFGF090 Fix Metal Studs (3-4) FF 28 100 18DEC08A 12MAR09A
Fix Metal Studs (3-4) FF

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 23 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBFFGF140 Plaster Works Walls 18 100 10JUN09A 08MAR10A
Plaster Works Walls
MBFFGF100 Fix Dry Boards & Insul 38 100 14AUG09A 09MAR10A
Fix Dry Boards & Insul
MBFFGF180 Putty & Primer Coat Ordinary 45 93 12OCT09A 25NOV10
Putty & Primer Coat Ordinary
MBFFGF120 Install Dry Board 2nd layer 12 100 29OCT09A 11MAR10A
Install Dry Board 2nd layer
MBFFGF160 Fix Ceramic Wall Tiles 21 80 01JUN10A 27NOV10
Fix Ceramic Wall Tiles
MBFF170 Putty Primer Anti Bact. Paint 28 0 27NOV10 28DEC10
Putty Primer Anti Bact. Paint

REAR BUILDING
MBMF7020GD Fix External Curtain Walls 38 0 29NOV10 11JAN11
Fix External Curtain Walls

Pre-Finishing Works Ceilings


Tower Basement Floor- Finishes
MBWF130 Grnd Inspctn-01 Abv Clng Sys 3 0 03FEB11 06FEB11
Grnd Inspctn-01 Abv Clng Sys
MBWF180 Install Ceiling Grid systems 10 0 07FEB11 17FEB11
Install Ceiling Grid systems
MBWF200 Install Gypsum Bd Ceiling 10 0 14FEB11 24FEB11
Install Gypsum Bd Ceiling
MBWF230 Install Alum Strip Ceiling 10 0 26FEB11 08MAR11
Install Alum Strip Ceiling

Tower Ground Floor-Finishes


MBWF130G Grnd Inspctn-01 Abv Clng Sys 3 0 23JAN11 25JAN11
Grnd Inspctn-01 Abv Clng Sys
MBWF180G Install Ceiling Grid systems 14 0 26JAN11 10FEB11
Install Ceiling Grid systems
MBWF200G Install Gypsum Bd Ceiling 10 0 12FEB11 22FEB11
Install Gypsum Bd Ceiling
MBWF230G Install Alum Strip Ceiling 10 0 23FEB11 06MAR11
Install Alum Strip Ceiling

Tower First Floor-Finishes


MBWF130F Grnd Inspctn-01 Abv Clng Sys 3 0 11JAN11 13JAN11
Grnd Inspctn-01 Abv Clng Sys
MBWF180F Install Ceiling Grid systems 14 0 15JAN11 30JAN11
Install Ceiling Grid systems
MBWF200F Install Gypsum Bd Ceiling 10 0 31JAN11 10FEB11
Install Gypsum Bd Ceiling
MBWF230F Install Alum Panel Ceiling 11 0 09FEB11 21FEB11
Install Alum Panel Ceiling

Tower Second Floor-Finishes


MBWF130S Grnd Inspctn-01 Abv Clng Sys 3 0 02JAN11 04JAN11
Grnd Inspctn-01 Abv Clng Sys

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 24 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBWF180S Install Ceiling Grid systems 14 0 05JAN11 20JAN11
Install Ceiling Grid systems
MBWF200S Install Gypsum Bd Ceiling 11 0 22JAN11 02FEB11
Install Gypsum Bd Ceiling
MBWF230S Install Alum Panel Ceiling 11 0 03FEB11 15FEB11
Install Alum Panel Ceiling

Tower Third Floor- Finishes


MBWF130T Grnd Inspctn-01 Abv Clng Sys 3 0 23DEC10 26DEC10
Grnd Inspctn-01 Abv Clng Sys
MBWF180T Install Ceiling Grid systems 14 0 28DEC10 12JAN11
Install Ceiling Grid systems
MBWF200T Install Gypsum Bd Ceiling 11 0 06JAN11 18JAN11
Install Gypsum Bd Ceiling
MBWF230T Install Alum Panel Ceiling 12 0 12JAN11 25JAN11
Install Alum Panel Ceiling

Tower Fourth Floor-Finishes


MBWF130R Grnd Inspctn-01 Abv Clng Sys 3 0 14DEC10 16DEC10
Grnd Inspctn-01 Abv Clng Sys
MBWF180R Install Ceiling Grid systems 14 0 18DEC10 02JAN11
Install Ceiling Grid systems
MBWF200R Install Gypsum Bd Ceiling 11 0 25DEC10 05JAN11
Install Gypsum Bd Ceiling
MBWF230R Install Alum Panel Ceiling 12 0 27DEC10 09JAN11
Install Alum Panel Ceiling

Tower Pent House Finishing Works


MBWF130P Grnd Inspctn-01 Abv Clng Sys 2 0 05DEC10 06DEC10
Grnd Inspctn-01 Abv Clng Sys
MBWF180P Install Ceiling Grid systems 5 0 07DEC10 12DEC10
Install Ceiling Grid systems
MBWF200P Install Gypsum Bd Ceiling 5 0 12DEC10 16DEC10
Install Gypsum Bd Ceiling
MBWF230P Install Alum Panel Ceiling 5 0 18DEC10 22DEC10
Install Alum Panel Ceiling

Finish Grnd Floor (4A,7A - 5B,6B) Rear Building


MBMF2300GD Grand Insptn Abv Ceiling 3 0 06JAN11 09JAN11
Grand Insptn Abv Ceiling
MBMF2320GD Install Ceiling Grids 15 0 10JAN11 26JAN11
Install Ceiling Grids
MBMF2350GD Install Gypsum Bd Ceiling 16 0 13JAN11 31JAN11
Install Gypsum Bd Ceiling
MBM2450GD Install Alum Panel Ceiling 16 0 01FEB11 19FEB11
Install Alum Panel Ceiling

Finish First Floor (4A,7A - 5B,6B) Rear Building


MBFGF240 Grand Insptn Abv Ceiling 3 0 30DEC10 02JAN11
Grand Insptn Abv Ceiling
MBFGF260 Install Ceiling Grids 15 0 10JAN11 26JAN11
Install Ceiling Grids

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 25 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBFGF280 Install Gypsum Bd Ceiling 16 0 17JAN11 03FEB11
Install Gypsum Bd Ceiling
MBFGF320 Install Alum Panel Ceiling 16 0 14FEB11 03MAR11
Install Alum Panel Ceiling

Finish Grnd Floor (4B,5A - 6A,7B) Rear Building


MBGFGF240 Grand Insptn Abv Ceiling 3 0 05JAN11 08JAN11
Grand Insptn Abv Ceiling
MBGFGF260 Install Ceiling Grids 15 0 15JAN11 31JAN11
Install Ceiling Grids
MBGFGF280 Install Gypsum Bd Ceiling 16 0 18JAN11 05FEB11
Install Gypsum Bd Ceiling
MBGFGF320 Install Alum Panel Ceiling 16 0 23JAN11 09FEB11
Install Alum Panel Ceiling

Finish First Floor (4B,5A - 6A,7B) Rear Building


MBFFGF240 Grand Insptn Abv Ceiling 3 0 16JAN11 18JAN11
Grand Insptn Abv Ceiling
MBFFGF260 Install Ceiling Grids 15 0 19JAN11 05FEB11
Install Ceiling Grids
MBFFGF280 Install Gypsum Bd Ceiling 16 0 06FEB11 23FEB11
Install Gypsum Bd Ceiling
MBFFGF320 Install Alum Panel Ceiling 16 0 09FEB11 27FEB11
Install Alum Panel Ceiling

Pre-Finishing Work
Tower Basement Floor- Finishes
MBWF245 Floor Screed 15 0 23NOV10 09DEC10
Floor Screed

Tower Ground Floor-Finishes


MBWF100G Floor Screed 15 0 11DEC10 27DEC10
Floor Screed

Tower First Floor-Finishes


MBWF100F Floor Screed 50 mm 30 100 22FEB10A 23MAR10A
Floor Screed 50 mm

Tower Second Floor-Finishes


MBWF100S Floor Screed 50 mm 4 100 24AUG09A 03MAR10A
Floor Screed 50 mm

Tower Third Floor- Finishes


MBWF100T Floor Screed 50 mm 4 100 28AUG09A 25FEB10A
Floor Screed 50 mm

Tower Fourth Floor-Finishes


MBWF100R Floor Screed 50 mm 4 100 28AUG09A 28JAN10A
Floor Screed 50 mm

Tower Pent House Finishing Works


MBWF100P Floor Screed 50 mm 20 100 29AUG09A 01FEB10A
Floor Screed 50 mm

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 26 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
Finish Grnd Floor (4A,7A - 5B,6B) Rear Building
MBMF1500GD Floor Screed 20 0 29DEC10 20JAN11
Floor Screed

Finish First Floor (4A,7A - 5B,6B) Rear Building


MBFGF360 Floor Screed 20 0 12JAN11 03FEB11
Floor Screed

Finish Grnd Floor (4B,5A - 6A,7B) Rear Building


MBGFGF360 Floor Screed 20 0 26JAN11 17FEB11
Floor Screed

Finish First Floor (4B,5A - 6A,7B) Rear Building


MBFFGF360 Floor Screed 20 0 09FEB11 03MAR11
Floor Screed

Final Floor Finishing Works


Tower Basement Floor- Finishes
MBWF270 Fix Porclean tiles 15 0 09MAR11 26MAR11
Fix Porclean tiles
MBWF220 Fix Marble Flooring Tiles 10 0 21MAR11 31MAR11
Fix Marble Flooring Tiles
MBWF285 Fix Porceline Skirting 10 0 27MAR11 06APR11
Fix Porceline Skirting
MBWF225 Fix Marble Skirting 10 0 02APR11 12APR11
Fix Marble Skirting
MBWF295 Fix Ceramic Floor Tiles 14 0 02APR11 17APR11
Fix Ceramic Floor Tiles
MBWF300 Fix Marble Thresholds 7 0 05APR11 12APR11
Fix Marble Thresholds
MBWF235 Fix Heavy Duty Vinyl Floor 10 0 13APR11 24APR11
Fix Heavy Duty Vinyl Floor
MBWF610 Epoxy Paint to Floor 7 0 25APR11 02MAY11
Epoxy Paint to Floor
MBWF290 Fix Tread / Risers 7 0 03MAY11 10MAY11
Fix Tread / Risers

Tower Ground Floor-Finishes


MBWF190G Levling Comp. for Vinyl Flooring 7 0 03MAR11 10MAR11
Levling Comp. for Vinyl Flooring
MBWF220G Fix Marble Flooring Tiles 10 0 21MAR11 31MAR11
Fix Marble Flooring Tiles
MBWF225G Fix Hard Wood Skirting 7 0 27MAR11 03APR11
Fix Hard Wood Skirting
MBWF285G Fix Marble Skirting 10 0 02APR11 12APR11
Fix Marble Skirting
MBWF250G Fix Vinyl Flooring 15 0 04APR11 20APR11
Fix Vinyl Flooring
MBWF300G Fix Thresholds 7 0 05APR11 12APR11
Fix Thresholds
MBWF240G Fix Ceramic Floor Tiles 9 0 18APR11 27APR11
Fix Ceramic Floor Tiles

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 27 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBWF260G Fix Vinyl Skirting 7 0 21APR11 28APR11
Fix Vinyl Skirting
MBWF245G Fix Carpet Auditorium 7 0 30APR11 07MAY11
Fix Carpet Auditorium
MBWF260G10 Epoxy Paint on Floor 20 0 30APR11 22MAY11
Epoxy Paint on Floor
MBWF290G Fix Tread / Risers 8 0 23MAY11 31MAY11
Fix Tread / Risers

Tower First Floor-Finishes


MBWF220F Fix marble Flooring Tiles 26 75 13MAR10A 30NOV10
Fix marble Flooring Tiles
MBWF225F Fix Marble Skirting 8 75 01JUN10A 24NOV10
Fix Marble Skirting
MBWF240F Fix Ceramic Floor Tiles 15 0 09FEB11 26FEB11
Fix Ceramic Floor Tiles
MBWF300F Fix Thresholds 5 0 26FEB11 02MAR11
Fix Thresholds
MBWF610F Epoxy Paint to Floor 10 0 03MAR11 14MAR11
Epoxy Paint to Floor
MBWF290F Fix Tread / Risers 6 0 15MAR11 21MAR11
Fix Tread / Risers

Tower Second Floor-Finishes


MBWF220S Fix Marble Flooring Tiles 26 75 02JAN10A 30NOV10
Fix Marble Flooring Tiles
MBWF225S Fix Marble Skirting 8 75 27MAR10A 24NOV10
Fix Marble Skirting
MBWF240S Fix Ceramic Floor Tiling 10 52 27SEP10A 28NOV10
Fix Ceramic Floor Tiling
MBWF610S Epoxy Paint to Floor 5 0 29NOV10 04DEC10
Epoxy Paint to Floor
MBWF300S Fix Thresholds 5 0 05DEC10 09DEC10
Fix Thresholds
MBWF290S Fix Tread / Risers 9 0 11DEC10 20DEC10
Fix Tread / Risers

Tower Third Floor- Finishes


MBWF220T Fix Marble Flooring Tiles 21 75 20FEB10A 28NOV10
Fix Marble Flooring Tiles
MBWF285T Fix Marble Skirting 8 75 25MAY10A 23NOV10
Fix Marble Skirting
MBWF240T Fix Ceramic Floor Tiles 8 80 20SEP10A 24NOV10
Fix Ceramic Floor Tiles
MBWF610T Epoxy Paint to Floor 5 0 24NOV10 29NOV10
Epoxy Paint to Floor
MBWF225T Fix Skirting Saudi Granite 5 0 29NOV10 04DEC10
Fix Skirting Saudi Granite
MBWF300T Fix Thresholds 5 0 05DEC10 09DEC10
Fix Thresholds

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 28 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBWF290T Fix Tread/Risers 9 0 11DEC10 20DEC10
Fix Tread/Risers

Tower Fourth Floor-Finishes


MBWF220R Fix Marble Flooring Tiles 21 90 07JAN10A 24NOV10
Fix Marble Flooring Tiles
MBWF285R Fix Marble Skirting 5 75 13APR10A 23NOV10
Fix Marble Skirting
MBWF240R Fix Ceramic Floor Tiles 8 95 21AUG10A 22NOV10
Fix Ceramic Floor Tiles
MBWF610R Epoxy Paint to Floor 5 0 24NOV10 29NOV10
Epoxy Paint to Floor
MBWF290R Fix Tread / Risers Saudi Grnt 9 0 25NOV10 05DEC10
Fix Tread / Risers Saudi Grnt
MBWF300R Fix Thresholds 5 0 30NOV10 05DEC10
Fix Thresholds

Tower Pent House Finishing Works


MBWF220P Fix Marble Flooring Tiles 3 80 24MAR10A 23NOV10
Fix Marble Flooring Tiles
MBWF240P Fix Ceramic Floor Tiling 3 0 23DEC10 26DEC10
Fix Ceramic Floor Tiling
MBWF290P Fix Tread / Risers Saudi Grnt 4 0 27DEC10 30DEC10
Fix Tread / Risers Saudi Grnt
MBWF285P Fix Marble Skirting 3 0 01JAN11 03JAN11
Fix Marble Skirting
MBWF610P Epoxy Paint to Floor 3 0 04JAN11 06JAN11
Epoxy Paint to Floor
MBWF300P Fix Thresholds 3 0 08JAN11 10JAN11
Fix Thresholds

TOWER BUILDING
MBWF360 Final Clean Up (Tower) 15 0 11JUN11 27JUN11
Final Clean Up (Tower)

Finish Grnd Floor (4A,7A - 5B,6B) Rear Building


MBMF4100GD Fix Marble Flooring Tiles 19 33 02AUG10A 07DEC10
Fix Marble Flooring Tiles
MBF4120 Fix Skirting Saudi Granite 10 0 08DEC10 19DEC10
Fix Skirting Saudi Granite
MBMF4300GD Fix Porcelain Tiles 20 0 20DEC10 11JAN11
Fix Porcelain Tiles
MBMF4400GD Fix Skirting Porcelain 10 0 12JAN11 23JAN11
Fix Skirting Porcelain
MBMF1610 Epoxy Paint to Floors 15 0 24JAN11 09FEB11
Epoxy Paint to Floors
MBMF4000GD Leveling Comp. for Vinyl Flooring 10 0 03FEB11 14FEB11
Leveling Comp. for Vinyl Flooring
MBMF1285 Fix Marble Tile Skirting 10 0 10FEB11 21FEB11
Fix Marble Tile Skirting
MBMF4050GD Fix Vinyl Flooring 10 0 15FEB11 26FEB11
Fix Vinyl Flooring

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 29 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBMF4200GD Fix Ceramic Floor Tiles 20 0 15FEB11 09MAR11
Fix Ceramic Floor Tiles
MBMF4060GD Fix Vinyl Skirting 7 0 17FEB11 24FEB11
Fix Vinyl Skirting
MBMF4500 Fix Thresholds 7 0 26FEB11 05MAR11
Fix Thresholds
MBMF1000 Carpet Flooring 7 0 28FEB11 07MAR11
Carpet Flooring

Finish First Floor (4A,7A - 5B,6B) Rear Building


MBFGF440 Fix Marble Flooring Tiles 21 45 03JUL10A 06DEC10
Fix Marble Flooring Tiles
MBFGF420 Fix Ceramic Floor Tiles 17 0 23NOV10 12DEC10
Fix Ceramic Floor Tiles
MBFGF460 Fix Skirting 10 0 07DEC10 18DEC10
Fix Skirting
MBFGF400 Levling Comp. for Vinyl Flooring 10 0 14DEC10 25DEC10
Levling Comp. for Vinyl Flooring
MBFGF500 Fix Vinyl Flooring 10 0 20DEC10 30DEC10
Fix Vinyl Flooring
MBFGF540 Fix Tread / Riser Marble 7 0 01JAN11 08JAN11
Fix Tread / Riser Marble
MBFGF620 Fix Vinyl Skirting 7 0 01JAN11 08JAN11
Fix Vinyl Skirting
MBFGF560 Epoxy Paint to Floors 15 0 09JAN11 25JAN11
Epoxy Paint to Floors
MBFGF600 Fix Marble Tile Skirting 10 0 09JAN11 19JAN11
Fix Marble Tile Skirting
MBFGF640 Fix Metal Thresholds 7 0 26JAN11 02FEB11
Fix Metal Thresholds

Finish Grnd Floor (4B,5A - 6A,7B) Rear Building


MBGFGF430 Fix Marble flooring Tiles 18 33 16MAY10A 06DEC10
Fix Marble flooring Tiles
MBGFGF460 Fix Skirting Marble 10 0 07DEC10 18DEC10
Fix Skirting Marble
MBGFGF480 Fix Porcelain Tiles 7 0 19DEC10 26DEC10
Fix Porcelain Tiles
MBGFGF650 Fix Skirting porcelain tiles 7 0 27DEC10 03JAN11
Fix Skirting porcelain tiles
MBGFGF560 Epoxy Paint to Floors 7 0 04JAN11 11JAN11
Epoxy Paint to Floors
MBGFGF400 Levling Comp. for Vinyl Flooring 7 0 14FEB11 21FEB11
Levling Comp. for Vinyl Flooring
MBGFGF420 Fix Ceramic Floor Tiles 20 0 22FEB11 16MAR11
Fix Ceramic Floor Tiles
MBGFGF500 Fix Vinyl Flooring 7 0 22FEB11 01MAR11
Fix Vinyl Flooring
MBGFGF620 Fix Vinyl Skirting 7 0 02MAR11 09MAR11
Fix Vinyl Skirting

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 30 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBGFGF630 Carpet flooring 7 0 10MAR11 17MAR11
Carpet flooring
MBGFGF640 Fix Metal Thresholds 7 0 19MAR11 26MAR11
Fix Metal Thresholds

Finish First Floor (4B,5A - 6A,7B) Rear Building


MBFFGF430 Fix Marble Fooring Tiles 21 45 15APR10A 06DEC10
Fix Marble Fooring Tiles
MBFFGF420 Fix Ceramic Floor Tiles 16 0 27NOV10 14DEC10
Fix Ceramic Floor Tiles
MBFFGF460 Fix Skirting Saudi Granite 7 0 07DEC10 14DEC10
Fix Skirting Saudi Granite
MBFFGF400 Levling Comp. for Vinyl Flooring 7 0 28FEB11 07MAR11
Levling Comp. for Vinyl Flooring
MBFFGF500 Fix Vinyl Flooring 7 0 08MAR11 15MAR11
Fix Vinyl Flooring
MBFFGF620 Fix Vinyl Skirting 6 0 15MAR11 21MAR11
Fix Vinyl Skirting
MBFFGF540 Fix Tread / Riser Marble 5 0 16MAR11 21MAR11
Fix Tread / Riser Marble
MBFFGF600 Fix Tiles Skirting 6 mm 7 0 22MAR11 29MAR11
Fix Tiles Skirting 6 mm
MBFFGF640 Fix Metal Thresholds 5 0 30MAR11 04APR11
Fix Metal Thresholds

REAR BUILDING
MBMF9000GD Final Clean Up (Rear) 7 0 03JUL11 10JUL11
Final Clean Up (Rear)

Final Wall Finishing Works


Tower Basement Floor- Finishes
MBFWB200 Final Coat Paint ordinary 15 0 10MAY11 26MAY11
Final Coat Paint ordinary
MBFWB320B Doors Paint 10 0 16MAY11 26MAY11
Doors Paint
MBPWF1500B Final Coats of Anti Bacteria 10 0 28MAY11 07JUN11
Final Coats of Anti Bacteria

Tower Ground Floor-Finishes


MBFWB200G Final Coat Paint ordinary 15 0 07MAY11 23MAY11
Final Coat Paint ordinary
MBFWB320G Doors Paint 10 0 12MAY11 23MAY11
Doors Paint
MBFWB1500G Final Coats of Anti Bacteria 10 0 24MAY11 04JUN11
Final Coats of Anti Bacteria
MBFWB240G Textured Paint 10 0 24MAY11 04JUN11
Textured Paint

Tower First Floor-Finishes


MBFWB200F Final Coat Paint ordinary 15 0 25APR11 11MAY11
Final Coat Paint ordinary

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 31 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBFWB320F Doors Paint 10 0 01MAY11 11MAY11
Doors Paint
MBFWB240F Textured Paint 10 0 12MAY11 23MAY11
Textured Paint
MBPWF1500F Final 2 Coats of Anti Bacteria 10 0 12MAY11 23MAY11
Final 2 Coats of Anti Bacteria

Tower Second Floor-Finishes


MBFWB200S Final Coat Paint ordinary 15 0 25APR11 11MAY11
Final Coat Paint ordinary
MBFWB320S Doors Paint 10 0 01MAY11 11MAY11
Doors Paint
MBFWB150S Final 2 Coats of Anti Bacteria 10 0 12MAY11 23MAY11
Final 2 Coats of Anti Bacteria
MBFWB240S Textured Paint 10 0 12MAY11 23MAY11
Textured Paint

Tower Third Floor- Finishes


MBFWB200T Final Coat Paint Ordinary 15 0 13APR11 30APR11
Final Coat Paint Ordinary
MBFWB1205 Doors Paint 10 0 19APR11 30APR11
Doors Paint
MBFWB150T Final 2 Coats of Anti Bacteria 10 0 01MAY11 11MAY11
Final 2 Coats of Anti Bacteria
MBFWB240T Textured Paint 10 0 01MAY11 11MAY11
Textured Paint

Tower Fourth Floor-Finishes


MBFWB200R Final Coat Paint ordinary 15 0 13APR11 30APR11
Final Coat Paint ordinary
MBFW120R Doors Paint 10 0 19APR11 30APR11
Doors Paint
MBFWB150R Final 2 Coats of Anti Bacteria 10 0 01MAY11 11MAY11
Final 2 Coats of Anti Bacteria
MBFWB240R Textured Paint 10 0 01MAY11 11MAY11
Textured Paint

Tower Pent House Finishing Works


MBFWB200P Final Coat Paint ordinary 6 0 12APR11 18APR11
Final Coat Paint ordinary
MBFWB320P Doors Paint 6 0 12APR11 18APR11
Doors Paint
MBFWB150P Final 2 Coats of Anti Bactaia 10 0 19APR11 30APR11
Final 2 Coats of Anti Bactaia
MBFWB240P Textured Paint 10 0 19APR11 30APR11
Textured Paint

Finish Grnd Floor (4A,7A - 5B,6B) Rear Building


MBMF3100GD Final Coat Paint ordinary 20 0 14MAY11 05JUN11
Final Coat Paint ordinary
MBMF320RG Doors Paint 14 0 21MAY11 05JUN11
Doors Paint

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 32 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBMF140R Final 2 Coats of Anti Bacteria 10 0 06JUN11 16JUN11
Final 2 Coats of Anti Bacteria
MBMF3130 Textured Paint 10 0 18JUN11 28JUN11
Textured Paint

Finish First Floor (4A,7A - 5B,6B) Rear Building


MBFGF700 Final Coat Paint ordinary 20 0 08MAY11 30MAY11
Final Coat Paint ordinary
MBFGF320R Doors Paint 14 0 15MAY11 30MAY11
Doors Paint
MBFGF720 Textured Paint 10 0 31MAY11 11JUN11
Textured Paint
MBMF140R1F Final 2 Coats of Anti Bacteria 10 0 12JUN11 22JUN11
Final 2 Coats of Anti Bacteria

Finish Grnd Floor (4B,5A - 6A,7B) Rear Building


MBGFGF700 Final Coat Paint ordinary 20 0 21APR11 14MAY11
Final Coat Paint ordinary
MBGF320R Doors Paint 14 0 28APR11 14MAY11
Doors Paint
MBGF140RG Final 2 Coats of Anti Bacteria 10 0 15MAY11 25MAY11
Final 2 Coats of Anti Bacteria
MBGFGF720 Textured Paint 10 0 22MAY11 01JUN11
Textured Paint

Finish First Floor (4B,5A - 6A,7B) Rear Building


MBFFGF700 Final Coat Paint ordinary 20 0 05APR11 27APR11
Final Coat Paint ordinary
MBFF320R Doors Paint 14 0 12APR11 27APR11
Doors Paint
MBFF140R Final 2 Coats of Anti Bacteria 10 0 28APR11 09MAY11
Final 2 Coats of Anti Bacteria
MBFFGF720 Textured Paint 10 0 10MAY11 21MAY11
Textured Paint

Final Ceiling Finishing Works


Tower Basement Floor- Finishes
MBWF330 Fix Min. Fiber Acc. Clng Panels 10 0 08JUN11 19JUN11
Fix Min. Fiber Acc. Clng Panels
MBWF331 Fix Fiber Glass Clng Panels 12 0 12JUN11 25JUN11
Fix Fiber Glass Clng Panels

Tower Ground Floor-Finishes


MBWF330G Fix Min. Fiber Acc. Clng Panels 10 0 05JUN11 15JUN11
Fix Min. Fiber Acc. Clng Panels
MBWF330G10 Fix Fiber Glass Clng Panels 15 0 11JUN11 27JUN11
Fix Fiber Glass Clng Panels

Tower First Floor-Finishes


MBWF330F Fix Min. Fiber Acc. Clng Panels 10 0 30MAY11 09JUN11
Fix Min. Fiber Acc. Clng Panels
MBWF330F10 Fix Fiber Glass Clng Panels 12 0 02JUN11 15JUN11
Fix Fiber Glass Clng Panels

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 33 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
Tower Second Floor-Finishes
MBWF330S Fix Min. Fiber Acc. Clng Panels 10 0 24MAY11 04JUN11
Fix Min. Fiber Acc. Clng Panels
MBWF330S10 Fix Fiber Glass Clng Panels 12 0 30MAY11 12JUN11
Fix Fiber Glass Clng Panels

Tower Third Floor- Finishes


MBWF330T Fix Min. Fiber Acc. Clng Panels 10 0 18MAY11 29MAY11
Fix Min. Fiber Acc. Clng Panels
MBWF330T10 Fix Fiber Glass Clng Panels 12 0 28MAY11 09JUN11
Fix Fiber Glass Clng Panels

Tower Fourth Floor-Finishes


MBWF330R Fix Min. Fiber Acc. Clng Panels 10 0 12MAY11 23MAY11
Fix Min. Fiber Acc. Clng Panels
MBWF330R10 Fix Fiber Glass Clng Panels 12 0 22MAY11 04JUN11
Fix Fiber Glass Clng Panels

Tower Pent House Finishing Works


MBWF330P Fix Min. Fiber Acc. Clng Panels 8 0 01MAY11 09MAY11
Fix Min. Fiber Acc. Clng Panels
MBWF330P10 Fix Fiber Glass Clng Panels 10 0 10MAY11 21MAY11
Fix Fiber Glass Clng Panels

Finish Grnd Floor (4A,7A - 5B,6B) Rear Building


MBMF2310 Fix Min. Fiber Acc. Clng Panels 12 0 03APR11 16APR11
Fix Min. Fiber Acc. Clng Panels
MBMF2320 Fix Fiber Glass Clng Panels 12 0 17APR11 30APR11
Fix Fiber Glass Clng Panels

Finish First Floor (4A,7A - 5B,6B) Rear Building


MBFGF810 Fix Fiber Glass Clng Panels 12 0 15FEB11 28FEB11
Fix Fiber Glass Clng Panels
MBFGF800 Fix Min. Fiber Acc. Clng Panels 20 0 10MAR11 02APR11
Fix Min. Fiber Acc. Clng Panels

Finish Grnd Floor (4B,5A - 6A,7B) Rear Building


MBGFGF810 Fix Fiber Glass Clng Panels 12 0 03APR11 16APR11
Fix Fiber Glass Clng Panels
MBGFGF800 Fix Min. Fiber Acc. Clng Panels 12 0 17APR11 30APR11
Fix Min. Fiber Acc. Clng Panels

Finish First Floor (4B,5A - 6A,7B) Rear Building


MBFFGF810 Fix Fiber Glass Clng Panels 20 0 10MAR11 02APR11
Fix Fiber Glass Clng Panels
MBFFGF800 Fix Min. Fiber Acc. Clng Panels 12 0 03APR11 16APR11
Fix Min. Fiber Acc. Clng Panels

Metal Works
TOWER BUILDING
MBWF500 Install Hand Rails 30 0 11JAN11 14FEB11
Install Hand Rails
MBWD1200 Toilet Cubicles 30 0 18JAN11 21FEB11
Toilet Cubicles

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 34 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBWF1200 Fix wall Guards 25 0 29JAN11 26FEB11
Fix wall Guards
MBWF520 Install Garbage Chute 21 0 09FEB11 05MAR11
Install Garbage Chute
MBWF1250 Expansion Joint Covers 21 0 22FEB11 17MAR11
Expansion Joint Covers

Special Construction
TOWER BUILDING
MBWF335 Auditorium-Arch.& ID Drgs.Approval 30 0 07DEC10 10JAN11
Auditorium-Arch.& ID Drgs.Approval
MBWF340 Auditorium-Raised Flooring Works 50 0 11JAN11 09MAR11
Auditorium-Raised Flooring Works
MBWF350 Hydrotheropy- Drgs.Approval 15 0 22FEB11 10MAR11
Hydrotheropy- Drgs.Approval
MBWF342 Auditorium-Interior & Finishes 45 0 10MAR11 01MAY11
Auditorium-Interior & Finishes
MBWF380 Hydrotheropy-Civil & Finishing Work 35 0 12MAR11 20APR11
Hydrotheropy-Civil & Finishing Work

Specialties
Tower Basement Floor- Finishes
MBWF730 Fix Counters / Case Work 12 0 14MAY11 26MAY11
Fix Counters / Case Work

Tower Ground Floor-Finishes


MBWF730G Fix Counters / Case Work 12 0 10MAY11 23MAY11
Fix Counters / Case Work

Tower First Floor-Finishes


MBWF730F Fix Counters / Case Work 12 0 28APR11 11MAY11
Fix Counters / Case Work

Tower Second Floor-Finishes


MBWF730S Fix Counters / Case Work 12 0 28APR11 11MAY11
Fix Counters / Case Work

Tower Third Floor- Finishes


MBWF730T Fix Counters / Case Work 12 0 17APR11 30APR11
Fix Counters / Case Work

Tower Fourth Floor-Finishes


MBWF730R Fix Counters / Case Work 12 0 17APR11 30APR11
Fix Counters / Case Work

Tower Pent House Finishing Works


MBWF730P Fix Counters / Case Work 12 0 05APR11 18APR11
Fix Counters / Case Work

TOWER BUILDING
MBW335 Install Sign Boards 30 0 15MAR11 18APR11
Install Sign Boards

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 35 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
Finish First Floor (4A,7A - 5B,6B) Rear Building
MBSGF100 Fix Counters / Case Work 15 0 19MAY11 05JUN11
Fix Counters / Case Work

Finish Grnd Floor (4B,5A - 6A,7B) Rear Building


MBGSGF100 Fix Counters / Case Work 15 0 14MAY11 30MAY11
Fix Counters / Case Work

Finish First Floor (4B,5A - 6A,7B) Rear Building


MBFSGF100 Fix Counters / Case Work 15 0 27APR11 14MAY11
Fix Counters / Case Work

REAR BUILDING
MBMF8000GD Install Sign Boards 16 0 26APR11 14MAY11
Install Sign Boards

Finishing Works
Tower Basement Floor- Finishes
MBFWB240 Textured Paint 15 0 28MAY11 13JUN11
Textured Paint

MECHANICAL WORKS
Plumbing Materials Submittal

MBAP1000 Get Appr Toilet utilities 5 100 16FEB09A 22JUL09A


Get Appr Toilet utilities
MBGP100 Get apprl. SUMP pump 12 100 28MAR09A 25JUN09A
Get apprl. SUMP pump
MBPWS1000 Submit Plumb Fixtures for Aprvl 18 100 23APR09A 13JUL09A
Submit Plumb Fixtures for Aprvl
MBPW1600M Get Appvl.Fire Sprinkler 6 100 07MAR10A 14MAR10A
Get Appvl.Fire Sprinkler
MBPW2050M Get Appvl.LPG Storage Tank 6 100 07MAR10A 14MAR10A
Get Appvl.LPG Storage Tank
MBPW2350M Get Appvl.FHC 6 100 07MAR10A 14MAR10A
Get Appvl.FHC
MBHW2060 Get App. Boiler & Accessories 6 100 14MAR10A 16MAR10A
Get App. Boiler & Accessories

FM-200 Meterial Submittal

MBMW2060M Get App.FM-200 Fire Fighting System 6 100 23OCT10A 29OCT10A


Get App.FM-200 Fire Fighting System

HVAC Materials Submittal

MBHW1300M Get Appvl.Insul.Chilled W.P 6 100 07MAR10A 14MAR10A


Get Appvl.Insul.Chilled W.P
MBHW1350 Get App. Pumps Chill 30 100 07MAR10A 14MAR10A
Get App. Pumps Chill

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 36 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBHW1450M Get Apprvl. AHU 6 100 07MAR10A 14MAR10A
Get Apprvl. AHU
MBHW1600M Get Appvl FCU with accessories 3 100 07MAR10A 14MAR10A
Get Appvl FCU with accessories
MBHW1750M Get Approval. Exhaust Fans 3 100 07MAR10A 14MAR10A
Get Approval. Exhaust Fans
MBHW1900M Get App.Flexible Ducts 5 100 07MAR10A 14MAR10A
Get App.Flexible Ducts
MBHW2050 Get App.Chillers 6 100 07MAR10A 14MAR10A
Get App.Chillers
MBHW2050M Get Approval BMS Room Layout / BMS Room 10 0 23NOV10 04DEC10
Get Approval BMS Room Layout / BMS Room
MBPW1750M Get Appvl. Supp. of Diffuser 15 0 23NOV10 09DEC10
Get Appvl. Supp. of Diffuser
MBPW2070M Get Appvl.Hepa Filters 15 0 23NOV10 09DEC10
Get Appvl.Hepa Filters
MBHW1380 Get apprl. Sound Attunaters 15 0 11DEC10 27DEC10
Get apprl. Sound Attunaters
MBHW1390 Get Apprl. Kitchen hood 25 0 28DEC10 25JAN11
Get Apprl. Kitchen hood

Elevator Submittal

MB1000 Get App Of Elevator 9 100 01APR10A 03APR10A


Get App Of Elevator

Delivery of Elevator

MB1020 Delivery of Elevator 30 50 02NOV10A 09DEC10


Delivery of Elevator

Delivery of Plumbing Material

KNGPP170 Delivery of Plumbing Utilities 30 100 16JUN09A 25AUG09A


Delivery of Plumbing Utilities
KNGPP160 Delievery of sanitary Fixture 45 100 27AUG09A 10NOV09A
Delievery of sanitary Fixture
MBHW2080 Delievery of Boiler 12 100 14MAR10A 01APR10A
Delievery of Boiler
MBPW1700M Delievery of Fire Sprinkler 6 100 01APR10A 03APR10A
Delievery of Fire Sprinkler
MBPW2450M Dilievery of FHC 6 100 01APR10A 01APR10A
Dilievery of FHC
MBPW2150M Delievery of LPG Gas Tank 30 0 23NOV10 27DEC10
Delievery of LPG Gas Tank

Delievery of FM-200 Firefighting Sys.

MBMW2080M Delievery FM-200 Fire Fighting Sys. 60 100 02JUN09A 17JUL10A


Delievery FM-200 Fire Fighting Sys.

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 37 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Delivery of HVAC Material

MBHW1420 Delivery of Chiller pump 15 100 07MAR10A 14MAR10A


Delivery of Chiller pump
MBHW1550M Delivery of AHU 12 100 07MAR10A 14MAR10A
Delivery of AHU
MBHW1700M Delivery of FCU 60 100 07MAR10A 14MAR10A
Delivery of FCU
MBHW2000M Delivery of Flex.Ducts 30 100 07MAR10A 14MAR10A
Delivery of Flex.Ducts
MBHW2150 Delivery of Chillers 12 100 07MAR10A 14MAR10A
Delivery of Chillers
MBHW1850M Delivery of Exhaust Fans 15 0 23NOV10 09DEC10
Delivery of Exhaust Fans
MBHW2150M Get approval BMS sys\Wiring 10 0 05DEC10 15DEC10
Get approval BMS sys\Wiring
MBPW1850M Delivery of Supp. Grill/ Diff. 52 0 11DEC10 08FEB11
Delivery of Supp. Grill/ Diff.
MBPW2090M Delievery Hepa Filters 45 0 11DEC10 31JAN11
Delievery Hepa Filters
MBDL120 Delivery of Sound Attunaters 40 0 28DEC10 12FEB11
Delivery of Sound Attunaters
MBDL130 Delivery of Kitchen hood 60 0 03JAN11 13MAR11
Delivery of Kitchen hood

Elevators
TOWER BUILDING
MBWM110 Install Elevators 90 40 22MAY10A 10JAN11
Install Elevators

HVAC Works
Basement Floor
MBHWB130 Install Ducts 30 100 22SEP09A 25DEC09A
Install Ducts
MBHWB120 Install Chilled Water Piping 30 97 22FEB10A 23NOV10
Install Chilled Water Piping
MBHWB160 Test Chilled Water Piping 15 40 30APR10A 27NOV10
Test Chilled Water Piping
MBHWB180 Insulate Ducting 15 71 01MAY10A 24NOV10
Insulate Ducting
MBHWB290 Install AHU 12 70 15MAY10A 27NOV10
Install AHU
MBHWB200 Insulate Chilled Water Pipes 10 25 23MAY10A 01DEC10
Insulate Chilled Water Pipes
MBHWB140 Test / Inspect Ducts 15 50 24MAY10A 01DEC10
Test / Inspect Ducts
MBHWB220 Install Flex Ducts /Supp. retrn Diff 15 0 19FEB11 07MAR11
Install Flex Ducts /Supp. retrn Diff

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 38 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBHWB280 Install BMS System / Equipements 30 0 09MAR11 12APR11
Install BMS System / Equipements

Ground Floor Tower


MBHWB120G Install Chilled Water Piping 89 95 29NOV07A 27NOV10
Install Chilled Water Piping
MBHWB200G Insulate Chilled Water Pipes 35 50 02JAN09A 21DEC10
Insulate Chilled Water Pipes
MBHWB160G Test Chilled Water Piping 30 50 01MAR10A 15DEC10
Test Chilled Water Piping
MBHWB260G Install FCU / IAHU connection 25 80 02MAR10A 28NOV10
Install FCU / IAHU connection
MBHWB100G Install Ducts HVAC 60 98 22MAR10A 23NOV10
Install Ducts HVAC
MBHWB180G Insulate Ducting 14 96 02MAY10A 23NOV10
Insulate Ducting
MBHWB140G Test / Inspect Ducts 25 70 31MAY10A 01DEC10
Test / Inspect Ducts
MBHWB220G Install Flex Ducts /Supp. retrn Diff 15 0 12FEB11 28FEB11
Install Flex Ducts /Supp. retrn Diff
MBHWB280G Install BMS System 15 0 23MAR11 09APR11
Install BMS System

First Floor Tower


MBHWB100F Install Ducts HVAC 30 100 25AUG07A 09MAR10A
Install Ducts HVAC
MBHWB120F Install Chilled Water Piping 80 95 01MAR08A 27NOV10
Install Chilled Water Piping
MBHWB200F Insulate Chilled Water Pipes 50 95 06FEB09A 25NOV10
Insulate Chilled Water Pipes
MBHWB180F Insulate Ducting 12 100 12SEP09A 08MAR10A
Insulate Ducting
MBHWB140F Test / Inspect Ducts 25 100 28JAN10A 24MAR10A
Test / Inspect Ducts
MBHWB260F Install FCU / IAHU connection 30 60 16FEB10A 06DEC10
Install FCU / IAHU connection
MBHWB160F Test Chilled Water Piping 20 60 28FEB10A 01DEC10
Test Chilled Water Piping
MBHWB220F Install Flex Ducts /Supp. retrn Diff 15 0 31JAN11 16FEB11
Install Flex Ducts /Supp. retrn Diff
MBHWB280F Install BMS System 15 0 06MAR11 22MAR11
Install BMS System

Second Floor Tower


MBHWB100S Install Ducts HVAC 18 100 11AUG07A 07MAR10A
Install Ducts HVAC
MBHWB120S Install Chilled Water Piping 70 95 26APR08A 27NOV10
Install Chilled Water Piping
MBHWB200S Insulate Chilled Water Pipes 50 95 21AUG08A 25NOV10
Insulate Chilled Water Pipes

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 39 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBHWB180S Insulate Ducting 12 100 31MAY09A 08MAR10A
Insulate Ducting
MBHWB260S Install FCU / connection 25 75 22DEC09A 29NOV10
Install FCU / connection
MBHWB140S Test / Inspect Ducts 25 100 02MAR10A 28MAR10A
Test / Inspect Ducts
MBHWB160S Test Chilled Water Piping 20 75 09MAR10A 28NOV10
Test Chilled Water Piping
MBHWB220S Install Flex Ducts /Supp. retrn Diff 15 0 22JAN11 07FEB11
Install Flex Ducts /Supp. retrn Diff
MBHWB280S Install BMS System 15 0 16FEB11 05MAR11
Install BMS System

Third Floor Tower


MBHWB100T Install Ducts HVAC 30 100 24DEC07A 08MAR10A
Install Ducts HVAC
MBHWB120T Install Chilled Water Piping 25 100 11MAY08A 10MAR10A
Install Chilled Water Piping
MBHWB200T Insulate Chilled Water Pipes 60 95 08JAN09A 25NOV10
Insulate Chilled Water Pipes
MBHWB180T Insulate Ducting 14 100 13AUG09A 08MAR10A
Insulate Ducting
MBHWB260T install FCU / Connection 40 65 02JAN10A 08DEC10
install FCU / Connection
MBHWB140T Test / Inspect Ducts 25 100 01MAR10A 28MAR10A
Test / Inspect Ducts
MBHWB160T Test Chilled Water Piping 8 75 14MAR10A 24NOV10
Test Chilled Water Piping
MBHWB220T Install Flex Ducts /Supp. retrn Diff 15 0 13JAN11 30JAN11
Install Flex Ducts /Supp. retrn Diff
MBHWB280T Install BMS System 15 0 27JAN11 13FEB11
Install BMS System

Fourth Floor Tower


MBHWB100R Install Ducts HVAC 30 100 22JAN08A 08MAR10A
Install Ducts HVAC
MBHWB120R Install Chilled Water Piping 25 100 22MAY08A 10MAR10A
Install Chilled Water Piping
MBHWB200R Insulate Chilled Water Pipes 60 90 14JAN09A 29NOV10
Insulate Chilled Water Pipes
MBHWB180R Insulate Ducting 12 100 21SEP09A 08MAR10A
Insulate Ducting
MBHWB160R Test Chilled Water Piping 25 75 11MAR10A 29NOV10
Test Chilled Water Piping
MBHWB140R Test / Inspect Ducts 25 100 15MAR10A 28MAR10A
Test / Inspect Ducts
MBHWB260R Install FCU / connection 36 65 17MAR10A 07DEC10
Install FCU / connection
MBHWB220R Install Flex Ducts /Supp. retrn Diff 15 0 03JAN11 19JAN11
Install Flex Ducts /Supp. retrn Diff

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 40 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBHWB280R Install BMS System 15 0 10JAN11 26JAN11
Install BMS System

Pent House
MBHWB100P Install Ducts HVAC 10 100 14JUL08A 08MAR10A
Install Ducts HVAC
MBHWB120P Install Chilled Water Piping 10 100 27AUG08A 08MAR10A
Install Chilled Water Piping
MBHWB200P Insulate Chilled Water Pipes 50 80 24JAN09A 04DEC10
Insulate Chilled Water Pipes
MBHWB260P Install FCU / Connection 50 65 14OCT09A 13DEC10
Install FCU / Connection
MBHWB180P Insulate Ducting 4 100 01NOV09A 07MAR10A
Insulate Ducting
MBHWB140P Test / Inspect Ducts 25 100 02MAR10A 28MAR10A
Test / Inspect Ducts
MBHWB160P Test Chilled Water Piping 7 75 01APR10A 23NOV10
Test Chilled Water Piping
MBHWB220P Install Flex Ducts /Supp. retrn Diff 15 0 13DEC10 29DEC10
Install Flex Ducts /Supp. retrn Diff
MBHWB280P Install BMS System 15 0 23DEC10 09JAN11
Install BMS System

TOWER BUILDING
MBHWB100 Install Ducts HVAC 36 65 29MAY08A 07DEC10
Install Ducts HVAC

Grnd Floor "5B - 6B" Rear Bldg Works


MBMH1500GD Install Chilled Water Piping 70 95 03JUN08A 27NOV10
Install Chilled Water Piping
MBMH1100GD Install Ducts HVAC 48 100 09SEP09A 13MAR10A
Install Ducts HVAC
MBMH1300GD Insulate Ducting 40 85 01NOV09A 29NOV10
Insulate Ducting
MBMH1550GD Test Chilled Water Piping 8 50 16FEB10A 27NOV10
Test Chilled Water Piping
MBMH1560GD Insulate Chilled Water Pipes 40 50 01MAR10A 15DEC10
Insulate Chilled Water Pipes
MBMH1200GD Test / Inspect Ducts 25 50 02MAR10A 07DEC10
Test / Inspect Ducts
MBMH2000GD Install Hepa Filters 10 0 01FEB11 12FEB11
Install Hepa Filters
MBMH3000GD Install Flex Ducts /Supp. retrn Diff 12 0 01FEB11 14FEB11
Install Flex Ducts /Supp. retrn Diff
MBMH4110GD Install BMS System 12 0 20FEB11 05MAR11
Install BMS System

First Floor "5B - 6B" Rear Bldg Works


MBHGF120 Fix Chilled Water Piping 70 95 18JUN08A 27NOV10
Fix Chilled Water Piping
MBHGF160 Test / Inspect Ducts 3 100 17OCT09A 21DEC09A
Test / Inspect Ducts

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 41 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBHGF200 Insulate Ducting 40 90 11NOV09A 27NOV10
Insulate Ducting
MBHGF100 Install Ducts HVAC 46 100 14NOV09A 13MAR10A
Install Ducts HVAC
MBHGF140 Test Chilled Water Piping 8 75 03MAY10A 24NOV10
Test Chilled Water Piping
MBHGF180 Insulate Chilled Water Pipes 10 50 13JUN10A 28NOV10
Insulate Chilled Water Pipes
MBHGF220 Install Hepa Filters 10 0 13FEB11 23FEB11
Install Hepa Filters
MBHGF260 Install Flex Ducts /Supp. retrn Diff 12 0 01MAR11 14MAR11
Install Flex Ducts /Supp. retrn Diff
MBHGF280 Install BMS System 12 0 05MAR11 17MAR11
Install BMS System

Grnd Floor "6A - 7B" Rear Bldg Works


MBGHGF120 Install Chilled Water Piping 70 95 07JUN08A 27NOV10
Install Chilled Water Piping
MBGHGF180 Insulate Chilled Water Pipes 40 50 24AUG09A 15DEC10
Insulate Chilled Water Pipes
MBGHGF100 Install Ducts HVAC 30 100 16NOV09A 10MAR10A
Install Ducts HVAC
MBGHGF140 Test Chilled Water Piping 7 50 02MAY10A 25NOV10
Test Chilled Water Piping
MBGHGF160 Test / Inspect Ducts 8 100 20MAY10A 22MAY10A
Test / Inspect Ducts
MBGHGF200 Insulate Ducting 24 90 30MAY10A 24NOV10
Insulate Ducting
MBGHGF260 Install Flex Ducts /Supp. retrn Diff 10 0 27JAN11 07FEB11
Install Flex Ducts /Supp. retrn Diff
MBGHGF220 Install Hepa Filters 10 0 24FEB11 07MAR11
Install Hepa Filters
MBGHGF280 Install BMS System 12 0 15MAR11 28MAR11
Install BMS System

First Floor "6A - 7B" Rear Bldg Works


MBFHGF120 Install Chilled Water Piping 25 100 11OCT08A 10MAR10A
Install Chilled Water Piping
MBFHGF180 Insulate Chilled Water Pipes 70 90 24APR09A 30NOV10
Insulate Chilled Water Pipes
MBFHGF100 Install Ducts HVAC 26 100 30SEP09A 10MAR10A
Install Ducts HVAC
MBFHGF200 Insulate Ducting 60 75 03DEC09A 09DEC10
Insulate Ducting
MBFHGF140 Test Chilled Water Piping 8 38 14APR10A 28NOV10
Test Chilled Water Piping
MBFHGF160 Test / Inspect Ducts 3 100 24MAY10A 24MAY10A
Test / Inspect Ducts
MBFHGF260 Install Flex Ducts /Supp. retrn Diff 12 0 24FEB11 09MAR11
Install Flex Ducts /Supp. retrn Diff

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 42 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBFHGF280 Install BMS System 12 0 28FEB11 13MAR11
Install BMS System
MBFHGF220 Install Hepa Filters 10 0 08MAR11 19MAR11
Install Hepa Filters

ROOF TOP
MBHFG245 Install AHU Roof Top (Rear) 16 65 23OCT09A 29NOV10
Install AHU Roof Top (Rear)
MBHWB290P Install AHU Roof Top (Tower) 26 65 28OCT09A 02DEC10
Install AHU Roof Top (Tower)
MBHWB270P Fix Exhaust Fans Roof Top (rear) 20 0 14DEC10 05JAN11
Fix Exhaust Fans Roof Top (rear)
MBRT290 Exhaust Fans Roof Top (Tower) 20 0 06JAN11 29JAN11
Exhaust Fans Roof Top (Tower)

Plumbing Works
Basement Floor
MBPBM1060 Drainage Pipes in Basement Raft 20 100 05JUL05A 27JUL05A
Drainage Pipes in Basement Raft
MBPWB100 Above Ceiling Drainage Pipes 10 100 30APR08A 08MAR10A
Above Ceiling Drainage Pipes
MBPWB120 Test Abv Ceiling Drainage Pipes 10 100 26JUN08A 11JUL10A
Test Abv Ceiling Drainage Pipes
MBPWB160 Install Cold/Hot Water Pipes 14 90 22NOV09A 24NOV10
Install Cold/Hot Water Pipes
MBPWB130 Insulat hot water pipes 11 85 08APR10A 25NOV10
Insulat hot water pipes
MBPWB180 Pressure Test Water pipe line 7 85 23MAY10A 27NOV10
Pressure Test Water pipe line
MBPWB140 Tag Hot/Cold Water Pipes line 7 0 25DEC10 01JAN11
Tag Hot/Cold Water Pipes line
MBPWB190 Condensate drain 12 0 28DEC10 10JAN11
Condensate drain

Ground Floor Tower


MBMP1100GA Sleeves Mech. in Ceiling Slab 5 100 07OCT06A 11OCT06A
Sleeves Mech. in Ceiling Slab
MBMP1100GC Sleeves Mech. in Ceiling Slab 5 100 21OCT06A 25OCT06A
Sleeves Mech. in Ceiling Slab
MBMP1100GB Sleeves Mech. in Ceiling Slab 5 100 09NOV06A 14NOV06A
Sleeves Mech. in Ceiling Slab
MBPWB160G Install Hot/Cold Water Pipes 22 90 25AUG07A 24NOV10
Install Hot/Cold Water Pipes
MBPWB180G Pressure Test Water pipe line 8 85 13MAR10A 25NOV10
Pressure Test Water pipe line
MBWB190G FCU condensate drain 12 70 15MAY10A 02DEC10
FCU condensate drain
MBPWB140G Tag Water Pipes line 7 0 16DEC10 23DEC10
Tag Water Pipes line

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 43 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
First Floor Tower
MBMP1100FA Sleeves Mech. in Celing Slab 5 100 02DEC06A 06DEC06A
Sleeves Mech. in Celing Slab
MBMP1100FC Sleeves Mech. in Ceiling Slab 5 100 17DEC06A 21DEC06A
Sleeves Mech. in Ceiling Slab
MBMP1100FB Sleeves Mech in Ceiling Slab 5 100 10JAN07A 15JAN07A
Sleeves Mech in Ceiling Slab
MBPWB160F Install Hot/Cold Water Pipes 15 100 16JAN08A 09MAR10A
Install Hot/Cold Water Pipes
MBPWB190F FCU condensate drain 30 100 19NOV09A
FCU condensate drain
MBPWB180F Pressure Test Water pipe line 8 90 10APR10A 23NOV10
Pressure Test Water pipe line
MBPWB135F Tag Hot/Cold Water Pipes line 7 0 02DEC10 09DEC10
Tag Hot/Cold Water Pipes line

Second Floor Tower


MBMP1100SA Sleeves Mech. in Ceiling Slab 5 100 24JAN07A 29JAN07A
Sleeves Mech. in Ceiling Slab
MBMP1100SC Sleeves Mech. in Ceiling Slab 5 100 10FEB07A 14FEB07A
Sleeves Mech. in Ceiling Slab
MBMP1100SB Sleeves Mech. in Ceiling Slab 5 100 26FEB07A 03MAR07A
Sleeves Mech. in Ceiling Slab
MBPWB160S Install Hot/Cold Water Pipes 15 100 02APR08A 08MAR10A
Install Hot/Cold Water Pipes
MBPWB190S FCU Condensate Drain 30 100 16NOV09A
FCU Condensate Drain
MBPWB180S Pressure Test Water pipe line 8 95 03APR10A 22NOV10
Pressure Test Water pipe line
MBPWB195S Tag Hot/Cold Water Pipes line 7 0 18DEC10 25DEC10
Tag Hot/Cold Water Pipes line

Third Floor Tower


MBMP1100TA Sleeves Mech. in Ceiling Slab 5 100 13MAR07A 18MAR07A
Sleeves Mech. in Ceiling Slab
MBMP1100TC Sleeves Mech in Ceiling Slab 5 100 22MAR07A 27MAR07A
Sleeves Mech in Ceiling Slab
MBMP1100TB Sleeves Mech. in Ceiling Slab 5 100 05APR07A 10APR07A
Sleeves Mech. in Ceiling Slab
MBPWB160T Install Hot/Cold Water Pipes 12 100 13MAR08A 08MAR10A
Install Hot/Cold Water Pipes
MBPWB190T FCU condensate drain 30 100 17DEC09A 10MAR10A
FCU condensate drain
MBPWB180T Pressure Test Water pipe line 10 95 25MAR10A 23NOV10
Pressure Test Water pipe line
MBPWB195T Tag Hot/Cold Water Pipes line 7 0 09DEC10 16DEC10
Tag Hot/Cold Water Pipes line

Fourth Floor Tower


MBMP11004C Sleeves Mech. in Ceiling Slab 5 100 03MAY07A 08MAY07A
Sleeves Mech. in Ceiling Slab

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 44 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBMP11004A Sleeves Mech. in Ceiling Slab 5 100 08MAY07A 13MAY07A
Sleeves Mech. in Ceiling Slab
MBPWB160R Install Hot/Cold Water Pipes 15 100 29MAR08A 07MAR10A
Install Hot/Cold Water Pipes
MBMP11004B Sleeves Mech in Ceiling Slab 5 100 17APR08A 22APR08A
Sleeves Mech in Ceiling Slab
MBPWB190R FCU condensate drain 30 100 16NOV09A
FCU condensate drain
MBPWB180R Pressure Test Water pipe line 8 95 12MAR10A 22NOV10
Pressure Test Water pipe line
MBPWB195R Tag Hot/Cold Water Pipes line 7 0 01DEC10 08DEC10
Tag Hot/Cold Water Pipes line

Pent House
MBMP1100RF Sleeves Mech in Ceiling Slab 5 100 08JUL07A 06SEP08A
Sleeves Mech in Ceiling Slab
MBPWB160P Install Hot/Cold Water Pipes 12 100 10JUL09A 07MAR10A
Install Hot/Cold Water Pipes
MBPWB180P Pressure Test Water pipe line 8 100 21DEC09A 23MAR10A
Pressure Test Water pipe line
MBPWB190P FCU condensate drain 12 20 06OCT10A 20DEC10
FCU condensate drain
MBPWB195P Tag Hot/Cold Water Pipes line 7 0 23NOV10 30NOV10
Tag Hot/Cold Water Pipes line

Tower Ground Floor-Finishes


MBPWB100G Abv Ceiling Drainage Pipes 24 100 16JUN07A 18NOV07A
Abv Ceiling Drainage Pipes
MBPWB120G Test Abv Clng Drainage Pipes 3 100 08JAN10A 10MAR10A
Test Abv Clng Drainage Pipes

Tower First Floor-Finishes


MBPWB100F Abv Cieling Drainage Pipes 24 100 07AUG07A 19JAN08A
Abv Cieling Drainage Pipes
MBPWB120F Test Abv Clng Drainage Pipes 3 100 12JAN08A 22JAN08A
Test Abv Clng Drainage Pipes

Tower Second Floor-Finishes


MBPWB100S Abv Cieling Drainage Pipes 24 100 04OCT07A 13MAR08A
Abv Cieling Drainage Pipes
MBPWB120S Test Abv Clng Drainage Pipes 3 100 26MAY08A 07JUN08A
Test Abv Clng Drainage Pipes

Tower Third Floor- Finishes


MBPWB100T Abv Cieling Drainage Pipes 24 100 17JAN08A 10JUN08A
Abv Cieling Drainage Pipes
MBPWB120T Test Abv Clng Drainage Pipes 3 100 08JUN08A 25JUN08A
Test Abv Clng Drainage Pipes

Tower Fourth Floor-Finishes


MBPWB100R Abv Ceiling Drainage Pipes 24 100 03APR08A 25JUN08A
Abv Ceiling Drainage Pipes

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 45 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBPWB120R Test Abv Clng Drainage Pipes 3 100 26JUN08A 03JUL08A
Test Abv Clng Drainage Pipes

TOWER BUILDING
MBDFR1200 Vanity Counter Tops 30 0 18JAN11 21FEB11
Vanity Counter Tops

Grnd. Floor "4A - 7A"Rear Bldg Works


MBP0700G Install U/Grnd Drainage Pipes 12 100 25JUN07A 08JUL07A
Install U/Grnd Drainage Pipes
MBP0705G Test Drainage Pipes U/Grnd 3 100 09JUL07A 11JUL07A
Test Drainage Pipes U/Grnd
MBM0995E Sleeves Mech. Susp. Slab 4 100 21AUG07A 11SEP07A
Sleeves Mech. Susp. Slab

First Floor "4A - 7A" Rear Bldg Works


MBBM1010G Sleeves Mech. Susp Slab 4 100 29OCT07A 24NOV07A
Sleeves Mech. Susp Slab

Grnd Floor "5B - 6B" Rear Bldg Works


MBMP1050GD Install U/ Gr Drainage Pipes 12 100 28AUG07A 24NOV07A
Install U/ Gr Drainage Pipes
MBP1050F Test U/ Grnd Drainage Pipe 62 100 11SEP07A 21NOV07A
Test U/ Grnd Drainage Pipe
MBP2000GFG Sleeves Mech Ceiling Slab GF 4 100 03DEC07A 26DEC07A
Sleeves Mech Ceiling Slab GF
MBMP1250GD Install Above Ceiling Drainage Pipe 20 100 23FEB08A 09MAR10A
Install Above Ceiling Drainage Pipe
MBMP1200GD Install Hot/Cold Water Pipe 26 95 24MAR08A 23NOV10
Install Hot/Cold Water Pipe
MBMP1210GD Pressure Test Hot/Cold Water Pipes 8 75 01APR10A 24NOV10
Pressure Test Hot/Cold Water Pipes
MBMP1260GD Test Drainage Pipes Above Ceiling 6 90 19APR10A 23NOV10
Test Drainage Pipes Above Ceiling
MBMPR190G FCU condensate drain 12 90 14SEP10A 25NOV10
FCU condensate drain
MBMP1215GD Insulate Hot Water Pipe 9 0 23NOV10 02DEC10
Insulate Hot Water Pipe
MBMP1212GD Chlorine Disnf Hot/Cold Watr Pipe 7 0 25NOV10 02DEC10
Chlorine Disnf Hot/Cold Watr Pipe
MBMP1216GD Tag Hot/Cold Water Pipes 7 0 04DEC10 11DEC10
Tag Hot/Cold Water Pipes

First Floor "5B - 6B" Rear Bldg Works


MBP18000G Sleeves Mech. Susp. Slab 4 100 19APR08A 22APR08A
Sleeves Mech. Susp. Slab
MBPGF100 Install Hot/Cold Water Pipe 20 100 11JUN08A 09MAR10A
Install Hot/Cold Water Pipe
MBMP190 FCU condensate drain 12 80 14APR10A 29NOV10
FCU condensate drain
MBPGF120 Pressure Test Hot/Cold Water Pipes 8 75 19MAY10A 24NOV10
Pressure Test Hot/Cold Water Pipes

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 46 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBPGF130 Insulate Hot Water Pipe 9 0 23NOV10 02DEC10
Insulate Hot Water Pipe
MBPGF125 Chlorine Disnf Hot/Cold Watr Pipe 7 0 25NOV10 02DEC10
Chlorine Disnf Hot/Cold Watr Pipe
MBPGF135 Tag Hot/Cold Water Pipes line 7 0 12DEC10 19DEC10
Tag Hot/Cold Water Pipes line

Grnd Floor "4B - 5A" Rear Bldg Works


MBP0750E Install U/Grnd Drainage Pipes 12 100 11DEC07A 06JUL08A
Install U/Grnd Drainage Pipes
MBP0760E Test U/Grnd Drainage Pipes 3 100 30DEC07A 07JUN08A
Test U/Grnd Drainage Pipes
MBM0900E Sleeves Mech. Susp. Slab 4 100 26FEB08A 21AUG08A
Sleeves Mech. Susp. Slab

First Floor "4B - 5A" Rear Bldg Works


MBP18010E Sleeve Mech Susp Slab 4 100 09JUL08A 22SEP08A
Sleeve Mech Susp Slab

Grnd Floor "6A - 7B" Rear Bldg Works


MBMP1055GD U/ Grnd Drainage Pipes 12 100 02JAN08A 18SEP08A
U/ Grnd Drainage Pipes
MBP1055D Test U/Grnd Drainage Pipes 3 100 14JAN08A 20SEP08A
Test U/Grnd Drainage Pipes
MBBP2005GD Sleeves Mech in Ceiling Slab 4 100 26FEB08A 21NOV08A
Sleeves Mech in Ceiling Slab
MBPED100G Drainage Pipes Above Ceiling 26 100 21APR08A 10MAR10A
Drainage Pipes Above Ceiling
MBGPGF100 Install Hot/Cold Water Pipe 24 100 24JUN08A 09MAR10A
Install Hot/Cold Water Pipe
MBGPGF120 Pressure Test Hot/Cold Water Pipes 8 70 06MAR10A 24NOV10
Pressure Test Hot/Cold Water Pipes
MBPED120G Test Pipes Draining Above Ceiling 50 100 10APR10A 16SEP10A
Test Pipes Draining Above Ceiling
MBGPGF130 Insulate Hot Water Pipe 9 0 23NOV10 02DEC10
Insulate Hot Water Pipe
MBPGF190 FCU condensate drain 12 90 23NOV10 25NOV10
FCU condensate drain
MBGPGF132 Chlorine Disnf Hot/Cold Watr Pipe 7 0 25NOV10 02DEC10
Chlorine Disnf Hot/Cold Watr Pipe
MBGPGF135 Tag Hot/Cold Water Pipes line 7 0 20DEC10 27DEC10
Tag Hot/Cold Water Pipes line

First Floor "6A - 7B" Rear Bldg Works


MBBP2000DE Sleeve Mech Clng Slab 4 100 09JUL08A 11JUN09A
Sleeve Mech Clng Slab
MBFPGF100 Install Hot/Cold Water Pipe 18 90 23AUG09A 24NOV10
Install Hot/Cold Water Pipe
MBFPGF120 Pressure Test Hot/Cold Water Pipes 8 70 13JUN10A 24NOV10
Pressure Test Hot/Cold Water Pipes
MBGPF190F FCU condensate drain 12 80 25SEP10A 29NOV10
FCU condensate drain

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 47 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBFPGF125 Insulate Hot Water Pipe 9 0 23NOV10 02DEC10
Insulate Hot Water Pipe
MBFPGF130 Chlorine Disnf Hot/Cold Watr Pipe 7 0 25NOV10 02DEC10
Chlorine Disnf Hot/Cold Watr Pipe
MBFPGF135 Tag Hot/Cold Water Pipes line 7 0 28DEC10 04JAN11
Tag Hot/Cold Water Pipes line

Fire Fighting Works


Basement Floor
MBPWB500 Install Fire Fighting Network 59 90 09JUL09A 29NOV10
Install Fire Fighting Network
MBPWB550 Painting Fire Water Pipes 9 50 26MAY10A 30NOV10
Painting Fire Water Pipes
MBPWB520 Press. Test Fire Fight. Network 7 30 30OCT10A 24NOV10
Press. Test Fire Fight. Network
MBPWB570 Tagging Fire Water Pipes 7 0 01DEC10 08DEC10
Tagging Fire Water Pipes

Ground Floor Tower


MBPWB500G Install Fire Fighting Network 60 95 12AUG07A 25NOV10
Install Fire Fighting Network
MBPWB535G Painting Fire Water Pipes 7 50 12AUG07A 27NOV10
Painting Fire Water Pipes
MBPWB520G Press. Test Fire Fight. Network 7 60 25SEP10A 01DEC10
Press. Test Fire Fight. Network
MBPWB536G Tagging of Fire Water Pipes 7 0 28NOV10 05DEC10
Tagging of Fire Water Pipes

First Floor Tower


MBPWB500F Install Fire Fighting Network 25 100 08MAY09A 10MAR10A
Install Fire Fighting Network
MBPWB535F Painting Fire Water Pipes 7 50 27MAR10A 24NOV10
Painting Fire Water Pipes
MBPWB520F Press. Test Fire Fight. Network 3 100 24APR10A 19SEP10A
Press. Test Fire Fight. Network
MBPWB536F Tagging of Fire Water Pipes 7 0 25NOV10 02DEC10
Tagging of Fire Water Pipes

Second Floor Tower


MBPWB500S Install Fire Fighting Network 25 100 08MAR09A 10MAR10A
Install Fire Fighting Network
MBPWB535S Painting Fire Water Pipes 7 95 01MAR10A 22NOV10
Painting Fire Water Pipes
MBPWB520S Press. Test Fire Fight. Network 3 100 22MAR10A 19SEP10A
Press. Test Fire Fight. Network
MBPWB536S Tagging of Fire Water Pipes 7 0 23NOV10 30NOV10
Tagging of Fire Water Pipes

Third Floor Tower


MBPWB500T Install Fire Fighting Network 25 100 08MAR09A 10MAR10A
Install Fire Fighting Network

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 48 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBPWB535T Painting Fire Water Pipes 3 100 09MAR10A 19SEP10A
Painting Fire Water Pipes
MBPWB520T Press. Test Fire Fight. Network 3 100 27MAR10A 18SEP10A
Press. Test Fire Fight. Network
MBPWB536T Tagging of Fire Water Pipes 7 0 23NOV10 30NOV10
Tagging of Fire Water Pipes

Fourth Floor Tower


MBPWB500R Install Fire Fighting Network 25 100 09SEP09A 10MAR10A
Install Fire Fighting Network
MBPWB535R Painting Fire Water Pipes 20 100 20JAN10A 10JUL10A
Painting Fire Water Pipes
MBPWB520R Press. Test Fire Fight. Network 3 100 20MAR10A 19SEP10A
Press. Test Fire Fight. Network
MBPWB536R Tagging of Fire Water Pipes 7 0 23NOV10 30NOV10
Tagging of Fire Water Pipes

Pent House
MBPWB500P Install Fire Fighting Network 12 95 08NOV09A 23NOV10
Install Fire Fighting Network
MBPWB520P Press. Test Fire Fight. Network 3 100 20APR10A 19SEP10A
Press. Test Fire Fight. Network
MBPWB535P Painting Fire Water Pipes 7 50 20MAY10A 24NOV10
Painting Fire Water Pipes
MBPWB536P Tagging of Fire Water Pipes 7 0 25NOV10 02DEC10
Tagging of Fire Water Pipes

Grnd Floor "5B - 6B" Rear Bldg Works


MBMP2000GD Install Fire Fighting Network 35 75 02DEC09A 02DEC10
Install Fire Fighting Network
MBMP2160GD Painting Fire Water Pipes 7 65 18APR10A 04DEC10
Painting Fire Water Pipes
MBMP2100GD Press. Test Fire Fight. Network 7 30 31OCT10A 24NOV10
Press. Test Fire Fight. Network
MBMP2170GD Tagging of Fire Water Pipes 7 0 12DEC10 19DEC10
Tagging of Fire Water Pipes

First Floor "5B - 6B" Rear Bldg Works


MBPGF200 Install Fire Fighting Network 35 95 02OCT09A 24NOV10
Install Fire Fighting Network
MBPGF235 Painting Fire Water Pipes 7 65 24APR10A 25NOV10
Painting Fire Water Pipes
MBPGF220 Press. Test Fire Fight. Network 7 0 25NOV10 02DEC10
Press. Test Fire Fight. Network
MBPGF236 Tagging of Fire Water Pipes 7 0 20DEC10 27DEC10
Tagging of Fire Water Pipes

Grnd Floor "6A - 7B" Rear Bldg Works


MBGPGF200 Install Fire Fighting Network 28 100 03NOV08A 10MAR10A
Install Fire Fighting Network
MBGPGF235 Painting Fire Water Pipes 7 60 12MAY10A 23NOV10
Painting Fire Water Pipes

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 49 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBGPGF220 Press. Test Fire Fight. Network 7 30 31OCT10A 24NOV10
Press. Test Fire Fight. Network
MBGPGF236 Tagging of Fire Water Pipes 7 0 28DEC10 04JAN11
Tagging of Fire Water Pipes

First Floor "6A - 7B" Rear Bldg Works


MBFPGF200 Install Fire Fighting Pipes 35 50 01AUG09A 13DEC10
Install Fire Fighting Pipes
MBFPGF235 Painting Fire Water Pipes 7 65 26APR10A 23NOV10
Painting Fire Water Pipes
MBFPGF220 Press. Test Fire Fight. Network 7 0 14DEC10 21DEC10
Press. Test Fire Fight. Network
MBFPGF236 Tagging of Fire Water Pipes 7 0 05JAN11 12JAN11
Tagging of Fire Water Pipes

Medical Gases Works


First Floor Tower
MBPWB700F Install Med Gases Fixtures 18 75 01NOV09A 28NOV10
Install Med Gases Fixtures

Second Floor Tower


MBPWB740S Install Med Gases Fixtures 18 75 02JAN10A 28NOV10
Install Med Gases Fixtures

Third Floor Tower


MBPWB720T Install Med Gases Fixtures 18 75 23NOV10 28NOV10
Install Med Gases Fixtures

Fourth Floor Tower


MBPWB700R Install Med Gases Fixtures 18 75 15FEB10A 28NOV10
Install Med Gases Fixtures

Grnd Floor "5B - 6B" Rear Bldg Works


MBP6100 Install Med Gases Fixtures 18 75 01APR10A 28NOV10
Install Med Gases Fixtures

First Floor "5B - 6B" Rear Bldg Works


MBPGF500 Install Med Gases Fixtures 18 90 30AUG09A 24NOV10
Install Med Gases Fixtures

Grnd Floor "6A - 7B" Rear Bldg Works


MBGPGF500 Install Med Gases Fixtures 18 75 08SEP09A 28NOV10
Install Med Gases Fixtures

First Floor "6A - 7B" Rear Bldg Works


MBFPGF300 Install Med Gases Fixtures 18 90 21SEP09A 24NOV10
Install Med Gases Fixtures

LPG Works
Ground Floor Tower
MBPWB220G Install LPG Gas Pipes /valves 15 0 23NOV10 09DEC10
Install LPG Gas Pipes /valves
MBWB800G Install LPG tank (External) 10 0 28DEC10 08JAN11
Install LPG tank (External)

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 50 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBPWB240G Press Test LPG Gas Pipes 3 0 09JAN11 11JAN11
Press Test LPG Gas Pipes

First Floor Tower


MBPWB400T Install LPG Gas piping valves 5 0 20FEB11 24FEB11
Install LPG Gas piping valves

Grnd Floor "5B - 6B" Rear Bldg Works


MBMP1270GD Install LPG Gas Pipes 10 0 25NOV10 06DEC10
Install LPG Gas Pipes
MBPGF100G Test LPG Gas Pipes 3 0 07DEC10 09DEC10
Test LPG Gas Pipes

Grnd Floor "6A - 7B" Rear Bldg Works


MBGPGF140 Install LPG Gas Pipes 10 0 25NOV10 06DEC10
Install LPG Gas Pipes
MBGPGF160 Test LPG Gas Pipes 3 0 07DEC10 09DEC10
Test LPG Gas Pipes

Elec- Mechanical Works


Basement Floor
MBPWB540 Install FHC 5 90 20JAN10A 22NOV10
Install FHC
MBPWB560 Fix Fire Sprinklers 15 0 19FEB11 07MAR11
Fix Fire Sprinklers
MBPWB420 Install sanitary Fixtures 15 0 02MAY11 18MAY11
Install sanitary Fixtures
MBHWB400 Install Air Supply Diffuser /return 15 0 30MAY11 15JUN11
Install Air Supply Diffuser /return
MBFMW500 Fix exhaust Grills 10 0 16JUN11 27JUN11
Fix exhaust Grills

Ground Floor Tower


MBPWB540G Install FHC 5 90 06JAN10A 22NOV10
Install FHC
MBPWB560G Fix Fire Sprinklers 15 0 12FEB11 28FEB11
Fix Fire Sprinklers
MBPWB420G Install sanitary Fixtures 15 0 14APR11 01MAY11
Install sanitary Fixtures
MBHWB400G Install Air Supply Diff. /return 15 0 01MAY11 17MAY11
Install Air Supply Diff. /return
MBHWB420G Fix exhaust Grills 10 0 18MAY11 29MAY11
Fix exhaust Grills

First Floor Tower


MBPWB540F Install FHC 3 100 12JAN10A 22OCT10A
Install FHC
MBPWB560F Fix Fire Sprinklers 10 0 31JAN11 10FEB11
Fix Fire Sprinklers
MBPWB420F Install sanitary Fixtures 15 0 27FEB11 15MAR11
Install sanitary Fixtures
MBHWB400F Install Air Supply Diff. /return 15 0 02APR11 18APR11
Install Air Supply Diff. /return

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 51 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBHWB420F Fix exhaust Grills 10 0 19APR11 30APR11
Fix exhaust Grills

Second Floor Tower


MBPWB540S Install FHC 6 100 20JAN10A 23OCT10A
Install FHC
MBPWB420S Install sanitary Fixtures 15 0 29NOV10 15DEC10
Install sanitary Fixtures
MBPWB560S Fix Fire Sprinklers 15 0 22JAN11 07FEB11
Fix Fire Sprinklers
MBHWB400S Install Air Supply Diff. /return 15 0 03MAR11 20MAR11
Install Air Supply Diff. /return
MBHWB420S Fix exhaust Grills 10 0 21MAR11 31MAR11
Fix exhaust Grills

Third Floor Tower


MBPWB540T Install FHC 6 100 01FEB10A 18OCT10A
Install FHC
MBPWB420T Install sanitary Fixtures 15 0 11DEC10 27DEC10
Install sanitary Fixtures
MBPWB560T Fix Fire Sprinklers 15 0 13JAN11 30JAN11
Fix Fire Sprinklers
MBHWB400T Install Air Supply Diff. /return 15 0 02FEB11 19FEB11
Install Air Supply Diff. /return
MBHWB420T Fix exhaust Grills 10 0 20FEB11 02MAR11
Fix exhaust Grills

Fourth Floor Tower


MBPWB540R Install FHC 6 100 06FEB10A 09SEP10A
Install FHC
MBPWB420R Install sanitary Fixtures 15 0 23NOV10 09DEC10
Install sanitary Fixtures
MBPWB560R Fix Fire Sprinklers 15 0 03JAN11 19JAN11
Fix Fire Sprinklers
MBHWB400R Install Air Supply Diff. /return 15 0 04JAN11 20JAN11
Install Air Supply Diff. /return
MBHWB420R Fix exhaust Grills 10 0 22JAN11 01FEB11
Fix exhaust Grills

Pent House
MBPWB540P Install FHC 1 100 09FEB10A 19JUL10A
Install FHC
MBPWB560P Fix Fire Sprinklers 6 0 13DEC10 19DEC10
Fix Fire Sprinklers
MBHWB400P Install Air Supply Diff. /return 6 0 23DEC10 29DEC10
Install Air Supply Diff. /return
MBPWB420P Install sanitary Fixtures 7 0 27DEC10 03JAN11
Install sanitary Fixtures
MBHWB420P Fix exhaust Grills 4 0 30DEC10 03JAN11
Fix exhaust Grills

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 52 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
Grnd Floor "5B - 6B" Rear Bldg Works
MBMH4000GD Install Air Supply Diff. /return 16 0 03JAN11 20JAN11
Install Air Supply Diff. /return
MBMPNG Fix Fire Sprinklers 16 0 27JAN11 14FEB11
Fix Fire Sprinklers
MBP6380 Fix Bed Head Units 15 0 09MAR11 26MAR11
Fix Bed Head Units
MBMP3000GD Install Sanitary Fixtures 16 0 10MAR11 28MAR11
Install Sanitary Fixtures
MBMH4100GD Fix exhaust Grills 8 0 31MAY11 08JUN11
Fix exhaust Grills

First Floor "5B - 6B" Rear Bldg Works


MBPGF705 Fix FHC 6 90 08FEB10A 23NOV10
Fix FHC
MBPGF660 Install Sanitary Fixtures 16 0 13DEC10 30DEC10
Install Sanitary Fixtures
MBPGF240 Fix Fire Sprinklers 16 0 27JAN11 14FEB11
Fix Fire Sprinklers
MBPGF620 Install Air Supply Diff. /return 16 0 03FEB11 21FEB11
Install Air Supply Diff. /return
MBPGF640 Fix exhaust Grills 8 0 03APR11 11APR11
Fix exhaust Grills

Grnd Floor "6A - 7B" Rear Bldg Works


MBGPGF705 Fix FHC 6 90 15FEB10A 23NOV10
Fix FHC
MBGPGF240 Fix Fire Sprinklers 16 0 01FEB11 19FEB11
Fix Fire Sprinklers
MBGPGF660 Install Sanitary Fixtures 16 0 17MAR11 04APR11
Install Sanitary Fixtures
MBGPGF620 Install Air Supply Diff. /return 16 0 03MAY11 21MAY11
Install Air Supply Diff. /return
MBGPGF640 Fix exhaust Grills 8 0 22MAY11 30MAY11
Fix exhaust Grills

First Floor "6A - 7B" Rear Bldg Works


MBFPGF705 Fix FHC 6 90 25FEB10A 22NOV10
Fix FHC
MBFPGF660 Install Sanitary Fixtures 16 0 15DEC10 02JAN11
Install Sanitary Fixtures
MBFPGF240 Fix Fire Sprinklers 16 0 06FEB11 23FEB11
Fix Fire Sprinklers
MBFPGF620 Install Air Supply Diff. /return 16 0 05APR11 23APR11
Install Air Supply Diff. /return
MBFPGF640 Fix exhaust Grills 8 0 24APR11 02MAY11
Fix exhaust Grills

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 53 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Specialties
Basement Floor
MBFWB265 Fix Toilet Accessories 20 0 02MAY11 24MAY11
Fix Toilet Accessories

Ground Floor Tower


MBFWB265G Fix Toilet Accessories 20 0 02MAY11 24MAY11
Fix Toilet Accessories

First Floor Tower


MBFW265F Fix Toilet Accesories 20 0 27FEB11 21MAR11
Fix Toilet Accesories

Second Floor Tower


MBFWB265S Fix Toilet Accessories 20 0 29NOV10 21DEC10
Fix Toilet Accessories

Third Floor Tower


MBFWB265T Fix Toilet Accessories 20 10 03JUL10A 13DEC10
Fix Toilet Accessories

Fourth Floor Tower


MBWF735R Fix Toilet Accessories 20 20 09JUN10A 11DEC10
Fix Toilet Accessories

Pent House
MBFWB275P Fix Toilet Accessories 12 0 04JAN11 17JAN11
Fix Toilet Accessories

Grnd Floor "5B - 6B" Rear Bldg Works


MBMP3300GD Fix Toilet Accessories 30 0 10MAR11 13APR11
Fix Toilet Accessories

First Floor "5B - 6B" Rear Bldg Works


MBSGF120 Fix Toilet Accessories 30 0 06JUN11 10JUL11
Fix Toilet Accessories

Grnd Floor "6A - 7B" Rear Bldg Works


MBGSGF120 Fix Toilet Accessories 30 0 31MAY11 04JUL11
Fix Toilet Accessories

First Floor "6A - 7B" Rear Bldg Works


MBFSGF120 Fix Toilet Accessories 30 0 15MAY11 18JUN11
Fix Toilet Accessories

TEST & COMMISSION


TOWER BUILDING
MBFC230 Flush /Cleaning Med. Gas system 10 0 29NOV10 09DEC10
Flush /Cleaning Med. Gas system
MBWM600 Test & Commis. Med. Gas system 12 0 11DEC10 23DEC10
Test & Commis. Med. Gas system
MBFC250 Flush /Cleaning LPG system 10 0 26FEB11 08MAR11
Flush /Cleaning LPG system
MBFC200 Flush /Cleaning Fire Figh. system 12 0 09MAR11 22MAR11
Flush /Cleaning Fire Figh. system

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 54 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBWM500 Test & Commis. LPG system 10 0 09MAR11 20MAR11
Test & Commis. LPG system
MBWM900 Test & Commis. Fire Figh. system 12 0 23MAR11 05APR11
Test & Commis. Fire Figh. system
MBFC220 Flush /Cleaning HVAC system 10 0 13APR11 24APR11
Flush /Cleaning HVAC system
MBFC210 Flush /Cleaning Plumb. system 10 0 25APR11 05MAY11
Flush /Cleaning Plumb. system
MBWM700 Test &Comm. HVAC/ CHW system 12 0 25APR11 08MAY11
Test &Comm. HVAC/ CHW system
MBWM800 Test & Commis. Plumb. system 12 0 07MAY11 19MAY11
Test & Commis. Plumb. system
MBWM950 Test & Balancing of HVAC 12 0 09MAY11 22MAY11
Test & Balancing of HVAC
MBWM400 Test & Commis. AHU 12 0 23MAY11 05JUN11
Test & Commis. AHU

REAR BUILDING
MBMP855 Flush/Cleaning Chilled W. Pipe 10 0 28NOV10 08DEC10
Flush/Cleaning Chilled W. Pipe
MBMG100 Flush /Cleaning Med. Gas system 10 0 29NOV10 09DEC10
Flush /Cleaning Med. Gas system
MBMG110 Test & Commis. Med. Gas system 12 0 11DEC10 23DEC10
Test & Commis. Med. Gas system
MBMP865 Flush/Cleaning Fire Fighting. Pipe 10 0 14DEC10 25DEC10
Flush/Cleaning Fire Fighting. Pipe
MBMP875 Flush/Cleaning Potable Water. Pipe 10 0 26DEC10 05JAN11
Flush/Cleaning Potable Water. Pipe
MBMP9000 Test Comm. Plumbing Works 12 0 27JAN11 09FEB11
Test Comm. Plumbing Works
MBMH9000 Test & Comm. Mechanical Works 12 0 04JUN11 16JUN11
Test & Comm. Mechanical Works

ELECTRICAL WORKS
Elec. Materials Submittal

MBEW1010E Get Appr Earthing&Lightning Sys 6 100 02FEB10A 02MAR10A


Get Appr Earthing&Lightning Sys
MBEW1600E Get Appvl.Transformer 6 100 02FEB10A 02MAR10A
Get Appvl.Transformer
MBEW1900E Get App.Bus Bar 6 100 02FEB10A 02MAR10A
Get App.Bus Bar
MBEW2350E Get App. UPS Sys. 6 100 02FEB10A 02MAR10A
Get App. UPS Sys.
MBEW2500E Get App. Sub Dist.Panel 6 100 02FEB10A 02MAR10A
Get App. Sub Dist.Panel
MBEW2800E Get App. PABX Panel 6 100 02FEB10A 02MAR10A
Get App. PABX Panel

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 55 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBEW3250E Get App. MDB 6 100 02FEB10A 02MAR10A
Get App. MDB
MBEW3400E Get App. Public Addr.System 6 100 02FEB10A 02MAR10A
Get App. Public Addr.System
MBEW3550E Get App. MATV System(Master Antena Television) 6 100 02FEB10A 02MAR10A
Get App. MATV System(Master Antena Television)
MBEW3700E Get Appvl. CCTV Sys.(Closed Cercuit T.V) 6 100 02FEB10A 02MAR10A
Get Appvl. CCTV Sys.(Closed Cercuit T.V)
MBEW3850E Get Aprovl. Light Fixtures 6 100 02FEB10A 02MAR10A
Get Aprovl. Light Fixtures
MBEW4000E Get App.Receptcls.& Switch 6 100 02FEB10A 02MAR10A
Get App.Receptcls.& Switch
MBEW4150E Get App. Fire Alarm System 20 100 02FEB10A 02MAR10A
Get App. Fire Alarm System
MBEW5000E Get Aprovel Generator 6 100 02FEB10A 02MAR10A
Get Aprovel Generator
MBEW6010E Get Appvl.Surgical Facility Panel(SFP) 6 100 02FEB10A 02MAR10A
Get Appvl.Surgical Facility Panel(SFP)
MBEW6050E Get Aproval Switch Gear (Medium Volatage) 6 100 02FEB10A 02MAR10A
Get Aproval Switch Gear (Medium Volatage)
MBEW6060E Get Appvl. Isolation panels 6 100 02FEB10A 02MAR10A
Get Appvl. Isolation panels
MBEW7010E Get Appvl.Data System 12 100 02FEB10A 02MAR10A
Get Appvl.Data System
MBEW7060E Get Appvl. Low Current Cables 6 100 02FEB10A 02MAR10A
Get Appvl. Low Current Cables
MBEW8000E Get Appvl. Disconect Switches 6 100 02FEB10A 02MAR10A
Get Appvl. Disconect Switches
MBEW8005E Get Appvl. Access Card System 6 100 02FEB10A 02MAR10A
Get Appvl. Access Card System
MBEW8065E Get Appvl. Clock System 6 100 02FEB10A 02MAR10A
Get Appvl. Clock System
MBEW9020E Get Appvl. Site Lighting Fixture 6 100 02FEB10A 02MAR10A
Get Appvl. Site Lighting Fixture
MBEW9080E Get Appvl. Nurse Call System 18 100 02FEB10A 02MAR10A
Get Appvl. Nurse Call System
MBEW2020E Get appr Audio & Video sys 18 0 23NOV10 13DEC10
Get appr Audio & Video sys
MBEW8060E Get Appvl. Bed Head Units 21 0 23NOV10 16DEC10
Get Appvl. Bed Head Units

Delivery of Elec. Material

MBEW2000E Delivery of Bus Bar 10 100 02JAN10A 02FEB10A


Delivery of Bus Bar
MBEW2600E Delivery of Sub Dist. Panel 10 100 02MAR10A 02MAR10A
Delivery of Sub Dist. Panel
MBEW3350E Delivery of MDB 10 100 02MAR10A 02MAR10A
Delivery of MDB

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 56 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBEW3500E Delivery Public Addr. Panel 6 100 02MAR10A 02MAR10A
Delivery Public Addr. Panel
MBEW3800E Delivery of CCTV Sys.(Closed Circuit TV) 6 100 02MAR10A 02MAR10A
Delivery of CCTV Sys.(Closed Circuit TV)
MBEW6000E Delievery of Generator 12 100 02MAR10A 02MAR10A
Delievery of Generator
MBEW6020E Delievry Surgical Facility Panel (SFP) 12 100 02MAR10A 02MAR10A
Delievry Surgical Facility Panel (SFP)
MBEW8015E Delievery Access Card System 12 100 02MAR10A 02MAR10A
Delievery Access Card System
MBEW9060E Delievery of light Fixture 60 100 16MAR10A 20MAR10A
Delievery of light Fixture
MBEW2450E Delivery of UPS Sys. 28 100 22MAR10A 22APR10A
Delivery of UPS Sys.
MBEW1700E Delivery of Transformer 60 100 24MAY10A 30MAY10A
Delivery of Transformer
MBEW9090E Delievery Nurse Call System 12 100 15AUG10A 21OCT10A
Delievery Nurse Call System
MBEW4100E Delivery Receptacl & Switch 90 100 17AUG10A 25OCT10A
Delivery Receptacl & Switch
MBEW4250E Delivery.Fire Alarm System 6 100 17AUG10A 29OCT10A
Delivery.Fire Alarm System
MBED1100 Delivery of LV cables 15 90 23AUG10A 24NOV10
Delivery of LV cables
MBEW2900E Delivery of PABX Panel 50 100 23AUG10A 26OCT10A
Delivery of PABX Panel
MBEW7080E Delievery Low Current Cables 20 70 24AUG10A 29NOV10
Delievery Low Current Cables
MBEW3650E Delivery MATV Sys.(Master Antena TV) 45 100 25AUG10A 20OCT10A
Delivery MATV Sys.(Master Antena TV)
MBEW7030E Delievery Data System 12 100 30AUG10A 26OCT10A
Delievery Data System
MBEW8075E Delievery Clock System 10 100 31AUG10A 19OCT10A
Delievery Clock System
MBED1000 Delivery of MV cables 26 0 23NOV10 22DEC10
Delivery of MV cables
MBEW7050E Delievery of Switch Gear (Medium Voltage) 35 0 23NOV10 02JAN11
Delievery of Switch Gear (Medium Voltage)
MBEW8040E Delievery of Disconect Switches 10 0 23NOV10 04DEC10
Delievery of Disconect Switches
MBED3000 Delivery Audio & Video sys 18 0 14DEC10 03JAN11
Delivery Audio & Video sys
MBEW9000E Delievery Bed Head Units 70 0 18DEC10 08MAR11
Delievery Bed Head Units

Electrical works
Ground Floor Tower
MBEGA1000 Fix Conduits in Ceiling Slab 4 100 05OCT06A 09OCT06A
Fix Conduits in Ceiling Slab

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 57 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBME1100GC Fix Conduits CeilingSlab 4 100 21OCT06A 24OCT06A
Fix Conduits CeilingSlab
MBME1100GB Fix Elec Conduits in Ceiling Slab 4 100 09NOV06A 13NOV06A
Fix Elec Conduits in Ceiling Slab

First Floor Tower


MBME1100FA Elec Conduiting in Ceiling Slab 4 100 02DEC06A 05DEC06A
Elec Conduiting in Ceiling Slab
MBME1100FC Elec Conduiting in Ceiling Slab 4 100 17DEC06A 20DEC06A
Elec Conduiting in Ceiling Slab
MBME1100FB Elec Conduiting in Ceiling Slab 4 100 10JAN07A 14JAN07A
Elec Conduiting in Ceiling Slab

Second Floor Tower


MBME1100SA Fix Conduits in Ceiling Slab 5 100 24JAN07A 29JAN07A
Fix Conduits in Ceiling Slab
MBME1100SC Elec Conduiting in Ceiling slab 5 100 10FEB07A 14FEB07A
Elec Conduiting in Ceiling slab
MBME1100SB Elec Conduiting in Ceiling Slab 5 100 26FEB07A 03MAR07A
Elec Conduiting in Ceiling Slab

Third Floor Tower


MBME1100TA Fix Conduits in Ceiling Slab 5 100 13MAR07A 18MAR07A
Fix Conduits in Ceiling Slab
MBME1100TC Elec Conduiting in Ceiling Slab 5 100 22MAR07A 27MAR07A
Elec Conduiting in Ceiling Slab
MBME1100TB Elec Conduiting in Ceiling Slab 5 100 05APR07A 10APR07A
Elec Conduiting in Ceiling Slab

Fourth Floor Tower


MBME11004C Elec Conduiting in Ceiling Slab 5 100 03MAY07A 08MAY07A
Elec Conduiting in Ceiling Slab
MBME11004A Elec Conduiting in Ceiling Slab 5 100 08MAY07A 13MAY07A
Elec Conduiting in Ceiling Slab
MBME11004B Elec Conduiting in Ceiling Slab 5 100 21MAY07A 26MAY07A
Elec Conduiting in Ceiling Slab

Pent House
MBME1100RF Elec. Conduiting in Ceiling Slab 4 100 08JUL07A 07SEP08A
Elec. Conduiting in Ceiling Slab

Tower Basement Floor- Finishes


MBEWB140 Wiring Elec Sockets 8 100 12DEC07A 21MAR10A
Wiring Elec Sockets
MBEWB220 Install F.A Conduit/Wiring 6 100 01MAR08A 23OCT08A
Install F.A Conduit/Wiring
MBEWB100 Conduit Wall All Elec Sys 14 100 08APR08A 21MAR10A
Conduit Wall All Elec Sys
MBEWB120 Install Cable Trays 7 100 08JUL08A 09AUG09A
Install Cable Trays
MBEWB260 Fix Sub Dist Panels 8 100 11NOV08A 23OCT10A
Fix Sub Dist Panels

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 58 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBEWB240 P. A Wiring 4 100 30DEC08A 21MAR10A
P. A Wiring
MBEWB160 Power Cables Puling & Termination 10 90 18JUN09A 23NOV10
Power Cables Puling & Termination
MBEWB450 Instl Bus Bar/Plug-in Units &Riser 6 100 11SEP09A 01FEB10A
Instl Bus Bar/Plug-in Units &Riser
MBEWB180 Fix MDB & termntion work 12 90 17SEP09A 23NOV10
Fix MDB & termntion work
MBEWB200 Data wiring 12 90 06NOV09A 23NOV10
Data wiring
MBEWB210 Telephone Wiring 6 100 16NOV09A 22MAR10A
Telephone Wiring
MBEWB750 FA CP Wiring 4 100 20FEB10A 22MAR10A
FA CP Wiring
MBEWB250 Wiring MATV Systems 12 90 07APR10A 23NOV10
Wiring MATV Systems
MBEWB270 Wiring CCTV systems 8 90 12JUN10A 23NOV10
Wiring CCTV systems
MBEWB800 Data Panel installation 8 0 23NOV10 01DEC10
Data Panel installation
MBEWB920 Clock System installation 10 0 24NOV10 05DEC10
Clock System installation
MBEWB930 Cable Trunking for LC rooms 6 0 24NOV10 30NOV10
Cable Trunking for LC rooms
MBEWB970 Cable Trunking for centeral PABX 6 0 01DEC10 07DEC10
Cable Trunking for centeral PABX
MBEW950 Cable trunking in PA box room 6 0 08DEC10 14DEC10
Cable trunking in PA box room
MBEWB710 Fiber Optic cables 10 0 19DEC10 29DEC10
Fiber Optic cables
MBME280B BMS (Conduit / Wiring) 10 0 23JAN11 02FEB11
BMS (Conduit / Wiring)

Tower Ground Floor-Finishes


MBEWB100G Conduit Wall All Elec Sys 14 100 07JUL07A 02JAN08A
Conduit Wall All Elec Sys
MBEWB120G Install Cable Trays 14 100 16JUL07A 10JUL08A
Install Cable Trays
MBEWB140G Wiring Elec Sockets 8 100 23JUL07A 06DEC07A
Wiring Elec Sockets
MBEWB175 Fix Sub Dist. Panels 9 100 18AUG08A 24AUG08A
Fix Sub Dist. Panels
MBEWB220G Fire Alarm System wiring 10 90 27SEP08A 23NOV10
Fire Alarm System wiring
MBEWB240G Install Public Address system wiring 10 90 30DEC08A 23NOV10
Install Public Address system wiring
MBEWB160G Powr Cables puling &Termntion 10 100 12JUN09A 22MAR10A
Powr Cables puling &Termntion
MBEWB260G Fix Conduits/Wiring 8 100 13JUL09A 16OCT09A
Fix Conduits/Wiring

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 59 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBEWB450G Install Bus Bar/Plug-in Units&Termination 8 100 16OCT09A 22MAR10A
Install Bus Bar/Plug-in Units&Termination
MBEWB650G Clock System 10 90 02NOV09A 23NOV10
Clock System
MBEWB180G Fix MDB & termination work 8 100 17NOV09A 22MAR10A
Fix MDB & termination work
MBEWB411 Data system wiring 10 90 24NOV09A 23NOV10
Data system wiring
MBEWB200G Tel System wiring 10 90 17DEC09A 23NOV10
Tel System wiring
MBEWB255 MATV System wiring 10 90 02FEB10A 23NOV10
MATV System wiring
MBEWB412 CCTV System wiring 7 90 27FEB10A 23NOV10
CCTV System wiring
MBEWB442 Wire pulling in conference room 7 70 22SEP10A 23NOV10
Wire pulling in conference room
MBEWB410 Wall trunking in LC rooms 7 0 24NOV10 01DEC10
Wall trunking in LC rooms
MBEWB432 Fixing conduit in Confrence room 7 0 24NOV10 01DEC10
Fixing conduit in Confrence room
MBEWB452 Instl. Audio& Video system in confrence room 7 0 24NOV10 01DEC10
Instl. Audio& Video system in confrence room
MBEWB462 Instl. projector in conference room 3 0 02DEC10 05DEC10
Instl. projector in conference room
MBME280G BMS (Conduit / Wiring) 10 0 11JAN11 22JAN11
BMS (Conduit / Wiring)

Tower First Floor-Finishes


MBEWB100F Conduit Wall All Elec Sys 14 100 18JUL07A 20NOV07A
Conduit Wall All Elec Sys
MBEWB140F Elect wiring Sockets 8 100 01AUG07A 20NOV07A
Elect wiring Sockets
MBEWB120F Install Cable Trays 10 100 28AUG07A 04NOV07A
Install Cable Trays
MBEWB175F Fix Dist. Panels 9 100 04AUG08A 13AUG08A
Fix Dist. Panels
MBEWB220F Fire Alarm System Wiring 4 100 17AUG08A 20AUG08A
Fire Alarm System Wiring
MBEWB240F Install Public Address system wiring 10 90 23DEC08A 23NOV10
Install Public Address system wiring
MBEWB160F Power Cables Pulling & Termntion 10 100 12JUL09A 22MAR10A
Power Cables Pulling & Termntion
MBEWB180F Fix MDB & termination work 8 100 25AUG09A 22MAR10A
Fix MDB & termination work
MBEWB450F Install Bus Bar/Plug-in Units&Termination 8 100 02NOV09A 22MAR10A
Install Bus Bar/Plug-in Units&Termination
MBEW300F Data system wiring 10 90 01DEC09A 23NOV10
Data system wiring
MBEWB650F Clock System wiring 7 90 18DEC09A 22NOV10
Clock System wiring

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 60 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBEWB200F Tel System Wiring 8 90 19DEC09A 23NOV10
Tel System Wiring
MBWB255F MATV System wiring 8 90 03FEB10A 23NOV10
MATV System wiring
MBEW300F10 CCTV Sys wiring 5 90 01MAR10A 23NOV10
CCTV Sys wiring
MBME270FF Nurse call Wiring 8 70 25OCT10A 24NOV10
Nurse call Wiring
MBME290FF BHU wiring 8 0 25NOV10 04DEC10
BHU wiring
MBEWB110F Wall trunking in LC rooms 5 0 05DEC10 09DEC10
Wall trunking in LC rooms
MBME280FF BMS (Conduit / Wiring) 8 0 02JAN11 10JAN11
BMS (Conduit / Wiring)

Tower Second Floor-Finishes


MBEWB100S Conduit Wall All Elec Sys 14 100 06SEP07A 22MAR10A
Conduit Wall All Elec Sys
MBEWB120S Install Cable Trays 10 100 24DEC07A 27MAR08A
Install Cable Trays
MBEWB140S Elect Wiring Sockets 8 100 21JUN08A 26JUN08A
Elect Wiring Sockets
MBEWB175S Fix Dist. Panels 9 100 05AUG08A 16AUG08A
Fix Dist. Panels
MBEWB220S Install F. A Conduits/Wiring 8 90 21AUG08A 23NOV10
Install F. A Conduits/Wiring
MBEWB240S Install Public Address system Wiring 6 90 27DEC08A 23NOV10
Install Public Address system Wiring
MBEW120 Data system wiring 10 90 02NOV09A 23NOV10
Data system wiring
MBEWB450S Install Bus Bar/Plug-in Units&Termination 8 100 17NOV09A 22MAR10A
Install Bus Bar/Plug-in Units&Termination
MBEWB650S Clock System 8 90 18NOV09A 23NOV10
Clock System
MBEWB180S Fix MDB & termination work 8 100 02DEC09A 22MAR10A
Fix MDB & termination work
MBEWB160S Power Cables puling & termntion 6 100 26DEC09A 22MAR10A
Power Cables puling & termntion
MBEWB255S MATV system Wiring 8 90 02FEB10A 23NOV10
MATV system Wiring
MBEW130 CCTV Sys wiring 7 90 27FEB10A 23NOV10
CCTV Sys wiring
MBEWB600S Acces.Con. Conduit/Wiring 8 100 28MAR10A 05APR10A
Acces.Con. Conduit/Wiring
MBME270F2 Nurse call sys Wiring 8 80 21AUG10A 24NOV10
Nurse call sys Wiring
MBEW290 BHU wiring 8 0 25NOV10 04DEC10
BHU wiring
MBEW110 Wall trunking in LC rooms 7 0 11DEC10 18DEC10
Wall trunking in LC rooms

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 61 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBME280F2 BMS (Conduit / Wiring) 8 0 23DEC10 01JAN11
BMS (Conduit / Wiring)

Tower Third Floor- Finishes


MBEWB100T Conduit Wall All Elec Sys 14 100 05JAN08A 10SEP09A
Conduit Wall All Elec Sys
MBEWB120T Install Cable Trays 10 100 04FEB08A 05MAY08A
Install Cable Trays
MBEWB140T Elect Wiring Sockets 8 100 22JUN08A 22MAR10A
Elect Wiring Sockets
MBEWB175T Fix Dist Panels 9 100 07AUG08A 18AUG08A
Fix Dist Panels
MBEWB220T Install F.A. Conduit/Wiring 8 100 26AUG08A 11SEP08A
Install F.A. Conduit/Wiring
MBEWB450T Inst.Bus Bar/Plug-in Units&Termination 8 100 16NOV09A 22MAR10A
Inst.Bus Bar/Plug-in Units&Termination
MBEW220 Data system wiring 10 90 03DEC09A 23NOV10
Data system wiring
MBEWB180T Fix MDB 8 100 03DEC09A 22MAR10A
Fix MDB
MBEWB200T Tel System Wiring 8 90 13DEC09A 23NOV10
Tel System Wiring
MBEWB650T Clock System wiring 8 90 16DEC09A 23NOV10
Clock System wiring
MBEWB160T Powr Cables puling & termntion 8 100 25DEC09A 22MAR10A
Powr Cables puling & termntion
MBE255T MATV system Wiring 8 90 28JAN10A 23NOV10
MATV system Wiring
MBEWB240T Install P.A Wiring 6 100 08FEB10A 17FEB10A
Install P.A Wiring
MBEW230 CCTV System wiring 7 90 02MAR10A 23NOV10
CCTV System wiring
MBME271F3 Nurse call sys Wiring 8 80 15AUG10A 24NOV10
Nurse call sys Wiring
MBEWB600T Wall trunking in LC rooms 7 0 24NOV10 01DEC10
Wall trunking in LC rooms
MBEWB290T BHU wiring 8 0 25NOV10 04DEC10
BHU wiring
MBME281F3 BMS (Conduit / Wiring) 8 0 14DEC10 22DEC10
BMS (Conduit / Wiring)

Tower Fourth Floor-Finishes


MBEWB140R Elect Wiring Sockets 8 100 28OCT07A 03NOV09A
Elect Wiring Sockets
MBEWB120R Install Cable Trays 10 100 12FEB08A 15MAY08A
Install Cable Trays
MBEWB100R Conduit Wall All Elec Sys 14 100 18FEB08A 10OCT09A
Conduit Wall All Elec Sys
MBEWB175R Fix Dist.Panels 9 100 07AUG08A 19AUG08A
Fix Dist.Panels

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 62 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBEWB200R Tel System wiring 8 90 13NOV09A 23NOV10
Tel System wiring
MBEWB450R Inst. Bus Bar Plug-in Units&Termination 8 100 16NOV09A 22MAR10A
Inst. Bus Bar Plug-in Units&Termination
MBEWB180R Fix MDB 8 100 03DEC09A 22MAR10A
Fix MDB
MBEWB650R Clock System wiring 8 90 16DEC09A 23NOV10
Clock System wiring
MBEW320 Data system wiring 6 90 23DEC09A 22NOV10
Data system wiring
MBEWB160R Powr Cables puling & termntion 8 100 25DEC09A 22MAR10A
Powr Cables puling & termntion
MBEWB240R Public Address wiring 8 90 01JAN10A 23NOV10
Public Address wiring
MBEWB220R Fire Alarm System wiring 8 90 27JAN10A 23NOV10
Fire Alarm System wiring
MBWB255R MATV System wiring 8 90 07FEB10A 23NOV10
MATV System wiring
MBEW330 CCTV Sys wiring 6 90 01APR10A 23NOV10
CCTV Sys wiring
MBME271F4 Nurse call sys Wiring 8 80 17JUL10A 24NOV10
Nurse call sys Wiring
MBEW310 Wall trunking in LC rooms 7 0 24NOV10 01DEC10
Wall trunking in LC rooms
MBEW290R BHU wiring 8 0 25NOV10 04DEC10
BHU wiring
MBME281F4 BMS (Conduit / Wiring) 8 0 05DEC10 13DEC10
BMS (Conduit / Wiring)

Tower Pent House Finishing Works


MBEWB140P Elect Wiring Sockets 2 100 01DEC08A 11OCT09A
Elect Wiring Sockets
MBEWB120P Install Cable Trays 2 100 10JUL09A 11SEP09A
Install Cable Trays
MBEWB100P Conduit Wall All Elec Sys 4 100 10AUG09A 14SEP09A
Conduit Wall All Elec Sys
MBEWB160P Powr Cables puling & termntion 2 100 12AUG09A 11OCT09A
Powr Cables puling & termntion
MBEWB260P Sub Dist Panels installation 4 100 03SEP09A 22MAR10A
Sub Dist Panels installation
MBEWB200P Tel System wiring 2pair 4 90 16NOV09A 22NOV10
Tel System wiring 2pair
MBEWB180P MDB installation & termination 8 100 16DEC09A 22MAR10A
MDB installation & termination
MBEWB510P Data Sys wiring 3 90 23DEC09A 22NOV10
Data Sys wiring
MBEWB220P Fire Alarm System wiring 8 90 25DEC09A 23NOV10
Fire Alarm System wiring
MBME281P BMS (Conduit / Wiring) 8 0 24NOV10 02DEC10
BMS (Conduit / Wiring)

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 63 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
Grnd. Floor "4A - 7A"Rear Bldg Works
MBE180G Conduiting under Grade Slab 8 100 14JUL07A 22JUL07A
Conduiting under Grade Slab
MBE0995E Conduits Susp. Slab 6 100 28AUG07A 11SEP07A
Conduits Susp. Slab

First Floor "4A - 7A" Rear Bldg Works


MBE1010G Conduits Boxes Susp Slab 6 100 26OCT07A 24NOV07A
Conduits Boxes Susp Slab

Grnd Floor "5B - 6B" Rear Bldg Works


MBE180F Conduits Under Grade Slab 8 100 16SEP07A 24SEP07A
Conduits Under Grade Slab
MBE2000GFG Conduit in Ceiling Slab GF 6 100 01JAN08A 26JAN08A
Conduit in Ceiling Slab GF

First Floor "5B - 6B" Rear Bldg Works


MBE18000G Conduit Susp Slab 6 100 15APR08A 26MAY08A
Conduit Susp Slab

Grnd Floor "4B - 5A" Rear Bldg Works


MBE180E Conduits Under Grade Slab 8 100 09JAN08A 10JUL08A
Conduits Under Grade Slab
MBE0900E Elec Conduits Susp Slab 6 100 19FEB08A 28AUG08A
Elec Conduits Susp Slab

First Floor "4B - 5A" Rear Bldg Works


MBE18010E Conduits Susp Slab 6 100 28JUN08A 23SEP08A
Conduits Susp Slab

Grnd Floor "6A - 7B" Rear Bldg Works


MBE180D Conduits Under Grade Slab 8 100 26JAN08A 09OCT08A
Conduits Under Grade Slab
MBME2000GD Conduits in Ceiling Slab GF 6 100 23FEB08A 17NOV08A
Conduits in Ceiling Slab GF

First Floor "6A - 7B" Rear Bldg Works


MBBE2000DE Elec Conduit Clng Slab 6 100 28JUN08A 12MAY09A
Elec Conduit Clng Slab

Finish Grnd Floor (4A,7A - 5B,6B) Rear Building


MBEGD1000 U/Gr. Elec Conduit Sec. "D" GF 10 100 25DEC07A 14JAN08A
U/Gr. Elec Conduit Sec. "D" GF
MBME2300GD Elec Wiring Sockets 15 100 23FEB08A 23MAR10A
Elec Wiring Sockets
MBME4625GD Fire Alarm System wiring 7 90 13MAR08A 23NOV10
Fire Alarm System wiring
MBME2100GD Install Cable Trays 16 100 19APR08A 01JUL08A
Install Cable Trays
MBME1500GD Fix Conduit Wall All Elec Sys 30 100 14NOV09A 24MAR10A
Fix Conduit Wall All Elec Sys
MBME3000GD Power Cables pulling & Termntion 8 100 16NOV09A 21MAR10A
Power Cables pulling & Termntion

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 64 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBME4600GD Public Address System wiring 7 90 17NOV09A 23NOV10
Public Address System wiring
MBME4500GD Tel System wiring 7 90 03DEC09A 23NOV10
Tel System wiring
MBRE920 Data system wiring 10 90 11DEC09A 23NOV10
Data system wiring
MBME3100GD Fix MDB& termination works 8 100 25DEC09A 21MAR10A
Fix MDB& termination works
MBRE950 SFP Installation 10 90 02JAN10A 23NOV10
SFP Installation
MBME3190GD MATV Sys wiring 8 90 16JAN10A 23NOV10
MATV Sys wiring
MBME3050GD Fix Dist. Panels 10 100 07FEB10A 24FEB10A
Fix Dist. Panels
MBRE930 CCTV Sys wiring 6 90 02MAR10A 23NOV10
CCTV Sys wiring
MBRE960 ACC Wiring 8 90 11APR10A 23NOV10
ACC Wiring
MBER100G Nurse call sys Wiring 12 70 01NOV10A 27NOV10
Nurse call sys Wiring
MBRE290 BHU wiring 8 0 28NOV10 06DEC10
BHU wiring
MBERG110 BMS (Conduit / Wiring) 8 0 21DEC10 29DEC10
BMS (Conduit / Wiring)
MBERG120 Wall trunking in operation theaters 6 0 30DEC10 05JAN11
Wall trunking in operation theaters

Finish First Floor (4A,7A - 5B,6B) Rear Building


MBEGF180 Elect Wiring Sockets 30 100 13MAR08A 24MAR10A
Elect Wiring Sockets
MBEGF140 Install Cable Trays 18 100 20MAY08A 19OCT09A
Install Cable Trays
MBEGF240 Fire Alarm System wiring 10 90 12AUG08A 23NOV10
Fire Alarm System wiring
MBEGF120 Fix Conduit Wall All Elec Sys 26 100 19OCT08A 09OCT09A
Fix Conduit Wall All Elec Sys
MBEGF195 Fix Dist. Panels 10 100 28OCT08A 22MAR10A
Fix Dist. Panels
MBEGF160 Power Cables puling & termntion 10 100 21AUG09A 22MAR10A
Power Cables puling & termntion
MBEGF200 Fix MDB & termination works 8 90 19NOV09A 23NOV10
Fix MDB & termination works
MBEGF520 Data system wiring 10 90 28NOV09A 23NOV10
Data system wiring
MBEGF260 Public Address System wiring 8 90 07DEC09A 23NOV10
Public Address System wiring
MBEGF220 Tel System wiring 8 90 28DEC09A 23NOV10
Tel System wiring
MBEGF530 CCTV Sys wiring 6 90 01FEB10A 23NOV10
CCTV Sys wiring

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 65 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBEGF275 MATV System wiring 8 90 23FEB10A 23NOV10
MATV System wiring
MBEGF550 SFP Installation 7 90 24FEB10A 23NOV10
SFP Installation
MBEGF560 ACC Wiring 7 90 24APR10A 23NOV10
ACC Wiring
MBER100F Nurse call sys Wiring 8 60 30OCT10A 25NOV10
Nurse call sys Wiring
MBEGF290 BHU wiring 8 0 24NOV10 02DEC10
BHU wiring
MBEGF510 Wall trunking in low current room 7 0 24NOV10 01DEC10
Wall trunking in low current room
MBEGF570 Wall trunking in operation theaters 7 0 02DEC10 09DEC10
Wall trunking in operation theaters
MBER110F BMS (Conduit / Wiring) 8 0 12DEC10 20DEC10
BMS (Conduit / Wiring)

Finish Grnd Floor (4B,5A - 6A,7B) Rear Building


MBGEGF140 Install Cable Trays 18 100 10MAY08A 19APR09A
Install Cable Trays
MBGEGF180 Elect wiring Sockets 10 100 29MAY08A 18JUN09A
Elect wiring Sockets
MBGEGF195 Fix Dist Panels & termination 10 100 29NOV08A 22MAR10A
Fix Dist Panels & termination
MBGEGF240 Fire Alarm System wiring 10 90 29NOV08A 23NOV10
Fire Alarm System wiring
MBGEGF120 Fix Conduit Wall All Elec Sys 22 100 10APR09A 02SEP09A
Fix Conduit Wall All Elec Sys
MBGEGF160 Powr Cables puling & Termntion 8 100 21AUG09A 22MAR10A
Powr Cables puling & Termntion
MBGEGF200 Fix MDB & termination works 8 100 27SEP09A 22MAR10A
Fix MDB & termination works
MBGEGF220 Tel System wiring 8 90 16DEC09A 23NOV10
Tel System wiring
MBGEGF260 Public Address System wiring 8 90 17DEC09A 23NOV10
Public Address System wiring
MBGFE820 Data system wiring 10 90 25DEC09A 23NOV10
Data system wiring
MBGEGF275 MATV System wiring 8 85 02MAR10A 23NOV10
MATV System wiring
MBGFE830 CCTV Sys wiring 6 90 02MAR10A 23NOV10
CCTV Sys wiring
MBGFE850 SFP Installation 10 90 07MAR10A 23NOV10
SFP Installation
MBGFE860 ACC Wiring 8 90 19APR10A 23NOV10
ACC Wiring
MBER100G2 Nurse call sys Wiring 8 70 23NOV10 24NOV10
Nurse call sys Wiring
MBGFE290 BHU wiring 9 0 24NOV10 04DEC10
BHU wiring

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 66 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBER110G2 BMS (Conduit / Wiring) 8 0 02DEC10 11DEC10
BMS (Conduit / Wiring)

Finish First Floor (4B,5A - 6A,7B) Rear Building


MBFEGF180 Wiring Elec Systems 9 100 14OCT08A 22MAR10A
Wiring Elec Systems
MBFEGF140 Install Cable Trays 16 100 25OCT08A 22SEP09A
Install Cable Trays
MBFEGF240 Fire Alarm System wiring 8 90 29NOV08A 23NOV10
Fire Alarm System wiring
MBFEGF120 Fix Conduit Wall All Elec Sys 18 100 10JUL09A 23MAR10A
Fix Conduit Wall All Elec Sys
MBFEGF160 Powr Cables puling & termntion 8 100 23AUG09A 22MAR10A
Powr Cables puling & termntion
MBFEGF196 Fix Dist. Panels 9 100 02SEP09A 22MAR10A
Fix Dist. Panels
MBFEGF220 Tel System wiring 8 90 30NOV09A 23NOV10
Tel System wiring
MBFEGF260 Public Address System wiring 8 90 09DEC09A 23NOV10
Public Address System wiring
MBEFF620 Data system wiring 10 90 19DEC09A 23NOV10
Data system wiring
MBFEGF200 Fix MDB 8 100 20DEC09A 22MAR10A
Fix MDB
MBFEGF275 MATV System wiring 12 90 01MAR10A 23NOV10
MATV System wiring
MBEFF630 CCTV Sys wiring 6 90 03MAR10A 23NOV10
CCTV Sys wiring
MBEFF650 SFP Installation 7 90 01APR10A 23NOV10
SFP Installation
MBER100F2 Nurse call sys Wiring 8 10 01NOV10A 30NOV10
Nurse call sys Wiring
MBER110F2 BMS (Conduit / Wiring) 8 0 23NOV10 01DEC10
BMS (Conduit / Wiring)
MBEFF290 BHU wiring 8 0 24NOV10 02DEC10
BHU wiring
MBEFF660 ACC Wiring 6 0 24NOV10 30NOV10
ACC Wiring

ROOF TOP
MBRT110 Cable Tray installation 7 90 22MAR10A 22NOV10
Cable Tray installation
MBRT100 Lightening Protectioning system 10 75 23NOV10 25NOV10
Lightening Protectioning system
MBRT120 Power cable puling & termnation 5 60 23NOV10 23NOV10
Power cable puling & termnation
MBRT130 Electrical work 5 80 24NOV10 24NOV10
Electrical work

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 67 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Electrical Fixtures
Tower Basement Floor- Finishes
MBEWB550 UPS System installation 8 100 09SEP10A 23OCT10A
UPS System installation
MBEWB950 CCTV Panel installation 7 0 24NOV10 01DEC10
CCTV Panel installation
MBEWB850 Public Address Panel installation 7 0 02DEC10 09DEC10
Public Address Panel installation
MBEWB900 MATV Panel installation 7 0 11DEC10 18DEC10
MATV Panel installation
MBEW600 Clock System 5 0 19DEC10 23DEC10
Clock System
MBEWB700 Central PABX Panel installation 10 0 30DEC10 10JAN11
Central PABX Panel installation
MBEWB280 Install Light Fixtures 14 0 02FEB11 17FEB11
Install Light Fixtures
MBEWB420 Inst. MATV & CCTV equip. 7 0 19FEB11 26FEB11
Inst. MATV & CCTV equip.
MBEWB300 Receptacles & Switches installation 12 0 27FEB11 12MAR11
Receptacles & Switches installation
MBEWB400 Inst. Data & Tel outlet, equip 10 0 27FEB11 09MAR11
Inst. Data & Tel outlet, equip
MBEWB430 Inst. FA & PA Devices 5 0 14JUN11 19JUN11
Inst. FA & PA Devices

Tower Ground Floor-Finishes


MBEWB280G Install Light Fixtures 16 0 22JAN11 08FEB11
Install Light Fixtures
MBEWB300G Receptacles & Switches installation 12 0 22JAN11 03FEB11
Receptacles & Switches installation
MBEWB400G Inst. Data & Tel outlet, equip 10 0 22JAN11 01FEB11
Inst. Data & Tel outlet, equip
MBEW1050 Inst. MATV & CCTV equip. 7 0 09FEB11 16FEB11
Inst. MATV & CCTV equip.
MBEWB422 BHU installation 8 0 01JUN11 09JUN11
BHU installation
MBEW1060 Inst. FA & PA Devices 5 0 11JUN11 15JUN11
Inst. FA & PA Devices

Tower First Floor-Finishes


MBEWB280F Install Light Fixtures 16 0 10JAN11 27JAN11
Install Light Fixtures
MBEWB300F Receptacles & Switches installation 12 0 10JAN11 23JAN11
Receptacles & Switches installation
MBEWB400F Inst. Data & Tel outlet, equip 10 0 10JAN11 20JAN11
Inst. Data & Tel outlet, equip
MBEW2050 Inst. MATV & CCTV equip. 7 0 29JAN11 05FEB11
Inst. MATV & CCTV equip.
MBEW300F20 BHU installation 8 0 23MAY11 31MAY11
BHU installation
Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT
Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 68 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBEW2060 Inst. FA & PA Devices 5 0 05JUN11 09JUN11
Inst. FA & PA Devices

Tower Second Floor-Finishes


MBEWB280S Install Light Fixtures 16 0 29DEC10 16JAN11
Install Light Fixtures
MBEWB300S Receptacles & Switches installation 12 0 29DEC10 11JAN11
Receptacles & Switches installation
MBEWB400S Inst. Data & Tel outlet, equip 10 0 29DEC10 09JAN11
Inst. Data & Tel outlet, equip
MBEW3050 Inst. MATV & CCTV equip. 7 0 17JAN11 24JAN11
Inst. MATV & CCTV equip.
MBEW140 BHU installation 8 0 14MAY11 22MAY11
BHU installation
MBEW3060 Inst. FA & PA Devices 5 0 30MAY11 04JUN11
Inst. FA & PA Devices

Tower Third Floor- Finishes


MBEWB280T Install Light Fixtures 16 0 18DEC10 04JAN11
Install Light Fixtures
MBEWB300T Receptacles & Switches installation 10 0 18DEC10 28DEC10
Receptacles & Switches installation
MBEWB400T Inst. Data & Tel outlet, equip 10 0 18DEC10 28DEC10
Inst. Data & Tel outlet, equip
MBE4010 Inst. MATV & CCTV equip. 7 0 05JAN11 12JAN11
Inst. MATV & CCTV equip.
MBEW240 BHU installation 8 0 04MAY11 12MAY11
BHU installation
MBE4020 Inst. FA & PA Devices 5 0 24MAY11 29MAY11
Inst. FA & PA Devices

Tower Fourth Floor-Finishes


MBEWB280R Install Light Fixtures 16 0 06DEC10 23DEC10
Install Light Fixtures
MBEWB300R Receptacles & Switches installation 10 0 06DEC10 16DEC10
Receptacles & Switches installation
MBEWB400R Inst. Data & Tel outlet, equip 10 0 06DEC10 16DEC10
Inst. Data & Tel outlet, equip
MBE5010 Inst. MATV & CCTV equip. 7 0 25DEC10 01JAN11
Inst. MATV & CCTV equip.
MBEW340 BHU installation 8 0 25APR11 03MAY11
BHU installation
MBE5020 Inst. FA & PA Devices 5 0 18MAY11 23MAY11
Inst. FA & PA Devices

Tower Pent House Finishing Works


MBEWB280P Install Light Fixtures 5 0 11JAN11 16JAN11
Install Light Fixtures
MBEWB300P Receptacles & Switches installation 4 0 11JAN11 15JAN11
Receptacles & Switches installation
MBEWB400P Inst. Data & Tel outlet, equip 4 0 11JAN11 15JAN11
Inst. Data & Tel outlet, equip

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 69 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBE6020 Inst. FA & PA Devices 5 0 04MAY11 09MAY11
Inst. FA & PA Devices

Finish Grnd Floor (4A,7A - 5B,6B) Rear Building


MBME5000GD Install Light Fixtures 17 0 16MAR11 04APR11
Install Light Fixtures
MBE7010 Inst. MATV & CCTV equip. 7 0 05APR11 12APR11
Inst. MATV & CCTV equip.
MBME4750GD Receptacles / Switches installation 10 0 05APR11 16APR11
Receptacles / Switches installation
MBE7020 Inst. FA & PA Devices 7 0 17APR11 24APR11
Inst. FA & PA Devices
MBEGF400G Inst. Data & Tel outlet, equip 9 0 17APR11 26APR11
Inst. Data & Tel outlet, equip
MBRE940 BHU installation 16 0 30MAY11 16JUN11
BHU installation

Finish First Floor (4A,7A - 5B,6B) Rear Building


MBEGF400 Install Light Fixtures 16 0 03FEB11 21FEB11
Install Light Fixtures
MBE8010 Inst. MATV & CCTV equip. 7 0 22FEB11 01MAR11
Inst. MATV & CCTV equip.
MBEGF420 Receptacles / Switches installation 10 0 22FEB11 05MAR11
Receptacles / Switches installation
MBE8020 Inst. FA & PA Devices 7 0 01MAR11 08MAR11
Inst. FA & PA Devices
MBEGF440 Inst. Data & Tel outlet, equip 9 0 06MAR11 15MAR11
Inst. Data & Tel outlet, equip
MBEGF540 BHU installation 14 0 30MAY11 14JUN11
BHU installation

Finish Grnd Floor (4B,5A - 6A,7B) Rear Building


MBE9020 Inst. FA & PA Devices 7 0 17APR11 24APR11
Inst. FA & PA Devices
MBGEGF400 Install Light Fixtures 12 0 14MAY11 26MAY11
Install Light Fixtures
MBE9010 Inst. MATV & CCTV equip. 7 0 28MAY11 04JUN11
Inst. MATV & CCTV equip.
MBGEGF420 Receptles / Switches installation 10 0 28MAY11 07JUN11
Receptles / Switches installation
MBGFE840 BHU installation 14 0 30MAY11 14JUN11
BHU installation
MBGEGF440 Inst. Data & Tel outlet, equip 9 0 08JUN11 18JUN11
Inst. Data & Tel outlet, equip

Finish First Floor (4B,5A - 6A,7B) Rear Building


MBE1020 Inst. FA & PA Devices 7 0 03APR11 10APR11
Inst. FA & PA Devices
MBFEGF400 Install Light Fixtures 14 0 05APR11 20APR11
Install Light Fixtures
MBE1010 Inst. MATV & CCTV equip. 7 0 21APR11 28APR11
Inst. MATV & CCTV equip.

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 70 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
MBFEGF420 Receptles / Switches installation 10 0 21APR11 02MAY11
Receptles / Switches installation
MBEFF640 BHU installation 15 0 30APR11 16MAY11
BHU installation
MBFEGF440 Inst. Data & Tel outlet, equip 9 0 03MAY11 12MAY11
Inst. Data & Tel outlet, equip

TEST & COMMISSION

MBME9000GD Test & Comm. Elec System 9 0 20JUN11 29JUN11


Test & Comm. Elec System

READY to HAND OVER


Final Clean Up to Hand Over

MBHO786 Ready to Hand over 3 0 11JUL11 13JUL11


Ready to Hand over

Out Patient Building


CIVIL WORKS
Mobilize
GROUND FLOOR
OP1000 Mobilize 30 100 03MAY05A 06JUN05A
Mobilize

Concrete Works
GROUND FLOOR
OPC100 Under Ground Concrete Works 40 100 20SEP05A 05NOV05A
Under Ground Concrete Works
OPC200 Super Structure Conc Works 295 100 06NOV05A 15OCT06A
Super Structure Conc Works

ARCHITECTURAL WORKS
Masonry Works
GROUND FLOOR
OPB100 Block Work (CMU) 45 100 16OCT06A 06DEC06A
Block Work (CMU)

FIRST FLOOR
OP1F100 Block Work (CMU) 50 100 08JAN07A 04FEB07A
Block Work (CMU)

SECOND FLOOR
OP2F100 Block Work (CMU) 50 100 10JAN07A 27MAR07A
Block Work (CMU)

ROOF TOP
OPRT200 Block Work (CMU) 20 100 10APR07A 28OCT09A
Block Work (CMU)

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 71 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Water Proofing & Insulation


GROUND FLOOR
OPW300 Water Proofing Wet Areas 15 100 01NOV09A 07NOV09A
Water Proofing Wet Areas

FIRST FLOOR
OP1F340 Water Proof Wet Areas 9 100 05NOV09A 10NOV09A
Water Proof Wet Areas

SECOND FLOOR
OP2F340 Water Proof Wet Areas 9 100 11NOV09A 14NOV09A
Water Proof Wet Areas

ROOF TOP
OPW160 Light Weight Conc Roof 12 100 08APR07A 01MAY07A
Light Weight Conc Roof
OPW180 Water Proofing Memb. Roof 16 100 21MAY07A 02FEB08A
Water Proofing Memb. Roof
OPW240 Roof Metal Flashing & Joints 8 100 08JAN08A 31JAN08A
Roof Metal Flashing & Joints
OPW220 Fix Roof Insulation Sheets 12 100 09FEB08A 27FEB08A
Fix Roof Insulation Sheets
OPW260 Roof Graveling on Insulation 8 100 24FEB08A 13APR08A
Roof Graveling on Insulation
OPW200 Test Roof Membrane 3 100 08APR08A 30APR08A
Test Roof Membrane

Doors & Windows


GROUND FLOOR
OPD120 Fix Door Frames 42 100 06OCT08A 09MAR10A
Fix Door Frames
OPD140 Fix Door metal Panels 30 8 01NOV09A 25DEC10
Fix Door metal Panels
OPD180 Fix Exterior Windows 24 80 15MAY10A 28NOV10
Fix Exterior Windows
OP190 Fix Interior Alum Windows 12 0 29NOV10 12DEC10
Fix Interior Alum Windows
OPD200 Fix Alum Doors 12 0 13DEC10 26DEC10
Fix Alum Doors
OPD150 Fix Wooden door panels 12 0 26DEC10 08JAN11
Fix Wooden door panels
OPD160 Fix Door Hard Ware 12 0 07FEB11 20FEB11
Fix Door Hard Ware

FIRST FLOOR
OP1F350 Fix Door Frames 25 100 13JUN08A 10MAR10A
Fix Door Frames
OP1F710 Fix Alum Windows 12 85 22MAY10A 24NOV10
Fix Alum Windows
OP1F450 Install Metal Door Panels 18 0 11DEC10 30DEC10
Install Metal Door Panels

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 72 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
OP1F760 Fix Aluminium Door 12 0 29DEC10 11JAN11
Fix Aluminium Door
OPD1F150 Fix Wooden door panels 20 0 01JAN11 23JAN11
Fix Wooden door panels
OP1F470 Fix Door Hardware 12 0 24JAN11 06FEB11
Fix Door Hardware

SECOND FLOOR
OP2F350 Fix Door Frames 42 100 08MAY08A 11MAR10A
Fix Door Frames
OP2F450 Install Metal Door Panels 15 0 23NOV10 09DEC10
Install Metal Door Panels
OP2F710 Fix Alum Windows 14 0 25NOV10 11DEC10
Fix Alum Windows
OP2F160 Fix Wooden door panels 20 0 11DEC10 02JAN11
Fix Wooden door panels
OP2F760 Fix Aluminium Door 15 0 12DEC10 28DEC10
Fix Aluminium Door
OP2F470 Fix Door Hardware 12 0 03JAN11 16JAN11
Fix Door Hardware

ROOF TOP
OPRT100 Fix Door Frames 7 0 23NOV10 30NOV10
Fix Door Frames
OPRT110 Fix Door metal Panels 5 0 01DEC10 06DEC10
Fix Door metal Panels
OPRT120 Fix Door Hard Ware 5 0 07DEC10 12DEC10
Fix Door Hard Ware
OPRT130 Fix Roof Sky Lights 30 0 27DEC10 30JAN11
Fix Roof Sky Lights

Pre-Finishing Works Walls


GROUND FLOOR
OPF120 Plaster Walls 70 100 19DEC06A 09MAR10A
Plaster Walls
OPF140 Fix Dry Boards on Metal Studs 80 100 25FEB07A 09MAR10A
Fix Dry Boards on Metal Studs
OPF660 Fix Sound Proof Panel Inert Room 4 100 04OCT07A 12DEC07A
Fix Sound Proof Panel Inert Room
OPF180 Putty & Primer Coat Ordinary 58 75 10FEB08A 09DEC10
Putty & Primer Coat Ordinary
OPF160 Fix Ceramic Wall Tiles 35 100 06JAN09A 25MAR10A
Fix Ceramic Wall Tiles
OPF100 Fix Studs Dry Wall Prtn 65 100 17SEP09A 09MAR10A
Fix Studs Dry Wall Prtn
OPF190 Putty Primer Anti Bact. Paint 48 0 11DEC10 03FEB11
Putty Primer Anti Bact. Paint

FIRST FLOOR
OP1F130 Plaster Works Walls Interior 60 100 01JAN07A 09MAR10A
Plaster Works Walls Interior

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 73 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
OP1F375 Fix Studs Dry Wall Prtn 65 100 22JAN07A 08MAR10A
Fix Studs Dry Wall Prtn
OP1F385 Fix Dry Boards on Metal Studs 80 100 25APR07A 09MAR10A
Fix Dry Boards on Metal Studs
OP1F395 Fix Sound Proof Panel Inert Room 4 100 04NOV07A 12MAR08A
Fix Sound Proof Panel Inert Room
OP1F380 Fix Ceramic Wall Tiles 38 100 18MAY09A 11MAR10A
Fix Ceramic Wall Tiles
OP1F390 Putty & Primer Coat Ordinary 48 95 19AUG09A 24NOV10
Putty & Primer Coat Ordinary
OPF190FF Putty Primer Anti Bact. Paint 48 0 25NOV10 19JAN11
Putty Primer Anti Bact. Paint

SECOND FLOOR
OP2F375 Fix Studs Dry Wall Prtn 65 100 22DEC06A 09MAR10A
Fix Studs Dry Wall Prtn
OP2F385 Fix Dry Boards on Metal Studs 80 100 25MAY07A 09MAR10A
Fix Dry Boards on Metal Studs
OP2F395 Fix Sound Proof Panel Inert Room 4 100 04JAN08A 12AUG08A
Fix Sound Proof Panel Inert Room
OP2F130 Plaster Works Walls Interior 60 100 01APR08A 09MAR10A
Plaster Works Walls Interior
OP2F380 Fix Ceramic Wall Tiles 38 100 19JUL09A 11MAR10A
Fix Ceramic Wall Tiles
OP2F390 Putty & Primer Coat Ordinary 48 95 22OCT09A 24NOV10
Putty & Primer Coat Ordinary
OPF190S Putty Primer Anti Bact. Paint 48 0 25NOV10 19JAN11
Putty Primer Anti Bact. Paint

ROOF TOP
OPRT900 Plaster Walls 12 100 19DEC06A 04APR10A
Plaster Walls
OPRT910 Putty & Primer Coat Ordinary 15 0 19AUG09A 09DEC10
Putty & Primer Coat Ordinary

Pre-Finishing Works Ceilings


GROUND FLOOR
OPF451 Grand Insptn Abv Ceiling 4 100 11MAY10A 15MAY10A
Grand Insptn Abv Ceiling
OPF240 Fix Grids False Ceiling 25 90 09JUN10A 24NOV10
Fix Grids False Ceiling
OPF310 Fix Gypsum Board Ceiling 20 0 25NOV10 18DEC10
Fix Gypsum Board Ceiling
OPF710 Fix Alum Panel Ceiling Wet Area 15 0 25NOV10 12DEC10
Fix Alum Panel Ceiling Wet Area
OPF460 First Coat + Prep Clng Paint 18 0 07DEC10 27DEC10
First Coat + Prep Clng Paint
OPF455 Paint Emulsion Celing 18 0 28DEC10 17JAN11
Paint Emulsion Celing

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 74 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
FIRST FLOOR
OP1F430 Grand Insptn Abv Ceiling 4 100 06MAY10A 10MAY10A
Grand Insptn Abv Ceiling
OP1F455 Fix Grids False Ceiling 25 55 22MAY10A 05DEC10
Fix Grids False Ceiling
OP1F465 Fix Gypsum Board Ceiling 20 0 06DEC10 28DEC10
Fix Gypsum Board Ceiling
OP1F490 Install Alum Ceiling Wet Areas 15 0 06DEC10 22DEC10
Install Alum Ceiling Wet Areas
OP1F435 First Coat + Prep Clng Paint 18 0 13JAN11 02FEB11
First Coat + Prep Clng Paint
OP1F445 Paint Emulsion Celing 18 0 03FEB11 23FEB11
Paint Emulsion Celing

SECOND FLOOR
OP2F430 Grand Insptn Abv Ceiling 4 100 02MAY10A 05MAY10A
Grand Insptn Abv Ceiling
OP2F455 Fix Grids False Ceiling 25 65 18MAY10A 29NOV10
Fix Grids False Ceiling
OP2F465 Fix Gypsum Board Ceiling 20 0 30NOV10 22DEC10
Fix Gypsum Board Ceiling
OP2F490 Install Alum Ceiling Wet Areas 15 0 30NOV10 16DEC10
Install Alum Ceiling Wet Areas
OP2F435 First Coat + Prep Clng Paint 18 0 23DEC10 12JAN11
First Coat + Prep Clng Paint
OP2F445 Paint Emulsion Celing 18 0 13JAN11 02FEB11
Paint Emulsion Celing

ROOF TOP
OPRT800 Plaster Ceiling 4 100 05APR10A 08APR10A
Plaster Ceiling

Pre-Finishing Work
GROUND FLOOR
OPF200 Floor Screed 8 100 14JAN10A 14FEB10A
Floor Screed

FIRST FLOOR
OP1F205 Floor Screed 8 100 24FEB10A 02MAR10A
Floor Screed

SECOND FLOOR
OP2F205 Floor Screed 6 100 03FEB10A 28FEB10A
Floor Screed

Final Floor Finishing Works


GROUND FLOOR
OPF280 Ceramic Floor Tiling 23 50 20JAN10A 06DEC10
Ceramic Floor Tiling
OPF220 Marble Floor Tiling 65 70 28MAR10A 15DEC10
Marble Floor Tiling

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 75 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
OPF290 Porclean Acid (400x400) 10 0 19DEC10 29DEC10
Porclean Acid (400x400)
OPF400 Fix Vinyl Base Skirting 12 0 19DEC10 01JAN11
Fix Vinyl Base Skirting
OPF225 Fix Joint Strips 8 0 02JAN11 10JAN11
Fix Joint Strips
OPF340 Fix Tread/Risers Saudi 12 0 06JAN11 19JAN11
Fix Tread/Risers Saudi
OPF325 Fix Marble Threshold 10 0 20JAN11 31JAN11
Fix Marble Threshold
OPF990 Final Cleaning 7 0 19MAY11 26MAY11
Final Cleaning

FIRST FLOOR
OP1F540 Fix MarbleFloor Tiles 22 72 05DEC09A 29NOV10
Fix MarbleFloor Tiles
OP1F510 Fix Ceramic Floor Tiles 15 52 22MAR10A 27NOV10
Fix Ceramic Floor Tiles
OP1F630 Fix Terrazo Floor Tiles 10 0 29DEC10 09JAN11
Fix Terrazo Floor Tiles
OP1F650 Saudi Granite Tread / Riser 12 0 10JAN11 23JAN11
Saudi Granite Tread / Riser
OP1F680 Marble Threshold 10 0 24JAN11 03FEB11
Marble Threshold
OP1F880 Final Cleaning 7 0 19MAY11 26MAY11
Final Cleaning

SECOND FLOOR
OP2F540 Fix Marble Floor Tiles 18 93 24FEB10A 23NOV10
Fix Marble Floor Tiles
OP2F510 Fix Ceramic Floor Tiles 15 100 13MAR10A 22MAR10A
Fix Ceramic Floor Tiles
OP2F630 Fix Terrazo Floor Tiles 10 0 23DEC10 03JAN11
Fix Terrazo Floor Tiles
OP2F650 Saudi Granite Tread / Riser 12 0 16JAN11 29JAN11
Saudi Granite Tread / Riser
OP2F680 Marble Threshold 10 0 30JAN11 09FEB11
Marble Threshold
OP2F880 Final Cleaning 7 0 02JUN11 09JUN11
Final Cleaning

ROOF TOP
OPRT400 Cement screed with epoxy paint 50mm 15 0 11DEC10 27DEC10
Cement screed with epoxy paint 50mm
OPFRT100 Marble Threshold 4 0 28DEC10 01JAN11
Marble Threshold

Final Wall Finishing Works


REAR BUILDING
OPF260 Exterior Aluminum Wall clading 70 99 24JAN09A 23NOV10
Exterior Aluminum Wall clading

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 76 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
OPF270 Exterior Curtain Walls 25 70 01JUN10A 29NOV10
Exterior Curtain Walls

GROUND FLOOR
OPF300G Final 2 Coats of Anti Bactaia 35 0 05FEB11 16MAR11
Final 2 Coats of Anti Bactaia
OPF420 Final Paint Coat Ordinary 28 0 10FEB11 14MAR11
Final Paint Coat Ordinary
OPF430 Texture Paint 30 0 17MAR11 20APR11
Texture Paint

FIRST FLOOR
OPF300F Final 2 Coats of Anti Bacteria 35 0 20JAN11 01MAR11
Final 2 Coats of Anti Bacteria
OP1F785 Final Paint Coat Emulsion 26 0 07FEB11 08MAR11
Final Paint Coat Emulsion
OP1F805 Texture Paint 25 0 02MAR11 30MAR11
Texture Paint

SECOND FLOOR
OPF300S Final 2 Coats of Anti Bactaia 35 0 20JAN11 01MAR11
Final 2 Coats of Anti Bactaia
OP2F785 Final Paint Coat Emulsion 26 0 10FEB11 12MAR11
Final Paint Coat Emulsion
OP2F805 Texture Paint 12 0 02MAR11 15MAR11
Texture Paint

ROOF TOP
OPRT920 Final paint 15 0 02JAN11 18JAN11
Final paint

Final Ceiling Finishing Works


GROUND FLOOR
OPF300 Fix Acc. Ceiling Tiles 16 0 30DEC10 17JAN11
Fix Acc. Ceiling Tiles

FIRST FLOOR
OP1F830 Fix Acc. Ceiling Tiles 13 0 15DEC10 29DEC10
Fix Acc. Ceiling Tiles

SECOND FLOOR
OP2F830 Fix Acc. Ceiling Tiles 13 0 30NOV10 14DEC10
Fix Acc. Ceiling Tiles

Metal Works
GROUND FLOOR
OPF380 Fix Hand Rails 8 0 28DEC10 05JAN11
Fix Hand Rails
OPF385 Fix Wall Guards 8 0 16JAN11 24JAN11
Fix Wall Guards

FIRST FLOOR
OP1F570 Fix Hand Rails 8 0 06JAN11 15JAN11
Fix Hand Rails

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 77 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
OOPF385 Fix Wall Guards 8 0 16JAN11 24JAN11
Fix Wall Guards

SECOND FLOOR
OP2F570 Fix Hand Rails 8 0 16JAN11 24JAN11
Fix Hand Rails
O1OPF385 Fix Wall Guards 8 0 25JAN11 02FEB11
Fix Wall Guards

Wood Works
GROUND FLOOR
OPT100 Fix Counters 14 0 11MAY11 26MAY11
Fix Counters
OPT130 Fix Case Work / shelving 13 0 15MAY11 29MAY11
Fix Case Work / shelving

Specialties
GROUND FLOOR
OPT360 Fix sign Boards 12 0 21APR11 04MAY11
Fix sign Boards

FIRST FLOOR
OP1F790 Install sign Boards 12 0 05MAY11 18MAY11
Install sign Boards

SECOND FLOOR
OP2F790 Install sign Boards 12 0 19MAY11 01JUN11
Install sign Boards

Furnishing
GROUND FLOOR
OP1G780 Fix Railing System for Curtains 7 0 27APR11 04MAY11
Fix Railing System for Curtains

FIRST FLOOR
OP1F750 Fix Railing System for Curtains 7 0 11MAY11 18MAY11
Fix Railing System for Curtains

MECHANICAL WORKS
Elevators
GROUND FLOOR
OPM360 Install Elevators 25 15 01SEP10A 16DEC10
Install Elevators

HVAC Works
GROUND FLOOR
OPH180 Fix Ducts 128 100 08NOV07A 14MAR10A
Fix Ducts
OPH220 Ducts Insulation 60 100 19MAR08A 10MAR10A
Ducts Insulation
OPH240 Fix Flexible Ducts/ return diff. 12 0 23NOV10 06DEC10
Fix Flexible Ducts/ return diff.

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 78 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
FIRST FLOOR
OP1F120 Install Ducts 96 100 09NOV08A 28DEC08A
Install Ducts
OP1F295 Ducts Insulation 60 100 22JUL09A 10MAR10A
Ducts Insulation
OP1F315 Fix Flexible Ducts for Supply 18 0 23NOV10 13DEC10
Fix Flexible Ducts for Supply
OP1F325 Install system HVAC 12 0 16DEC10 29DEC10
Install system HVAC
OP1F355 Fix Grills / Diffusers 20 0 08JAN11 30JAN11
Fix Grills / Diffusers

SECOND FLOOR
OP2F120 Install Ducts 96 100 09MAY08A 13MAR10A
Install Ducts
OP2F295 Ducts Insulation 60 100 22AUG09A 10MAR10A
Ducts Insulation
OP2F315 Fix Flexible Ducts for Supply 12 0 23NOV10 06DEC10
Fix Flexible Ducts for Supply
OP2F355 Fix Grills / Diffusers 20 0 15DEC10 06JAN11
Fix Grills / Diffusers

ROOF TOP
OPRT310 Ducts Insulation roof / cladding 60 80 22FEB07A 06DEC10
Ducts Insulation roof / cladding
OPRT300 Install HVAC Equipments Roof 70 80 01SEP09A 15DEC10
Install HVAC Equipments Roof
OP2F335 Install Exhaust Fans roof 21 0 07DEC10 30DEC10
Install Exhaust Fans roof

Plumbing Works
GROUND FLOOR
OPP100 Fix Drainage Pipes 60 100 16OCT06A 24DEC06A
Fix Drainage Pipes
OPP120 Test Drainage Pipes 40 100 14NOV06A 30DEC06A
Test Drainage Pipes
OPP180 Fix Hot/Cold Water Pipes 60 100 20NOV06A 10MAR10A
Fix Hot/Cold Water Pipes
OPP400 Fix Drainage Pipes Abv Ceiling 45 100 25DEC06A 18FEB07A
Fix Drainage Pipes Abv Ceiling
OPP425 Test Drainage Pipes Abv Clng 30 100 21JAN07A 24FEB07A
Test Drainage Pipes Abv Clng
OPP450 Fix Rain Water Pipes 18 100 31JAN08A 20FEB08A
Fix Rain Water Pipes
OPP200 Test Hot/Cold Water Pipes 22 100 07JUL08A 09MAR10A
Test Hot/Cold Water Pipes
OPP215 Fix Floor Drains 4 100 17APR10A 20APR10A
Fix Floor Drains
OPP211 Tag Hot/Cold Water Pipes 7 0 23NOV10 30NOV10
Tag Hot/Cold Water Pipes

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 79 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
OPP220 Fix sanitary Fixtures 22 0 05DEC10 29DEC10
Fix sanitary Fixtures

FIRST FLOOR
OP1F555 Fix Drainage Pipes 60 100 16OCT06A 24DEC06A
Fix Drainage Pipes
OP1F565 Test Drainage Pipes 40 100 14NOV06A 30DEC06A
Test Drainage Pipes
OP1F575 Fix Hot/Cold Water Pipes 60 100 20NOV06A 10MAR10A
Fix Hot/Cold Water Pipes
OP1F585 Fix Drainage Pipes Abv Ceiling 45 100 25DEC06A 18FEB07A
Fix Drainage Pipes Abv Ceiling
OP1F595 Test Drainage Pipes Abv Clng 30 100 21JAN07A 24FEB07A
Test Drainage Pipes Abv Clng
OP1F605 Fix Rain Water Pipes 18 100 31JAN08A 20FEB08A
Fix Rain Water Pipes
OP1F615 Fix Floor Drains 4 100 12FEB08A 15MAR08A
Fix Floor Drains
OP1F625 Test Hot/Cold Water Pipes 40 100 07JUL08A 09MAR10A
Test Hot/Cold Water Pipes
OP1F635 Tag Hot/Cold Water Pipes 7 0 23NOV10 30NOV10
Tag Hot/Cold Water Pipes
OP1F685 Fix sanitary Fixtures 22 0 16DEC10 10JAN11
Fix sanitary Fixtures

SECOND FLOOR
OP2F555 Fix Drainage Pipes 60 100 16OCT06A 24DEC06A
Fix Drainage Pipes
OP2F565 Test Drainage Pipes 40 100 14NOV06A 30DEC06A
Test Drainage Pipes
OP2F575 Fix Hot/Cold Water Pipes 60 100 20NOV06A 10MAR10A
Fix Hot/Cold Water Pipes
OP2F585 Fix Drainage Pipes Abv Ceiling 45 100 25DEC06A 18FEB07A
Fix Drainage Pipes Abv Ceiling
OP2F595 Test Drainage Pipes Above Ceiling 30 100 21JAN07A 09MAR10A
Test Drainage Pipes Above Ceiling
OP2F605 Fix Rain Water Pipes 18 100 31JAN08A 20FEB08A
Fix Rain Water Pipes
OP2F635 Tag Hot/Cold Water Pipes 2 100 21MAY08A 22DEC08A
Tag Hot/Cold Water Pipes
OP2F625 Test Hot/Cold Water Pipes 40 100 07JUL08A 09MAR10A
Test Hot/Cold Water Pipes
OP2F615 Fix Floor Drains 4 100 06APR10A 10APR10A
Fix Floor Drains
OP2F685 Fix sanitary Fixtures 22 0 11DEC10 04JAN11
Fix sanitary Fixtures

Fire Fighting Works


GROUND FLOOR
OPP700 Install Fire Fighting Pipes 70 100 13DEC06A 16JAN08A
Install Fire Fighting Pipes
Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT
Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 80 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
OPP740 Painting Fire Water Pipes 3 100 14MAR07A 07MAR10A
Painting Fire Water Pipes
OPP745 Tagging of Fire Water Pipes 2 100 24OCT08A 26DEC08A
Tagging of Fire Water Pipes
OPF735 Fix FHC 5 100 02JAN09A 14JUL10A
Fix FHC
OPP725 Press. Test Fire Fight. Pipes 48 100 21SEP09A 23SEP09A
Press. Test Fire Fight. Pipes
OPP750 Fix Fire Sprinklers 18 0 25NOV10 15DEC10
Fix Fire Sprinklers
OPP760 Fix Fire Extinguishers 8 0 16DEC10 25DEC10
Fix Fire Extinguishers

FIRST FLOOR
OP1F150 Install Fire Fighting Pipes 28 100 09AUG08A 10SEP08A
Install Fire Fighting Pipes
OP1F250 Tagging of Fire Water Pipes 2 100 24AUG08A 26SEP08A
Tagging of Fire Water Pipes
OP1F530 Fix FHC 5 100 24JUN09A 28OCT09A
Fix FHC
OP1F220 Press. Test Fire Fight. Pipes 4 100 21JUL09A 25JUL09A
Press. Test Fire Fight. Pipes
OP1F230 Painting Fire Water Pipes 3 100 21JUL09A 09MAR10A
Painting Fire Water Pipes
OP1F480 Fix Fire Sprinklers 18 0 23NOV10 13DEC10
Fix Fire Sprinklers
OP1F520 Fix Flow Switches 8 0 14DEC10 22DEC10
Fix Flow Switches

SECOND FLOOR
OP2F150 Install Fire Fighting Pipes 28 100 19AUG09A 22OCT09A
Install Fire Fighting Pipes
OP2F220 Press. Test Fire Fight. Pipes 4 100 21AUG09A 24OCT09A
Press. Test Fire Fight. Pipes
OP2F230 Painting Fire Water Pipes 3 100 21SEP09A 22MAR10A
Painting Fire Water Pipes
OP2F530 Fix FHC 5 100 05APR10A 10APR10A
Fix FHC
OP2F250 Tagging of Fire Water Pipes 8 0 23NOV10 01DEC10
Tagging of Fire Water Pipes
OP2F480 Fix Fire Sprinklers 18 0 23NOV10 13DEC10
Fix Fire Sprinklers
OP2F520 Fix Flow Switches 8 0 14DEC10 22DEC10
Fix Flow Switches

Medical Gases Works


GROUND FLOOR
OPM200 Install Med Gases Fixtures 15 75 06SEP10A 25NOV10
Install Med Gases Fixtures

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 81 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Specialties
GROUND FLOOR
OPT300 Fix Toilet Cubicles 14 0 02DEC10 18DEC10
Fix Toilet Cubicles
OPT120 Fix Toilet Accessories 12 0 28DEC10 10JAN11
Fix Toilet Accessories

FIRST FLOOR
OP1F135 Fix Toilet Cubicles 14 0 30NOV10 15DEC10
Fix Toilet Cubicles
OP1F145 Fix Toilet Accessories 12 0 11JAN11 24JAN11
Fix Toilet Accessories

SECOND FLOOR
OP2F135 Fix Toilet Cubicles 14 0 24NOV10 09DEC10
Fix Toilet Cubicles
OP2F145 Fix Toilet Accessories 12 0 05JAN11 18JAN11
Fix Toilet Accessories

TEST & COMMISSION

OPM100 Flush /Cleaning Med. Gas system 8 0 27NOV10 05DEC10


Flush /Cleaning Med. Gas system
OPM225 Test & Comm. Med Gases 10 0 06DEC10 16DEC10
Test & Comm. Med Gases
OPP735 Flush /Clean Fire Fighting Pipe 8 0 26DEC10 03JAN11
Flush /Clean Fire Fighting Pipe
OPP230 Flush /Cleaning Water Pipe 10 0 30DEC10 10JAN11
Flush /Cleaning Water Pipe
OP2F695 Test Comm HVAC 12 0 11JAN11 24JAN11
Test Comm HVAC

ELECTRICAL WORKS
Electrical works
GROUND FLOOR
OPE160 Fix Conduit in Walls 95 100 07DEC06A 13DEC07A
Fix Conduit in Walls
OPE190 Fix Cable Trays 32 100 03FEB07A 05FEB08A
Fix Cable Trays
OPE180 Conduit / Wiring Ceiling 65 100 25FEB07A 14FEB08A
Conduit / Wiring Ceiling
OPE200 Powr Cables puling & termntion 30 100 18JUN07A 14APR08A
Powr Cables puling & termntion
OPE240 Install Dist. Panels 24 100 13AUG08A 14OCT08A
Install Dist. Panels
OPE300 Fire Alarm System wiring 18 100 28OCT08A 14APR09A
Fire Alarm System wiring
OPE280 Public Address System wiring 16 100 07OCT09A 14DEC09A
Public Address System wiring

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 82 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
OPE220 Install MDB & termination work 10 100 14FEB10A 14MAR10A
Install MDB & termination work
OPE255 Data system wiring 8 100 14FEB10A 14MAR10A
Data system wiring
OPE285 Central Clock System wiring 8 100 13MAR10A 31MAR10A
Central Clock System wiring
OPE260 Tel. System wiring 16 100 14MAR10A 17MAR10A
Tel. System wiring
OPE305 MATV system wiring 6 100 14MAR10A 01APR10A
MATV system wiring

FIRST FLOOR
OP1F110 Fix Conduits in Walls 76 100 02APR07A 23APR07A
Fix Conduits in Walls
OP1F190 Fix Cable Trays 32 100 12MAR08A 27MAR08A
Fix Cable Trays
OP1F730 Powr Cables puling & termntion 12 100 01APR08A 09APR08A
Powr Cables puling & termntion
OP1F260 Conduiting / Wiring Abv Ceiling 36 100 01JUN08A 25JUN08A
Conduiting / Wiring Abv Ceiling
OP1F640 Telephone System wiring 12 92 08SEP09A 23NOV10
Telephone System wiring
OP1F270 Fire Alarm system wiring 16 95 12SEP09A 23NOV10
Fire Alarm system wiring
OP1F620 Install Sub Dist. Panels 8 100 12OCT09A 22MAR10A
Install Sub Dist. Panels
OP1F700 Public address Sysytem wiring 12 95 22OCT09A 23NOV10
Public address Sysytem wiring
OP1F320 Data system wiring 12 95 25OCT09A 23NOV10
Data system wiring
OP1F720 Central Clock System wiring 8 95 08NOV09A 22NOV10
Central Clock System wiring
OP1F780 Inst floor trunk & box 8 90 20MAR10A 23NOV10
Inst floor trunk & box

SECOND FLOOR
OP2F110 Fix Conduits in Walls 76 100 01APR07A 30APR07A
Fix Conduits in Walls
OP2F190 Fix Cable Trays 32 100 03MAR08A 19MAR08A
Fix Cable Trays
OP2F730 Powr Cables puling & termntion 12 95 20MAR08A 23NOV10
Powr Cables puling & termntion
OP2F260 Conduiting / Wiring Abv Ceiling 36 100 02JUL08A 27JUL08A
Conduiting / Wiring Abv Ceiling
OP2F620 Install Sub Dist. Panels 8 100 12SEP09A 22MAR10A
Install Sub Dist. Panels
OP2F270 Fire Alarm system wiring 16 95 23SEP09A 23NOV10
Fire Alarm system wiring
OP2F320 Data system wiring 12 95 10NOV09A 23NOV10
Data system wiring

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 83 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
OP2F700 Public address Sysytem wiring 12 95 10NOV09A 23NOV10
Public address Sysytem wiring
OP2F640 Telephone System wiring 12 92 24NOV09A 23NOV10
Telephone System wiring
OP2F720 Central Clock System wiring 8 95 24NOV09A 22NOV10
Central Clock System wiring
OP2F740 ACC wiring 10 100 22MAR10A 01APR10A
ACC wiring

ROOF TOP
OPRT610 Cable Tray installation 2 100 21OCT09A 07MAR10A
Cable Tray installation
OPRT620 Power cable puling & termntion 2 70 24NOV09A 23NOV10
Power cable puling & termntion
OPRT630 Electrical work 1 90 01FEB10A 22NOV10
Electrical work
OPRT600 Lightening Protectioning work 3 90 24MAR10A 22NOV10
Lightening Protectioning work

Electrical Fixtures
GROUND FLOOR
OPE320 Fix Elec Lights 12 16 10OCT10A 04DEC10
Fix Elec Lights
OPE330 Fix LC equip. 10 0 10FEB11 21FEB11
Fix LC equip.
OPE245 Fix receptacles Outlet & Switches 10 0 22FEB11 05MAR11
Fix receptacles Outlet & Switches

FIRST FLOOR
OP1F800 Install Light Fixtures 18 60 19JUN10A 30NOV10
Install Light Fixtures
OP1F740 Fix LC equip. 8 0 09MAR11 17MAR11
Fix LC equip.
OP1F560 Power Receptacles & Switches 10 0 19MAR11 29MAR11
Power Receptacles & Switches

SECOND FLOOR
OP2F800 Install Light Fixtures 18 55 26JUN10A 01DEC10
Install Light Fixtures
OP2F750 Fix LC equip. 8 0 13MAR11 21MAR11
Fix LC equip.
OP2F560 Power Receptacles & Switches 10 0 22MAR11 02APR11
Power Receptacles & Switches

TEST & COMMISSION

OPRT640 Test & commission Elect work 21 0 05DEC10 28DEC10


Test & commission Elect work

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 84 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

READY to HAND OVER


Final Clean Up to Hand Over

OPHO786 Ready to Hand Over 7 0 11JUN11 18JUN11


Ready to Hand Over

Kidney Center
CIVIL WORKS
Mobilize
GROUND FLOOR
KN1000 Mobilize 40 100 16JUL05A 02AUG06A
Mobilize

Struc plans Submittal


GROUND FLOOR
KNGD010C Get Aprvl Exc Plan/Layout Gr-1 28 100 06AUG06A 21DEC06A
Get Aprvl Exc Plan/Layout Gr-1
KNGDC100 Get Aprvl Grd Beam Gr-2 30 100 16DEC07A 19MAR08A
Get Aprvl Grd Beam Gr-2

Earth Works
GROUND FLOOR
KNKC1100G Excavate Foundations 6 100 15JAN06A 21JAN06A
Excavate Foundations
KNKC1500G Back fill to Grade Level 4 100 02APR06A 05APR06A
Back fill to Grade Level

Concrete Works
GROUND FLOOR
KNKC1200G Under Grnd Conc Works 60 100 22JAN06A 01APR06A
Under Grnd Conc Works
KNKC2000G Superstructure Concrete works 325 100 06APR06A 23APR07A
Superstructure Concrete works

ARCHITECTURAL WORKS
Architectural Plans Submittal
GROUND FLOOR
KNDF010F Get Aprvl Floor Plans Gr-1 15 100 22JAN08A 10FEB08A
Get Aprvl Floor Plans Gr-1
KNGDF100 Get Aprvl Ref. Clng Plan Gr-2 30 100 11FEB08A 14APR08A
Get Aprvl Ref. Clng Plan Gr-2
KNGDF200 Get Aprvl Door/Wind Sch Gr-3 20 100 02FEB10A 13SEP10A
Get Aprvl Door/Wind Sch Gr-3
KNGDF300 Get Aprvl Toilet Det Gr-4 20 100 25FEB10A 16SEP10A
Get Aprvl Toilet Det Gr-4

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 85 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Arch. Materials Submittal


GROUND FLOOR
KNG5115SMF Get Aprvl Ceramic Wall Tiles 26 100 01APR08A 30APR08A
Get Aprvl Ceramic Wall Tiles
KNG5125SMF Get Approval Ceramic Floor Tiling 26 100 02APR08A 31MAY08A
Get Approval Ceramic Floor Tiling
KNG5100SMF Get Aprvl Plaster Accesories 18 100 11MAR09A 31MAR09A
Get Aprvl Plaster Accesories
KNG5130SMF Get Approval Procelain Tiles 1 100 01JUN09A 02JUN10A
Get Approval Procelain Tiles
KNG5145SMF Get Aprvl Alum. Ceiling System 21 100 29MAY10A 22JUN10A
Get Aprvl Alum. Ceiling System
KNG5135SMF Get Aprvl Metal Ceiling Tiles 18 100 08JUN10A 28JUN10A
Get Aprvl Metal Ceiling Tiles
KNG5120SMF Get Approval Painting Materials 18 0 23NOV10 13DEC10
Get Approval Painting Materials
KNG5150SMF Get Aprvl Terrazo Tiles 3 0 23NOV10 25NOV10
Get Aprvl Terrazo Tiles
KNG5155SMF Get Aprvl Mrbl Tread/Riser 3 0 27NOV10 29NOV10
Get Aprvl Mrbl Tread/Riser
KNG5160SMF Get Aprvl Stair Hand Rail 3 0 30NOV10 02DEC10
Get Aprvl Stair Hand Rail
KNG5170SMF Get Aprvl Sign Boards 18 0 30NOV10 20DEC10
Get Aprvl Sign Boards
KNG5140SMF Get Aprvl Ext Granito Paint 18 0 14DEC10 03JAN11
Get Aprvl Ext Granito Paint

Procure Arch Materials


GROUND FLOOR
KNG5115PRF Procure Ceramic Wall Tiles 60 100 07JUN10A 16SEP10A
Procure Ceramic Wall Tiles
KNG5125PRF Procure Ceramic Floor Tiles 60 100 07JUN10A 16SEP10A
Procure Ceramic Floor Tiles
KNG5130PRF Procure Porcelein Floor Tiles 12 0 23NOV10 06DEC10
Procure Porcelein Floor Tiles
KNG5135PRF Procure Metal Ceiling Tiles 30 0 23NOV10 27DEC10
Procure Metal Ceiling Tiles
KNG5145PRF Proc. Aluminum Ceiling System 20 0 23NOV10 15DEC10
Proc. Aluminum Ceiling System
KNG6100PRF Procure Plaster Accesories 12 0 23NOV10 06DEC10
Procure Plaster Accesories
KNG5150PRF Procure Terrazo Tiles 15 0 27NOV10 13DEC10
Procure Terrazo Tiles
KNG5155PRF Proc Mrbl Stair Tread/ riser 12 0 30NOV10 13DEC10
Proc Mrbl Stair Tread/ riser
KNG5160PRF Procure Stair Hand Rails 15 0 04DEC10 20DEC10
Procure Stair Hand Rails

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 86 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
KNG5120PRF Procure Painting Materials 21 0 14DEC10 06JAN11
Procure Painting Materials
KNG5170PRF Procure Sign Boards 30 0 21DEC10 24JAN11
Procure Sign Boards
KNG5140PRF Procure Ext Granito Paint 26 0 04JAN11 02FEB11
Procure Ext Granito Paint

Masonry Works
GROUND FLOOR
KNKB1200G Block Work (CMU) 103 100 25DEC06A 14DEC09A
Block Work (CMU)

FIRST FLOOR
KDCF1000 Block Work (CMU) 50 100 10FEB08A 06MAR08A
Block Work (CMU)

ROOF TOP
KDCRT300 Block Work (CMU) 20 100 10APR08A 08MAR10A
Block Work (CMU)

Water Proofing & Insulation


GROUND FLOOR
KNKW1050 Water Proof Wet Areas 9 100 08MAR10A 17MAR10A
Water Proof Wet Areas

FIRST FLOOR
KDCF1320 Water Proof Wet Areas 9 100 01MAR10A 11MAR10A
Water Proof Wet Areas

ROOF TOP
KNKW1800 Fix Roof Insulation / Gravel 7 100 02MAR08A 24MAY08A
Fix Roof Insulation / Gravel
KNKW1100 Roof Screed 4 100 12MAR08A 16MAR08A
Roof Screed
KNKW1200 Water Proof Membrane 8 100 17MAR08A 26MAR08A
Water Proof Membrane
KNKW2000 Metal Flashing & Caulking 4 100 25MAR08A 26MAR08A
Metal Flashing & Caulking
KNKW1500 Water Test Roof Membrane 3 100 27MAR08A 30MAR08A
Water Test Roof Membrane

Doors & Windows


GROUND FLOOR
KNKD1100 Fix Door Frames 50 100 10AUG09A 13MAR10A
Fix Door Frames
KNKD1200 Install Metal Door Panels 7 0 11DEC10 18DEC10
Install Metal Door Panels
KNKD1500 Fix Wooden door panels 12 0 19DEC10 01JAN11
Fix Wooden door panels
KNKD2000 Alum Windows Double Glazed 8 0 19DEC10 27DEC10
Alum Windows Double Glazed

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 87 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
KNKD2100 Fix Aluminium Door 5 0 28DEC10 02JAN11
Fix Aluminium Door
KNKD1300 Fix Door Hardware 12 0 05JAN11 18JAN11
Fix Door Hardware

FIRST FLOOR
KDCF1460 Fix Door Frames 18 100 16AUG09A 09MAR10A
Fix Door Frames
KDCF1510 Alum Windows Double Glazed 8 0 23NOV10 01DEC10
Alum Windows Double Glazed
KDCF1750 Install Metal Door Panels 7 0 02DEC10 09DEC10
Install Metal Door Panels
KDCF1770 Fix Aluminium Door 5 0 02DEC10 07DEC10
Fix Aluminium Door
KNKDF150 Fix Wooden door panels 10 0 11DEC10 21DEC10
Fix Wooden door panels
KDCF1940 Fix Door Hardware 12 0 22DEC10 04JAN11
Fix Door Hardware

ROOF TOP
KDCFRT200 Fix Door Frames 6 0 23NOV10 29NOV10
Fix Door Frames
KDCFRT210 Fix Door metal Panels 5 0 30NOV10 05DEC10
Fix Door metal Panels
KDCFRT220 Fix Door Hard Ware 5 0 06DEC10 11DEC10
Fix Door Hard Ware

Pre-Finishing Works Walls


GROUND FLOOR
KNKF1200G Plaster Works Walls Interior 60 100 28FEB07A 28DEC07A
Plaster Works Walls Interior
KNKF1300 Putty & Primer Coat Ordinary 48 100 09JAN08A 13MAR10A
Putty & Primer Coat Ordinary
KNKF1340 Fix Ceramic Wall Tiles 38 100 15APR08A 09MAR10A
Fix Ceramic Wall Tiles
KNKF1210 Exterior Alumn Panel 21 98 15OCT09A 22NOV10
Exterior Alumn Panel
KNKF1220 Exterior Curtain Wall Glasses 14 95 24JUL10A 23NOV10
Exterior Curtain Wall Glasses
KNKF190G Putty Primer Anti Bact. Paint 28 0 23NOV10 25DEC10
Putty Primer Anti Bact. Paint

FIRST FLOOR
KDCF1030 Plaster Works Walls Interior 60 100 21MAY09A 10MAR10A
Plaster Works Walls Interior
KDCF1190 Putty & Primer Coat Ordinary 60 100 27MAY09A 13MAR10A
Putty & Primer Coat Ordinary
KDCF1330 Fix Ceramic Wall Tiles 50 100 26SEP09A 13MAR10A
Fix Ceramic Wall Tiles
KDCF1480 Exterior Alumn Panel 21 100 16OCT09A 16SEP10A
Exterior Alumn Panel

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 88 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
KDCF1200 Exterior Curtain Wall Glasses 10 100 24JUL10A 19SEP10A
Exterior Curtain Wall Glasses
KNKF190F Putty Primer Anti Bact. Paint 28 0 23NOV10 25DEC10
Putty Primer Anti Bact. Paint

ROOF TOP
KDCRT5010 Internal Plaster (Walls, Col. & Stair) 10 100 26APR10A 04MAY10A
Internal Plaster (Walls, Col. & Stair)
KDCRT500 Putty & Primer Coat Ordinary 9 100 06MAY10A 16MAY10A
Putty & Primer Coat Ordinary

Pre-Finishing Works Ceilings


GROUND FLOOR
KNKF7200 Plaster Ceiling 10 100 10AUG09A 21SEP09A
Plaster Ceiling
KNKF7000 Install F. Ceiling Grid 25 75 01JUN10A 29NOV10
Install F. Ceiling Grid
KNKF7300 Grand Insptn Abv Ceiling 4 100 26JUN10A 30JUN10A
Grand Insptn Abv Ceiling
KNKF7100 Install Alum Ceiling Wet Areas 12 0 16DEC10 29DEC10
Install Alum Ceiling Wet Areas

FIRST FLOOR
KDCF1610 Plaster Ceiling 10 100 16MAY09A 26MAY09A
Plaster Ceiling
KDCF1670 Grand Insptn Abv Ceiling 4 100 16MAY10A 23MAY10A
Grand Insptn Abv Ceiling
KDCF2070 Install F. Ceiling Grid 25 75 27MAY10A 29NOV10
Install F. Ceiling Grid
KDCF2140 Install Alum Ceiling Wet Areas 12 0 30NOV10 13DEC10
Install Alum Ceiling Wet Areas

ROOF TOP
KDCCRT100 Ceiling Grid 9 75 14JUN10A 23NOV10
Ceiling Grid
MDCCRT110 Ceiling tiles 3 0 24NOV10 27NOV10
Ceiling tiles

Final Floor Finishing Works


GROUND FLOOR
KNKF1350 Fix Ceramic Floor Tiles 9 100 17FEB10A 25APR10A
Fix Ceramic Floor Tiles
KNKF1360 Fix Marble Floor Tiles 60 95 08JUL10A 25NOV10
Fix Marble Floor Tiles
KNKF1365 Fix Terrazo Floor Tiles 10 0 10JAN11 20JAN11
Fix Terrazo Floor Tiles
KNKF1400 Saudi Granite Tread / Riser 10 0 22JAN11 01FEB11
Saudi Granite Tread / Riser
KNKF1500 Marble Threshold 8 0 02FEB11 10FEB11
Marble Threshold

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 89 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
KNKF9000 Final Cleaning 3 0 31MAY11 04JUN11
Final Cleaning

FIRST FLOOR
KDCF2080 Fix Marble Floor Tiles 21 95 14NOV09A 23NOV10
Fix Marble Floor Tiles
KDCF2020 Fix Ceramic Floor Tiles 9 100 27FEB10A 29APR10A
Fix Ceramic Floor Tiles
KDCF2120 Fix Terrazo Floor Tiles 10 0 29DEC10 09JAN11
Fix Terrazo Floor Tiles
KDCF2170 Saudi Granite Tread / Riser 10 0 10JAN11 20JAN11
Saudi Granite Tread / Riser
KDCF2240 Marble Threshold 8 0 22JAN11 30JAN11
Marble Threshold
KDCF2430 Final Cleaning 3 0 29MAR11 02APR11
Final Cleaning

ROOF TOP
KDCRT100 Fix MarbleFloor Tiles 10 0 09DEC10 20DEC10
Fix MarbleFloor Tiles
KDCRT110 Fix Terrazo Floor Tiles 7 0 21DEC10 28DEC10
Fix Terrazo Floor Tiles
KDCRT115 Marble Threshold 3 0 21DEC10 23DEC10
Marble Threshold

Final Wall Finishing Works


GROUND FLOOR
KNKF300 Final 2 Coats of Anti Bacteria 20 0 18JAN11 09FEB11
Final 2 Coats of Anti Bacteria
KNKF1320 Final Painting Coat 20 0 12MAR11 03APR11
Final Painting Coat

FIRST FLOOR
KDCF300 Final 2 Coats of Anti Bacteria 20 0 26DEC10 17JAN11
Final 2 Coats of Anti Bacteria
KDCF2250 Final Painting Coat 20 0 16FEB11 10MAR11
Final Painting Coat

ROOF TOP
KDCRT400 Final Painting Coat 10 0 25DEC10 04JAN11
Final Painting Coat

Final Ceiling Finishing Works


GROUND FLOOR
KNKF7500 Install Metal Ceiling Panels 15 0 04APR11 20APR11
Install Metal Ceiling Panels

FIRST FLOOR
KDCF2380 Install Metal Ceiling Panels 15 0 12MAR11 28MAR11
Install Metal Ceiling Panels

ROOF TOP
KDCFRT600 Armstrong accoustic Ceiling 10 0 28NOV10 08DEC10
Armstrong accoustic Ceiling

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 90 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Metal Works
GROUND FLOOR
KNKF6160 Fix Wall Guards 7 0 01DEC10 08DEC10
Fix Wall Guards
KNKF1410 Fix Stair Hand Rails 6 0 02FEB11 08FEB11
Fix Stair Hand Rails

FIRST FLOOR
KDCF1520 Fix Wall Guards 7 0 23NOV10 30NOV10
Fix Wall Guards
KDCF2230 Fix Stair Hand Rails 6 0 09FEB11 15FEB11
Fix Stair Hand Rails

Specialties
GROUND FLOOR
KNKF2500 Install sign Boards 9 0 04APR11 13APR11
Install sign Boards

FIRST FLOOR
KDCF2260 Install sign Boards 9 0 12MAR11 21MAR11
Install sign Boards

Furnishing
GROUND FLOOR
KNKF6125 Fix Railing System for Curtains 10 0 28DEC10 08JAN11
Fix Railing System for Curtains

FIRST FLOOR
KDCF1760 Fix Railing System for Curtains 10 0 02DEC10 13DEC10
Fix Railing System for Curtains

MECHANICAL WORKS
Plumbing Plans Submittal
GROUND FLOOR
KNGDP050 Get Aprvl. Water Supply Gr-2 30 100 24DEC07A 27FEB08A
Get Aprvl. Water Supply Gr-2
KNGDP100 Get Aprvl Ceiling Drain Gr-3 30 100 28FEB08A 01APR08A
Get Aprvl Ceiling Drain Gr-3
KNNDG010P Get Aprvl Drain. Plans Gr-1 20 100 01MAR10A 01APR10A
Get Aprvl Drain. Plans Gr-1
KNGDP200 Get Aprvl Firefighting Gr-4 20 100 14MAR10A 01APR10A
Get Aprvl Firefighting Gr-4
KNGDP210 Get Appr. Toilet utilites 6 100 14MAR10A 01APR10A
Get Appr. Toilet utilites
KNGDP220 Get Appr. Plumbing Fixtures 6 100 14MAR10A 01APR10A
Get Appr. Plumbing Fixtures

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 91 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

HVAC Plans Submittal


GROUND FLOOR
KNGD010H Get Aprvl HVAC Plans 60 100 16OCT08A 27NOV08A
Get Aprvl HVAC Plans

Plumbing Materials Submittal


GROUND FLOOR
KNG500MP Get Appr. Toilet Utilities 6 100 14MAR10A 14MAR10A
Get Appr. Toilet Utilities
KNG5115SMP Get Approval Water Piping 18 100 14MAR10A 14MAR10A
Get Approval Water Piping
KNG5125SMP Get Approval Plumbing Fixtures 26 100 14MAR10A 14MAR10A
Get Approval Plumbing Fixtures
KNGM010P Get Aprvl Drainage Piping 18 100 14MAR10A 14MAR10A
Get Aprvl Drainage Piping

KNGP1000 Get Appr. RO Plant (Alternate submittal) 14 0 23NOV10 08DEC10


Get Appr. RO Plant (Alternate submittal)

HVAC Materials Submittal


GROUND FLOOR
KNG5125SMM Get Aprvl HVAC Duct Materials 18 100 14MAR10A 14MAR10A
Get Aprvl HVAC Duct Materials
KNG5200SMM Get Aprvl HVAC Equipments 48 100 14MAR10A 14MAR10A
Get Aprvl HVAC Equipments

Procure Plumbing Materials


GROUND FLOOR
KNG5115PRP Procure Water Piping 40 100 14JAN07A 01MAR07A
Procure Water Piping
KNG5125PRP Procure Plumbing Fixtures 30 50 18OCT10A 01JAN11
Procure Plumbing Fixtures
KNG1000PRP Procure Toilet Utilities 30 0 23NOV10 27DEC10
Procure Toilet Utilities

Procure HVAC Materials


GROUND FLOOR
KNG5200PRM Proc. HVAC Equipments 120 100 07FEB10A 01MAR10A
Proc. HVAC Equipments
KNG5125PRM Proc. HVAC Duct Materials 36 100 14MAR10A 31MAR10A
Proc. HVAC Duct Materials

Delivery of Plumbing Material

KNGPP150 Delievery of R.O Plant 25 0 09DEC10 06JAN11


Delievery of R.O Plant

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 92 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Elevators
GROUND FLOOR
KNKM6200 Install Elevator 55 25 26JUN10A 09JAN11
Install Elevator

HVAC Works
GROUND FLOOR
KNKH1100 Install Ducts 50 100 22FEB07A 25NOV07A
Install Ducts
KNKH1200 Test HVAC Ducts 3 100 03DEC07A 06DEC07A
Test HVAC Ducts
KNKH1300 Insulate Ducts HVAC 16 100 08MAR10A 08MAR10A
Insulate Ducts HVAC
KNKH3000 Install Ceiling Diffusers 15 0 23NOV10 09DEC10
Install Ceiling Diffusers
KNKH2100 Install Split Type Units 12 0 11DEC10 23DEC10
Install Split Type Units

FIRST FLOOR
KDCF1020 Install Ducts 50 100 10MAY09A 06SEP09A
Install Ducts
KDCF1150 Test HVAC Ducts 3 100 12AUG09A 15AUG09A
Test HVAC Ducts
KDCF1110 Insulate Ducts HVAC 16 100 06SEP09A 23SEP09A
Insulate Ducts HVAC
KDCF2310 Install Ceiling Diffusers 15 0 11DEC10 27DEC10
Install Ceiling Diffusers
KDCF1580 Install Split Type Units 12 0 16DEC10 29DEC10
Install Split Type Units

ROOF TOP
KNKH3500 Install Package Units 5 100 22MAY09A 22MAR10A
Install Package Units
KNKH2500 Install Roof Exhaust Fans 21 0 23NOV10 16DEC10
Install Roof Exhaust Fans

Plumbing Works
GROUND FLOOR
KNKP1050G Fix U/Grnd Drainage Pipes 8 100 30JAN06A 07FEB06A
Fix U/Grnd Drainage Pipes
KNKP1200G Install Hot/Cold Water Pipes Walls 18 100 28APR07A 17MAY07A
Install Hot/Cold Water Pipes Walls
KNKP1700 Fix Drainage Pipes Abv Ceiling 12 100 28APR07A 10MAY07A
Fix Drainage Pipes Abv Ceiling
KNKP1800 Test Drainage Pipe Abv Clng 3 100 12MAY07A 14MAY07A
Test Drainage Pipe Abv Clng
KNKP1300G Test Hot/Cold Water pipes 3 100 19MAY07A 21MAY07A
Test Hot/Cold Water pipes
KNKP1500 Hot/Cold Water Piping Abv Ceiling 12 100 24JUL07A 02DEC07A
Hot/Cold Water Piping Abv Ceiling

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 93 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
KNKP1600 Test Hot/Cold Water Piping Abv Ceiling 4 100 21MAR09A 24MAY09A
Test Hot/Cold Water Piping Abv Ceiling
KNKP2950 Fix Floor Drains 4 100 01APR10A 01APR10A
Fix Floor Drains
KNKP1675 Tag Hot/Cold Water Pipes 8 0 23NOV10 01DEC10
Tag Hot/Cold Water Pipes
KNKP2975 Install R.O. Plant 30 0 08JAN11 10FEB11
Install R.O. Plant
KNKP3000 Install Plumbing Fixtures 14 0 21APR11 07MAY11
Install Plumbing Fixtures
KNKP3100 Fix Toilet Accessories 12 0 08MAY11 21MAY11
Fix Toilet Accessories

FIRST FLOOR
KDCF1080 Fix Drainage Pipes Abv Ceiling 12 100 10APR09A 23MAY09A
Fix Drainage Pipes Abv Ceiling
KDCF1090 Test Drainage Pipe Abv Clng 3 100 01JUN09A 01JUN09A
Test Drainage Pipe Abv Clng
KDCF1120 Hot/Cold Water Piping Abv Ceiling 12 100 05JUL09A 17AUG09A
Hot/Cold Water Piping Abv Ceiling
KDCF1070 Install Hot/Cold Water Pipes Walls 18 100 12JUL09A 02AUG09A
Install Hot/Cold Water Pipes Walls
KDCF1100 Test Hot/Cold Water pipes 3 100 01SEP09A 01SEP09A
Test Hot/Cold Water pipes
KDCF1490 Tag Hot/Cold Water Pipes 2 100 01SEP09A 30SEP09A
Tag Hot/Cold Water Pipes
KDCF1500 Test Hot/Cold Water Piping Abv Ceiling 4 100 21NOV09A 24NOV09A
Test Hot/Cold Water Piping Abv Ceiling
KDCF1260 Fix Floor Drains 4 100 01APR10A 01APR10A
Fix Floor Drains
KDCF2400 Install Plumbing Fixtures 14 0 29MAR11 13APR11
Install Plumbing Fixtures
KDCF2410 Fix Toilet Accessories 12 0 14APR11 27APR11
Fix Toilet Accessories

Fire Fighting Works


GROUND FLOOR
KNKP8000 Install Fire Fighting Pipes 28 100 28APR07A 14MAR08A
Install Fire Fighting Pipes
KNKP8040 Tagging of Fire Water Pipes 2 100 24SEP07A 26DEC08A
Tagging of Fire Water Pipes
KNKP8035 Painting Fire Water Pipes 3 100 21AUG09A 26SEP09A
Painting Fire Water Pipes
KNKP8025 Press. Test Fire Fight. Pipes 4 100 21NOV09A 24NOV09A
Press. Test Fire Fight. Pipes
KNKP8100 Fix FHC 5 100 13MAR10A 16MAR10A
Fix FHC
KNKP8050 Fix Fire Sprinklers 12 0 30NOV10 13DEC10
Fix Fire Sprinklers

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 94 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
KNKP8075 Fix Flow Switches 8 0 14DEC10 22DEC10
Fix Flow Switches

FIRST FLOOR
KDCF1050 Install Fire Fighting Pipes 28 100 10JUL08A 12SEP08A
Install Fire Fighting Pipes
KDCF1630 Painting Fire Water Pipes 3 100 21SEP09A 21MAR10A
Painting Fire Water Pipes
KDCF1530 Press. Test Fire Fight. Pipes 4 100 09NOV09A 14NOV09A
Press. Test Fire Fight. Pipes
KDCF2220 Fix FHC 5 100 13MAR10A 16MAR10A
Fix FHC
KDCF1650 Tagging of Fire Water Pipes 6 0 23NOV10 29NOV10
Tagging of Fire Water Pipes
KDCF2130 Fix Fire Sprinklers 12 0 30NOV10 13DEC10
Fix Fire Sprinklers
KDCF2180 Fix Flow Switches 8 0 14DEC10 22DEC10
Fix Flow Switches

Medical Gases Works


GROUND FLOOR
KNKM1120 Install Med Gases Fixtures 18 75 16SEP10A 28NOV10
Install Med Gases Fixtures

FIRST FLOOR
KDCF2270 Install Med Gases Fixtures 18 75 18SEP10A 28NOV10
Install Med Gases Fixtures

TEST & COMMISSION

KDCF100 Flush /Cleaning Med. Gas system 6 0 29NOV10 05DEC10


Flush /Cleaning Med. Gas system
KDCF2280 Test & Comm. Med Gases 12 0 06DEC10 19DEC10
Test & Comm. Med Gases
KNKP8110 Flush /Clean Fire Fighting Pipe 6 0 23DEC10 29DEC10
Flush /Clean Fire Fighting Pipe
KNKH9000 Test / Commission HVAC 8 0 22MAY11 30MAY11
Test / Commission HVAC
KNKP2985 Flush /Clean Water Pipe 6 0 22MAY11 28MAY11
Flush /Clean Water Pipe

ELECTRICAL WORKS
Elec Plans Submittal
GROUND FLOOR
KNGD010E Get Aprvl power Layout Elec 20 100 17FEB08A 11MAR08A
Get Aprvl power Layout Elec
KNGDE100 Get Aprvl Lighting Layout 30 100 07MAR10A 14MAR10A
Get Aprvl Lighting Layout
KNGDE120 get Aprvl TV, Tel & Data Layout 30 100 14MAR10A 14MAR10A
get Aprvl TV, Tel & Data Layout

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 95 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Elec. Materials Submittal


GROUND FLOOR
KNG5100SME Get Approval Elec Conduits 25 100 14APR09A 14MAR10A
Get Approval Elec Conduits
KNG5135SME Get Approval Elec. Cables 25 100 14MAR10A 14MAR10A
Get Approval Elec. Cables
KNG5150SME Get Approval MDB 25 100 14MAR10A 14MAR10A
Get Approval MDB
KNG5400SME Get Approval Light Fixtures 6 100 08MAY10A 14JUN10A
Get Approval Light Fixtures
KNG5450SME Get Aprvl Central Clock System 6 100 15JUN10A 21JUN10A
Get Aprvl Central Clock System
KNG5500SME Get Approval Fire Alarm Sytem 6 100 22JUN10A 28JUN10A
Get Approval Fire Alarm Sytem

Procure Elec Materials


GROUND FLOOR
KNG5100PRE Procure Elec Conduits 12 100 14MAR10A 14MAR10A
Procure Elec Conduits
KNG5135PRE Procure Electrical Cables 30 100 14MAR10A 14MAR10A
Procure Electrical Cables
KNG5150PRE Procure MDB 70 100 14MAR10A 14MAR10A
Procure MDB
KNG5400PRE Procure Light Fixtures 70 100 01SEP10A 16SEP10A
Procure Light Fixtures
KNG5450PRE Procure Central Clock System 30 100 04SEP10A 27OCT10A
Procure Central Clock System
KNG5500PRE Procure Fire Alarm System 30 100 04SEP10A 27OCT10A
Procure Fire Alarm System

Electrical works
GROUND FLOOR
KNKE1500G Fix Conduits in Walls 76 100 11JAN07A 02DEC07A
Fix Conduits in Walls
KNKE3400 Telephone System wiring 12 100 16SEP07A 28NOV07A
Telephone System wiring
KNKE1800 Conduiting / Wiring Abv Ceiling 36 100 10DEC07A 13DEC07A
Conduiting / Wiring Abv Ceiling
KNKE3000 Fire Alarm system wiring 16 92 13DEC08A 23NOV10
Fire Alarm system wiring
KNKE3600 Public address Sysytem wiring 12 92 21JAN09A 23NOV10
Public address Sysytem wiring
KNKE2200 Install MDB & termination work 10 93 14OCT09A 23NOV10
Install MDB & termination work
KNKE2300 Install Sub Dist. Panels 8 100 17OCT09A 26OCT09A
Install Sub Dist. Panels
KNKE2000 Powr Cables puling & termintion 12 93 28OCT09A 23NOV10
Powr Cables puling & termintion

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 96 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
KNKE3500 Data System wiring KNKE3500 12 92 19NOV09A 23NOV10
Data System wiring KNKE3500
KNKE3700 Central Clock System wiring 10 95 28DEC09A 22NOV10
Central Clock System wiring
KNKE5010 MATV system wiring 10 90 08FEB10A 23NOV10
MATV system wiring
KNKE1300G Nurse call sys(Cndut/Wiring) 10 75 14AUG10A 24NOV10
Nurse call sys(Cndut/Wiring)
KNKE290 BHU wiring 10 0 25NOV10 06DEC10
BHU wiring

FIRST FLOOR
KDCF1010 Fix Conduits in Walls 76 100 10NOV08A 06FEB09A
Fix Conduits in Walls
KDCF1160 Conduiting / Wiring Abv Ceiling 36 100 10NOV08A 21DEC08A
Conduiting / Wiring Abv Ceiling
KDCF1880 Install Sub Dist. Panels 8 100 14FEB09A 22FEB09A
Install Sub Dist. Panels
KDCF1350 Fire Alarm system wiring 16 92 12SEP09A 23NOV10
Fire Alarm system wiring
KDCF2340 Central Clock System wiring 10 95 03OCT09A 22NOV10
Central Clock System wiring
KDCF1140 Telephone System wiring 12 92 04NOV09A 23NOV10
Telephone System wiring
KDCF1370 Public address Sysytem wiring 12 93 18NOV09A 23NOV10
Public address Sysytem wiring
KDCF1470 Data system wiring 12 92 19DEC09A 23NOV10
Data system wiring
KDCF2350 Power Cables puling &Termination 12 93 02JAN10A 23NOV10
Power Cables puling &Termination
KDCF2390 MATV system wiring 10 90 16FEB10A 23NOV10
MATV system wiring
KNKE1300FF Nurse call sys Wiring 10 0 24NOV10 05DEC10
Nurse call sys Wiring
KDCF290 BHU wiring 10 0 06DEC10 16DEC10
BHU wiring

ROOF TOP
KDCRT210 Cable Tray installation 2 100 28AUG09A 07MAR10A
Cable Tray installation
KDCRT220 Power cable puling & termntion 5 90 28NOV09A 22NOV10
Power cable puling & termntion
KDCRT230 Electrical work 3 90 22JAN10A 22NOV10
Electrical work
KDCRT200 Lightening Protectioning work 5 90 03JUN10A 22NOV10
Lightening Protectioning work

Electrical Fixtures
GROUND FLOOR
KNKE5000 Install Light Fixtures 18 45 26JUN10A 04DEC10
Install Light Fixtures
Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT
Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 97 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
KNKE2500 Power Receptacles 10 0 24NOV10 05DEC10
Power Receptacles
KNKE2700 Fix Switches 8 0 06DEC10 14DEC10
Fix Switches
KNKE5030 Fixing LC equip. 8 0 15DEC10 23DEC10
Fixing LC equip.
KNKE5020 BHU installation 14 0 28MAR11 12APR11
BHU installation

FIRST FLOOR
KDCF1700 Power Receptacles 10 100 24JAN09A 31JAN09A
Power Receptacles
KDCF2370 Install Light Fixtures 18 55 01JUL10A 05DEC10
Install Light Fixtures
KDCF1900 Fix Switches 8 0 23NOV10 01DEC10
Fix Switches
KDCF2450 Fix LC equip. 8 0 06DEC10 14DEC10
Fix LC equip.
KDCF2440 BHU installation 14 0 12MAR11 27MAR11
BHU installation

TEST & COMMISSION

KDCRT240 Test & commission elect work 26 0 13APR11 12MAY11


Test & commission elect work

READY to HAND OVER


Final Clean Up to Hand Over

KDHO786 Ready to hand over 5 0 05JUN11 09JUN11


Ready to hand over

Single Female Residential Building "A"


CIVIL WORKS
Concrete Works
GROUND FLOOR
SFRC100 Under Grnd Concrete Works 6 100 30APR06A 06MAY06A
Under Grnd Concrete Works
SFRC400 Super Struc. Conc works 200 100 30JUN06A 18FEB07A
Super Struc. Conc works

ARCHITECTURAL WORKS
Masonry Works
GROUND FLOOR
SFRB100 Block Work (CMU) 60 100 19FEB07A 23DEC09A
Block Work (CMU)

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 98 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
FIRST FLOOR
SFRB1F380 Block Work (CMU) 50 100 10FEB08A 20DEC09A
Block Work (CMU)

SECOND FLOOR
SFRB2F280 Block Work (CMU) 50 100 10NOV08A 20DEC09A
Block Work (CMU)

Water Proofing & Insulation


GROUND FLOOR
RFW240 Water Proofing Wet Areas 16 100 16SEP09A 02NOV09A
Water Proofing Wet Areas

FIRST FLOOR
SF1F620 Water Proof Wet Areas 9 100 16SEP09A 25NOV09A
Water Proof Wet Areas

SECOND FLOOR
SF2F520 Water Proof Wet Areas 9 100 16AUG09A 25NOV09A
Water Proof Wet Areas

ROOF TOP
RFW100 Light Weight Conc Roof 14 100 11JUL08A 02AUG08A
Light Weight Conc Roof
RFW180 Roof Metal Flashing & Joints 10 100 25JUL08A 06SEP08A
Roof Metal Flashing & Joints
RFW120 Water Proofing Memb. Roof 18 100 11AUG08A 06SEP08A
Water Proofing Memb. Roof
RFW160 Fix Roof Insulation Sheets 12 100 25AUG08A 06SEP08A
Fix Roof Insulation Sheets
RFW200 Roof Graveling on Insulation 9 100 09OCT08A 09DEC09A
Roof Graveling on Insulation
RFW140 Test Roof Membrane 3 100 28NOV08A 29NOV08A
Test Roof Membrane

Doors & Windows


GROUND FLOOR
SFDG120 Fix Door Frames 36 100 10AUG09A 03APR10A
Fix Door Frames
SFDG100 Fix Window frames 15 100 09SEP09A 11NOV09A
Fix Window frames
SFDG180 Fix Exterior Windows 36 90 03MAY10A 27NOV10
Fix Exterior Windows
SFDG140 Fix Door metal Panels 18 0 23NOV10 13DEC10
Fix Door metal Panels
SFDG150 Fix Wooden door panels 9 0 04DEC10 13DEC10
Fix Wooden door panels
SFDG160 Fix Door Hard Ware 12 0 14DEC10 27DEC10
Fix Door Hard Ware

FIRST FLOOR
SF1AD120 Fix Door Frames 18 100 17NOV09A 10JAN10A
Fix Door Frames

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 99 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SF1AD130 Fix Window frames 15 100 08DEC09A 08DEC09A
Fix Window frames
SF1AD160 Fix Exterior Windows 36 90 22MAR10A 27NOV10
Fix Exterior Windows
SF1AD140 Fix Door metal Panels 21 0 23NOV10 16DEC10
Fix Door metal Panels
SF1AD170 Fix Wooden door panels 9 0 07DEC10 16DEC10
Fix Wooden door panels
SF1AD150 Fix Door Hard Ware 12 0 18DEC10 30DEC10
Fix Door Hard Ware

SECOND FLOOR
SF2AD120 Fix Door Frames 18 100 20NOV09A 09MAR10A
Fix Door Frames
SF2AD130 Fix Window frames 15 100 08DEC09A 08JAN10A
Fix Window frames
SF2AD160 Fix Exterior Windows 36 90 21APR10A 27NOV10
Fix Exterior Windows
SF2AD140 Fix Wooden Door Panels 24 0 23NOV10 20DEC10
Fix Wooden Door Panels
SF2AD180 Fix Door Metal Panels 12 0 07DEC10 20DEC10
Fix Door Metal Panels
SF2AD150 Fix Door Hard Ware 10 0 21DEC10 01JAN11
Fix Door Hard Ware
SF2AD170 Fix Roof Sky Lights 15 0 02JAN11 18JAN11
Fix Roof Sky Lights

Pre-Finishing Works Walls


GROUND FLOOR
RFF100 Plaster Walls Internal 30 100 26MAR07A 08MAR10A
Plaster Walls Internal
RFF180 Putty & Primer Coat Ordinary 35 100 27APR07A 09MAR10A
Putty & Primer Coat Ordinary
RFF120 Plaster Walls External 60 100 14APR09A 10MAR10A
Plaster Walls External
RFF160 Fix Ceramic Wall Tiles 40 100 10NOV09A 30DEC09A
Fix Ceramic Wall Tiles

FIRST FLOOR
SF1AW200 Plaster Walls Internal 30 100 26MAR07A 17DEC09A
Plaster Walls Internal
SF1AW210 Putty & Primer Coat Ordinary 35 100 27APR07A 08MAR10A
Putty & Primer Coat Ordinary
SF1AW230 Plaster Walls External 60 100 14APR09A 10MAR10A
Plaster Walls External
SF1AW220 Fix Ceramic Wall Tiles 40 100 25OCT09A 19DEC09A
Fix Ceramic Wall Tiles

SECOND FLOOR
SF2AW200 Plaster Walls Internal 30 100 26MAR07A 14DEC09A
Plaster Walls Internal

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 100 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SF2AW210 Putty & Primer Coat Ordinary 35 100 27APR07A 09MAR10A
Putty & Primer Coat Ordinary
SF2AW220 Fix Ceramic Wall Tiles 40 100 13AUG08A 19DEC09A
Fix Ceramic Wall Tiles
SF2AW230 Plaster Walls External 60 100 14APR09A 08MAR10A
Plaster Walls External

Pre-Finishing Works Ceilings


GROUND FLOOR
RFF105 Plaster Celings Internal 56 100 23JUN09A 28OCT09A
Plaster Celings Internal
RFF240 Fix Grids False Ceiling 12 95 03NOV09A 23NOV10
Fix Grids False Ceiling
RFF540 Fix Gypsum Board Ceiling 10 90 04MAR10A 23NOV10
Fix Gypsum Board Ceiling
RFF110 Grand Insptn Abv Ceiling 3 100 24APR10A 27APR10A
Grand Insptn Abv Ceiling
RFF500 Fix Metal Ceiling 12 0 07DEC10 20DEC10
Fix Metal Ceiling
RFF300 Fix False Ceiling Tiles 10 0 16DEC10 27DEC10
Fix False Ceiling Tiles
RFF560 Ceiling Paint 15 0 28DEC10 13JAN11
Ceiling Paint

FIRST FLOOR
SF1A520 Plaster Celings Internal 56 100 30MAY09A 21SEP09A
Plaster Celings Internal
SF1A540 Fix Grids False Ceiling 12 100 03NOV09A 18JUN10A
Fix Grids False Ceiling
SF1A510 Fix Gypsum Board Ceiling 10 90 18APR10A 23NOV10
Fix Gypsum Board Ceiling
SF1A530 Grand Insptn Abv Ceiling 3 100 24APR10A 27APR10A
Grand Insptn Abv Ceiling
SF1A500 Fix Metal Ceiling 12 0 23NOV10 06DEC10
Fix Metal Ceiling
SF1A550 Fix False Ceiling Tiles 10 0 05DEC10 15DEC10
Fix False Ceiling Tiles
SF1A560 Ceiling Paint 15 0 16DEC10 02JAN11
Ceiling Paint

SECOND FLOOR
SF2A520 Plaster Celings Internal 56 100 11MAY09A 21DEC09A
Plaster Celings Internal
SF2A510 Fix Gypsum Board Ceiling 10 100 16NOV09A 08MAR10A
Fix Gypsum Board Ceiling
SF2A530 Grand Insptn Abv Ceiling 3 100 13APR10A 15APR10A
Grand Insptn Abv Ceiling
SF2A540 Fix Grids False Ceiling 26 100 25APR10A 19MAY10A
Fix Grids False Ceiling
SF2A500 Fix Metal Ceiling 12 0 23NOV10 06DEC10
Fix Metal Ceiling
Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT
Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 101 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SF2A550 Fix False Ceiling Tiles 10 0 05DEC10 15DEC10
Fix False Ceiling Tiles
SF2A560 Ceiling Paint 15 0 19FEB11 07MAR11
Ceiling Paint

Pre-Finishing Work
GROUND FLOOR
RFF200 Floor Screed 18 100 27AUG09A 19OCT09A
Floor Screed

FIRST FLOOR
SF1AF200 Floor Screed 18 100 13AUG09A 17OCT09A
Floor Screed

SECOND FLOOR
SF2AF200 Floor Screed 18 100 06AUG09A 24OCT09A
Floor Screed

Final Floor Finishing Works


GROUND FLOOR
RFF220 Marble Flooring Tile 40 80 06DEC09A 01DEC10
Marble Flooring Tile
RFF280 Ceramic Floor Tiling 26 100 17MAR10A 24MAR10A
Ceramic Floor Tiling
RFF320 Granite Floor Tiling 25 0 23NOV10 21DEC10
Granite Floor Tiling
RFF405 Fix Base Porcelain 6 0 15DEC10 21DEC10
Fix Base Porcelain
RFF340 Fix Tread Risers for Stairs 36 0 22DEC10 01FEB11
Fix Tread Risers for Stairs
RFF400 Fix Wall Base Granite 6 0 22DEC10 28DEC10
Fix Wall Base Granite
RFF410 Fix Marble Threshold 8 0 27DEC10 04JAN11
Fix Marble Threshold
RFF900 Final Cleaning 7 0 08MAY11 15MAY11
Final Cleaning

FIRST FLOOR
SF1AF300 Marble Flooring Tile 50 80 09DEC09A 04DEC10
Marble Flooring Tile
SF1AF310 Ceramic Floor Tiling 30 100 06MAR10A 25APR10A
Ceramic Floor Tiling
SF1AF360 Fix Wall Base marble 8 75 14JUN10A 24NOV10
Fix Wall Base marble
SF1AF320 Fix Base Porcelain 8 0 06DEC10 14DEC10
Fix Base Porcelain
SF1AF340 Granite Floor Tiling 18 0 06DEC10 26DEC10
Granite Floor Tiling
SF1AF330 Fix Marble Threshold 10 0 15DEC10 26DEC10
Fix Marble Threshold

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 102 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SF1AF350 Fix Tread Risers for Stairs 18 0 27DEC10 16JAN11
Fix Tread Risers for Stairs
SF1AF370 Final Cleaning 3 0 03JAN11 05JAN11
Final Cleaning

SECOND FLOOR
SF2AF300 Marble Flooring Tile 50 95 10JAN10A 25NOV10
Marble Flooring Tile
SF2AF310 Ceramic Floor Tiling 30 100 28FEB10A 23MAR10A
Ceramic Floor Tiling
SF2AF360 Fix Wall Base Marble 8 75 10APR10A 24NOV10
Fix Wall Base Marble
SF2AF320 Fix Base Porcelain 8 0 27NOV10 05DEC10
Fix Base Porcelain
SF2AF330 Fix Marble Threshold 10 0 06DEC10 16DEC10
Fix Marble Threshold
SF2AF340 Granite Floor Tiling 18 0 06DEC10 26DEC10
Granite Floor Tiling
SF2AF350 Fix Tread Risers for Stairs 18 0 27DEC10 16JAN11
Fix Tread Risers for Stairs
SF2AF370 Final Cleaning 5 0 08MAR11 13MAR11
Final Cleaning

Final Wall Finishing Works

RFF260 Textured Paint External Walls 36 75 08MAR10A 02DEC10


Textured Paint External Walls
RFF420 Final Paint Coat Walls 21 0 19JAN11 12FEB11
Final Paint Coat Walls

Metal Works
GROUND FLOOR
RFF380 Fix Hand Rails 12 0 25JAN11 07FEB11
Fix Hand Rails

FIRST FLOOR
SF1F740 Fix Hand Rails 12 0 08FEB11 21FEB11
Fix Hand Rails

SECOND FLOOR
SF2F640 Fix Hand Rails 12 0 22FEB11 07MAR11
Fix Hand Rails

MECHANICAL WORKS
HVAC Works
GROUND FLOOR
RFH120 Fix Ducts 26 100 17SEP08A 08MAR10A
Fix Ducts
RFH140 Test Ducts 4 100 17NOV08A 07MAR10A
Test Ducts

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 103 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
RFH180 Fix Flexible Ducts Exhaust 8 100 22MAR10A 30MAR10A
Fix Flexible Ducts Exhaust
RFH200 Fix Exhaust Grills 20 0 29NOV10 21DEC10
Fix Exhaust Grills
RFH300 Fix Window Type A/c Units 15 0 03FEB11 20FEB11
Fix Window Type A/c Units

FIRST FLOOR
SF1AH600 Fix Ducts 26 100 17AUG08A 08MAR10A
Fix Ducts
SF1AH610 Test Ducts 4 100 17NOV08A 07MAR10A
Test Ducts
SF1AH630 Fix Flexible Ducts Exhaust 8 100 22MAR10A 30MAR10A
Fix Flexible Ducts Exhaust
SF1AH660 Fix Ex Grills 20 0 23NOV10 15DEC10
Fix Ex Grills
SF1AH680 Fix Window Type A/c Units 22 0 08FEB11 05MAR11
Fix Window Type A/c Units

SECOND FLOOR
SF2AH600 Fix Ducts 26 100 17JUL08A 08MAR10A
Fix Ducts
SF2AH610 Test Ducts 4 100 17NOV08A 07MAR10A
Test Ducts
SF2AH630 Fix Flexible Ducts Exhaust 8 100 24APR10A 02MAY10A
Fix Flexible Ducts Exhaust
SF2AH660 Fix Ex Grills 20 0 07DEC10 29DEC10
Fix Ex Grills
SF2AH680 Fix Window Type A/c Units 22 0 13FEB11 09MAR11
Fix Window Type A/c Units

ROOF TOP
RF240 Fix Exhaust Fans 20 0 10MAR11 02APR11
Fix Exhaust Fans

Plumbing Works
GROUND FLOOR
RFP160 Test Hot&Cold Water 62 100 16SEP08A 14MAR10A
Test Hot&Cold Water
RFP180 Fix Rain Water Pipes 18 100 26DEC08A 18JAN09A
Fix Rain Water Pipes
RFP200 Test Rain Water Pipes 3 100 20JAN09A 07MAR10A
Test Rain Water Pipes
RFFP210 Fix FCO & Floor Drains 20 100 13MAR10A 21APR10A
Fix FCO & Floor Drains
RFP220 Install Plumbing Fixtures 35 0 23NOV10 02JAN11
Install Plumbing Fixtures
RFP240 Install Elec. Water Heaters 25 0 03JAN11 31JAN11
Install Elec. Water Heaters

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 104 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
FIRST FLOOR
SF1AP700 Fix Rain Water Pipes 18 100 26NOV07A 18JAN08A
Fix Rain Water Pipes
SF1AP710 Test Rain Water Pipes 3 100 20JAN08A 07MAR10A
Test Rain Water Pipes
SF1AP720 Test Hot&Cold Water 62 100 16SEP08A 14MAR10A
Test Hot&Cold Water
SF1AP740 Fix FCO & Floor Drains 20 100 13MAR10A 17APR10A
Fix FCO & Floor Drains
SF1AP750 Install Plumbing Fixtures 35 0 03JAN11 12FEB11
Install Plumbing Fixtures
SF1AP760 Install Elec. Water Heaters 25 0 13FEB11 13MAR11
Install Elec. Water Heaters

SECOND FLOOR
SF2AP700 Fix Rain Water Pipes 18 100 26DEC07A 18FEB08A
Fix Rain Water Pipes
SF2AP710 Test Rain Water Pipes 3 100 20JAN08A 07MAR10A
Test Rain Water Pipes
SF2AP720 Test Hot&Cold Water 62 100 16SEP08A 14MAR10A
Test Hot&Cold Water
SF2AP740 Fix FCO & Floor Drains 20 100 14FEB10A 29MAR10A
Fix FCO & Floor Drains
SF2AP750 Install Plumbing Fixtures 35 0 13FEB11 24MAR11
Install Plumbing Fixtures
SF2AP760 Install Elec. Water Heaters 25 0 26MAR11 23APR11
Install Elec. Water Heaters

Fire Fighting Works


GROUND FLOOR
RFP100 Install Fire Water Pipes 26 100 13AUG07A 21JUN08A
Install Fire Water Pipes
RFP120 Test Fire Pipes 3 100 22SEP08A 07MAR10A
Test Fire Pipes
RFP140 Fix Fire Hose Cabinets 5 100 21JUN09A 08MAR10A
Fix Fire Hose Cabinets
RFP130 Painting Fire Water Pipes 3 100 22JAN10A 24FEB10A
Painting Fire Water Pipes
RFP135 Tagging of Fire Water Pipes 5 0 23NOV10 28NOV10
Tagging of Fire Water Pipes
RFP145 Fix Fire Extinguishers 10 0 23NOV10 04DEC10
Fix Fire Extinguishers

FIRST FLOOR
SF1A100 Install Fire Water Pipes 26 100 13NOV07A 21APR08A
Install Fire Water Pipes
SF1A120 Test Fire Pipes 3 100 22JUN08A 07MAR10A
Test Fire Pipes
SF1A150 Fix Fire Hose Cabinets 5 100 21SEP09A 08MAR10A
Fix Fire Hose Cabinets

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 105 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SF1A110 Painting Fire Water Pipes 3 100 22FEB10A 28FEB10A
Painting Fire Water Pipes
SF1A140 Tagging of Fire Water Pipes 5 0 23NOV10 28NOV10
Tagging of Fire Water Pipes
SF1A160 Fix Fire Extinguishers 10 0 05DEC10 15DEC10
Fix Fire Extinguishers

SECOND FLOOR
SF2A100 Install Fire Water Pipes 26 100 13AUG07A 21FEB08A
Install Fire Water Pipes
SF2A120 Test Fire Pipes 3 100 22APR08A 07MAR10A
Test Fire Pipes
SF2A150 Fix Fire Hose Cabinets 5 100 21JUL09A 08MAR10A
Fix Fire Hose Cabinets
SF2A110 Painting Fire Water Pipes 3 100 22FEB10A 08MAR10A
Painting Fire Water Pipes
SF2A140 Tagging of Fire Water Pipes 5 0 23NOV10 28NOV10
Tagging of Fire Water Pipes
SF2A160 Fix Fire Extinguishers 10 0 16DEC10 27DEC10
Fix Fire Extinguishers

TEST & COMMISSION

RFP250 Flush/Clean Water Pipe 3 0 12FEB11 14FEB11


Flush/Clean Water Pipe
RFP900 Test & Comm. Mech Works 12 0 24APR11 07MAY11
Test & Comm. Mech Works

ELECTRICAL WORKS
Electrical works
GROUND FLOOR
RFE100 Conduit / Wiring Ceiling 100 100 06NOV07A 14DEC07A
Conduit / Wiring Ceiling
RFE160 Install Dist. Panels 18 100 29JUL08A 11AUG08A
Install Dist. Panels
RFE120 Power Cables puling & termantion 24 95 08OCT08A 23NOV10
Power Cables puling & termantion
RFE220 Fire Alarm System wiring 18 95 17NOV08A 23NOV10
Fire Alarm System wiring
RFE140 Install MDB & termination work 8 100 19JUN09A 22MAR10A
Install MDB & termination work
RFE180 Tel. System wiring 18 90 18NOV09A 24NOV10
Tel. System wiring
RFE190 TV System wiring 12 90 01MAR10A 23NOV10
TV System wiring

FIRST FLOOR
SF1AE100 Conduit / Wiring Ceiling 100 100 06MAY07A 14SEP07A
Conduit / Wiring Ceiling

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 106 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SF1AE110 Install Dist. Panels 18 100 29JUL07A 11AUG07A
Install Dist. Panels
SF1AE130 Power Cables puling & termntion 24 95 11NOV08A 23NOV10
Power Cables puling & termntion
SF1AE120 Fire Alarm System 18 95 17NOV08A 23NOV10
Fire Alarm System
SF1AE140 Tel. System wiring 18 90 16NOV09A 24NOV10
Tel. System wiring
SF1AE150 TV System wiring 15 90 10MAR10A 24NOV10
TV System wiring

SECOND FLOOR
SF2AE100 Conduit / Wiring Ceiling 100 100 06NOV06A 14NOV06A
Conduit / Wiring Ceiling
SF2AE110 Install Dist. Panels 18 100 29JUL08A 11AUG08A
Install Dist. Panels
SF2AE130 Powr Cables puling & termntion 24 95 11OCT08A 23NOV10
Powr Cables puling & termntion
SF2AE120 Fire Alarm System wiring 18 95 17NOV08A 23NOV10
Fire Alarm System wiring
SF2AE170 Install MDB 8 100 17JUL09A 22MAR10A
Install MDB
SF2AE140 Tel. System wiring 18 90 12OCT09A 24NOV10
Tel. System wiring
SF2AE150 TV System wiring 12 90 15MAR10A 23NOV10
TV System wiring

ROOF TOP
SFRT120 Cable Tray installation 2 100 25APR09A 07MAR10A
Cable Tray installation
SFRT140 Electrical work 3 90 01FEB10A 22NOV10
Electrical work
SFRT110 Lightening Protectioning work 5 90 20MAR10A 22NOV10
Lightening Protectioning work

Electrical Fixtures
GROUND FLOOR
RFE240 Fix Elec Lights 21 40 20MAY10A 07DEC10
Fix Elec Lights
RFE270 Fix LC equip. 7 0 12DEC10 19DEC10
Fix LC equip.
RFE260 Fix Receptacles / Switches 12 0 20DEC10 02JAN11
Fix Receptacles / Switches

FIRST FLOOR
SF1AE190 Fix Elec Lights 21 60 20MAY10A 01DEC10
Fix Elec Lights
SF1AE200 Fix Receptacles / Switches 15 0 02DEC10 19DEC10
Fix Receptacles / Switches
SF1AE210 Fix LC equip. 7 0 04DEC10 11DEC10
Fix LC equip.

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 107 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SECOND FLOOR
SF2AE190 Fix Elec Lights 21 70 15MAY10A 29NOV10
Fix Elec Lights
SF2AE220 Fix LC equip. 7 0 25NOV10 02DEC10
Fix LC equip.
SF2AE200 Fix Receptacles / Switches 12 0 30NOV10 13DEC10
Fix Receptacles / Switches

TEST & COMMISSION

SF2TCE210 Test Comm. Electrical Works 26 0 03JAN11 01FEB11


Test Comm. Electrical Works

READY to HAND OVER


Final Clean Up to Hand Over

SFAHO786 Ready to hand over 5 0 16MAY11 21MAY11


Ready to hand over

Single Female Residential Building "B"


CIVIL WORKS
Concrete Works
GROUND FLOOR
RFC100S Under Grnd Concrete Works 50 100 30JUN05A 27AUG05A
Under Grnd Concrete Works
RFC400S Super Struc. Conc works 200 100 28AUG05A 17APR06A
Super Struc. Conc works

ARCHITECTURAL WORKS
Masonry Works
GROUND FLOOR
RFB100S Block Work (CMU) 60 100 18APR06A 23OCT09A
Block Work (CMU)

FIRST FLOOR
SF1F1018S Block Work (CMU) 50 100 10JAN07A 20OCT09A
Block Work (CMU)

SECOND FLOOR
SF2F1018S Block Work (CMU) 50 100 10JUL07A 20OCT09A
Block Work (CMU)

Water Proofing & Insulation


GROUND FLOOR
RFW240S Water Proofing Wet Areas 21 100 17NOV09A 09DEC09A
Water Proofing Wet Areas

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 108 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
FIRST FLOOR
SF1B1042S Water Proof Wet Areas 9 100 17NOV09A 26DEC09A
Water Proof Wet Areas

SECOND FLOOR
SF2B1042S Water Proof Wet Areas 9 100 17NOV09A 26DEC09A
Water Proof Wet Areas

ROOF TOP
RFW100S Light Weight Conc Roof 14 100 11JUL06A 02AUG06A
Light Weight Conc Roof
RFW160S Fix Roof Insulation Sheets 12 100 25AUG06A 30OCT07A
Fix Roof Insulation Sheets
RFW120S Water Proofing Memb. Roof 18 100 11SEP06A 16SEP06A
Water Proofing Memb. Roof
RFW180S Roof Metal Flashing & Joints 8 100 25SEP06A 28NOV08A
Roof Metal Flashing & Joints
RFW200S Roof Graveling on Insulation 9 100 04NOV07A 11SEP09A
Roof Graveling on Insulation
RFW140S Test Roof Membrane 3 100 28NOV07A 29NOV07A
Test Roof Membrane

Doors & Windows


GROUND FLOOR
RFD180S Fix Windows frame 30 100 05MAY09A 10MAR10A
Fix Windows frame
RFD120S Fix Door Frames 36 100 11AUG09A 11MAR10A
Fix Door Frames
RFD140S Fix Door metal Panels 18 5 23NOV10 27DEC10
Fix Door metal Panels
RFD150S Fix Wooden door panels 22 0 28DEC10 22JAN11
Fix Wooden door panels
RFD160S Fix Door Hard Ware 20 0 23JAN11 14FEB11
Fix Door Hard Ware

FIRST FLOOR
SF1B120S Fix Door Frames 36 100 11JUL09A 09MAR10A
Fix Door Frames
SF1B123S Fix Windows frame 30 100 03AUG09A 10MAR10A
Fix Windows frame
SF1B121S Fix Door metal Panels 24 0 14DEC10 10JAN11
Fix Door metal Panels
SF1BD160S Fix Wooden door panels 22 0 11JAN11 05FEB11
Fix Wooden door panels
SF1B122S Fix Door Hard Ware 20 0 06FEB11 28FEB11
Fix Door Hard Ware

SECOND FLOOR
SF2B120S Fix Door Frames 36 100 11JUN09A 09MAR10A
Fix Door Frames
SF2B123S Fix Windows frames 30 100 03SEP09A 10MAR10A
Fix Windows frames

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 109 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SF2B121S Fix Door metal Panels 18 0 23NOV10 13DEC10
Fix Door metal Panels
SF2B160S Fix Wooden door panels 22 0 14DEC10 08JAN11
Fix Wooden door panels
SF2B122S Fix Door Hard Ware 20 0 09JAN11 31JAN11
Fix Door Hard Ware
SF2B124S Fix Roof Sky Lights 25 0 01FEB11 01MAR11
Fix Roof Sky Lights

Pre-Finishing Works Walls


GROUND FLOOR
RFF100S Plaster Walls Internal 120 100 23JAN08A 08MAR10A
Plaster Walls Internal
RFF160S Fix Ceramic Wall Tiles 115 100 18FEB08A 17AUG09A
Fix Ceramic Wall Tiles
RFF180S Putty & Primer Coat Ordinary 268 100 25JUL08A 09MAR10A
Putty & Primer Coat Ordinary
RFF120S Plaster Walls External 55 100 09JUL09A 10MAR10A
Plaster Walls External

FIRST FLOOR
SF1BW200 Plaster Walls Internal 120 100 23MAY06A 02JAN10A
Plaster Walls Internal
SF1BW210 Putty & Primer Coat Ordinary 268 100 25JUL08A 07MAR10A
Putty & Primer Coat Ordinary
SF1BW220 Fix Ceramic Wall Tiles 115 100 18APR09A 26DEC09A
Fix Ceramic Wall Tiles
SF1BW230 Plaster Walls External 55 100 11JUL09A 10MAR10A
Plaster Walls External

SECOND FLOOR
SF2BW200 Plaster Walls Internal 120 100 23APR08A 03JAN10A
Plaster Walls Internal
SF2BW210 Putty & Primer Coat Ordinary 268 100 25JUN08A 21MAR10A
Putty & Primer Coat Ordinary
SF2BW220 Fix Ceramic Wall Tiles 115 100 18MAY09A 13NOV09A
Fix Ceramic Wall Tiles
SF2BW230 Plaster Walls External 55 100 11JUN09A 10MAR10A
Plaster Walls External

Pre-Finishing Works Ceilings


GROUND FLOOR
RFF105S Plaster Celings Internal 50 100 11FEB08A 07MAR08A
Plaster Celings Internal
RFF540S Fix Gypsum Board Ceiling 10 100 02OCT09A 08MAR10A
Fix Gypsum Board Ceiling
RFF110S Grand Insptn Abv Ceiling 3 100 24APR10A 27APR10A
Grand Insptn Abv Ceiling
RFF240S Fix Grids False Ceiling 26 100 04MAY10A 16SEP10A
Fix Grids False Ceiling

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 110 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
RFF300S Fix False Ceiling Tiles 18 0 23NOV10 13DEC10
Fix False Ceiling Tiles
RFF500S Fix Metal Ceiling 12 0 23NOV10 06DEC10
Fix Metal Ceiling
RFF560S Ceiling Paint 20 0 01FEB11 23FEB11
Ceiling Paint

FIRST FLOOR
SF1B502S Plaster Celings Internal 50 100 11MAR08A 07APR09A
Plaster Celings Internal
SF1B501S Fix Gypsum Board Ceiling 10 100 03SEP09A 07JAN10A
Fix Gypsum Board Ceiling
SF1B503S Grand Insptn Abv Ceiling 3 100 19APR10A 22APR10A
Grand Insptn Abv Ceiling
SF1B504S 85Fix Grids False Ceiling 26 100 29APR10A 10JUN10A
85Fix Grids False Ceiling
SF1B500S Fix Metal Ceiling 12 0 23NOV10 06DEC10
Fix Metal Ceiling
SF1B505S Fix False Ceiling Tiles 18 0 23NOV10 13DEC10
Fix False Ceiling Tiles
SF1B506S Ceiling Paint 20 0 20JAN11 12FEB11
Ceiling Paint

SECOND FLOOR
SF2B502S Plaster Celings Internal 50 100 11APR08A 20NOV09A
Plaster Celings Internal
SF2B501S Fix Gypsum Board Ceiling 10 100 03SEP09A 02JAN10A
Fix Gypsum Board Ceiling
SF2B503S Grand Insptn Abv Ceiling 3 100 14APR10A 15APR10A
Grand Insptn Abv Ceiling
SF2B504S Fix Grids False Ceiling 26 100 20APR10A 09JUN10A
Fix Grids False Ceiling
SF2B500S Fix Metal Ceiling 12 0 23NOV10 06DEC10
Fix Metal Ceiling
SF2B505S Fix False Ceiling Tiles 18 0 23NOV10 13DEC10
Fix False Ceiling Tiles
SF2B506S Ceiling Paint 20 0 28DEC10 19JAN11
Ceiling Paint

Pre-Finishing Work
GROUND FLOOR
RFF200S Floor Screed 18 100 07JUL09A 01NOV09A
Floor Screed

FIRST FLOOR
SF1B200S Floor Screed 25 100 22MAR09A 19APR09A
Floor Screed

SECOND FLOOR
SF2B200S Floor Screed 18 100 25MAY09A 07OCT09A
Floor Screed

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 111 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Final Floor Finishing Works


GROUND FLOOR
RFF220S Marble Flooring Tile 30 80 07NOV09A 29NOV10
Marble Flooring Tile
RFF280S Ceramic Floor Tiling 36 100 23MAR10A 24APR10A
Ceramic Floor Tiling
RFF320S Granite Floor Tiling 18 0 23NOV10 13DEC10
Granite Floor Tiling
RFF405S Fix Base Porcelain 7 0 30NOV10 07DEC10
Fix Base Porcelain
RFF400S Fix Wall Base Granite 10 0 14DEC10 25DEC10
Fix Wall Base Granite
RFF340S Fix Tread Risers for Stairs 20 0 30JAN11 21FEB11
Fix Tread Risers for Stairs
RFF900S Clean Up Hand Over 3 0 31MAR11 03APR11
Clean Up Hand Over

FIRST FLOOR
SF1B300S Marble Flooring Tile 30 80 29OCT09A 06DEC10
Marble Flooring Tile
SF1B301S Ceramic Floor Tiling 42 100 20MAR10A 17APR10A
Ceramic Floor Tiling
SF1B304S Granite Floor Tiling 18 0 23NOV10 13DEC10
Granite Floor Tiling
SF1B302S Fix Base Porcelain 7 0 07DEC10 14DEC10
Fix Base Porcelain
SF1B306S Fix Wall Base Granite 10 0 14DEC10 25DEC10
Fix Wall Base Granite
SF1B305S Fix Tread Risers for Stairs 20 0 06JAN11 29JAN11
Fix Tread Risers for Stairs
SF1B307S Clean Up Hand Over 3 0 01MAR11 03MAR11
Clean Up Hand Over

SECOND FLOOR
SF2B300S Marble Flooring Tile 30 90 18OCT09A 25NOV10
Marble Flooring Tile
SF2B301S Ceramic Floor Tiling 42 100 10MAR10A 23MAR10A
Ceramic Floor Tiling
SF2B304S Granite Floor Tiling 18 0 23NOV10 13DEC10
Granite Floor Tiling
SF2B302S Fix Base Porcelain 7 0 27NOV10 04DEC10
Fix Base Porcelain
SF2B306S Fix Wall Base Granite 10 0 11DEC10 21DEC10
Fix Wall Base Granite
SF2B305S Fix Tread Risers for Stairs 20 0 14DEC10 05JAN11
Fix Tread Risers for Stairs
SF2B307S Clean Up Hand Over 3 0 01FEB11 03FEB11
Clean Up Hand Over

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 112 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Final Wall Finishing Works


GROUND FLOOR
RFF260S Textured Paint External Walls 25 80 13MAR10A 28NOV10
Textured Paint External Walls
SFFPW100S Primer Base Paint 15 95 03APR10A 23NOV10
Primer Base Paint
SFFPW200S 1st coat Paint 17 90 24APR10A 24NOV10
1st coat Paint
RFF420S Final Paint Coat Walls 25 0 02MAR11 30MAR11
Final Paint Coat Walls

FIRST FLOOR
SF1B510S Primer Base Paint 15 95 13MAR10A 23NOV10
Primer Base Paint
SF1B410S Textured Paint External Walls 25 85 25MAR10A 27NOV10
Textured Paint External Walls
SF1B520S 1st coat Paint 17 90 15APR10A 24NOV10
1st coat Paint
SF1B420S Final Paint Coat Walls 25 0 26DEC10 23JAN11
Final Paint Coat Walls

SECOND FLOOR
SF2B400S Primer Base Paint 15 95 01MAR10A 23NOV10
Primer Base Paint
SF2B700S Textured Paint External Walls 18 85 13MAR10A 25NOV10
Textured Paint External Walls
SF2B600S 1st coat Paint 17 77 11APR10A 27NOV10
1st coat Paint
SF2B402S Final Paint Coat Walls 25 0 22DEC10 19JAN11
Final Paint Coat Walls

Metal Works
GROUND FLOOR
RFF380S Fix Hand Rails 12 0 10FEB11 23FEB11
Fix Hand Rails

FIRST FLOOR
SF1B380S Fix Hand Rails 12 0 30JAN11 12FEB11
Fix Hand Rails

SECOND FLOOR
SF2B380S Fix Hand Rails 12 0 06JAN11 19JAN11
Fix Hand Rails

MECHANICAL WORKS
HVAC Works
GROUND FLOOR
RFH120S Fix Ducts 26 100 14NOV08A 08MAR10A
Fix Ducts
RFH140S Test Ducts 4 100 14DEC08A 07MAR10A
Test Ducts

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 113 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
RFH180S Fix Flexible Ducts exhaust 15 0 23NOV10 09DEC10
Fix Flexible Ducts exhaust
RFH200S Fix Exhaust Grills 15 0 11DEC10 27DEC10
Fix Exhaust Grills
RFH300S Fix Window Type A/c Units 15 0 31MAR11 17APR11
Fix Window Type A/c Units

FIRST FLOOR
SF1B800 Fix Ducts 26 100 14NOV08A 08MAR10A
Fix Ducts
SF1B810 Test Ducts 4 100 14DEC08A 07MAR10A
Test Ducts
SF1B830 Fix Flexible Ducts exhaust 15 0 11DEC10 27DEC10
Fix Flexible Ducts exhaust
SF1B840 Fix Exhaust Grills 15 0 28DEC10 13JAN11
Fix Exhaust Grills
SF1B880 Fix Window Type A/c Units 15 0 29JAN11 14FEB11
Fix Window Type A/c Units

SECOND FLOOR
SF2B800 Fix Ducts 26 100 14NOV08A 08MAR10A
Fix Ducts
SF2B810 Test Ducts 4 100 14DEC08A 07MAR10A
Test Ducts
SF2B830 Fix Flexible Ducts exhaust 15 0 28DEC10 13JAN11
Fix Flexible Ducts exhaust
SF2B840 Fix Exhaust Grills 15 0 15JAN11 31JAN11
Fix Exhaust Grills
SF2B880 Fix Window Type A/c Units 15 0 20JAN11 06FEB11
Fix Window Type A/c Units

ROOF TOP
SF2B850 Fix Exhaust Fans 15 0 01FEB11 17FEB11
Fix Exhaust Fans

Plumbing Works
GROUND FLOOR
RFP180S Fix Rain Water Pipes 18 100 26FEB08A 18MAR08A
Fix Rain Water Pipes
RFP160S Fix & Test Hot/Cold Water Mains 62 100 01JUL08A 11OCT08A
Fix & Test Hot/Cold Water Mains
RFP200S Test Rain Water Pipes 3 100 19AUG08A 21SEP08A
Test Rain Water Pipes
RFFP210S Fix FCO & Floor Drains 20 100 23MAR10A 12JUN10A
Fix FCO & Floor Drains
RFP220S Install Plumbing Fixtures 15 0 23NOV10 09DEC10
Install Plumbing Fixtures
RFP240S Install Elec. Water Heaters 18 0 22JAN11 10FEB11
Install Elec. Water Heaters

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 114 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
FIRST FLOOR
SF1B510 Fix Rain Water Pipes 18 100 26MAR08A 18MAY08A
Fix Rain Water Pipes
SF1B500 Fix & Test Hot/Cold Water Mains 62 100 01JUN08A 11SEP08A
Fix & Test Hot/Cold Water Mains
SF1B520 Test Rain Water Pipes 3 100 19JUN08A 21JUL08A
Test Rain Water Pipes
SF1B540 Fix FCO & Floor Drains 20 100 21MAR10A 14APR10A
Fix FCO & Floor Drains
SF1B550 Install Plumbing Fixtures 15 0 23NOV10 09DEC10
Install Plumbing Fixtures
SF1B560 Install Elec. Water Heaters 18 0 01JAN11 20JAN11
Install Elec. Water Heaters

SECOND FLOOR
SF2B510 Fix Rain Water Pipes 18 100 26JAN08A 18MAY08A
Fix Rain Water Pipes
SF2B500 Fix & Test Hot/Cold Water Mains 62 100 01MAY08A 11NOV08A
Fix & Test Hot/Cold Water Mains
SF2B520 Test Rain Water Pipes 3 100 19JUL08A 21AUG08A
Test Rain Water Pipes
SF2B540 Fix FCO & Floor Drains 20 100 15MAR10A 04APR10A
Fix FCO & Floor Drains
SF2B550 Install Plumbing Fixtures 15 0 23NOV10 09DEC10
Install Plumbing Fixtures
SF2B560 Install Elec. Water Heaters 18 0 11DEC10 30DEC10
Install Elec. Water Heaters

Fire Fighting Works


GROUND FLOOR
RFP100S Install Fire Water Pipes 26 100 10OCT07A 05DEC07A
Install Fire Water Pipes
RFP120S Test Fire Pipes 3 100 11SEP08A 14NOV08A
Test Fire Pipes
RFP140S Fix Fire Hose Cabinets 5 100 15JUL09A 19SEP09A
Fix Fire Hose Cabinets
RFP130S Painting Fire Water Pipes 3 100 21JUL09A 22MAR10A
Painting Fire Water Pipes
RFP135S Tagging of Fire Water Pipes 5 0 23NOV10 28NOV10
Tagging of Fire Water Pipes

FIRST FLOOR
SF1B100 Install Fire Water Pipes 26 100 10OCT07A 05JAN08A
Install Fire Water Pipes
SF1B120 Test Fire Pipes 3 100 11NOV08A 14NOV08A
Test Fire Pipes
SF1B150 Fix Fire Hose Cabinets 5 100 15AUG09A 19SEP09A
Fix Fire Hose Cabinets
SF1B110 Painting Fire Water Pipes 3 100 21AUG09A 23MAR10A
Painting Fire Water Pipes

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 115 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SF1B140 Tagging of Fire Water Pipes 5 0 29NOV10 04DEC10
Tagging of Fire Water Pipes

SECOND FLOOR
SF2B100 Install Fire Water Pipes 26 100 10OCT07A 29JAN08A
Install Fire Water Pipes
SF2B120 Test Fire Pipes 3 100 11NOV08A 14DEC08A
Test Fire Pipes
SF2B150 Fix Fire Hose Cabinets 5 100 15JUL09A 19AUG09A
Fix Fire Hose Cabinets
SF2B110 Painting Fire Water Pipes 3 100 21SEP09A 23MAR10A
Painting Fire Water Pipes
SF2B140 Tagging of Fire Water Pipes 5 0 05DEC10 09DEC10
Tagging of Fire Water Pipes

ELECTRICAL WORKS
Electrical works
GROUND FLOOR
RFE100S Conduit / Wiring Ceiling 100 100 06NOV07A 17NOV07A
Conduit / Wiring Ceiling
RFE140S Install MDB & termination work 8 100 09MAY08A 17JUN08A
Install MDB & termination work
RFE160S Install Dist. Panels 18 100 29JUL08A 11AUG08A
Install Dist. Panels
RFE220S Fire Alarm System wiring 18 95 17NOV08A 23NOV10
Fire Alarm System wiring
RFE190S TV System wiring 12 90 03OCT09A 23NOV10
TV System wiring
RFE120S Powr Cables puling & termntion 24 100 12OCT09A 23MAR10A
Powr Cables puling & termntion
RFE180S Tel. System wiring 18 90 12OCT09A 24NOV10
Tel. System wiring

FIRST FLOOR
SF1B200 Conduit / Wiring Ceiling 100 100 06OCT07A 17OCT07A
Conduit / Wiring Ceiling
SF1B210 Install Dist. Panels 18 100 29JUN08A 11JUL08A
Install Dist. Panels
SF1B220 Fire Alarm System wiring 18 95 17JAN09A 23NOV10
Fire Alarm System wiring
SF1B230 Power Cables puling & termntion 24 100 12SEP09A 23MAR10A
Power Cables puling & termntion
SF1B250 TV System wiring 12 90 03OCT09A 23NOV10
TV System wiring
SF1B240 Tel. System wiring 18 90 12OCT09A 24NOV10
Tel. System wiring

SECOND FLOOR
SF2B200 Conduit / Wiring Ceiling 100 100 06JAN08A 17FEB08A
Conduit / Wiring Ceiling

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 116 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SF2B210 Install Dist. Panels 18 100 29OCT08A 11DEC08A
Install Dist. Panels
SF2B220 Fire Alarm System wiring 18 95 17JAN09A 23NOV10
Fire Alarm System wiring
SF2B230 Powr Cables puling & termnation 24 100 12SEP09A 23MAR10A
Powr Cables puling & termnation
SF2B240 Tel. System wiring 18 90 12SEP09A 24NOV10
Tel. System wiring
SF2B250 TV System wiring 12 90 03OCT09A 23NOV10
TV System wiring

ROOF TOP
SFBRT120 Cable Tray installation 2 100 02SEP09A 07MAR10A
Cable Tray installation
SFBRT130 Power cable puling & termntion 2 100 04NOV09A 07MAR10A
Power cable puling & termntion
SFBRT140 Electrical work 3 90 01FEB10A 22NOV10
Electrical work
SFBRT110 Lightening Protectioning work 5 90 03JUN10A 22NOV10
Lightening Protectioning work

Electrical Fixtures
GROUND FLOOR
RFE240S Fix Elec Lights 21 45 24MAY10A 06DEC10
Fix Elec Lights
RFE260S Fix Receptacles / Switches 12 0 07DEC10 20DEC10
Fix Receptacles / Switches
RFE260S10 Fix LC equip. 8 0 13DEC10 21DEC10
Fix LC equip.

FIRST FLOOR
SF1B290 Fix Elec Lights 21 70 20MAY10A 29NOV10
Fix Elec Lights
SF1B300 Fix Receptacles / Switches 12 0 30NOV10 13DEC10
Fix Receptacles / Switches
SF1B310 Fix LC equip. 8 0 04DEC10 12DEC10
Fix LC equip.

SECOND FLOOR
SF2B290 Fix Elec Lights 21 70 15MAY10A 29NOV10
Fix Elec Lights
SF2B310 Fix LC equip. 8 0 24NOV10 02DEC10
Fix LC equip.
SF2B300 Fix Receptacles / Switches 12 0 30NOV10 13DEC10
Fix Receptacles / Switches

READY to HAND OVER


Final Clean Up to Hand Over

SFBHO786 Ready to hand over 3 0 04APR11 06APR11


Ready to hand over

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 117 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Service Building
CIVIL WORKS
Struc plans Submittal
GROUND FLOOR
SBG4000 Fnlz Change to Scope Of Work 500 100 03MAY05A 06DEC06A
Fnlz Change to Scope Of Work
SBG4010 Get Aprvl Struc Plans 50 100 07DEC06A 06FEB07A
Get Aprvl Struc Plans

Concrete Works
GROUND FLOOR
SBC900 Under Grnd Concrete Works 50 100 10MAR07A 20FEB08A
Under Grnd Concrete Works
SBC910 Super Struc. Conc works 200 100 01JAN08A 09OCT08A
Super Struc. Conc works

ARCHITECTURAL WORKS
Masonry Works
GROUND FLOOR
SBB100 Block Work (CMU) 60 100 07APR08A 06DEC09A
Block Work (CMU)

FIRST FLOOR
SB1F100 Block Work (CMU) 60 100 11JUN08A 14MAR10A
Block Work (CMU)

Water Proofing & Insulation


GROUND FLOOR
SBW360 Water Proofing Wet Areas 15 32 24JUL10A 29NOV10
Water Proofing Wet Areas

FIRST FLOOR
SB1F340 Water Proof Wet Areas 7 100 22JUL10A 18SEP10A
Water Proof Wet Areas

ROOF TOP
SBW200 Light Weight Conc Roof 12 100 20JAN09A 09MAY09A
Light Weight Conc Roof
SBW220 Water Proofing Memb. Roof 14 100 28FEB09A 12NOV09A
Water Proofing Memb. Roof
SBW240 Test Roof Membrane 4 100 24MAY09A 10NOV09A
Test Roof Membrane
SBW280 Roof Metal Flashing & Joints 8 100 29MAY09A 11DEC09A
Roof Metal Flashing & Joints
SBW260 Fix Roof Insulation Sheets 6 100 30MAY09A 10DEC09A
Fix Roof Insulation Sheets
SBW300 Roof Graveling on Insulation 6 100 11JUN09A 02JAN10A
Roof Graveling on Insulation

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 118 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Doors & Windows


GROUND FLOOR
SBD100 Fix Door Frames 20 80 09JUN10A 27NOV10
Fix Door Frames
SBD130 Fix Door metal Panels 18 15 23OCT10A 09DEC10
Fix Door metal Panels
SBD190 Fix Exterior Windows 15 90 23OCT10A 24NOV10
Fix Exterior Windows
SBD140 Fix Roll Up Door 12 0 11DEC10 23DEC10
Fix Roll Up Door
SBD150 Fix Wooden door panels 7 0 11DEC10 18DEC10
Fix Wooden door panels
SBD160 Fix Door Hard Ware 10 0 22DEC10 02JAN11
Fix Door Hard Ware
SBD210 Fix Interior Alum Windows 4 0 25DEC10 28DEC10
Fix Interior Alum Windows

FIRST FLOOR
SB1D100 Fix Door Frames 20 60 10JUN10A 02DEC10
Fix Door Frames
SB1D120 Fix Door metal Panels 18 16 25OCT10A 09DEC10
Fix Door metal Panels
SB1D110 Fix Exterior Windows 15 0 25NOV10 12DEC10
Fix Exterior Windows
SB1D130 Fix Door 12 0 11DEC10 23DEC10
Fix Door
SB1D140 Fix Door Hard Ware 10 0 11DEC10 21DEC10
Fix Door Hard Ware
SB1D150 Fix Alum Windows 4 0 25DEC10 28DEC10
Fix Alum Windows

Pre-Finishing Works Walls


GROUND FLOOR
SBF100 Plaster Works Walls Interior 45 100 15NOV08A 23MAR10A
Plaster Works Walls Interior
SBF110 Install Metal Stud 26 100 21DEC08A 22MAR10A
Install Metal Stud
SBF105 Plaster Works Exterior Walls 22 100 07FEB09A 23MAR10A
Plaster Works Exterior Walls
SBF120 Install Dry Boards with Insultn 26 100 11MAY09A 05OCT10A
Install Dry Boards with Insultn
SBF140 Putty & Primer Coat Ordinary 30 100 08NOV09A 09OCT10A
Putty & Primer Coat Ordinary
SBF130 Fix Ceramic Wall Tiles 18 45 02OCT10A 04DEC10
Fix Ceramic Wall Tiles

FIRST FLOOR
SB1FW200 Plaster Works Walls Interior 45 100 15NOV08A 23MAR10A
Plaster Works Walls Interior

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 119 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SB1FW210 Install Metal Stud 26 100 21DEC08A 06AUG09A
Install Metal Stud
SB1FW220 Plaster Works Exterior Walls 40 100 07FEB09A 23MAR10A
Plaster Works Exterior Walls
SB1FW230 Install Dry Boards with Insultn 20 100 11JUN09A 09MAR10A
Install Dry Boards with Insultn
SB1FW250 Putty & Primer Coat Ordinary 18 87 21APR10A 27NOV10
Putty & Primer Coat Ordinary
SB1FW240 Fix Ceramic Wall Tiles 18 95 25SEP10A 23NOV10
Fix Ceramic Wall Tiles

Pre-Finishing Works Ceilings


GROUND FLOOR
SBF255 Grand Insptn Abv Ceiling 3 0 23DEC10 26DEC10
Grand Insptn Abv Ceiling
SBF240 Install Ceiling Grid systems 15 0 01JAN11 17JAN11
Install Ceiling Grid systems
SBF260 Install Gypsum Bd Ceiling 10 0 18JAN11 29JAN11
Install Gypsum Bd Ceiling
SBF300 Install Acc. Ceiling Panels 9 0 18JAN11 27JAN11
Install Acc. Ceiling Panels

FIRST FLOOR
SB1FC270 Grand Insptn Abv Ceiling 2 0 09DEC10 11DEC10
Grand Insptn Abv Ceiling
SB1FC280 Install Ceiling Grid systems 15 0 12DEC10 28DEC10
Install Ceiling Grid systems
SB1FC290 Install Gypsum Bd Ceiling 10 0 29DEC10 09JAN11
Install Gypsum Bd Ceiling
SB1FC300 Install Acc. Ceiling Panels 7 0 29DEC10 05JAN11
Install Acc. Ceiling Panels

Pre-Finishing Work
GROUND FLOOR
SBF360 Floor Screed 50 mm 25 85 02MAY10A 27NOV10
Floor Screed 50 mm

FIRST FLOOR
SBF370 Floor Screed 50 mm 3 100 25AUG10A 29AUG10A
Floor Screed 50 mm

Final Floor Finishing Works


GROUND FLOOR
SBF405 Fix Marble Tiles 15 30 10JUN10A 01DEC10
Fix Marble Tiles
SBF390 Fix Ceramic Floor Tiling 15 0 02DEC10 19DEC10
Fix Ceramic Floor Tiling
SBF465 Fix Skirting marbles 12 0 02DEC10 15DEC10
SBF390 Fix Skirting marbles
SBF570 Epoxy Paint to Floor 15 0 02DEC10 19DEC10
Epoxy Paint to Floor

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 120 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SBF495 Fix Tread / Risers Saudi Grnt 10 0 16DEC10 27DEC10
Fix Tread / Risers Saudi Grnt
SBF510 Fix Tread/Risers 6mm AntiSttc 10 0 16DEC10 27DEC10
Fix Tread/Risers 6mm AntiSttc
SBF525 Fix Tile Skirting 6 mm 10 0 20DEC10 30DEC10
Fix Tile Skirting 6 mm
SBF900 Final Clean Up for Hand Over 7 0 02MAR11 09MAR11
Final Clean Up for Hand Over

FIRST FLOOR
SB1FF310 Fix Marble Tiles 15 85 10APR10A 24NOV10
Fix Marble Tiles
SB1FF330 Fix Skirting Marble 12 60 23SEP10A 24NOV10
Fix Skirting Marble
SB1FF320 Fix Ceramic Floor Tiling 15 0 25NOV10 12DEC10
Fix Ceramic Floor Tiling
SB1FF340 Fix Tread / Risers Saudi Grnt 10 0 25NOV10 06DEC10
Fix Tread / Risers Saudi Grnt
SB1FF350 Fix Tread/Risers 6mm AntiSttc 10 0 25NOV10 06DEC10
Fix Tread/Risers 6mm AntiSttc
SB1FF380 Epoxy Paint to Floor 15 0 25NOV10 12DEC10
Epoxy Paint to Floor
SB1FF360 Fix Tile Skirting 6 mm 10 0 13DEC10 23DEC10
Fix Tile Skirting 6 mm
SB1FF450 Final Clean Up for Hand Over 7 0 23MAR11 30MAR11
Final Clean Up for Hand Over

Final Wall Finishing Works


GROUND FLOOR
SBF190 Primer Base Paint 15 90 05APR10A 24NOV10
Primer Base Paint
SBF150 External Walls Textured Coat 16 75 23SEP10A 27NOV10
External Walls Textured Coat
SBF180 1st coat Paint 17 0 25NOV10 14DEC10
1st coat Paint
SBF170 Final Painting Coat 18 0 09FEB11 01MAR11
Final Painting Coat

FIRST FLOOR
SB1F760 Primer Base Paint 15 90 12MAR10A 24NOV10
Primer Base Paint
SB1F740 External Walls Textured Coat 15 75 23NOV10 25NOV10
External Walls Textured Coat
SB1F770 1st coat Paint 17 0 25NOV10 14DEC10
1st coat Paint
SB1F780 Final Painting Coat 12 0 17JAN11 30JAN11
Final Painting Coat

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 121 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Final Ceiling Finishing Works


GROUND FLOOR
SBF280 Install Alum Panel Ceiling 15 0 22JAN11 07FEB11
Install Alum Panel Ceiling

FIRST FLOOR
SB1F830 Install Alum Panel Ceiling 10 0 10JAN11 20JAN11
Install Alum Panel Ceiling

Metal Works
GROUND FLOOR
SBF700 Install Hand Rails 7 0 28DEC10 04JAN11
Install Hand Rails

FIRST FLOOR
SB1F570 Fix Hand Rails 8 0 16DEC10 25DEC10
Fix Hand Rails

Specialties
FIRST FLOOR
SB1F790 Fix Toilet Accessories 14 0 22JAN11 06FEB11
Fix Toilet Accessories
SB2F120 Fix Over Head Crane 30 0 22JAN11 24FEB11
Fix Over Head Crane

MECHANICAL WORKS
HVAC Works
GROUND FLOOR
SBH130 Chilled Water Piping 36 90 02NOV08A 27NOV10
Chilled Water Piping
SBH100 Install Ducts HVAC 21 95 14DEC08A 23NOV10
Install Ducts HVAC
SBP465 Install Boiler 100 100 21AUG09A 22JUN10A
Install Boiler
SBH160 Test / Inspct Ducts 20 75 19APR10A 23NOV10
Test / Inspct Ducts
SBH250 Insulate Ducting 15 90 25APR10A 23NOV10
Insulate Ducting
SBH330 Install FCU 18 90 10MAY10A 24NOV10
Install FCU
SBP485 Boiler accessories 50 80 23JUN10A 04DEC10
Boiler accessories
SBH25 Fix Controls HVAC System 20 0 24NOV10 16DEC10
Fix Controls HVAC System
SBH280 Fix Flex Ducts Supply Diffusers 16 0 24NOV10 12DEC10
Fix Flex Ducts Supply Diffusers
SBH190 Test Chilled Water Piping 7 0 28NOV10 05DEC10
Test Chilled Water Piping

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 122 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SBP475 Boiler Test 12 0 05DEC10 18DEC10
Boiler Test
SBH195 Install Pumps (Chilled Water) 10 0 06DEC10 16DEC10
Install Pumps (Chilled Water)
SBH220 Insulate Chilled Water Pipes 16 0 06DEC10 23DEC10
Insulate Chilled Water Pipes
SBH310 Install Chillers / piping 16 0 18DEC10 04JAN11
Install Chillers / piping
SBH290 Install BMS system 15 0 29DEC10 15JAN11
Install BMS system
SBH370 Install Air Supply Diff. /return 10 0 01JAN11 11JAN11
Install Air Supply Diff. /return
SBH400 Fix Exhaust Grills 10 0 05JAN11 16JAN11
Fix Exhaust Grills

FIRST FLOOR
SB1FH420 Install Ducts HVAC 21 95 14DEC08A 23NOV10
Install Ducts HVAC
SB1FH400 Install Chilled Water Piping 36 90 02JUL09A 27NOV10
Install Chilled Water Piping
SB1FH410 Test Chilled Water Piping 7 75 12APR10A 23NOV10
Test Chilled Water Piping
SB1FH440 Test / Inspct Ducts 3 95 22APR10A 22NOV10
Test / Inspct Ducts
SB1FH450 Insulate Chilled Water Pipes 12 50 26APR10A 29NOV10
Insulate Chilled Water Pipes
SB1FH470 Insulate Ducting 10 90 28APR10A 23NOV10
Insulate Ducting
SB1FH490 Install FCU 18 90 10MAY10A 24NOV10
Install FCU
SB1FH500 Fix Flex Ducts Supply Diffusers 12 0 24NOV10 07DEC10
Fix Flex Ducts Supply Diffusers
SB1FH520 Install Air Supply Diff. /return 10 0 08DEC10 19DEC10
Install Air Supply Diff. /return
SB1FH480 Fix Controls HVAC System 20 0 18DEC10 09JAN11
Fix Controls HVAC System
SB1FH530 Fix Grills 7 0 20DEC10 27DEC10
Fix Grills
SB1FH540 Install BMS system 15 0 29DEC10 15JAN11
Install BMS system

ROOF TOP
SBH340 Fix Exhaust Fans 18 0 11DEC10 30DEC10
Fix Exhaust Fans

Plumbing Works
GROUND FLOOR
SBP330 Instl Hot/Cold Water Pipe Walls 12 100 11JUN08A 31DEC08A
Instl Hot/Cold Water Pipe Walls
SBP280 Install Abv Cieling Drainage Pipes 8 100 07JUL08A 18JUN09A
Install Abv Cieling Drainage Pipes
Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT
Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 123 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SBP355 Inst Hot/Cold Watr Pipe Above Ceiling 12 80 16JUL08A 24NOV10
Inst Hot/Cold Watr Pipe Above Ceiling
SBP305 Test Above Ceiling Drainage Pipes 3 100 22JAN10A 24FEB10A
Test Above Ceiling Drainage Pipes
SBP380 Pressure Test Piping Wall 7 80 13APR10A 23NOV10
Pressure Test Piping Wall
SBP405 Test Above Ceiling Hot/Cold Water Piping 7 0 25NOV10 02DEC10
Test Above Ceiling Hot/Cold Water Piping
SBP415 Tag Hot/Cold Water Pipes 5 0 04DEC10 08DEC10
Tag Hot/Cold Water Pipes
SBP302 Install RO Plant 21 0 08JAN11 31JAN11
Install RO Plant
SBP430 Install Plumbing Fixtures 15 0 08FEB11 24FEB11
Install Plumbing Fixtures

FIRST FLOOR
SB1FP640 Install Abv Cieling Drainage Pipes 8 100 07AUG08A 18NOV08A
Install Abv Cieling Drainage Pipes
SB1FP670 Instl Hot/Cold Water Pipe Walls 12 100 11NOV08A 24JAN09A
Instl Hot/Cold Water Pipe Walls
SB1FP650 Inst Hot/Cold Watr Pipe Above Ceiling 15 90 16JAN09A 23NOV10
Inst Hot/Cold Watr Pipe Above Ceiling
SB1FP680 Test Above Ceiling Drainage Pipes 3 100 22MAR10A 24MAR10A
Test Above Ceiling Drainage Pipes
SB1FP720 Pressure Test Piping Wall 7 50 06MAY10A 24NOV10
Pressure Test Piping Wall
SB1FP690 Tag Hot/Cold Water Pipes 5 0 24NOV10 29NOV10
Tag Hot/Cold Water Pipes
SB1FP700 Test Above Ceiling Hot/Cold Water Piping 5 0 24NOV10 29NOV10
Test Above Ceiling Hot/Cold Water Piping
SB1FP750 Install Plumbing Fixtures 15 0 22JAN11 07FEB11
Install Plumbing Fixtures

Fire Fighting Works


GROUND FLOOR
SBP660 Install Fire Fighting Network 26 100 11FEB09A 10JUN09A
Install Fire Fighting Network
SBP687 Painting Fire Water Pipes 5 85 13MAR10A 22NOV10
Painting Fire Water Pipes
SBP690 Fix FHC 3 100 18MAY10A 20JUN10A
Fix FHC
SBP685 Press. Test Fire Fight. Network 4 100 02OCT10A 31OCT10A
Press. Test Fire Fight. Network
SBP688 Tagging of Fire Water Pipes 4 0 23NOV10 27NOV10
Tagging of Fire Water Pipes
SBP750 Fix Pipes FM-200 Fire Fight Sys 15 0 23NOV10 09DEC10
Fix Pipes FM-200 Fire Fight Sys
SBP800 Install Control System FM-200 7 0 06DEC10 13DEC10
Install Control System FM-200

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 124 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SBP710 Fix Fire Sprinklers 10 0 29JAN11 08FEB11
Fix Fire Sprinklers

FIRST FLOOR
SB1FT800 Install Fire Fighting Network 26 100 11DEC08A 10APR09A
Install Fire Fighting Network
SB1FT810 Painting Fire Water Pipes 5 85 25MAR10A 22NOV10
Painting Fire Water Pipes
SB1FT850 Fix FHC 3 100 30MAY10A 01JUN10A
Fix FHC
SB1FT830 Press. Test Fire Fight. Network 4 100 03OCT10A 02NOV10A
Press. Test Fire Fight. Network
SB1FT840 Tagging of Fire Water Pipes 4 0 23NOV10 27NOV10
Tagging of Fire Water Pipes
SB1FT920 Fix Fire Sprinklers 9 0 06JAN11 16JAN11
Fix Fire Sprinklers

Medical Gases Works


GROUND FLOOR
SBP1225 Install Med Gases Fixtures 15 0 09FEB11 26FEB11
Install Med Gases Fixtures

Specialties
GROUND FLOOR
SBP435 Fix Toilet Accessories 15 0 26FEB11 14MAR11
Fix Toilet Accessories

TEST & COMMISSION

SBP440 Flush/Clean Water Pipe 5 0 23NOV10 28NOV10


Flush/Clean Water Pipe
SBP810 Flush/Clean Fire Fighting Pipe 5 0 23NOV10 28NOV10
Flush/Clean Fire Fighting Pipe
SBP300 Test & Commission Boiler 10 0 19DEC10 29DEC10
Test & Commission Boiler
SB1FH550 Test & Commission HVAC 18 0 26FEB11 17MAR11
Test & Commission HVAC
SBP100 Flush /Cleaning Med. Gas system 5 0 27FEB11 03MAR11
Flush /Cleaning Med. Gas system
SBP110 Test & Comm. Med Gases 12 0 05MAR11 17MAR11
Test & Comm. Med Gases
SB1FP760 Test & Comm. Plumbing Works 7 0 15MAR11 22MAR11
Test & Comm. Plumbing Works

ELECTRICAL WORKS
Electrical works
GROUND FLOOR
SBE150 Fix Conduit Wall All Elec Sys 25 90 01JUL08A 25NOV10
Fix Conduit Wall All Elec Sys

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 125 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SBE350 Fix Sub Dist Panels 26 90 06AUG08A 25NOV10
Fix Sub Dist Panels
SBE200 Wiring Elec system 35 90 08SEP08A 27NOV10
Wiring Elec system
SBE175 Install Cable Trays 16 100 24JAN09A 29MAY09A
Install Cable Trays
SBE300 Fire Alarm System wiring 16 90 31JAN09A 24NOV10
Fire Alarm System wiring
SBE325 Public Address System wiring 12 95 04FEB09A 23NOV10
Public Address System wiring
SBE500 Main Bus Bar frm M. Bldg 20 95 08JUN09A 23NOV10
Main Bus Bar frm M. Bldg
SBE250 Fix MDB & termination work 15 85 26SEP09A 23NOV10
Fix MDB & termination work
SBE275 Tel System wiring 12 90 12OCT09A 23NOV10
Tel System wiring
SBE395 Clock system wiring 7 90 01NOV09A 23NOV10
Clock system wiring
SBE385 Data wiring 8 90 01FEB10A 23NOV10
Data wiring
SBE355 Generator installation 10 90 10MAY10A 23NOV10
Generator installation
SBBE540 Transformer in S.bldg 15 90 05JUN10A 24NOV10
Transformer in S.bldg
SBE225 Power Cables puling & Termntion 40 80 13JUN10A 01DEC10
Power Cables puling & Termntion
SBE100 Multi Pair cable / Tel. & Data 10 50 25OCT10A 28NOV10
Multi Pair cable / Tel. & Data
SBE365 Generator Accessories instl. 15 0 24NOV10 11DEC10
Generator Accessories instl.
SBE140 BMS (Conduit/Wiring) 12 0 09DEC10 22DEC10
BMS (Conduit/Wiring)
SBBE520 Switch gear MV 20 0 03JAN11 25JAN11
Switch gear MV
SBBE530 MV cable clanding & termntion 15 0 26JAN11 12FEB11
MV cable clanding & termntion

FIRST FLOOR
SB1FE220 Fix Conduit Wall All Elec Sys 25 90 01JUL08A 25NOV10
Fix Conduit Wall All Elec Sys
SB1FE240 Wiring Elec Systems 35 90 08SEP08A 27NOV10
Wiring Elec Systems
SB1FE260 Install Cable Trays 16 90 24JAN09A 24NOV10
Install Cable Trays
SB1FE270 Fire Alarm System wiring 16 90 31JAN09A 24NOV10
Fire Alarm System wiring
SB1FE280 Public Address System wiring 12 90 04FEB09A 23NOV10
Public Address System wiring
SB1FE340 Tel System wiring 12 90 06DEC09A 23NOV10
Tel System wiring

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 126 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
SBE1F100 Data Wiring 8 70 03JAN10A 24NOV10
Data Wiring
SB1FE350 Fix MDB & termination work 8 80 12APR10A 24NOV10
Fix MDB & termination work
SBE140F BMS (Conduit/Wiring) 12 0 25NOV10 08DEC10
BMS (Conduit/Wiring)

ROOF TOP
SBRT510 Cable Tray installation 2 100 16NOV09A 07MAR10A
Cable Tray installation
SBRT530 Fix Electrical conduits 7 90 22JAN10A 22NOV10
Fix Electrical conduits
SBRT550 Wiring for electrical system 7 90 23JAN10A 22NOV10
Wiring for electrical system
SBRT500 Lightening Protectioning work 3 70 19OCT10A 23NOV10
Lightening Protectioning work

Electrical Fixtures
GROUND FLOOR
SBE375 Install Light Fixtures 28 0 28NOV10 29DEC10
Install Light Fixtures
SBE400 Power Receptacles & Switches 18 0 28NOV10 18DEC10
Power Receptacles & Switches
SBBE550 Fix LC equip. 10 0 13JAN11 24JAN11
Fix LC equip.

FIRST FLOOR
SB1FE320 Install Light Fixtures 20 0 28NOV10 20DEC10
Install Light Fixtures
SB1FE330 Power Receptacles & Switches 18 0 19DEC10 08JAN11
Power Receptacles & Switches
SB1FE360 Fix LC equip. 10 0 02JAN11 12JAN11
Fix LC equip.

TEST & COMMISSION

SBRT540 Test & commissioning Elect. work 28 0 25JAN11 26FEB11


Test & commissioning Elect. work

READY to HAND OVER


Final Clean Up to Hand Over

SBHO786 Ready for hand over 7 0 31MAR11 07APR11


Ready for hand over

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 127 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

SCECO Room
CIVIL WORKS
Concrete Works

SC100 Old & New Structural Work-SCECO Bldg. 90 70 26JUL08A 16DEC10


Old & New Structural Work-SCECO Bldg.

ARCHITECTURAL WORKS
Finishing Works

SC400 Finishing Work-SCECO Bldg. 25 0 18DEC10 15JAN11


Finishing Work-SCECO Bldg.

MECHANICAL WORKS
Elec- Mechanical Works

SC600 Elec-Mech Works-SCECO Bldg. 30 0 16JAN11 19FEB11


Elec-Mech Works-SCECO Bldg.
SC610 Fixing & Testing- Panels/ Equipements 40 0 20FEB11 06APR11
Fixing & Testing- Panels/ Equipements

Water Tank
CIVIL WORKS
Earth Works

WR100 Excavate Water Tank 12 100 08NOV06A 18JAN07A


Excavate Water Tank

Concrete Works

WR110 PCC Water Tank 2 100 11FEB07A 12FEB07A


PCC Water Tank
WR130 Form Raft Foundations 2 100 13FEB07A 14FEB07A
Form Raft Foundations
WR140 Conc Raft Water Tank 1 100 27FEB07A 27FEB07A
Conc Raft Water Tank
WR150 Fix Reinf Ret Wall-1 Water Tank 4 100 16APR07A 19APR07A
Fix Reinf Ret Wall-1 Water Tank
WR160 Form Ret Wall-1 Water Tank 8 100 21APR07A 29APR07A
Form Ret Wall-1 Water Tank
WR180 Fix Reinf Ret Wall-2 Water Tank 4 100 01MAY07A 05MAY07A
Fix Reinf Ret Wall-2 Water Tank
WR210 Fix Reinf Ret Wall-3 Water Tank 4 100 01MAY07A 05MAY07A
Fix Reinf Ret Wall-3 Water Tank

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 128 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
WR190 Form Ret Wall-2 Water Tank 8 100 06MAY07A 14MAY07A
Form Ret Wall-2 Water Tank
WR220 Form Ret Wall-3 Water Tank 8 100 06MAY07A 14MAY07A
Form Ret Wall-3 Water Tank
WR200 Conc Ret Wall-2 Water Tank 1 100 17MAY07A 17MAY07A
Conc Ret Wall-2 Water Tank
WR230 Conc Ret Wall-3 Water Tank 1 100 17MAY07A 17MAY07A
Conc Ret Wall-3 Water Tank
WR240 Fix Reinf Ret Wall-4 Water Tank 4 100 05JUL07A 10JUL07A
Fix Reinf Ret Wall-4 Water Tank
WR250 Form Ret Wall-4 Water Tank 8 100 10JUL07A 19JUL07A
Form Ret Wall-4 Water Tank
WR260 Conc Ret Wall-4 Water Tank 1 100 19JUL07A 19JUL07A
Conc Ret Wall-4 Water Tank
WR120 Fix Reif Raft Water Tank 12 100 13FEB08A 26APR08A
Fix Reif Raft Water Tank
WR300 Form Roof Deck Water Tanks 22 100 29MAR08A 07APR08A
Form Roof Deck Water Tanks
WR320 Fix Reinf Deck water Tank 10 100 10APR08A 03JUN08A
Fix Reinf Deck water Tank
WR170 Conc Ret Wall-1 Water Tank 1 100 30APR08A 30APR08A
Conc Ret Wall-1 Water Tank
WR360 Conc Deck Water Tank 1 100 07JUN08A 07JUN08A
Conc Deck Water Tank

MECHANICAL WORKS
Plumbing Works

WR330 Sleeves Mech Roof Deck Water Tank 4 100 12APR08A 29APR08A
Sleeves Mech Roof Deck Water Tank
WR500 Mech Works Water Tank 26 100 12MAR09A 12JUL09A
Mech Works Water Tank

ELECTRICAL WORKS
Electrical works

WR340 Conduits Deck Water Tank 4 100 11APR08A 30MAY08A


Conduits Deck Water Tank

Guard Houses
CIVIL WORKS
Concrete Works

GH100 Structural Works Guard Houses 120 100 25JUN08A 26AUG09A


Structural Works Guard Houses

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 129 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

ARCHITECTURAL WORKS
Masonry Works

GH100F Block Work Guard Houses 26 100 31AUG09A 10MAR10A


Block Work Guard Houses

Water Proofing & Insulation

GHWP440 Water Proof Wet Areas 12 0 05DEC10 18DEC10


Water Proof Wet Areas

Doors & Windows

GHDG200 Fix Windows frame 10 0 22DEC10 02JAN11


Fix Windows frame
GHDG210 Fix Door Frames 5 0 03JAN11 08JAN11
Fix Door Frames
GHDG220 Fix Door metal Panels 7 0 09JAN11 16JAN11
Fix Door metal Panels
GHDG230 Fix Door Hard Ware 5 0 17JAN11 22JAN11
Fix Door Hard Ware

Pre-Finishing Works Walls

GHWG300 Plaster Walls Internal 10 0 23NOV10 04DEC10


Plaster Walls Internal
GHWG320 Putty & Primer Coat Ordinary 10 0 05DEC10 15DEC10
Putty & Primer Coat Ordinary
GHWG330 Plaster/ Cladding-External Walls 15 0 05DEC10 21DEC10
Plaster/ Cladding-External Walls
GHWG310 Fix Ceramic Wall Tiles 10 0 16DEC10 27DEC10
Fix Ceramic Wall Tiles

Pre-Finishing Works Ceilings

GHC700 Plaster Ceiling 10 0 05DEC10 15DEC10


Plaster Ceiling
GHC800 Ceiling Paint 10 0 28DEC10 08JAN11
Ceiling Paint

Final Floor Finishing Works

GHF600 Marble Flooring Tile 10 0 09JAN11 19JAN11


Marble Flooring Tile
GHF610 Ceramic Floor Tiling 5 0 20JAN11 25JAN11
Ceramic Floor Tiling

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 130 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Final Wall Finishing Works

GHPW310 1st coat Paint 10 0 16DEC10 27DEC10


1st coat Paint
GHPW320 2nd Final Coat Paint- Walls 10 0 23JAN11 02FEB11
2nd Final Coat Paint- Walls

ELECTRICAL WORKS
Electrical works

GH100M Elec / Mech Works Guard Houses 15 50 11NOV09A 27FEB11


Elec / Mech Works Guard Houses

READY to HAND OVER


Final Clean Up to Hand Over

GH300F Clean Up Guard Houses 5 0 24FEB11 01MAR11


Clean Up Guard Houses

Driver Room
CIVIL WORKS
Concrete Works

DR1000 Structural Work-Driver Bldg. 70 100 22JAN10A 02MAR10A


Structural Work-Driver Bldg.

ARCHITECTURAL WORKS
Finishing Works

DR1010 Finishing Work-Driver Room 35 0 23NOV10 02JAN11


Finishing Work-Driver Room

MECHANICAL WORKS
Elec- Mechanical Works

DR1020 Elec-Mech Works-Driver Room 25 0 16DEC10 13JAN11


Elec-Mech Works-Driver Room

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 131 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

Switch Gear Room


CIVIL WORKS

SW0990 Approval Of Drgs.For Switch Gear Room 12 0 29NOV10 12DEC10


Approval Of Drgs.For Switch Gear Room
SW1000 Civil Work-Switch Gear Room 45 0 16DEC10 06FEB11
Civil Work-Switch Gear Room

ARCHITECTURAL WORKS

SW1100 Arch Works-Switch Gear Room 25 0 07FEB11 07MAR11


Arch Works-Switch Gear Room

ELECTRICAL WORKS

SW1500 Elec Work/Equipment/Panels Installation 45 0 01FEB11 24MAR11


Elec Work/Equipment/Panels Installation

Tunnel Works
MECHANICAL WORKS
Plumbing Works

MBPWB150 Tunnel cold/ Hot water pipe 30 0 23NOV10 27DEC10


Tunnel cold/ Hot water pipe

Chilled Water

TUCW100 Tunnel Chilled water piping 20 90 10MAR10A 23NOV10


Tunnel Chilled water piping

Fire Fighting Works

MBPWB580 Tunnel Fire Fighting piping 20 90 01AUG10A 24NOV10


Tunnel Fire Fighting piping
TUNFF300 Press. test Fire Fighting network 7 0 25NOV10 02DEC10
Press. test Fire Fighting network

Medical Gases Works

MBMGB100 Install Med Gases Fixtures 18 55 01SEP10A 01DEC10


Install Med Gases Fixtures

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 132 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

LPG Works

MBLPG100 Tunnel LPG Gas piping 25 0 19DEC10 16JAN11


Tunnel LPG Gas piping

Steam Work

MBST1000 Tunnel Steam piping 25 80 22AUG10A 28NOV10


Tunnel Steam piping
MBST1010 Steam pipe Insulation 20 20 19OCT10A 11DEC10
Steam pipe Insulation

TEST & COMMISSION

TNW300 Flush /Cleaning Med. Gas system 10 0 02DEC10 13DEC10


Flush /Cleaning Med. Gas system
TNW310 Test & Comm. Med Gases 20 0 14DEC10 05JAN11
Test & Comm. Med Gases
TNW100 Flush/Cleaning Mech. works 10 0 17JAN11 27JAN11
Flush/Cleaning Mech. works
TNW200 Test & Commission Mech. works 18 0 20FEB11 12MAR11
Test & Commission Mech. works

Waste Collecting Room


CIVIL WORKS

WC10SW0990 Drawings Approval For Waste Collection Room 12 0 02DEC10 15DEC10


Drawings Approval For Waste Collection Room
WC10SW1000 Civil Works Waste Collection Room 30 0 16DEC10 19JAN11
Civil Works Waste Collection Room

ARCHITECTURAL WORKS

WC10SW1100 Arch Works Waste Collection Room 30 0 09JAN11 12FEB11


Arch Works Waste Collection Room

ELECTRICAL WORKS
Electrical works

WCSW1500 Elec Works 20 0 13FEB11 07MAR11


Elec Works

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 133 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish

TEST & COMMISSION

TCE100 Test & Commission Elec Works 7 0 08MAR11 15MAR11


Test & Commission Elec Works

External Landscaping
CIVIL WORKS
Earth Works

EWX110 Fill to Granular Base Level 15 50 26MAY10A 28NOV10


Fill to Granular Base Level
EWX140 Place Granular / Sub Base 15 40 07JUN10A 06DEC10
Place Granular / Sub Base
EWX103 Approval For Shifting Off.,Stores,Accom.,etc. 15 0 23NOV10 09DEC10
Approval For Shifting Off.,Stores,Accom.,etc.
EWX105 Shifting Offices,Stores,Accom.,etc. 20 0 11DEC10 02JAN11
Shifting Offices,Stores,Accom.,etc.
EWX107 Backfilling 15 0 03JAN11 19JAN11
Backfilling
EWX100 General Grading External 15 0 15JAN11 31JAN11
General Grading External

Concrete Works

EXX200 External Manholes / Handholes 25 0 23NOV10 21DEC10


External Manholes / Handholes
STP100 Civil Work-Sewage 20 0 23NOV10 15DEC10
Civil Work-Sewage

Land / Hard Scaping

EX001 External Boundry Wall 56 100 08MAR09A 11AUG09A


External Boundry Wall
EXM338 Fountain-Prep.& Approval Of Drgs. 10 0 09JAN11 19JAN11
Fountain-Prep.& Approval Of Drgs.
EXM335 Fence Around Chillers 10 0 12JAN11 23JAN11
Fence Around Chillers
EXM330 Fence Around LPG Tanks 8 0 15JAN11 23JAN11
Fence Around LPG Tanks
EXM340 Fountain-Structural Work 21 0 20JAN11 13FEB11
Fountain-Structural Work
EXW005 Fix Pergolas 10 0 01FEB11 12FEB11
Fix Pergolas
EXM350 Fountain Finishing Work 18 0 14FEB11 06MAR11
Fountain Finishing Work
EWX180 Fix Curb Stones 30 0 20FEB11 26MAR11
Fix Curb Stones

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 134 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
EWX160 Asphalt / Concrete Work 45 0 09MAR11 30APR11
Asphalt / Concrete Work
EWX200 Concrete Walkway / Pavers 40 0 13APR11 29MAY11
Concrete Walkway / Pavers
EWX240 Tree Plantation 21 0 30MAY11 22JUN11
Tree Plantation

ARCHITECTURAL WORKS
Metal Works

EWX120 External Wall Gates 25 0 02APR11 30APR11


External Wall Gates
EWX115 Parking Sheds 28 0 10APR11 11MAY11
Parking Sheds

MECHANICAL WORKS
Plumbing Works

EXM100 Fix External Drainage Piping 15 0 23NOV10 09DEC10


Fix External Drainage Piping
STP200 Mech Work-Seawage Treatment 18 0 16DEC10 05JAN11
Mech Work-Seawage Treatment
EXM200 Fix External Water Pipes 15 0 20DEC10 05JAN11
Fix External Water Pipes
STP210 Pump Room Fire / Water 12 0 20DEC10 02JAN11
Pump Room Fire / Water
EXM300 External Irrigation Water Piping 15 0 23DEC10 09JAN11
External Irrigation Water Piping
EXM400 Treated water piping 15 0 30DEC10 16JAN11
Treated water piping
EXM500 Soft water piping 12 0 03JAN11 16JAN11
Soft water piping
EXM310 LPG Tanks / LPG piping 12 0 06JAN11 19JAN11
LPG Tanks / LPG piping
EXM320 Diesel Tanks 12 0 20JAN11 02FEB11
Diesel Tanks
EXM420 Diesel Fuel piping 12 0 03FEB11 16FEB11
Diesel Fuel piping
EXM360 Fountain Elec / Mech Works 18 0 26FEB11 17MAR11
Fountain Elec / Mech Works

ELECTRICAL WORKS
Electrical works

EWXE140 Laying MV Cables 14 0 23NOV10 08DEC10


Laying MV Cables

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 135 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010
Activity Activity Orig % Early/ Early/
ID Description Dur Comp. Actual Actual 2005 2006 2007 2008 2009 2010 2011
Start Finish
EWX250 Fixing Package TR 12 0 09DEC10 22DEC10
Fixing Package TR
EWXE300 Laying LV cables 12 0 23DEC10 05JAN11
Laying LV cables
EXWE330 Laying LC cables 12 0 26DEC10 08JAN11
Laying LC cables
EXWE350 Electrical manholes 15 0 09JAN11 25JAN11
Electrical manholes
EXWE360 Substation Grounding 12 0 26JAN11 08FEB11
Substation Grounding
EXWE370 Substation installation 10 0 09FEB11 20FEB11
Substation installation
EXWE400 Sub distribution panel installation 10 0 21FEB11 03MAR11
Sub distribution panel installation
EXWE420 Cables laying for STP 10 0 28FEB11 10MAR11
Cables laying for STP
EXWE450 Cable termination for STP 11 0 08MAR11 20MAR11
Cable termination for STP
EXWE500 Laying of Fiber optic cables 12 0 13MAR11 26MAR11
Laying of Fiber optic cables
EXWE430 Install Electrical Poles 25 0 10APR11 08MAY11
Install Electrical Poles
EWX260 Installationg light fixture 20 0 12MAY11 04JUN11
Installationg light fixture
EWX270 Testing & Cleaning 7 0 05JUN11 12JUN11
Testing & Cleaning

Final TO Hand Over


READY to HAND OVER

END111 Request Ministry Inspection 5 0 14JUL11 19JUL11


Request Ministry Inspection
END333 Hand Over 10 0 20JUL11 31JUL11
Hand Over

Start Date 03MAY05 ALAWI TUNSI ESTABLISHMENT


Early Bar
Finish Date 31JUL11 PROGRAMME WITH PROGRESS UPDATE Date Revision Checked Approved
Progress Bar
Data Date 23NOV10 20OCT10 Programme With Progress Update-
Critical Activity
FOR ENTIRE PROJECT Sheet 136 of 136
© Primavera Systems, Inc. as on Data Date 23/11/2010