Informe del resumen de costos de los recursos

ACERO CLAVO ALAMBRE


MADERA TRIPLAY
BLOQUE SISTEMA PLACA
CONCRETO
MATERIALES VARIOS
Total General
Tipo Material

Costo Año Trimestre Semana


2019
T2
Recursos Semana 18 Semana 19 Semana 20 Semana 21 Semana 22
ACERO CLAVO ALAMBRE 2478.75 7436.25 744.66 651.57 9566.07
MADERA TRIPLAY 18.396 73.584 11169.9 9773.73 4322.19
BLOQUE SISTEMA PLACA 5944.24536 20584.43984 0 0 0
CONCRETO 0 0 0 0 37700.0331
MATERIALES VARIOS 573.1003333 2703.263 1280 1280 4639.58
Total General 9014.491693 30797.53684 13194.56 11705.3 56227.8731
Total 2019
Total T2
Semana 23 Semana 24 Semana 25 Semana 26 Semana 27
12050.76 17008.26 13288.155 11154.375 4957.5 79336.35 79336.35
4411.56 4503.54 4390.968 101.178 73.584 38838.63 38838.63
0 26528.6852 1375.85188 27904.53708 23776.98144 106114.7408 106114.7408
25647.47925 15586.0704 20988.19995 385.9758 0 100307.7585 100307.7585
2944.486667 2724.81 1131.051 1955.011 1439.068 20670.37 20670.37
45054.28592 66351.3656 41174.22583 41501.07688 30247.13344 345267.8493 345267.8493
Total General

79336.35
38838.63
106114.7408
100307.7585
20670.37
345267.8493