Você está na página 1de 74

PROJECT REPORT FOR PROPOSED

RESIDENTIAL APARTMENT PROJECT

At
Survey No. 53/1 and Site No.394,
Gubbalala Village, Uttarahalli Hobli,
Bangalore South Taluk, Bangalore.

Submitted By
M/s. Rohan Gruh Nirman LLP.,
#1201, 1st Floor, Divyashakti,
100 feet road, Indiranagar,
Bangalore – 560 038.

Submitted to
State Environment Impact Assessment Authority,
Karnataka.

ENVIRONMENTAL CONSULTANTS
M/s. AQUA TECH ENVIRO ENGINEERS,
# 3391, 6th Main, 3rd Cross, RPC Layout,
Vijaynagra II Stage, Bangalore – 560 040.
Tele Phone: 080 - 23141679
Fax: 080 – 23148166
INDEX
SL NO DESCRIPTION PAGE NO.
1 APPLICATION IN FORM I 1-14
2 APPLICATION IN FORM I A 15-25
ANNEXURE TO APPLICATIONS 26-71

A COMPREHENSIVE PROJECT REPORT 27 - 30

B WATER REQUIREMENT DETAILS FOR THE PROJECT 31-32

C SEWAGE GENERATION, UTILITY OF TREATED SEWAGE & DESIGN 33-43


DETAILS OF SEWAGE TREATMENT PLANTS

D WATER BALANCE CHART 44

E WATER REQUIREMENT AND SEWAGE DISPOSAL DURING 45


CONSTRUCTION PHASE

F SOLID WASTE GENERATION & MANAGEMENT DETAILS 46-49


(CONSTRUCTION & OPERATION PHASE)

G ENVIRONMENTAL MONITORING AND MANAGEMENT PLAN (EMP) FOR 50-61


CONSTRUCTION AND OCCUPANCY PHASES

H RAIN WATER MANAGEMENT SCHEME 62-63

I DISASTER MANAGEMENT PLAN FOR PRE-CONSTRUCTION PHASE 64

J EMP FOR CONTROL OF DUST AND NOISE DURING 65-66


CONSTRUCTION PHASE.

K RISK ASSESSMENT & MANAGEMENT PLAN 67

L GEO TECHNICAL INVESTIGATION REPORT 68

M TRAFFIC SURVEY AND ITS MANAGEMENT 69

N SAVINGS IN ELECTRICAL POWER CONSUMPTION 70

0 PROJECT RELATED DRAWINGS/PLANS 71


M/s. Rohan Gruh Nirman LLP., Residential Apartment

Annexure &
Details to Application in
Form 1 and Form 1A

26 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE – A

COMPREHENSIVE PROJECT REPORT

PROJECT AT GLANCE

PROPOSED PROJECT Residential Apartment Project with 434 Flats


LOCATION Survey No. 53/1 and Site No.394,
Gubbalala Village, Uttarahalli Hobli,
Bangalore South Taluk, Bangalore.
TOTAL PLOT AREA 20,398 sq m (5.04 Acres)
TOTAL BUILT UP AREA 69,834 sq m

TOTAL COST OF PROJECT Rs. 128,00,00,000/-


(Rupees One Hundred and Twenty Eight Crores Only)

NO. OF FLOORS PROPOSED Projects consist of Block 1 and 2 with Basement, Ground and
14 Upper Floors.
CAR PARKING DETAILS Total No. of parking space proposed is 493 Cars
WATER SUPPLY Water supply is from BWSSB sources.
PROPOSED SANITATION Under Ground Sanitary System Facility for conveying the
wastewater to the Proposed Sewage Treatment Plant.
SOLID WASTE MANAGEMENT Collection and Segregation at source of generation and the
Organic waste will be treated in Organic Converter and the
Inorganic Waste will be sent for recycling.
AIR POLLUTION/ NOISE 2 x 380 kVA capacity DG sets with acoustics are proposed to
GENERATION SOURCE be provided with adequate stack height.

BACKGROUND OF THE PROPOSED APARTMENT PROJECT:

M/s. Rohan Gruh Nirman LLP., #1201, 1st Floor, Divyashakti, 100 Feet Road, Indiranagar, Bangalore –
560 038 intend to develop Residential Apartment project with 434 Flats at Survey No. 53/1 and Site No.
394, Gubbalala Village, Uttarahalli Hobli, Bangalore South Taluk, Bangalore. The project is designed in
accordance with the bye laws of planning authority.

27 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

LAND USE PATTERN FOR THE PROPOSED PROJECT:

No. Particulars Area in sq m Area in Acres Percentage


1 Total Plot area 20,398.00 5.04 100
2 Ground Coverage area 9,200.64 2.27 45.10
3 Paved area 4,639.41 1.14 22.74
4 Landscape area
On natural earth 6,557.95 1.62 32.14
(Including CA Area)
On podium 3,605.81 0.89 -

AREA STATEMENT FOR THE PROPOSED PROJECT:

Sl. Description Built up area in sq m Activity / No. of Flats


No. (Block 1 and 2)
1 Basement 12,415.49 Parking
2 Ground Floor 10,258.12 Parking
3 1st Floor 3,376.39 30
4 2nd Floor 3,205.48 30
5 3rd Floor 3,749.64 30
6 4th Floor 3,446.62 30
7 5th Floor 3,625.13 30
8 6th Floor 3,643.60 30
9 7th Floor 3,190.19 30
10 8th Floor 3,331.75 30
11 9th Floor 3,331.75 30
12 10th Floor 3,331.75 30
13 11th Floor 3,190.19 30
14 12th Floor 3,190.72 30
15 13th Floor 3,273.54 30
16 14th Floor 3,273.54 14
Total 69,834.00 434

CAR PARKING STATEMENT:


Total spaces proposed at
a) Basement floor: 247 Cars
b) Ground floor: 235 Cars
c) Surface parking: 11
d) Total parking spaces: 493 Cars

28 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

AIR POLLUTION SOURCES & ITS MANAGEMENT:

The anticipated power required for the project (about 1880 kVA) will be supplied from BESCOM. The
primary sources of air pollution from the establishment are from the operation of diesel generator sets. The
project will be provided with DG set of following capacity and is installed to serve as an alternative back up
source of power supply in the event of breakdown of power supply BESCOM. The details of capacities &
fuel consumption for the DG sets are given below.

Air Pollution Sources for the Proposed Project:


Sl. Stack Details Stack Attached to
No
Physical Details D.G Set
1 Capacity 2 x 380 kVA sets capacity.
2 Fuel quantity 76 L/hr
3 Fuel used Ultra Pure Low Sulphur Content Diesel
4 Stack height Chimneys (Above roof level) of 5 m for each DG
set.
5 Stack diameter 80 mm
Emission Details
1 Sulphur dioxide 0.033 g/s for each DG set
2 Suspended Particulate 0.033 g/s for each DG set
Matter (SPM)
3 Oxides of Nitrogen 1.022 g/s for each DG set

NOISE GENERATION SOURCES:

Major noise producing sources of the residential apartment is expected to be from DG set, Vehicular
movements from and to the proposed project. The DG sets are provided with acoustic enclosures to control
the noise levels in such a way that the noise levels are within the permissible limits specified for ambient
noise levels. More over the DG sets are operated only during the emergencies when there is power failure.

29 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

PROJECTED COST OF THE PROJECT:

The total projected cost of the proposed project is presented as below.

Sl. Particulars Cost in Rupees.


No.
1. Land Cost at Rs. 1000/sft Rs. 21,94,82,480/-
2. Construction Cost @ rate of Rs. 1,05,19,79,376/-
Rs. 1,400/sft of built up area
Rs. 1,27,14,61,856/-
TOTAL Or say
Rs. 1,28,00,00,000/-

Rupees One Hundred and Twenty Eight Crores Only

30 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE: B
SOURCE OF WATER FOR THE PROPOSED PROJECT:
The most important aspect under the water supply scheme is the selection of source of Water, which
should be reliable and potable. The water required for the project will be supply from BWSSB source.

DETAILS OF WATER CONSUMPTION OF THE PROJECT:

The apartment being a residential one, water demand is for domestic purpose, public uses and fire fighting
purposes. It includes the quantity of water required in the houses for drinking, bathing, cooking, washing
etc., The quantity of water required for domestic purposes depends on the habits, social status, climatic
conditions and customs of the people. In India on an average the domestic water consumption under
normal conditions is about 135 litres/capita/day as per NBC, the details of domestic consumption is as
follows.

Sl. Utility Consumption in Litres per


No. Capita per day
1 Drinking 5
2 Bathing 20
3 Cooking 5
4 Washing of clothes 40
5 Utensils washing
6 Washing of floor
7 Flushing of Toilets 45
8 Others 20
Total 135

The anticipated water demand is worked out by taking into consideration that the project is fully developed
and the residents have fully occupied their respective flats.

31 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

WATER CONSUMPTION OF THE PROPOSED PROJECT:


No. Water requirement
1.1 No. of units 434
Total contributing population considering 5 person per 434 X 5 = 2,170
flats
1.2 Total number of occupants in the project 2,170 persons
1.3 Water requirement for the Residential Apartment by 2170 X 135 =
considering water demand of 135 LPCD 2,92,950 Litres/day or say
293 KLD ---- A
1.4 Considering 10% extra for club house 29.3 or say
30 KLD ---- B
TOTAL WATER REQUIRED FOR PROPOSED PROJECT: A + B = 293 + 30
= 323 KLD

WATER DISTRIBUTION SYSTEM:

The proposed water supply scheme to cater to the public and domestic water requirement of the proposed
project consists of sourcing pre-treated potable water from Public supply into a common collection facility
known as the Raw Water Sump. The Raw Water Sump will be constructed in RCC. The water from the UG
sump will be pumped to overhead tank. The OHTs are staged on terrace depending on the contour of its
distribution network.

32 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE: C
1. SEWAGE GENERATION AND DISPOSAL SYSTEM:
Wastes of different type such as spent water from bath rooms, water closets/pans, house and street
washings, semi liquid waste of human excreta, dry refuse of house and street sweepings, broken furniture,
crockery etc., are produced daily. If proper arrangement for collection treatment and disposal of all the
wastes produced are not made, unsanitary conditions will develop and it will become impossible for the
public to live. Therefore, it is most essential to collect, treat and dispose all the sanitary waste produced.
Generally, it has been observed that about 90 % of the water supplied comes out as sewage. Therefore,
the total quantity of wastewater generated from the proposed Residential Apartment Project is worked out
as below.

Water required for the project = 323 KLD


Wastewater generation : 323 X 0.90 = 290.7 or say 291 KLD
(Assuming 90 % of the water
supplied comes out as wastewater)
Domestic wastewater generated from the proposed project will be conveyed to Sewage Treatment Plant of
capacity 300 KLD for treatment and disposal.

TREATED SEWAGE DISPOSAL:


a. Toilet Flushing:
Total contribution population from the proposed project is 2170 Persons.
Toilet flushing water requirement at the rate of 45 LPCD
= 2170 X 45 =97650 L/day or say 98 KLD
b. Gardening:
Treated water used for gardening @ rate of 7 L/sq m/day
Area available for landscape development: 10,163.76 sq m
Total water used for landscape development is 10,163.76 x 7
= 71,146.32 or say 72,000 L/day Or say 72 KLD
c. Excess quantity of 121 KLD will be discharged to UGD facilities / given to construction projects,
used for water avenue plantations.

33 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

TECHNICAL PROPOSAL FOR THE PROPOSED SEWAGE TREATMENT PLANT (300 KLD):
TREATMENT METHODOLOGY ADOPTED:
1. Bar Screen:
The sewage is screened before treatment using mild steel grate bars. Any solid particles thus screened off
will be manually removed periodically and disposed. This process helps to avoid clogging of pumps in
further treatment.

2. Collection cum equalization:


The wastewater from apartment will be collected in this collection sump for equalization. The equalized
wastewater is passed into an aeration tank. Further, to keep the wastewater in this tank fresh and to get
uniformity, the contents in this sump are aerated by means of coarse membrane diffuser, which is fed by a
common blower.

3. Sequencing Batch Reactor Process:


The operating principles of a batch activated sludge process, or SBR, are characterized in six discrete
periods:
1. Anoxic fill
2. Aerated Fill
3. React
4. Settle
5. Decant
6. Idle

Anoxic Fill
The influent wastewater is distributed throughout the settled to provide good contact between the
microorganisms and the substrate. Most of this period occurs without aeration to create an environment
that favors the procreation of microorganisms with good settling characteristics. Aeration begins at the
beginning of this period.

34 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

Settle Aerated Fill


Mixed liquor is mixed with the influent flow in the motive liquid pump, and discharged, as motive liquid. This
initiates the feast period. Feast is when the microorganisms have been in contact with the substrate and a
large amount of oxygen is provided to facilitate the substrate consumption. Nitrification and denitrification
occurs at the beginning of this stage.

React
During this period aeration continues until complete biodegradation of BOD is achieved. After the substrate
is consumed famine stage starts. During this stage some microorganisms will die because of the lack of
food and will help reduce the volume of the settling sludge. The length of the aeration period determines
the degree of BOD consumption.
Aeration is discontinued at this stage and solids separation takes place leaving clear, treated water above
the sludge blanket. During this clarifying period no liquids should enter or leave the tank to avoid turbulence
in the supernatant.

Decant
This period is characterized by the withdrawal of treated effluent from approximately two feet below the
surface of the mixed liquor by the floating solids excluding decanter. This removal must be done without
disturbing the settled sludge.

Idle
The time in this stage can be used to waste sludge. The wasted sludge is pumped to Sludge holding tank
to reduce the volume of the sludge to be discarded. The frequency of sludge wasting ranges between once
each cycle to once every two to three months depending upon sludge volume index.

4. Filter press:
The excess sludge from sludge conditioning tank will be pumped to filter press, where it is subsequently
dewatered mechanically. This dewatered sludge can be used as solid manure for agriculture and
gardening.

35 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

5. Tertiary Treatment:
The treated water stored in the decant Water Tank will be pumped through Pressure sand Filter and
Activated Carbon Filter where the turbidity and residual BOD present will be completely minimized. The
treated water is then collected in the final collection tank. Before reaching this tank, chlorine solution is
dosed in to this water stream, with the help of a Dosing pump, to disinfect as well as to digest any residual
organic matters. The treated water so collected shall be pumped and used for gardening and irrigation.
Also, the same water shall be used for back washing of filters. The back wash drain, filter rinse drain and
the decanted water shall be pumped/drained back to the equalization tank. Low as 10 mg/L with tertiary
treatment.
QUALITY OF DOMESTIC SEWAGE BEFORE & AFTER TREATMENT:
The quality Raw Domestic Sewage & treated sewage after the treatment as per the Standards stipulated by
KSPCB are as appended below

No. Parameter Quality Of Raw Sewage


1 pH 6–8
2 BOD, mg/l 250
3 Turbidity, NTU 100
4 E. coli ---
5 Residual Cl2, mg/l ---

Sl. Quality of Treated Sewage as per CPCB


Parameter
No. directions
1 pH 6.5 – 9.0
2 BOD (3 days at 27o C), mg/l Not more than 10
3 CoD Not more than 50
4 Total Suspended Solids, mg/l Not more than 20
5 Ammonical – Nitrogen, mg/l Not more than 5
6 Total Nitrogen, mg/l Not more than 10
7 Fecal Coliform (MPN/100 ml) Less than 100

DESIGN DETAILS FOR THE PROPOSED SEWAGE TREATMENT PLANT AND DESIGN
ASSUMPTIONS (300 KLD Capacity) .
1 BAR SCREEN
* Size of the unit : 1.0 m x 1.5 m x 1.0 m
*Function : To separate coarse matter from the Raw
Sewage

36 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

2. OIL AND GREASE SEPARATOR


* Flow rate : 300 m3/day = 12.5 m3/hr
* Detention time provided : 30 minutes
* Volume of oil separation
tank required : 6.25 m3
* Let the depth of the unit be : 1.2 m
* Therefore area of oil
Separator required : 5.2 m2
* Let the width of the unit be : 1.0 m
* Size of unit proposed : 2.3 m x 1.0 m x 1.2 m SWD
* Function : To separate oil & grease from raw sewage

3. EQUALISATION TANK
OBJECTIVE: To equalize the flow and pollutant concentration. Generally, 6 - 8 hrs
Hydraulic retention time is given for equalization tank.
Provide one no. Equalization tank of 8 hrs hydraulic retention.
Q max = 300 m3/day
Average flow rate = 12.5 m3/hr
Tank volume required = 12.5 x 8 = 100 m3
Size of the unit = 5.3 m x 5.3 m x 3.5 m SWD
Average BOD of sewage at the inlet of the Pre-aeration tank. : 300 mg/lit.
Total organic load with 20 % BOD reduction considered. : 60 mg/lit.
Quantity of BOD to be removed =( 60 x 300 )/1000 = 18 kg/day
Total oxygen required assuming 2 Kg of O2/kg of BOD Removed
: 18 x 2 = 36 Kg/day.
Air required for pre aeration : 85.03 m3/hr.

4. RAW SEWAGE PUMP


Volume of sewage : 300 m3 / day ~ 37.5 m3/hr

5. SBR TANK
OBJECTIVE: To oxidize the organic content in the influent and to avoid any objectionable odor. As
chemical not used in the process is biological in nature, the DO levels need to be high for maintaining the
oxygen demand in the system.

Flow (design) = 300 m3/day


BOD = 300 mg/l
SBR tank volume = Q x BOD
F/M x MLSS
= 300 x 300
4000

37 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

SBR tank volume = 225 m3


Provide 30% for sludge accumulation
Total SBR tank volume provided = 293 m3
Assume SWD to be 3.5 m
Therefore plan area required = 293/3.5 = 83.71 m2
Size of Aeration Tank Required: 9.1 m x 9.1 m x 3.5 m SWD with partition

DIFFUSED AERATION SYSTEM


Flow = 300 cum/day
Inlet BOD = 300 mg/l
Organic load = BOD X Flow rate
1000
Total organic load in the system: (300 X 300)/ 1000 = 90 Kg/day

Total oxygen required assuming that 2 Kg of O2/kg of BOD Removed


= 2 X 90= 180 Kg/day
Assume alpha =0.6 and β= 0.7
Consider oxygen transfer at 0.35 m depth = 25%
Density of Air = 1.2 Kg/m3
Percentage of Oxygen in Atmospheric air = 21%

Air required = 180


1.2 x 0.21 x 0.6 x 0.7 x 0.25
= 6802.72 m3/day
= 425.17 m3/hr.
Calculation of diffuser required:
Considering 12 m3/hour diffusion of air through the diffuser /m length
Number of diffusers required = 425.17/12
= 35 diffusers.
Number of diffusers provided = 35 No’s
* Type of aeration : Membrane Fine pore diffused aeration System

6. SLUDGE TRANSFER PUMP.

* Discharge rate : 1.0 m3/hr @ 15 m head.


* Type of pump : Horizontal centrifugal with CI open impeller self-priming type
coupled to motor of required speed with B Class insulation and
IP 55 protection hood.
* Function : To transfer the sludge to Filter press

7. PLATE & FRAME FILTER PRESS.


* Assumed Type of Sludge : Secondary Biological

38 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

* Design Liquid Sludge Flow : 9000 Lts/Day


* Concentration of Solids : 1%
* Specific Gravity : 1.2
* Minimum Dry Solids allowable in the sludge solid cake : 25-30%
Sludge Cake Characteristics:
* Cake Thickness : 32 mm
* Wet Cake Density : 1280 Kg/m3
Operating Time
* 10 Hrs/Day : 6 Days /Week
Cycle Time
* Feed : 20 Minutes
* Compression : 15 Minutes
* Cake Discharge : 25 Minutes
* Total : 60 Minutes
Daily Sludge Solid Generation
* Rate : 9000 x 0.01 X 1.2 = 108 Kg/Day
* Quantity of sludge solids load
on filter press : 108 x 7(Three days in a week operation)
: 756 Kg/week
* Assuming that the filter press is operated for 5 days/week.
* Therefore Solid Load/day =756 / 5 = 151.2 Kg/day
* Assuming that sludge holding capacity as = 0.61 x 0.61 x 0.032 x 1280
= 15.24 Kg/m2
* The size of Filter press required = 151.2/15.24 = 9.9 m2
* Let the size of each Plate be (0.61x 0.61 m) = 0.37 m2
* Therefore the number of such chambers required will be
= 9.9/0.37 = 26.81 No.s
Note: However provide 27 chambered filter press of size 0.61 m x 0.61 m with Collection tray, Filtrate line
with Hydraulic/Power packed mechanism.

8. SCREW PUMP 2 No.s (1 W + 1 SB)


* Flow rate =2-2.5 m3/hr
* Type Single Screw Type with shaft mounted gear box
* Working Pressure4 to 6 kg/cm2

9. SLUDGE HOLDING TANK


* Anticipated quantity of secondary sludge from the STP
: 9000 liters per day
= 9.0 m3/day

* Capacity of aerobic digester required : 1000 liters


* Size of aerobic digester required : 2.4 x 2.4 x 1.5 m SWD
* Considering air required as 1.0 m3/hr per cum of volume

39 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

* Air required for aerobic : 1.0 X volume of the tank digestion


: 1 m3/Hr/cum volume x 9.0 m3/day
= 9.0 m3/hr
* Type of air diffusion : Membrane/HDPE air grid
* Function : To supplement oxygen for aerobic digestion of secondary sludge.

10. PRE FILTRATION TANK /DECANT TANK


Average flow = 12.5 m3/hr
Provide 8 hr holding capacity
Volume of the tank required= 100 m3
Providing SWD 3.0 m
Final collection tank size is 5.8 m x 5.8 m x 3.0 m SWD

11. FILTER FEED PUMP – 2 Nos. (1 W + 1 SB)


Pumping Rate : 37.5 m3/Hr
Type of pump : Horizontal centrifugal with CI open impeller self priming
type coupled to motor of required speed with B Class
Insulation and IP 55 protection hood.
Function : To pump the clarified water through Pressure Sand and
Carbon Filters.

12. PRESSURE SAND FILTER


OBJECTIVE: To filter the residual suspended solids from the clarified water.
* Total Flow : 300 m3/day
* Duration of Pumping considered : 8 Hr/day
* Pumping rate : 37.5 m3/hr
* Surface Loading considered : 12 m2/m3/hr
* Area of filter required : 3.125 m2
* Dia of the Filter : 2.0 m
* Number of Sand Filters :1
* Number of Carbon Filters :1
* Height of the Shell : 1.5 m
* Media for sand filter Pebbles, Grit, Stilt, Gravel Coarse & Fine sand
* Function of Sand Filter For removal of suspended impurities

13. ACTIVATED CARBON FILTER:


OBJECTIVE: To remove the odor and color from the clarified water.
* Total Flow : 300 m3/day
* Duration of Pumping considered : 8 Hr/day
* Pumping rate : 37.5 m3/hr
* Surface Loading considered : 12 m2/m3/hr
* Area of filter required : 3.125 m2
* Dia of the Filter : 2.0 m

40 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

* Number of Sand Filters :1


* Number of Carbon Filters :1
* Height of the Shell : 1.5 m
* Media for Carbon Filter Pebbles, Gravel and Activated Carbon
* Function of Carbon Filter For removal of color and Odor

14. ULTRA VIOLET SYSTEM:


UV disinfection is a physical process that instantaneously neutralizes microorganisms as they pass by
ultraviolet lamps submerged in the effluent.
Provide Alpha make UV Filter system for dosing 9.375 Cum/Hr

15. ULTRA FILTRATION TANK


Size of the tank = 2.9 x 6.9 x 1.85 m SWD

16. UF FEED PUMP


* Volume of the treated Water : 300 m3/day
* Discharge Rate : 3.75 m3/Hr @ 4 batch

17. CHLORINE DOSER


Provide Milton Roy Asia LMI/ Prominent make metering pump of dosing capacity 4-6
LPH with 1000 Liters capacity dosing tank.

18. FINAL COLLECTION TANK


Average flow = 12.5 m3/hr
Provide 8 hr holding capacity
Volume of the tank required= 100 m3
Providing SWD 3.0 m
Final collection tank size is 5.8 m x 5.8 m x 3.0 m SWD

19. BLOWER CAPACITY


Blower capacity: Air for pre-aeration + SBR Tank + final Collection tank
= 85.03 + 425.17 + 100
= 610.2 m3/hr or say 620 m3/hr.

Note: The capacity of Common Twin Lobe Roots Air blower suitable to discharge about 620 m3/hr @ 0.45
KSC – 2 No.s (1 W + 1 SB). The common blower shall supply the air required for the Aeration Tank & final
storage tank.

NOTE: In the proposed project; Sewage Treatment Plant of 300 KLD -2 no.s capacity are proposed, which
will be designed as per the above design methodology.

41 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

UNIT DETAILS
Description Size
Bar Screen Chamber 1.0 m x 1.5 m x 1.0 m
Oil separation tank 2.3 m x 1.0 m x 1.2 m SWD
Equalization tank 5.3 m x 5.3 m x 3.5 m SWD
SBR tank 9.1 m x 9.1 m x 3.5 m SWD with partition
Sludge Holding Tank 2.4 x 2.4 x 1.5 m SWD
Pre filtration tank /decant tank 5.8 m x 5.8 m x 3.0 m SWD
Ultra Filtration tank 2.9 x 6.9 x 1.85 m SWD
Final collection tank 5.8 m x 5.8 m x 3.0 m SWD

42 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

FLOW CHART OF PROPOSED SEWAGE TREATMENT PLANT


(300 KLD)

Raw Sewage

Bar Screen
chamber

Equalization Tank

Excess sludge
Disposed in to SBR
Filter Press for
Drying

Decant Tank

PSF

ACF

Chlorine
Dosage
SBR- Sequential Batch
Final Holding Reactor
Tank
PSF- Pressure Sand
Filter
To Reuse for
Flushing / ACF- Activated
Gardening purposes Carbon Filter

43 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE: D
WATER BALANCE CHART

Total Raw Water


demand (Start Up)
323 KLD

Daily water Requirement


323-98=225 KLD

Recycle for Toilet


Flushing Wastewater generated 291 KLD

STP Designed for


300 KLD

Landscape Excess quantity of 121 KLD


Toilet Flushing
Development will be discharged to UGD
98 KLD
72 KLD facilities / used for Watering
Avenue Plantation.

44 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE: E

WATER REQUIREMENT & SEWAGE DISPOSAL DURING CONSTRUCTION PHASE

Domestic water requirements during construction phase.


Total number of manpower required : 250
Water requirements @ of 100 LPCD : 250 x 100 = 25,000 L/day
Total domestic water requirements : 25 KLD
Wastewater discharge (Considering 90% of water consumed comes out as wastewater)
= 25,000 X 0.90 = 22,500 L/day or say 23 KLD

The wastewater generated will be treated in Package Sewage Treatment Plant of 25 KLD Capacity.
Unit size of package STP designed for 25 KLD
Description Size
Bar Screen Chamber 1.0 x 1.5 x 1.0 m
Equalization Tank 2.6 x 2.6 x 3.5 m SWD
SBR Tank 2.7 x 2.7 x 3.5 m SWD
Pressure Sand filter 0.5 m dia x 1.5 HOS
Activated Carbon Filter 0.5 m dia x 1.5 HOS

45 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE: F

SOLID WASTE GENERATION & ITS MANAGEMENT - CONSTRUCTION PHASE:


The total manpower : 250
Considering solid waste generation @ 0.25 kg/capita/day
Total solid waste generation : 250 x 0.25 = 62.5 Kg/day or
say 63 kg/day
The domestic wastes will be disposed through BBMP.

OCCUPANCY PHASE:
The wastes that are generated from the day to day activities which are in solid form are categorized as
solid wastes. Solid Wastes include dry refuse of house and street sweepings, crockery, Kitchen Wastes,
and also electronic wastes. The quantity of solid waste generated from the proposed project is calculated
as follows.

Total Contributing population from the Apartment 2170 Persons


Assuming solid waste generation rate as 0.4 kg/person/day for Residential Apartment
Quantity of solid waste generated from the project 868 Kg/day
Organic solid waste: 60 % of the total waste 521 kgs/day
Inorganic solid waste: 40 % of the total waste 347 kgs/day

The solid Wastes generated will be segregated at its point of generation and collected separately in
different color coded Synthetic Bins depending upon the basis of its Bio Degradability at a common
designated point. Organic solid waste from the project will be treated in an organic converter and is used as
manure for Landscape or used as fuel. The inorganic solid waste is proposed to be recycled.

46 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

47 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

The compost formed by this method will have a pH value of 6.5 – 7.5 C: N ratio of 15:1 and organic matter
of 40 – 50%. There will not be any pathogens and the pellets manufactured will have a calorific value of
3500 to 4000 Kcal/Kg.

48 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

SECONDARY SLUDGE FROM STPs:

The solid waste generated from the STP’s of secondary settling is in the form of stabilized secondary
sludge. Then is passed through the Plate & Frame filter press, the solids obtained as semi solid cakes are
used as organic manure for the development of plantations within the premises. The quantity of secondary
sludge from the secondary settling units of the treatment

* Rate: 300 m3/day and Sludge - 108 Kgs/Day

HAZARDOUS WASTE:
The Hazardous waste generated from the project is waste oil of about 500 Litres/annum which will be
stored in closed barrels and disposed to KSPCB approved and CPCB register waste oil re-processors.
Authorization will be obtained from KSPCB as per Hazardous waste (Management & Handling)
Amendment Rules, 2008.

BIO MEDICAL WASTE:

The Bio Medical Waste generated from the project will be collected and segregated at source based on
their categorization as per the Biomedical Waste (Management and Handling) Rules in containers and will
be disposed as per the guidelines. Common designated place will be earmarked for the storage of bio
medical waste and will be disposed scientifically.

e - WASTE:

The Electronic Waste (e-waste) such as CD’s, Pen drives, computer and its components, used batteries,
etc., from the project will be segregated, collected and stored at a designated place and will be handed
over to authorized recyclers.

49 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE – G
ENVIRONMENTAL MANAGEMENT PLAN:

1. INTRODUCTION:
The Environmental Management Plan (EMP) is aimed at mitigating the possible adverse impact of a project
and ensuring the existing environmental quality. The EMP converse all aspects of planning, construction
and operation of the project relevant to environment. It is essential to implement the EMP right from the
planning stage continuing throughout the construction and operation stage. Therefore the main purpose of
the Environmental Management Plan (EMP) is to identify the project specific activities that would have to
be considered for the significant adverse impacts and the mitigation measures required.

The construction phase impacts are mostly short term, restricted to the plot area and not envisaged
on the larger scale. In the operational phase the environmental impacts are due to continuous operation of
the project, hence, the emphasis in the Environment Management Plan (EMP) is to minimize such impacts.
The following mitigation measures are recommended in order to synchronize the economic development of
the project area with the environmental protection of the region.

The emphasis on the EMP development is on the following;


 Mitigation measures for each of the activities causing the environmental Impact.
 Monitoring plans for checking activities and environmental parameters and monitoring
responsibilities.
 Role responsibilities and resource allocation for monitoring; and
 Implementation of the Scheduled plan.

2. EMP DURING CONSTRUCTION PHASE:


During Construction phase, the activities which need to be monitored and managed from the point of
pollution are detailed in the subsequent sections.

2.1 LEVELLING AND SITE CLEARANCE:


The proposed project is residential apartment project having basement floor and earth excavation is
necessary. The total quantity of excavated soil is about 19,000 cum. About 8,000 cum will be used for

50 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

landscape development, about 6,000 cum will be used for backfilling and 5,000 cum will be used for
formation and hardscaping activities within the project site.

Environmental Management Plan during Leveling and Site Clearance:


Environmental Mitigation Proposed Remarks
Impacts
Noise generation:  Most optimum no. of operation by To reduce noise level,
Caused due to the heavy equipment Equipment provided
Excavators and  Selection of equipment with less noise with noise control
Bulldozers generation. devices is only used.
 The earth moving equipment shall be
periodically checked and maintained for
noise levels.
 The workers will be provided with PPE
such as ear plugs
Dust generation:  The site cleared will be periodically Tertiary treated water
Leveling operations watered to reduce dust emissions to be used.
results in the emission of  Barricades like metal sheets will be
dust. provided all round the premises to avoid
fugitive dust emission in to the
neighboring area apart from water
sprinkling.
 The workers will be provided with PPE
such as nose masks and goggles to
reduce impact.

2.2 TRANSPORTATION OF CONSTRUCTION MATERIALS:


During the Transportation of construction materials, minimum no. of vehicles will be used. Most optimum
route is planned to reduce the impact of transportation activity on the environment.
Environmental Management during Transportation

51 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

Environmental Impacts Mitigation Proposed


Noise generation  Quality fuel will be used.
 Periodic maintenance of vehicles is required.
Dust generation  Quality packaging of the construction materials
 Construction materials will be covered with tarpaulin sheet to
prevent from being air borne
 The vehicle speed shall be regulated
 The workers transporting materials will be provided with PPE such
as nose masks to reduce impact of air borne dust on their health
Vehicular emissions  Periodic emission check for vehicles will be done
 Clean fuel will be used for vehicles

2.3 CONSTRUCTION ACTIVITIES:


During the construction work, the following impacts are identified to monitor and mitigate the level of
impact.
Environmental Management during Construction
Environmental Impacts Mitigation Proposed Remarks

Noise generation  Less noise generating equipment Implementation


 Personnel Protective Equipment (PPE) such as responsibility:
ear plugs and helmets will be provided for Contractor - Civil
workers Works
 The working hours to be imposed on the
construction workers.
Dust generation  PPE in the form of nose masks will be provided Implementation
for construction workers. responsibility:
 Use of water sprays to prevent dust from being air Contractor
borne.
 Barricades like metal sheets will be provided all
around the premises to avoid fugitive dust

52 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

emission in to the neighboring area apart from


water sprinkling.
Water discharge  Sewage generated will be treated in Package Implementation
(Construction works) STP. responsibility:
Contractor
Air Emissions from  Periodic check and regular maintenance of Implementation
Construction construction machinery for emissions. responsibility:
machinery  Clean fuel are used in equipments Contractor

2.4 WASTEWATER DISCHARGE:


The sewage generated from the labors during construction is estimated to be about 23 KLD will be treated
in Package STP.
2.4.1 LABOUR CAMPS:
Environmental Management for Labor Camp:
Environmental Mitigation Proposed Remarks
Impacts
Wastewater Provision of adequate sanitation facilities. Responsibility:
generation Contractor
Usage of water Water for labor camps will be supplied in required Responsibility:
quantities. Contractor
Solid waste Segregation of Dry Waste and Wet Waste. Implementation
generation Adequate facilities to handle solid wastes shall be responsibility:
provided and will be disposed through BBMP. Contractor –
maintenance.

2.5 DISPOSAL OF EXCAVATED EARTH:


The proposed project is residential apartment project having basement floor and earth excavation is
necessary. The total quantity of excavated soil is about 19,000 cum. About 8,000 cum will be used for
landscape development, about 6,000 cum will be used for backfilling and 5,000 cum will be used for
formation and hardscaping activities within the project site.

53 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

2.6 PERSONNEL SAFETY SYSTEM:


It is planned to adopt the safe working practices which shall govern all construction works undertaken
throughout the project. Following Safety Aids to all laborers will be provided:

 Safety Helmets, Safety Belts, Safety Shoes, Hand gloves


 Gumboots while concreting
 Safety Goggles while welding/ Stone dressing etc.
 Facemasks and full body kit while Pest control
Implementation of Safety procedures such as:
• Using proper lifting techniques
• Using Safe Scaffolds
• Hot work permits for Fabrication and Welding

FINANCIAL ALLOCATION AND BUDGETARY PROVISION FOR EMP ASPECTS (CONSTRUCTION


ASPECTS)
Sl. Description Financial Provision in
No. Lakhs
Capital Recurring
Cost Cost
1 Environmental Management Plan during construction phase:
Using tertiary treated water for
• Sprinkling to control fugitive dusts 1.0 0.5
 Construction & curing purposes 1.0 0.5
 Flushing 1.0 0.5
2 Sewage Treatment Plant for Operation Phase 100.0 -
3 Potable water requirement for the construction workers 1.0 0.5
4 Maintenance of Vehicles and equipments - 2.0
5 Top Soil Conservation 2.0 -
6 Temporary Storm Water Drains 5.0 1.0
7 Personal protection safety gadgets and health care. 1.0 0.5
8 First aid facilities for workers 1.0 0.5
9 Plantation of Saplings 10.0 -
10 Environmental Monitoring Plan (Air, Noise, Water and Soil). - 2.0
11 TOTAL 123 8
Contingency at 10 % 12.3 0.8
TOTAL 135.3 8.8

54 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

3. EMP DURING OPERATION PHASE:


Following are the identified operational phase activities in the impact assessment, which may have
impact on the environment.
1. Air quality
2. Water quality
3. Noise quality
4. Solid waste disposal
5. Green belt development
6. Storm water Management

3.1 AIR QUALITY MANAGEMENT:


The pollutants envisaged from the proposed project are SPM, SO2, NOx, HC and CO mainly due to burning
of liquid fuel (HSD) in DG sets.
Exhaust from DG set will be emitted from stack of adequate height for dispersion of gaseous
pollutants. The following Table presents the EMP for air quality management during operation phase.
Air Quality Management during Operation Phase
Environmental Impacts Mitigation Proposed
DG set  Equipment selected will ensure the exhaust emission
standard as prescribed as per the latest amendments
from the MoEF.
 DG will be used as stand-by unit
 Periodic check and maintenance
Ambient air quality  Ambient air quality monitoring as per the prescribed
norms at regular interval.

3.2 WATER QUALITY MANAGEMENT:


Water requirement of project will be augmented through Bore wells with obtaining permission from KGWA.
Details of water requirement and Water balance is presented in Annexure B & D respectively.
The sewage generated from the proposed project will be treated in the proposed STP of 300 KLD. The
treatment scheme for domestic sewage generated from project is discussed in Annexure - C. Treated water
will be reused for flushing, gardening etc., and the following Table presents the EMP for water quality.

55 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

Water Quality Management during Operation Phase


Environmental impacts Mitigation Proposed
Wastewater  Treated with proposed Sewage Treatment
Plant to produce tertiary treated water which is reused for secondary
purposes such as flushing landscaping development etc.,
 Water conservation measures will be encouraged

3.3 NOISE MANAGEMENT:


High noise generating units such as DG set will be provided with acoustic enclosures. Green belt on
the project boundary will further act as noise barrier and helps in attenuation of noise. The Table presents
the EMP for noise level.
Noise Management during Operation Phase
Environmental Impacts Mitigation Proposed

Noise from DG set area  Acoustic enclosures will be provided for DG set
 DG set will be installed in an area (utility section) where the access will be
restricted
 The use of PPE (ear plugs) will be mandatory in this area.
 Selection of equipment to ensure that the residual noise level of <55 dB(A)
 Noise levels will be checked periodically using a noise pressure level meter

3.4 SOLID WASTE MANAGEMENT:


The solid wastes generated during operation phase can be categorized under
Three types: Domestic/Residential Waste
Wet Garbage: Food waste, Lawn mowing wastes etc.
Dry Garbage: Paper, Plastic, Bottles, etc.
Sludge from Sewage Treatment Plant (STP)
The solid waste generated and its management is detailed in Annexure – F.
The various mitigation measures to be adopted during collection and disposal of wastes are as follows:
 It is preferable that the container and bins used for collection of waste should be of closed type and
waste is not exposed thus possibility of spreading of disease through flies and mosquitoes is
minimized.
56 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

 Collection system should be properly supervised so that quick and regular removal of waste from
the dustbin is practiced.
 Door to door collection shall be done in each building to collect the solid wastes.

3.5 STORM WATER MANAGEMENT:


As the project location is blessed with fairly good rainfall, it is planned to collect the storm water at
different gradients of the location. There will be rainfall runoff from building roof-tops, roads and pavements
and greenbelt area. Necessary provision will be made to collect the quantity of rainfall runoff during the
most rainy day of season. Necessary rain harvesting pit/recharge pit at every 30 m centre to centre have
been envisaged. A storm water drain with 600mm wide with RCC precast perforated cover and 1800 mm
dia RCC precast Ring soak pit will be provided around the periphery of property and designed as per
building by-law (schedule 12).

3.6 LANDSCAPE DEVELOPMENT:


Vegetation is the natural extension of the soil ecosystem on a site. It can provide summer shade, wind
protection and a low-maintenance landscape that is adapted to the local environment. In the project there
are 237 trees (Mango – 9, Coconut – 212, Jackfruit – 3, Tamarind – 6 and Jungle wood – 7), out of it 151
Coconut trees will be felled and remaining 86 tress will be retained (Mango – 9, Coconut – 61, Jackfruit – 3,
Tamarind – 6 and Jungle wood – 7). Along with this about 80 trees of native / indigenous species of the
below combination will be planted at site.

57 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

List of plant species proposed:


Sl. Proposed Trees Quantity
No Botanical Name Common Name (Nos)
1 Champaka Sampige 8
2 Azadirachta indica Neem 5
3 Plumeria Alba Temple tree 4
4 Pongamia Pinnata Indian Beech Tree 5
5 Cassia Fistula Gold shower tree 8
6 Alstonia Scholaris Indian devil tree 4
7 Murraya Koenigi Curry leaf 5
8 Dalbergia Sissoo Indian Redwood 6
9 Putrangia Roxburghi Putravanti 4
10 Mangifera Indica Mango tree 5
11 Tabebuia Avellandae Pink accent tree 6
12 Agle Marmelos Bilwa patra tree 6
13 Anthocephalus Cadamba tree 4
cadamba
14 Philanthes Emblica Amla Tree 5
15 Ficus Carcia Anjura/fig tree 5
16 Total 80

4. MANAGEMENT OF SOCIO-ECONOMIC ISSUES:


1) Schools for laborer’s children
Temporary education centers (Creche) will be provided for education of the children of the laborers.
2) Health camp for laborer’s family
Periodical health camps will be organized to monitor and facilitate the occupants of the labor camps.

HEALTH RISK AND DISASTER MANAGEMENT:


Public health and safety:
Since all the construction related activities are confined to the project site, minimal health related impacts
are envisaged within the project influenced area during the construction stage.
At the project site on an average of 250 no. of persons will be engaged, who face direct exposure to dust
and noise generated from the construction activity. This is likely to cause health related affects such as
asthma, bronchitis etc., and hearing impairments respectively.
To minimize these anticipated impacts, suitable actions like
• Use of water sprinklers to prevent dust from being air borne.

58 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

• Providing suitable Personal Protective Equipments (PPE) like mouth mask with filters, noise mask,
helmets etc.,
• Periodic health check up camp for the laborers will be arranged.
• Provision of safety belts.
• In case of injury on site medical treatment and transport will be organized.
Due to operation of the proposed project, there will be enhancement in public Health and safety.
 Regular visit of resident medical officer to take care of the first aid and primary medication in case
of emergency for project occupants and laborers.
 First aid kit with primary medicines will always be available in the medical Centre.
 Display of action plan and preparedness measures during emergency situations.

5. EMP IMPLEMENTATION SCHEDULE:


Phased according to the priority, the implementation schedule is presented in the following table.
Implementation Schedule for EMP
No. Recommendations Requirement
1 Air pollution control measures Before commissioning of respective units
2 Water pollution control measures Before commissioning of the project
3 Noise control measures Along with the commissioning of the project
4 Solid waste management During commissioning of the project
5 Green belt development Stage-wise implementation

The responsibility of EMP implementation lies with the project promoter for a period of 3 years. Once the
residents' society is established, the EMP responsibility will be properly handed over with clearly defined
procedures and guidelines.

59 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

FINANCIAL ALLOCATION AND BUDGETARY PROVISION FOR EMP ASPECTS (OCCUPANCY PHASE)
Sl. Description Financial Provision in
No. Lakhs
Capital Recurring
Cost Cost
1 Operation of Sewage Treatment Plant - 3.0
2 Reclaimed Sewage Distribution Network 10.0 1.0
3 Rain water harvesting tanks and its facilities 10.0 1.0
4 Ground water recharging pits & its management 10.0 1.0
5 DG sets acoustic & Maintenance 5.0 1.0
6 Landscaping 10.0 3.0
7 Solid waste management 8.0 1.0
8 Environmental Monitoring Plan per annum (Air, Noise, Water and - 2.0
Soil)
9 TOTAL 53 13
Contingency at 10 % 5.3 1.3
TOTAL 58.3 14.3

60 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

6. ENVIRONMENTAL MONITORING ROUTINES:


A comprehensive monitoring program is suggested below:
Monitoring Schedule for Environmental Parameters
Sl. Particulars Monitoring Duration of Important
No frequency monitoring parameters for
monitoring
I Air Quality
1. Ambient Air monitoring
Project premises Once in a 24 hourly sample RSPM, SPM, SO2,
month NOx
2. Stack monitoring Once in a year Grab SPM, SO2, NOx,
if required HC, CO

II Water and Wastewater Quality


1. Water Quality
i. Groundwater at two locations (up- Once in a Grab As per KSPCB
gradient and down-gradient) of treated month requirements
effluent discharge area/land
2. Wastewater quality
i. Inlet into STP NA NA -
ii. Treated effluent prior to discharge NA NA -
III Soil Quality
1. Within project premises at 1 location on Once in 6 Composite As per KSPCB
effluent discharging area/land month sample requirements
2. Ecological preservation and up gradation Seasonal Visual Survival rate
observations
IV Noise monitoring
1. Project premises Once in 6 Day and night As per KSPCB
month requirements

61 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE: H

RAINWATER MANAGEMENT PLAN:

RAIN WATER HARVESTING:

The water collected from the terraces of the buildings shall be collected in the rainwater collection sump
and reused for domestic purpose after necessary treatment.

VOLUME OF RAIN WATER HARVESTED:

The total quantity of water i.e., received in the form of rainfall over an area is called the rain water
endowment of that area, out of which the amount of water that can be effectively harvested is called the
rain water harvesting potential.
Rain Water harvesting potential = Intensity of Rainfall (m) x Roof Area x Impermeability Factor.

The collection efficiency accounts for the fact that all the rain water falling over an area cannot be
effectively harvested due to losses on account of evaporation, spillage or run off etc.,
According to the data available from the Indian Meteorological Department, the Average annual rainfall
around month of September = 194.80 mm
Assuming that about 90 % Rainfall can be effectively harvested.
Number of Rainy Days = 9.3
Therefore the I.R = 194.80/9.3= 20.94 mm/day or 0.02094 m/Day or 0.021 m/day
The Quantity of roof top rainwater harvested from the proposed is calculated as under:
The top 14th floor area of the proposed project is about 3,273.54 sq m
For rain water harvesting consider 75 % of this total area is 2,455.15 sq m
Quantity of Rain Water that can be harvested from the building is as follows.
Rain water (Q) from Roof top = 0.021 x 2,455.15 x 0.9
= 4.6.40 cum/day or say 47 cum/day
Rain water storage sump of 75 cum (1 no) capacity is constructed to collect the rain water and is being
reused for domestic purposes.

62 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

STORM WATER MANAGEMENT:


Storm water disposal is divided into 2 Groups:
 Terrace Storm water disposal: The entire rainwater from the terrace would be disposed through
suitable rain water pipes and collecting in the dedicated rain water collection sump, which is
proposed at site level. This water will be utilized for domestic purpose
 Site (Paved and landscape area) Storm water disposal: The entire storm water from the site would
be disposed off through suitable RCC Box drainage system to the rainwater recharge pits and the
excess is diverted to external storm water drainage.
The amount of storm water that the paved area will produce can be determined by considering the
impermeability factor to be 0.9.
Q = 0.021 x 4,639.41 sq m x 0.9
= 87.68 cum/day or say 88 cum/day
The amount of storm water that the landscaped area will produce can be determined by considering the
impermeability factor to be 0.3
Q = 0.021 x 6,557.95 sq m x 0.3
= 41.31 cum/day or say 42 cum/day
The Total amount of storm water = paved area + landscaped area
= 88 + 42 cum/day
= 130 cum/day

The Proponents shall also Provide Recharging Pits along the inner periphery of the boundary wall with
recharging pit of size 1.2 m dia x 2.5 m deep spaced at 20 m centre to centre. These recharging pits are
filled with graded media comprising of Boulder at bottom and with coarse aggregates to facilitate
percolation of harvested rain water to Recharge Ground Water table.

63 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE: I

DISASTER MANAGEMENT PLANS FOR PRE CONSTRUCTION PHASE:

Risk and disaster management plan:


Disaster is an unexpected event due to sudden failure of the system, external threats, internal
disturbances, earth quakes, fire and accidents. Thus an appropriate management plan shall be
incorporated.

Precautions:
 Once the likelihood of the disaster is suspected, preventive actions should be undertaken by the
project in-charge.
 Conditional maintenance of equipments, materials and expertise for use during emergency.
 The electrical systems shall be provided with automatic circuit breakers activated by over current.
 Proper escape routes are planned and displayed in the public domain.
 Selected representatives are given proper training to guide other inhabitants during Fire accidents.
 Periodic awareness program is conducted for the workers on their roles during emergency situations.

Important telephone numbers like police authorities, fire department and hospitals etc., of use during
emergency situations will be made available.

64 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE: J

Environmental Management Plan for control of Dust and Noise pollution during construction phase:

 Barricades like metal sheets will be provided all round the premises of the project to avoid fugitive dust
emission into the neighboring area and frequent water sprinkling will also be carried out.

Environmental Impacts Mitigation Proposed


1. Leveling and Site Clearance:
Noise generation: Caused  Most optimum no. of operation by the heavy equipment
due to Excavators and
 Selection of equipment with less noise generation to be used
Bulldozers
 The earth moving equipment will be periodically checked and
maintained for noise level.
 The workers will be provided with adequate PPE such as ear
plugs to reduce impact of high noise levels.
Dust generation: Leveling  The site cleared will be periodically watered to reduce
operations results in the emission of dust particles
emission of dust.
 Barricades like metal sheets will be provided all round the
premises to avoid fugitive dust emission in to the neighboring
area apart from water sprinkling.
 The workers will be provided with PPE such as nose masks and
goggles to reduce impact on health.
2. Transportation of Construction Materials:
 Noise generation  Quality fuel will be used.
 Periodic maintenance of vehicles is required.
 Dust generation  Quality packaging of the construction materials
 Construction materials will be covered with tarpaulin sheet to
prevent from being air borne
 The vehicle speed shall be regulated
 The workers transporting materials will be provided with PPE
such as nose masks to reduce impact of air borne dust on
their health
1. Construction Activities:
 Noise generation  Selection of Less noise generating equipment
 Personnel Protective Equipment (PPE) such as ear plugs and

65 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

helmets will be provided for workers


 The working hours will be imposed on the construction
workers.
 Dust generation  PPE in the form of nose masks will be provided for
construction workers
 Use of water sprays to prevent dust from being air borne.
 Barricades like metal sheets will be provided all around the
premises to avoid fugitive dust emission in to the neighboring
area apart from water sprinkling

66 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE: K

RISK ASSESSMENT & MANAGEMENT PLAN

a. Construction Phase:
Sl. Potential Mitigation
No.
1 Accidental fire Fire safety gadgets.
2 Fall of objects Use of personal protection devices-helmets
3 Working at great heights Protection to prevent fall, with life safety belts and nets.
4 Accidents from machinery Personal protection gadgets
5 Electrical mishap Adopting safety measures to prevent any act of negligence
and providing electrical safety measures like fire
extinguishers.

b. All necessary measures will be taken to avoid accidents and mishaps during operation phase.

Precautions for Risk and Disaster Management Plan:


 Once the likelihood of the disaster is suspected, preventive actions should be undertaken by the
project in-charge.
 Conditional maintenance of equipments, materials, and expertise for use during emergency.
 The electrical systems shall be provided with automatic circuit breakers activated by over current.
 Fire extinguishers provided at pre-notified locations inside the building.
 Proper escape routes will be planned and displayed in the public domain.
 Selected representatives will be given proper training to guide other inhabitants during Fire accidents.
 Periodic awareness program is conducted for the occupants on their roles during emergency
situations.

Important telephone numbers like police authorities, fire department and hospitals etc., of use during
emergency situations are made available.

67 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE: L
SOIL INVESTIGATION REPORT

Report on the Soil Investigation for the Proposed Residential Apartment project with 434 Flats at Survey
No. 53/1 and Site No. 394, Gubbalala Village, Uttarahalli Hobli, Bangalore South Taluk, Bangalore.

INTRODUCTION:
M/s. Rohan Gruh Nirman LLP., #1201, 1st Floor, Divyashakti, 100 Feet Road, Indiranagar, Bangalore –
560 038 have conducted Soil Investigation for the proposed Residential Apartment Project and primary
objective of this investigation is to establish the ground condition at the site and to evaluate the soil
characteristics through various tests.

SUBSURFACE PROFILE:
The sub-soil profile indicates that the Silty sand with gravels (SM/GA) sustain a safe bearing capacity of 25
T/m2 at depth below proposed cellular bottom level or 3.0 m below existing ground level for open
foundations. The subsoil profile indicates that the Soft Weathered rock sustain a safe bearing capacity of
28.00 to 35.00 T/m2 at 3.5 to 5.0 below existing ground level for open foundations. The Soft Weathered to
Soft to Medium Hard Rock is encountered at deeper depths.

CONCLUSIONS:
The following conclusions are given based on field investigations.
1. The subsoil stratum is found to be medium stiff/medium dense in nature.
2. The silt/clay present in the soil, medium compressible in nature.
3. During the time of investigation water table was not encountered up to termination depth.

68 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE: M
TRAFFIC MANAGEMENT MEASURES

• Merging of vehicles will be performed only to left traffic from the exit gates, this ensures safety.
• To establish smooth entry & exit of vehicles, bell mouth shape geometry is provided at the gates.
This ensures smooth transition for merging of vehicles.
• Yellow paint junction boxes are painted at the locations to create psychological barrier for through
drivers to control the speed.
• Rubber humps are introduced for the outgoing vehicles at the exit gate drive way. All gates are
manned with efficient security who can guide the entry and exit of vehicles.
• Adequate sign & guide posts for traffic as per IRC (Indian Roads Congress).
• Road marking, STOP lines, parking lanes, slot numbers etc, must be clearly painted so as to guide
the vehicles.

69 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE: N
ENERGY CONSERVATION ASPECTS PROPOSED IN THE PROJECT:

a. Energy Efficient motors, whose efficiency is not lower than the limits specified in section 8.2.2 of the
Energy Conservation Building Code will be installed.

b. Dry type Transformer with efficiency not lower than the limits specified in section 8.2.1 of the code shall
be considered.

c. Power monitoring, recording and check metering will be provided in the main LT panels on the incoming
feeders and individual outgoing feeders covering all parameters such as Current, Voltage, Energy & THDI
as stipulated in section 8.2.4 of the code.

d. Cable sizing and design of distribution system will ensure that the total distribution loss will not exceed
1% of the total energy consumed as stipulated in section 8.2.5.1 of the code.

e. Timer controls will be incorporated in the distribution board of external lighting to save energy as
stipulated in section 7.4 of the code.

f. Power conditioning equipment will be installed to limit THDI to 5% which shall also improve power factor
to 0.95 as stipulated in section 8.2.3 of the code.

g. Solar Lighting shall be provided at strategic locations in outdoor areas.

h. Water cooled Chillers are used instead of air cooled chillers which provide energy savings.

j. VFD drives shall be provided for secondary pumps for water cooled chillers and lifts which will result in
energy savings.

70 PROJECT REPORT
M/s. Rohan Gruh Nirman LLP., Residential Apartment

ANNEXURE – 0
PROJECT RELEATED DRAWINGS & PLANS

71 PROJECT REPORT

Você também pode gostar