Você está na página 1de 2

PROJECT TITLE : CONSTRUCTION OF EXTENSION FENCE

OWNER : RENARD JOHN M. REA


LOCATION : MERCEDES HOMES, BRGY. SAN MIGUEL, STO. TOMAS, BATANGAS
SUBJECT : SPECIFICATION

GENERAL CONDITIONS:

I. SCOPE OF WORK
The work to be undertaken in this contract shall include:
a. Furnishing of all necessary materials, labor and equipment required in the
construction.
b. Complete construction in accordance with the plan and specification submitted
herewith.
c. All works took be done shall be of the highest quality of workmanship and to the
fullest intent of the plan and specification unless otherwise specified by the
Engineer.

II. PLANS AND SPECIFICATIONS


a. The plan and specifications shall be considered as cooperatives and all labors and
materials contained in one but not mentioned or indicated in the other, out vice
versa shall be considered as if they are duly mentioned in both.
b. If numerical indications appear on plans, they shall be carefully followed but if not
indicated, the numerical notation on the specification shall govern not the scale on
drawings. In case of discrepancies on figures and drawing, the matter shall
immediately be submitted took the Engineer.
c. No charges in drawings and specifications shall be made by the other contractor or
workmen without prior agreement or approval of the Engineer.

III. LOCATION
a. The proper structure is to be created.
b. The structure shall be staked out and grade established by the Engineer or his
authorized representative.
c. All materials shall be stored within our near sure work and shall be conducted in
such a manner as to preserve all works by the Engineer.

IV. EXCAVATION
a. All excavation required for foundation indicated on the site drawing shall be done by
the contractor by his expense.
b. Excavation shall be done in accordance from the bottom of the excavation before
setting up the footing and no footing shall be rest on fill.
c. All fills shall be placed 1 layer not exceeding 150mm thickness, each layer is to be
compacted by wetting, tamping and rolling.
d. After forms have been removed from footings, the materials from excavation shall
be used for backfilling. Materials not used shall be placed on an immediate premise
as directed by the Engineer provided the contractor shall not require moving such
materials more than 50 meters.

V. CONCRETE AND MASONRY


a. All concrete shall be done in accordance with the specification for concrete and
reinforced concrete as accepted by the Department of Public Works and Highways.

VI. FRAMING
a. All framing shall be mortised and tenoned and fitted together with closed tight joints
in approved manner. No joint on the purlins will be allowed between bearings. Ask
openings shall have frames or dimensions shown on the drawings.
VII. HARDWARE
a. Hardware to be used in this building shall be approved typed depending upon the
owner's request with the approval of the Engineer with respect to the adaptability
and availability on the market.

VII. PAINTING
a. All painting materials shall have first grade quality and shall meet the requirements
of the Government Standard Specifications and shall be approved and delivered in
original container. No ready mixed paint shall be allowed.
b. No painting shall be done in wet weather. All works shall be done in first class
workmanship. No succeeding costs shall be done it applied unless the preceding
costs have been inspected and accepted by the Engineer.

IX. MISCELLANEOUS
a. Any work in connection with these specifications, which are not specified herewith
but necessary to have and desired by the owner with the approval of the Engineer
shall be done in the best and approved manner in accordance with the standard
practice and based on reasonable interpretation of the plan.

Prepared by: Engr. Paul Cedrick M. Rea