LINE LIST

Document No. 19BARA-BID-0XX-01-LS2


1 of 5
Rev. P1 Date 05-31-2019

ENGINEERING, PROCUREMENT, AND CONSTRUCTION OF


ASPHALT DRUMMING PLANT
PACIRAN - LAMONGAN

LAMONGAN SHOREBASE
2019

P1 Issued For Preliminary 31 May 19 AGG BTR SHA


COMPANY
Rev. DESCRIPTION DATE PREPARED CHECKED APPROVED
APPROVAL
LINE LIST

Document No. 19BARA-BID-0XX-01-LS2


2 of 5
Rev. P1 Date 05-31-2019

LEMBAR REVISI

Rev. Date Description

P1 05/31/2019 Issued for Preliminary


LINE LIST

Document No. 19BARA-BID-0XX-01-LS2


3 of 5
Rev. P1 Date 05-31-2019

DAFTAR ISI

1 GENERAL.................................................................................................................... 4
1.1 Scope .................................................................................................................. 4
1.2 References .......................................................................................................... 4
2 ATTACHMENT ............................................................................................................ 4
LINE LIST

Document No. 19BARA-BID-0XX-01-LS2


4 of 5
Rev. P1 Date 05-31-2019

1 GENERAL

1.1 Scope
This document summarizes the list of equipment listed / illustrated in the P & ID of
Asphalt Drumming Plant

1.2 References
Project Document
19BARA-BID-0XX-01-PFD Process Flow Diagram Asphalt Drumming Plant
19BARA-BID-0XX-01-PID1 P & ID Legend & Symbols
19BARA-BID-0XX-01-PID2 Jetty & Transfer Pump
19BARA-BID-0XX-01-PID3 Asphalt Storage Tank
19BARA-BID-0XX-01-PID4 Filling Shed
19BARA-BID-0XX-01-PID5 Hot Oil Package

2 ATTACHMENT

The following is a list of “Line List” used in this project and illustrated in P & ID.
LINE LIST

Document No. 19BARA-BID-0XX-01-LS2


5 of 5
Rev. P1 Date 05-31-2019

ATTACHMENT 1 – LINE LIST


ENGINEERING, PROCUREMENT, AND COSTRUCTION OF
ASPHALT DRUMMING PLANT
LINE LIST
No. NPS Fluid Material Pipe Pipe Tag No. P&ID References Description Fluid Phase Flow Rate Operating Operating Design Design Insulation Remarks
Code Code Code Sequence Pressure Temperature Pressure Temperature Thickness
Number
Max / Normal Max / Normal Max / Min Max / Min
kg/cm²G °C kg/cm²G °C mm
1 8" AS CS 001 8"-AS-CS-001 19BARA-BID-0XX-01-PID2 Jetty transfer Pipe to Metering Package Cair 217 10,0 110,0 12,0 130,0 75 Insulated with HDPE and Polyurethane
m³/jam
2 8" AS CS 002 8"-AS-CS-002 19BARA-BID-0XX-01-PID2 Jetty transfer Pipe to Inlet Header of Transfer Pump Cair 217 10,0 110,0 12,0 130,0 75 Insulated with HDPE and Polyurethane
m³/jam
3 8" AS CS 003 8"-AS-CS-003 19BARA-BID-0XX-01-PID2 Inlet Header of Transfer Pump Cair 217 10,0 110,0 12,0 130,0 75 Insulated with HDPE and Polyurethane
m³/jam
4 8" AS CS 004 8"-AS-CS-004 19BARA-BID-0XX-01-PID2 Suction Pipe of Jetty Transfer Pump P-01A Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
5 8" AS CS 005 8"-AS-CS-005 19BARA-BID-0XX-01-PID2 Discharge Pipe of Jetty Transfer Pump P-01A Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
6 8" AS CS 006 8"-AS-CS-006 19BARA-BID-0XX-01-PID2 Suction Pipe of Jetty Transfer Pump P-01B Cair 60 10,0 110,0 12,0 130,0 75
m³/jam

7 8" AS CS 007 8"-AS-CS-007 19BARA-BID-0XX-01-PID2 Discharge Pipe of Jetty Transfer Pump P-01B Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
8 8" AS CS 008 8"-AS-CS-008 19BARA-BID-0XX-01-PID2 Suction Pipe of Filling Shed Transfer Pump P-02A Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
9 8" AS CS 009 8"-AS-CS-009 19BARA-BID-0XX-01-PID2 Discharge Pipe of Filling Shed Transfer Pump P-02A Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
10 8" AS CS 010 8"-AS-CS-010 19BARA-BID-0XX-01-PID2 Suction Pipe of Filling Shed Transfer Pump P-02B Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
11 8" AS CS 011 8"-AS-CS-011 19BARA-BID-0XX-01-PID2 Discharge Pipe of Filling Shed Transfer Pump P-02B Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
12 8" AS CS 012 8"-AS-CS-012 19BARA-BID-0XX-01-PID2 Spare Pipe for Filling Shed Transfer Pump Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
13 8" AS CS 013 8"-AS-CS-013 19BARA-BID-0XX-01-PID2 By Pass Pipe at Transfer Pump Header Cair 60 10,0 110,0 12,0 130,0 75
m³/jam

14 8" AS CS 014 8"-AS-CS-014 19BARA-BID-0XX-01-PID2 Outlet Header of Jetty Transfer Pump Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
15 6" AS CS 015 6"-AS-CS-015 19BARA-BID-0XX-01-PID2 Outlet Header Pipe to Filling Shed Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
16 8" AS CS 016 8"-AS-CS-016 19BARA-BID-0XX-01-PID2 Outlet Header Pipe to Inlet Nozzle of Asphalt Tank Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
17 8" AS CS 017 8"-AS-CS-017 19BARA-BID-0XX-01-PID2 By Pass Pipe at Inlet Nozzle of Asphalt Tank Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
18 8" AS CS 018 8"-AS-CS-018 19BARA-BID-0XX-01-PID2 Drain Pipe at Asphalt Tank Cair 60 10,0 110,0 12,0 130,0 75
m³/jam
19 8" AS CS 019 8"-AS-CS-019 19BARA-BID-0XX-01-PID2 Outlet Nozzle of Asphalt Tank to Inlet Header of Transfer Cair 60 10,0 110,0 12,0 130,0 75
Pump m³/jam
20 2" IA CS 001 2"-IA-CS-001 19BARA-BID-0XX-01-PID2 Utility Air System Pipe Cair TBA TBA TBA TBA TBA 75

21 2" IA CS 002 2"-IA-CS-002 19BARA-BID-0XX-01-PID2 Utility Air System Pipe to Air Receiver Tank V-01A Cair TBA TBA TBA TBA TBA 75

22 2" IA CS 003 2"-IA-CS-003 19BARA-BID-0XX-01-PID2 Utility Air System Pipe to Suction of Transfer Pump Cair TBA TBA TBA TBA TBA 75

23 2" IA CS 004 2"-IA-CS-004 19BARA-BID-0XX-01-PID2 Utility Air System Pipe to Discharge of Transfer Pump Cair TBA TBA TBA TBA TBA 75

24 2" IA CS 005 2"-IA-CS-005 19BARA-BID-0XX-01-PID2 Utility Air System Pipe to Air Receiver Tank V-01B Cair TBA TBA TBA TBA TBA 75

25 4" HO CS 001 4"-HO-CS-001 19BARA-BID-0XX-01-PID2 Hot Oil Outlet Nozzle of Asphalt Tank to Hot Oil Package Cair TBA TBA TBA TBA TBA TBA

26 4" HO CS 002 4"-HO-CS-002 19BARA-BID-0XX-01-PID2 Hot Oil Package to Hot Oil Inlet Nozzle of Asphalt Tank Cair TBA TBA TBA TBA TBA TBA