- DATOS DE LA OBRA
PROYECTO:
MEJORAMIENTO DE LAS CONDICIONES BASICAS DE CALIDAD DE LA INFRAESTRUCTURA FISICO-E
SAN MARTIN
68052
ENTIDAD: UNSM
MODALIDAD: POR CONTRATA
UBICACIÓN: SAN MARTIN - RIOJA -RIOJA
DIRECCION: JR. SANTO TORIBIO 1239
PROGRAMADO
MES DESCRIPCION
PROGRAMADO % % ACUM
OCTUBRE VALORIZACION 01 S/. 10,648.47 0.35% 0.35%
NOVIEMBRE VALORIZACION 02 S/. 422,948.87 13.73% 14.08%
DICIEMBRE VALORIZACION 03 S/. 988,827.76 32.10% 46.18%
ENERO VALORIZACION 04 S/. 741,014.19 24.06% 70.24%
FEBRERO VALORIZACION 05 S/. 511,398.37 16.60% 86.84%
MARZO VALORIZACION 06 S/. 316,215.90 10.27% 97.11%
ABRIL VALORIZACION 07 S/. 89,142.18 2.89% 100.00%
018-UNSM/R/NLU
ADO EJECUTADO
PROGR. ACUM EJECUTADO % % ACUM EJECT. ACUM
S/. 10,648.47 S/. 17,381.11 0.56% 0.56% S/. 17,381.11
S/. 433,597.34 S/. 408,243.87 13.25% 13.82% S/. 425,624.98
S/. 1,422,425.10 S/. 419,040.35 13.60% 27.42% S/. 844,665.33
S/. 2,163,439.29 S/. 438,727.43 14.24% 41.67% S/. 1,283,392.76
S/. 2,674,837.66
S/. 2,991,053.56
S/. 3,080,195.74
CCIONES SAC
DEL 30/10/2018 AL 15/11/2018
DEL 16/11/2018 - ACTUALIDAD
DEL 30/10/2018 AL 14/11/2018
DEL 15/11/2018 - ACTUALIDAD
DE SAN MARTIN - SEDE RIOJA EN EL DISTRITO DE RIOJA PROVINCIA DE RIOJA
1.- DATOS DE LA OBRA
PROYECTO:
MEJORAMIENTO DE LAS CONDICIONES BASICAS DE CALIDAD DE LA INFRAESTRUCTURA FISICO-E
PROVINCIA DE MOYOBAMBA SAN MARTIN
68052
ENTIDAD: UNSM
MODALIDAD: POR CONTRATA
UBICACIÓN: SAN MARTIN - RIOJA -RIOJA
DIRECCION: JR. SANTO TORIBIO 1239
PROGRAMADO
MES DESCRIPCION
PROGRAMADO % % ACUM
JUNIO VALORIZACION 01 S/. 307,378.02 13.76% 13.76%
JULIO VALORIZACION 02 S/. 347,065.04 15.54% 29.30%
AGOSTO VALORIZACION 03 S/. 696,121.97 31.16% 60.46%
SEPTIEMBRE VALORIZACION 04 S/. 663,611.58 29.71% 90.16%
OCTUBRE VALORIZACION 05 S/. 121,876.05 5.46% 95.62%
NOVIEMBRE VALORIZACION 06 S/. 51,775.20 2.32% 97.94%
DICIEMBRE VALORIZACION 07 S/. 46,067.05 2.06% 100.00%
018-UNSM/R/NLU
ADO EJECUTADO
PROGR. ACUM EJECUTADO % % ACUM EJECT. ACUM
S/. 307,378.02 S/. 528,667.14 23.67% 23.67% S/. 528,667.14
S/. 654,443.06 S/. 813,559.02 36.42% 60.08% S/. 1,342,226.16
S/. 1,350,565.03 S/. 559,364.91 25.04% 85.12% S/. 1,901,591.07
S/. 2,014,176.61 S/. 112,499.20 5.04% 90.16% S/. 2,014,090.27
S/. 2,136,052.66 S/. 99,735.43 4.46% 94.63% S/. 2,113,825.70
S/. 2,187,827.86 S/. 74,449.02 3.33% 97.96% S/. 2,188,274.72
S/. 2,233,894.91 S/. 28,134.89 1.26% 99.22% S/. 2,216,409.61
CCIONES SAC
DEL 30/10/2018 AL 15/11/2018
DEL 16/11/2018 - ACTUALIDAD
DEL 30/10/2018 AL 14/11/2018
DEL 15/11/2018 - ACTUALIDAD
DE SAN MARTIN - SEDE MOYOBAMBA, EN EL DISTRITO DE MOYOBAMBA
1.- DATOS DE LA OBRA
PROYECTO:
MEJORAMIENTO DE LAS CONDICIONES BASICAS DE DE LOS LABORATORIOS DE FORMACION GEN
74543
ENTIDAD: UNSM
MODALIDAD: POR CONTRATA
UBICACIÓN: SAN MARTIN - RIOJA -RIOJA
DIRECCION: JR. SANTO TORIBIO 1239
PROGRAMADO
MES DESCRIPCION
PROGRAMADO % % ACUM
JULIO VALORIZACION 01 S/. 401,343.35 9.25% 9.25%
AGOSTO VALORIZACION 02 S/. 745,063.83 17.18% 26.43%
SETIEMBRE VALORIZACION 03 S/. 683,598.20 15.76% 42.19%
OCTUBRE VALORIZACION 04 S/. 929,653.58 21.43% 63.63%
NOVIEMBRE VALORIZACION 05 S/. 862,649.75 19.89% 83.52%
DICIEMBRE VALORIZACION 06 S/. 714,972.32 16.48% 100.00%
018-UNSM/R/NLU
ADO EJECUTADO
PROGR. ACUM EJECUTADO % % ACUM EJECT. ACUM
S/. 401,343.35 S/. 401,343.35 9.25% 9.25% S/. 401,343.35
S/. 1,146,407.18 S/. 745,063.83 17.18% 26.43% S/. 1,146,407.18
S/. 1,830,005.38 S/. 683,598.20 15.76% 42.19% S/. 1,830,005.38
S/. 2,759,658.96 S/. 929,653.58 21.43% 63.63% S/. 2,759,658.96
S/. 3,622,308.71 S/. 913,320.83 21.06% 84.68% S/. 3,672,979.79
S/. 4,337,281.03 S/. 664,301.23 15.32% 100.00% S/. 4,337,281.03
CCIONES SAC
DEL 30/10/2018 AL 15/11/2018
DEL 16/11/2018 - ACTUALIDAD
DEL 30/10/2018 AL 14/11/2018
DEL 15/11/2018 - ACTUALIDAD
TARIA, EN EL DISTRITO DE MORALES, PROVINCIA DE SAN MARTIN
1.- DATOS DE LA OBRA
PROYECTO:
MEJORAMIENTO DE LAS CONDICIONES BASICAS DE DE LOS LABORATORIOS DE FORMACION GEN
74543
ENTIDAD: UNSM
MODALIDAD: POR CONTRATA
UBICACIÓN: SAN MARTIN - RIOJA -RIOJA
DIRECCION: JR. SANTO TORIBIO 1239
PROGRAMADO
MES DESCRIPCION
PROGRAMADO % % ACUM
ENERO VALORIZACION 01 S/. 155,524.68 21.04% 21.04%
FEBRERO VALORIZACION 02 S/. 24,535.69 3.32% 24.36%
MARZO VALORIZACION 03 S/. 0.00 0.00% 24.36%
ABRIL VALORIZACION 04 S/. 0.00 0.00% 24.36%
MAYO VALORIZACION 05 S/. 0.00 0.00% 24.36%
JUNIO VALORIZACION 06 S/. 0.00 0.00% 24.36%
JULIO VALORIZACION 07 S/. 0.00 0.00% 24.36%
AGOSTO VALORIZACION 08 S/. 0.00 0.00% 24.36%
SEPTIEMBRE VALORIZACION 09 S/. 0.00 0.00% 24.36%
OCTUBRE VALORIZACION 10 S/. 17,776.01 2.41% 26.77%
NOVIEMBRE VALORIZACION 11 S/. 241,849.69 32.72% 59.49%
DICIEMBRE VALORIZACION 12 S/. 149,939.41 20.29% 79.78%
ENERO VALORIZACION 13 S/. 149,468.70 20.22% 100.00%
S/. 739,094.18 100.00%
018-UNSM/R/NLU
ADO EJECUTADO
PROGR. ACUM EJECUTADO % % ACUM EJECT. ACUM
S/. 155,524.68 S/. 177,131.50 23.97% 23.97% S/. 177,131.50
S/. 180,060.37 S/. 0.00 0.00% 23.97% S/. 177,131.50
S/. 180,060.37 S/. 0.00 0.00% 23.97% S/. 177,131.50
S/. 180,060.37 S/. 0.00 0.00% 23.97% S/. 177,131.50
S/. 180,060.37 S/. 0.00 0.00% 23.97% S/. 177,131.50
S/. 180,060.37 S/. 0.00 0.00% 23.97% S/. 177,131.50
S/. 180,060.37 S/. 0.00 0.00% 23.97% S/. 177,131.50
S/. 180,060.37 S/. 0.00 0.00% 23.97% S/. 177,131.50
S/. 180,060.37 S/. 0.00 0.00% 23.97% S/. 177,131.50
S/. 197,836.38 S/. 10,233.01 1.38% 25.35% S/. 187,364.51
S/. 439,686.07 S/. 166,232.11 22.49% 47.84% S/. 353,596.62
S/. 589,625.48 S/. 385,497.56 52.16% 100.00% S/. 739,094.18
S/. 739,094.18 S/. 0.00 0.00% 100.00% S/. 739,094.18
S/. 739,094.18 100.00%
CCIONES SAC