Escolar Documentos
Profissional Documentos
Cultura Documentos
SPECIFICATION
For the Fulfillment of
Prepared in Behalf of
Dr. Peter Laurel
7th Floor Lyceum of the Philippines
109 LP Leviste St. Salcedo Village
Makati City
LPU University Town – Phase 01 is a School building having 5 storeys and is owned by Lyceum of the
Philippines. The project is situated in Brgy. Cabantian, Buhangin, Davao City has an area of
approximately 17.26 hectares. Its main entrance can be accessed through the Maharlika Highway, a
main thoroughfare, which also leads to the nearby airport.. Parties involved in the fulfillment of this
project are as follows:
Site mobilization starts on January 2017 and is scheduled to be finished on 28 February 2018
In general, the proposed description of the façade system/s to be used in this project shall be:
See Wall Types as reflected in Appendix A and the details as shown in the Façade Drawings of the
Tender Drawing Package.
The items listed below are deemed to be not included in the façade works described in this
specification:
This project is not considered to be designed, constructed and operated in accordance to LEED
requirements program. In case other sustainability and environmental considerations are required,
specification concerning to this requirement shall be obtained from a separate client endorsed
consultant specializing in this matter.
The façade contractor and its work shall comply with the contract documents for the main building
works, the approved drawings, and the main programme.
It is the responsibility of the façade contractor to provide the client and its representative a
comprehensive or detailed schedule as well as to ensure that all façade related activities be
coordinated with the works listed below:
• Main Structure Concrete Works;
• Main and Peripheral (not included in the scope) Steel works;
• Concrete Waterproofing;
• Sheet Metal Roofing and Roofdecking;
• Building Maintenance Unit;
• Fireproofing;
• Plumbing;
• Doors and Frames not included in the scope;
• Gypsum Plasterboard;
• Floor Tiling and Finishing;
• Landscaping;
• Exterior Lighting (if not included in scope);
• Building Security;
• Lightning Protection;
• Blockwork.
The works listed may not represent all trades needing proper coordination with the façade contractor.
In such case, the façade contractor shall be held liable for instigating the needed coordination. 5
In general, the façade contractor is responsible for the contract guaranties, management, insurances,
labor, equipment, materials, and services needed to fully execute the manufacture, assembly,
logistics, reproduction of shop drawings, courier services, and installation of all façade related works
as stipulated in the contract documents.
Specifically, the façade contractor’s work includes:
• Shop Drawings together with Engineering Calculations;
• Erection Drawings;
• Material Sample Submission and Related Tests;
• Extruded Aluminum Framing for the Curtainwall System;
• External Architectural Features as listed in Section 1.2 of this specification;
• Provision for and Coordination of Tie Back Anchors;
• Anchors, Brackets, and other Connecting Materials to the Main Structure;
• Miscellaneous Steel Necessary to Support the Façade;
• All necessary materials to ensure air & water tightness of the façade (e.g. sealants, backing
material, vents, weeps, gutters, end dams, etc…);
• Field Testing and all related Materials, Equipment, and Tools;
• Protection of Façade Related Materials from Assembly until it is handed over;
• Removal of Protection and Final Cleaning of Finished Works.
All works stated above must conform with the requirements of the contract, generally and in special
conditions, together with the approved drawings and other related contract documents.
It is the façade contractor’s responsibility to come up with working façade system and treat
Architectural Drawings only as guides. Furthermore, design drawings may differ through the different
stages of the project, depending on the requirements.
The façade contractor has a responsibility to submit all requirements on time, to have sufficient
manufacturing capability, and to provide the necessary machinery & skilled manpower for the project
to be completed on time and with the approved quality.
Any discrepancies or inconsistencies between the drawings and specifications must be brought up
during the tender stage.
Glass thickness and appearance of each glass type must be consistent throughout the project
including the spares or attic stock.
The façade contractor has a responsibility to thoroughly check site measurements including
plumbness and squareness prior to the acceptance of the structure- leading to the installation. In case
any field condition exists, which may inhibit the installation, the façade contractor shall notify other
contractor and the client for the most appropriate action. It is also their responsibility to provide,
design, and supervise the installation cast-in embeds. In case post-installed anchors are to be used, it
shall be provided, designed, and installed by the façade contractor.
1.6. Standards Compliant with Standards
6
All façade works described in this specification shall be compliant with the codes and standards as
outlined below.
ASCE 7-10 Minimum Design Loads for Buildings and Other Structures
The above listed codes may have more updated releases. In such cases, please refer to superseding
releases.
In case codes listed above have contents overlapping each other, the most stringent standard shall
govern unless otherwise stated by the client. 11
1.7. Submittals
The Façade Contractor shall be required to submit the items listed in this section. It is stressed that all
these submittals be presented unto the client and all necessary members of the project team within
the prescribed date by the client or Project Manager.
It is expected that all submissions must be clear, on time, presentable, and of highest quality. It is also
expected that the design intention shall have one initial submission and one resubmission.
1.7.1. Tender
Timeframe: within 2-4 weeks upon invitation
The following documents shall be submitted by the prospective façade contractor at no cost or
obligation to the tendering body. No considerations shall be given to incomplete and late
submissions. Softcopies of all files listed below are to be provided.
a. Preliminary Design Shop Drawings (with the anchorage system), printed on A3 sheets
and readable, representative of all façade systems or wall types.
b. Structural calculations, printed on A4 sheets and readable, in conjunction with the shop
drawings mentioned above. This includes the derivation of loads, frame analysis, glass
& sealant analysis, connection checks, anchoring check, thermal analysis, and
peripheral framing system analysis.
c. Façade Works Programme for the design, approval, pertinent submissions, local
government consent and approval, testing, material procurement, fabrication and
assembly, installation, cleaning, and handover of the building envelope.
d. Outline of Quality Plan, conforming to ISO 9001, from Manufacturing to Handover
e. Materials Schedule together with its respective suppliers
f. Confirmation on providing warranties as required by this specification or as requested
by the Client
g. Preliminary method statement, including the needed storage area and equipment to be
used, for the supply and installation of façade systems or wall types
h. Preliminary Manpower & Equipment loading for the design and installation of building
envelope
i. Organizational chart of prospective contractor and curriculum vitae of all key staff
involved in the project
j. List of current and completed jobs, concerning building envelopes, within the past 5
years of the prospective contractor
k. Statement coming from the prospective Façade Contractor that they accept the
specification and will fully comply to its content as well as any related regulatory
requirements coming from the Authority.
Timeframe: within 2 weeks upon completion of Mockup Testing or Visual Mockup (if no PMU)
After the Performance Mockup has been concluded and deemed to pass, the façade
contractor shall submit 5 sets of the following samples
a. Aluminum extrusion shapes with finish fastened to a sufficiently rigid board
b. Fasteners and connection materials labeled with alloy and finish fastened to a
sufficiently rigid board
c. Gaskets, shims, sealants, trims, flashing, air seals, foams, baffles, and other
miscellaneous items used in the PMU as part of the façade system. These are items,
labeled with their respective material name and/or brands, are to be fastened to a
sufficiently rigid board
The Façade Contractor must provide a fully comprehensive, dimensioned and detailed shop
drawings indicating all set-out and adjacent work done by others. It must also include other
details not included in the manufacturer’s product data of all proprietary products.
Review of shop drawings shall be 10 working days upon receipt of each submission
and/or resubmission. Approval sought shall be of the member sizes, finishing and structural
adequacy only. Fabrication related approval shall not be rendered.
All resubmissions must indicate a revision cloud showing all alterations or modifications
requested by the approving party. Every correction or comment must be addressed and be
kept tallied using a separate comment reply sheet.
Any manufacturing or assembly works shall not be permitted until approval is given to all
relevant shop drawings and/or structural computation.
Shop drawings package, written in English language, must include the items listed below.
a. Drawing index sheet showing all drawing numbers and description of content.
b. General notes showing:
1) relevant codes and standards;
2) loading assumptions and other performance related criteria such as acoustics and
thermal properties;
3) tempering and properties of glass;
4) alloy and properties of metal;
5) material properties and specifications of other materials such as silicone, gasket,
foam baffles, backing material, flashing, etc…;
6) hardware schedule;
7) mechanical connection schedule including anchor bolts.
c. Elevations and plans for the entire building showing:
1) Scope of works for the façade;
2) Dimensions as to be reviewed and approved by the Project Architect
3) Critical dimensions of the façade and its components;
4) Zoning of the building;
5) Fire Access panel location, equipment opening, and other emergency exit
d. Setting-out of façade works, indicated on plans, sections and elevations, including the
following:
1) Reference points
2) Edge conditions
3) Tolerance (if any)
e. Tables showing scaled and dimensioned sections of extrusions and structural members
indicating their respective alloy, paint area, finish, and other pertinent specification. 14
The Façade Contractor is required to substantiate the shop and/or installation drawings by
providing structural computations done in accordance with accepted engineering practice and
shall conform with the guides and standards listed in section 1.6 of this specification.
All pages of the calculation must be numbered, dated, and referenced. Any revision done to
address corrections must be labeled with a revision cloud. In case additional sheets are
needed on the revision, the original page numbers shall not be altered. The additional sheet
shall be inserted in between original page numbers and shall be page numbered as “xx-1, xx-
2, etc…” (e.g. additional page is needed between pages 3 & 4, it will be inserted in between
these pages and the inserted pages shall be numbered 3-1, 3-2, etc…) 15
All sections of the calculation must refer to drawing/sheet number showing the appropriate
dimensions and details. A free body diagram showing the applied loads, reactions, and
eccentricities must be incorporated into each analysis.
Ratio of the strength and serviceability check (or Unity Check) must always be less than or
equal to unity (1).
For Proof loading related analysis (150% of the design load), no connection must fail and yield
stresses shall not be exceeded. Deflection under this criterion shall not be permanent.
All software generated structural calculation must have a summation of reaction loads equal to
the applied loads.
The first page of each section shall be used for a tabularized summary for the strength and
service check of each component under that section. Succeeding pages shall show the
detailed computation in which the summary was derived.
The following items shall be analyzed and submitted for review.
a. Load Derivation
1) Wind (if wind tunnel test result not provided or if wind load is not provided)
2) Dead loads based on Material Densities provided by codes or suppliers
3) Seismic
4) Blast (if needed)
5) Live Loads (for balusters, railings, doors, windows, coping) and Roof Live Load
(for Skylights, roof cladding), if nor provided
b. Glass and Glazing
1) Stress check for each type considering typical panes and critically large panes
2) Deflection check for each type considering typical panes and critically large
panes
3) Finite Element Analysis for Point Fixed Glass units or any equivalent analysis
considering stress concentration at holes and edges
4) Sealant bite for primary and secondary (IGU’s) seals. No loads parallel to the
plane of glass shall be permitted to be carried by the sealant
c. Aluminum Sheet Cladding
1) Stress check for each type considering typical panels and critically large panels
2) Deflection check for each type considering typical panels and critically large
panels
3) Stress & Deflection check for panel stiffeners if required
4) Strength check of stiffener to panel connection and stiffener to frame member
connections
5) Stress and Deflection check for panel frames and sub-frames
d. Stone Cladding (If applicable)
1) Strength and service check for each type considering typical panels and critically
large panels
2) Strength and deflection check for panel stiffeners if required
3) Strength check for Stone anchors, bracketing system, and clips
e. Typical Wall Mullions & Transoms
1) Strength and deflection check at midspan for typical and critically long frames
2) Strength check at support considering reduced section
3) Strength and serviceability check of extrusion legs at splices considering
transferred shear 16
4) Strength and deflection check for dummy framing systems (if needed)
f. Corner Mullions & Transoms
1) Checks mentioned for the typical wall mullions and transoms but considering
corner condition loadings such as:
a) Both side loading (combined stresses)
b) One side only loaded with positive pressure (weak axis bending)
c) One side only loaded with negative pressure (weak axis bending)
2) Deflection of mullion parallel to the load when loaded at one side only (weak axis
bending)
g. Baluster and Railings
1) Stress due to prescribed load combination (dead, wind, live)
2) Deflection check due to loads acting parallel and/or perpendicular to the wall
3) Stress check for Infill to frame connection
4) Stress check for infill at embedment
5) Connection check at embedment/anchoring to concrete
h. Connections
1) All mechanical connections between framing interface (mullion to transom,
mullion to railing, metal splice connection) shall be checked for strength
2) Hardware or fittings connection shall be checked for strength of as specified by
the manufacturer
i. Operable Sash
1) Strength and deflection check for the window frame
2) Strength check for the components and devices holding the window against
negative pressure
j. Anchors
1) Tensile and Shear Strength check for anchors embedded on concrete
considering typical and critically large panels
2) Bending Strength check for anchors having non-rigid spacers
k. BMU Pins/Tie Backs
1) Strength and deflection check for Tie Back steel assembly
2) Strength check for tie back to steel assembly to framing system connection
l. Thermal Stress
1) Strength and deflection check for all both-ends restrained framing system due to
thermal loads or movement
2) Strength check for the connection of both-ends restrained framing system
The Façade Contractor shall submit the following site drawings for reference and traceability
requirement of the QA/QC process:
a. Embed layout schedule complete with proper tagging;
b. Panel and cladding tag elevation/schedule complete with unique numbering system and
manufacturing date
c. Sealant schedule reflected on the panel tag elevation showing sealant batch and
manufacture date
1.7.9. Project Manual (Installation, Operation, and Maintenance)
Timeframe: 4 Weeks upon award of project 17
The Façade Contractor is required to submit a Project Manual containing the manuals
pertaining to the installation, operation, and maintenance of the façade system. Additionally, it
must include the Factory Inspection and Test Plan, Project Quality Plan, and Project Health,
Safety, and Environment Plan.
The Factory Inspection and Test Plan shall include the contractor’s inspection procedure for:
a. Extruded Aluminum Profiles
b. Each finishes (e.g. Powder paint, PVDF, Anodizing, etc…) on extrusion and sheet
c. Cladding panels (e.g. Solid aluminum, ACP, SS, Galvanized, etc…)
d. Float Glass
e. Heat Treated Glass
f. Coated Glass
g. Laminated Glass
h. Insulating Glass Unit
i. Structural Glazing
j. Gaskets & Glazing Materials
k. Connection and Fasteners
l. Panel Assembly & Packing
The Façade Contractor shall be required to provide As-built Drawings, Photographs, and any
other records as work progresses. This can be monthly or as required by the Client or its
representative.
As-built drawings must show updated construction related modifications to the original
drawings, indexed and bound. These drawings are necessary for Quality Assurance and as
required by Local Municipality.
1.8. Qualifications
It is imperative that all façade works are performed by a sole façade contractor with its chosen and
client approved sub-contractors and suppliers. This Façade contractor shall have a record of doing
business in the design, manufacturing, assembly, and installation of building envelope and related
works.
1.9.1. General
The design criteria discussed in this chapter is to ensure that the building façade system is
weartherproof, structurally adequate, free to accommodate movements or displacements, and
retain its aesthetics for the service life of the building envelope without failure or degradation of
its components.
The system shall be designed such that air infiltration is minimized. Air leakage for both the
fixed wall and operable windows must conform to the values specified by ASTM E283. These
values are to be confirmed through actual testing or through available test results on the same
façade system.
The façade system must be 100% watertight and all draining shall occur outside. In no
manner, shall water be allowed to infiltrate the building interior. Unitized & Semi-unitized
system shall be designed to be pressure equalized to allow proper drainage.
Water which enters the system, including condensation or leakage, must not be trapped and
shall be drained out to the exterior of the façade system to inhibit fungal or algal propagation.
The system shall be designed to conform to ASTM E331/ASTM E547/ASTM E1105 or any
equivalent codes (AAMA) and shall be verified through testing.
b. Dead load
Self weight shall be based on material densities reflected in the NSCP unless otherwise
stated and certified by the supplier of the component. Allow 10% increase on weight
due to connection and peripherals.
c. Seismic load
Seismic loads are to be derived through the latest iteration of NSCP unless otherwise 20
stated by the consultant or its representative. Note that variables based on the
geography of the project such as seismic zone, soil profile type, seismic source type,
etc.… must be coordinated and verified with the project Structural Engineer.
d. Special loads
1) Live load of 0.73 kN/m OR 0.89kN perpendicular to the plane of infill (any
direction) for parapets and balusters. These loads are located at the top or at
least 1.1 meter from the point of support.
2) Live load of 0.22kN applied in an area of 300mm x 300mm for intermediate rails
but not with handrails
3) A downward acting live load of 1.5kN applied to 100mm x 100mm area on all
horizontal surfaces such as coping, sills, and canopies.
4) Roof live loads for skylights and canopies shall be based on the latest NSCP
5) Parapet supports and/or façade components that may support Building
Maintenance Unit (BMU) at its resting position or during operation must be able to
support its full weight and the load it carries
6) Façade System with integrated BMU Tie Back shall have its framing and
connection designed to accommodate a point load of 2.7kN at all directions but
not acting simultaneously.
e. Load Combinations
All loads considered must be analyzed based on combinations (LRFD or ASD)
stipulated by the NSCP. Note that an increase in allowable stress is permitted only
to certain load combinations.
f. Deflection Limits
1) Framing members 21
Load Per pendicular t o t he Wall
Fr aming Member Limit Pr ovision f or L
General L/ 175 Clear Span up t o 4.1m
General L/ 175 + 6.35mm Clear Span from 4.101m t o 12m
General min(L/ 175, 19mm) Clear Span of Glass along t he Frame
Clear Span and used t o support Building
St eel L/ 300
Cladding Component s and Frames
Clear Span and used t o support Plast er
Skylight L/ 360
Ceiling
Clear Span and NOT support ing Plast er
Skylight L/ 240
Ceiling
Skylight L/ 180 Clear Span NOT support ing any ceiling
Clear Span wit h at t ached brit t le finish or
General L/ 240
dry wall
General L/ 120 Clear Span wit h at t ached flexible finish
Load Par allel t o t he Wall
Fr aming Member Limit Pr ovision f or L
General, due t o Due t o Dead Load, Span Support ing Fixed
3mm
weight Glass
General, due t o Due t o Dead Load, Span Support ing and
1.5mm
weight Opening (Door or Window)
General, due t o
10mm Due t o Wind Load
wind
Not e: for cant ilevers, L is t aken as t wice t he clear span
2) Cladding Components
Component Displacement Remar ks
Connect ion Point of Reference is from frame
1.5 mm
frame t o anchor member t o building st ruct ure
Clamped Connect ion 3 mm Up t o 150% of Design Load
3) Glass & Metal Panel
22
Material Criteria Limit
minimum
Glass Pane Edge of Glass
(L/175, 19mm)
Glass Pane Center of Glass a/60
minimum
Metal Panel Center of Panel
(L/120, 19mm)
Note: L=Clear Span
a=Smaller Glass Dimension
g. Anchoring to Concrete
Design of concrete anchors shall also take into consideration fatigue. Due to this, an
additional overload factor of 1.33 (multiplicative) shall be considered. This factor shall
be applied to all transient as well as permanent loads. In case a factor at least 1.33 is
already considered in the design philosophy (e.g. PCI Handbook Chapter 6), there is no
need to take into consideration another fatigue overload factor.
h. Lifting
Bracket assemblies and façade components directly connected to the lifting mechanism
shall be designed to have an additional dead load safety factor of 2 (multiplicative) on
top of the dead load factor specified by codes (e.g. 1.4DL or 1.2DL or 0.9DL based on
ASCE 7 LRFD Load Combinations). Indirectly connected façade components shall have
an additional load factor of 1.5.
The façade system shall be able to accommodate movements due to member deflection,
thermal displacement, building construction tolerances, fabrication tolerances, and the like
without causing disengagement, failure, permanent distortion, or any kind of damage to any
façade component
Thermal range by which the system must be designed to be as follows:
a. Exterior air temperature range: 24⁰C to 33⁰C
b. Metal surface temperature: Light Colors – 65⁰C
Dark Colors – 82⁰C
c. Interior temperature range: 10⁰C To 38⁰C
Construction tolerances by which the façade bracketing system must accommodate are as
follows:
a. Up/Down: +13mm/-13mm
b. In/out: +25mm / -25mm
c. Left/right: +25mm / -25mm
Inter-story differential movement of +20 mm/- 20 mm shall be accommodated by the system
based on the following:
Application of structural silicone is only permitted for surfaces with the following finishes: (a)
Anodized; (b) Alodine Conversion Coating; (c) Polyester Powder Coating (PPC); and (d)
Polyvinylidene fluoride 2 (PVF2). In no case, shall structural glazing be in contact or applied to
mill finished aluminum surfaces.
Application of 2-part silicone shall only be permitted under controlled environment or inside the
factory unless otherwise permitted by the client or its representative. In no case shall 3 side
adhesion of silicone be applied.
The façade system shall be designed, fabricated, and installed such that floors shall be
isolated on the event of smoke or fire. Performance of the façade components when
exposed to fire or high temperature shall be designed in accordance with the following
procedure
a. Non-combustibility: ASTM E136
b. Spread of Flame: ASTM E84
c. Fire Resistive Rating: ASTM E119
d. Mock-up Test: ASTM E2307
1.9.9. Other Environmental Considerations
a. Acoustics
The façade system shall be designed to be meet the performance requirements of
Outdoor-Indoor Transmission Class: Minimum [26] [30] [34] based on test according
to ASTM E90 and ratings determined by ASTM E1332 Unless otherwise stated by
the client or its representative.
b. Noise Minimization
The façade system including its components must be designed, fabricated, and
installed to cause no noise due to thermal expansion, pressure gradient, dynamic
loading, and BMU/cleaning operations. Façade system generated noise examples
are whistling due to wind, creaking, drumming, and rattling.
c. Lightning/Grounding
Electical continuity and conductivity must be provided within the window wall
systems. This includes provision of earthing straps connected to building conductors
by others.
The client and/or its representative has the right to visit all the subcontractors, suppliers, and testing
facilities engaged by the Façade Contractor any time during the progress of the façade works.
The Façade Contractor shall record and maintain all the certified inspection for quality of finishes and
shall be available upon request of the client or its representative.
The Façade contractor shall submit and implement a detailed and project specific Quality Plan
as described in section 1.7.9 paragraph 5. All proprietary products shall come from reputable
manufacturers and its quality assurance documentation (including ISO 90001 certification)
must be submitted. 25
The Façade Contractor shall appoint a full time coordinator available for design and site
implementation inquiries. Furthermore, the coordinator has a responsibility to:
a. Coordinate with other trades or their subcontractors on the requirements pertaining to
the façade works;
b. Ensure the quality and safety of the building envelope supporting systems;
c. Ensure maintenance/equipment/temporary access is provided at all façade areas
specified by the client or its representative; and
d. Report any nonconformance or works by other trades which may impede the on time
progress of the façade works.
Structural components of the façade works as well as its supporting framing or systems must
be sealed and certified by locally registered Structural Engineer appointed by the Façade
Contractor.
The façade contractor shall retrieve a certification from the glass supplier containing the
following:
a. Shop drawing review and acceptance;
b. Structural calculation thru accepted standards and codes specified in section 1.6;
c. Heat Soaking Test (if applicable); and
d. Thermal stress analysis and acceptance.
The façade contractor shall retrieve a certification from the sealant supplier containing
the following:
a. Shop drawing and structural calculation review and acceptance;
b. Independent laboratory testing for the structural sealants;
c. Compatibility and adhesion test reports;
d. Non-staining test reports; and
e. Water immersion test reports.
In general, a notice of 48 hours must be given to the consultant prior to the following activities:
a. Commencement of the Visual or Performance Mockup (unless overseas, in which case,
minimum of 2 weeks);
b. Start of any required test (e.g. sealant adhesion, gutter test, etc…), may it be on or off
the construction site;
c. Factory inspection of raw or processed materials;
d. Panel assembly inspection at factory delivery;
e. Façade works framing and/or subframing inspection done by the façade contractor;
f. Anchor bolt inspection and testing;
g. Miscellaneous façade components (e.g. BMU components, grounding, lighting, etc…)
inspection; 26
h. Preparation and commencement of site glazing and reglazing;
i. Other inspection or tests required by the client or its representative on the façade works.
Factory related inspections must be done after a minimum number of panels or components to
be inspected has been agreed upon by the project team.
The Façade Contractor shall propose holding points in which subsequent works shall be
halted if the current work (hold point) is not satisfied through inspection and/or testing.
Additionally, a benchmark for each wall type having an area of about 25 m2 to 50 m2 Shall be
provided by the contractor. This area shall be inspected and accepted by the Project Architect,
Consultant, and the Client before any further work shall proceed. The benchmark, as the
name implies, shall be a basis on the quality and consistency of future works regarding the
same wall type.
The Façade Contractor shall be required to conform to requirements in this specification as well as
other applicable building codes. In case of overlap, the more conservative or stringent literature shall
govern. Furthermore, the contractor must secure all applicable permits or documents from the local
Municipality and must allow them to review and approve the façade works without causing delay to the
project.
The Façade Contractor, through a certification, must ensure that all spares must be available off the
shelf or with a lead time not exceeding 4 weeks from date of order. The said certification must also
include all manufacturer’s information such as its name, address, and contact information. Spares
shall be new, well protected in an approved manner, and securely stored at a dedicated area specified
by the client or its representative. The following table shows the minimum required quantity of spares
for each type of material.
During the course of rectification or replacement works, the Façade Contractor shall provide
temporary enclosure for the area affected which will shield it from external elements and will render
the building safe during this period.
1.13. Testing
27
1.13.1. Performance Mock-up (PMU) (Not Applicable)
The Façade Contractor shall be required to conduct on site test as listed in this section. All
equipment and materials such as scaffolds, gondola, hose, water supply, etc… as well as
manpower needed to conduct these tests shall be in the account of the façade contractor.
Furthermore, any cost related to corrective works or retests due to failure shall also be on the
account of the façade contractor.
Field tests to be conducted and its description are shown below. A written methodology shall
be submitted by the façade contractor and approved by the façade consultant prior to any
testing. Testing done without the consent of the Façade Consultant shall be rendered void and
invalid.
All remedial works shall only proceed if submitted and given approval by the client or its
representative.
Every material test herein after shall be firstly done and satisfied before pursuing mass
production of the façade wall and its related components.
A written methodology shall be submitted by the façade contractor and approved by the
façade consultant prior to any testing. Testing done without the consent of the Façade
Consultant shall be rendered void and invalid.
Material testing to be fulfilled by the Façade Contractor are as follows:
30
Act ivit y Frequency Code Reference
Fixing Bracket s Combined Shear &
5 per t ype BS 5080
Tension Test
Object ive
To verify st uct ural adequacy of anchoring t o concret e bracket s
Met hodology
•Fix bracket s & anchor bolt s t o prefabricat ed concret e blocks which
represent s t he base st ruct ure. Concret e st rengt h and fixing dimensions
such as edge dist ance and embedment dept h shall be t he same as in
act ual condit ion OR
•Fix bracket s along t he main st ruct ure but t hese bracket s are only
dedicat ed for t est ing and should not be used t o support act ual window
wall syst em
•Proceed wit h Shear & Tensile Test in accordance wit h t he code reference.
Modificat ion of t he code is allowed t o accommodat e combined shear and
t ension t est provided t hat met hodology is submit t ed and approved
•Proof load t est (150% of t he design load) is required and shall not exhibit
any failure
•Dest ruct ive t est is opt ional and only allowed if t est is not done on t he
main st ruct ure
Crit eria for Failure
•St eel or concret e failure including observable yielding of st eel
•Slippage having a failure great er t han displacement shown in 1.9.4.f.2
All façade components delivered on site shall be identifiable by clear markings and their appropriate
locations on the building shall be reflected on a submitted and approved site logistics plan. The site
logistics plan shall be coordinated with and also approved by the Main Contractor. In case of very
small items needing storage or if in case items were not included in the approved site logistics plan,
the Main Contractor shall direct the Façade Contractor to the area and manner of storage.
Façade components shall be packaged in such a manner that it will be protected from damage during
shipping, hoisting, and storage. Glass shall be further protected from any possibility of water intrusion
or condensation during the shipping, storage, and handling.
1.15. Warranty
Upon handover of the project stated under the Contract Agreement issued by the Project Manager,
the deflects liability period shall take effect and shall last until the Façade Contractor is given a
Certificate of Practical Completion. A warranty period of 15 years shall then take effect for the building
envelope system. Under this period, the Façade Contractor shall agree to repair or replace defective
materials and workmanship without additional costs incurred to the client.
Any damage incurred due to the defective materials or workmanship of the façade works shall be the
responsibility of the Façade Contractor.
Specific warranties are as follows:
34
Warranty
Item Subitem Warranties against:
Period
Water penetration and improper drainage
Façade Air infiltration exceeding specified limits
General 15 years
System Structural failure with limits bound by this specification
Breakage and defects due to improper workmanship
Breakage and corrosion due to defects in the material
Cracking due to ozone & ultra-violet attack
Growth of ogranic elements (mildew, mould, etc…)
Excessive discoloration¹ & non-uniformity² due to sunlight
and weathering
Stainless
Steel
Galvanized
Metal and 15 years Rusting
Painted
Steel
Aluminum
¹Excessive fading - change in appearance perceivable and objectionable as defined by the client when viewed
²Excessive nonuniformity - fading to the extent that adjacent parts have a color difference greater than the original color
range set by the client or its representative
1.16. Others
35
It is the responsibility of the Façade Contractor to adjust the Façade Works Programme as precaution
to the danger put by the installation during heavy rains.
2. PRODUCTS
2.1. General
This section shall cover the material requirements and its certification coming from the suppliers
and to be submitted to the Façade Consultant for review and approval. Product manufacturers for
extruders, architectural aluminum panels, sheet metals, and bar stocks shall have a minimum
experience of 5 years prior to their engagement to this Project.
2.2. Certification
2.2.1. Glass
The façade fabricator shall obtain the following certification/s from the Glass
Manufacturer:
• Source of Glass Material;
• Probability of breakage less than 8/1000;
• Thermal Analyses for each type of exterior glass;
• Recommendation for glass replacement procedure; and
• Review of the façade fabricator’s glass strength and deflection analyses due to
applied wind load.
2.2.2. Sealant
The façade fabricator shall obtain the following test reports and certificates (short term
and long term effects) of the proposed sealant type from the Sealant Manufacturer:
• Chemical Composition;
• Adhesion, cohesion, and Bond Strength;
• Elongation, Hardness, Compression set, Low temperature flexibility and Modulus
of Elasticity;
• Water Absorption and Viscosity;
• Compatibility to proposed material substrates;
• Stain resistance, color stability and effects of exposure to ozone & UV light
• Adhesion test thru ASTM C794 to actual material substrates done on site
2.2.3. Structural Sealant
The façade fabricator must ensure to obtain a certificate coming from the Structural
Sealant Manufacturer that the stress of the sealant does not exceed 140 kPa when
subjected to the design wind load.
2.2.4. Aluminum
The façade fabricator must ensure to obtain a certificate coming from the Aluminum
Extruder/Manufacturer that each batch of aluminum supplied is of the right temper/alloy
and the their welders are duly certified.
2.2.5. Steelwork
The façade fabricator must obtain test certicates of all steelworks coming from its
manufacturer. The test certificates must comply with ASTM A370 or BS EN 10002-1.
2.2.6. Stainless Steel
The façade fabricator must ensure to obtain a certificate coming from the Stainless Steel
Manufacturer that each batch of stainless steel supplied is of the right temper/alloy and
the their welders are duly certified.
2.3. Materials
36
2.3.1. Glass
a. General
Thickness of the glass shall be as per schedule shown in below:
2.3.2. Aluminum
a. Extrusions
Aluminum extrusions shall conform to ASTM B221. Acceptable grades/alloys for
extrusions are 6061 or 6063 with temper T5 or T6. Minimum thicknesses are as
follows:
• Principal extrusions – 3 mm;
• Non-structural times/caps – 1.5mm.
Any extruder/manufacturer having ISO 9001 are acceptable and can be considered.
b. Sheets & Plates
Aluminum sheets and plates shall conform to ASTM B209. Acceptable grades/alloy are
3003 or 5005 with temper H14 or H18. Minimum thicknesses are as follows:
• Cold formed Shapes – 3.175mm;
• Exterior panels – 3mm;
• Panels for canopy soffits and fascias – 5mm;
• Copings – 3mm.
Flatness deviations shall be only 1.5mm per 1.5 m of length/width.
Any extruder/manufacturer having ISO 9001 are acceptable and can be considered.
c. Aluminum Composite Materials
Aluminum Composite Panels must have a flatness of 0.5% at 25mm apart and at
temperature of 30°C. Acceptable brands are Alpolic or Alucobond or equivalent.
Welding on composite panels must conform to AWS D1.2.
2.3.3. Steel
a. Conformance to Standards
Steel works must conform to the following codes:
• Hot Rolled Shapes, Plates, & Bars – ASTM A992, ASTM A36 or ASTM A501
• Sheet & Strip, Cold Rolled – ASTM A500
• Sheet & Strip, Hot Rolled – ASTM A1011
• Sheet, Hot Dip Galvanized – ASTM A653
• Structural Tubing, Hot Formed, Welded – ASTM A618
• Aluminized Steel Sheet – ASTM A463 with coating T1-40
• Galvanized Steel Sheet – ASTM A792 with coating AZ50
38
• Hot Dip Galvanizing Zinc Coatings – ASTM A123
• Forged Steel – ASTM A668
• Cast Iron & Cast Steel – ASTM A48 for Grey Cast Iron, ASTM A47 for Malleable
Cast Iron, ASTM A536 for Spheroidal Graphie Cast Iron, BS EN 10293 for Carbon
Manganese
b. Protection
Minimum requirement for steel works for protection from corrosion and degradation
shall be Hot Dip Galvanizing (HDG). HDG shall conform to the following provisions:
• Minimum dry film of 70 microns for concealed steelworks;
• Protection by Dulux, Taubmans, Coultards for exposed steelwork;
• 3 or 4 part inorganic silicate system;
• Blast cleaned to Sa 2.5 in accordance to ISO 8501-1 surface preparation;
• 75 micron min dry film thickness of Primer Ethyl Zinc Silicate;
• 75 micron min dry fil thickness of two pack epoxy Micaceous Iron;
• Oxide (MIO) as barrier coat;
• Finish coat (specified by architect).
c. Fireproofing
Shall fireproofing be required for steelworks, Intumescent paint shall be considered as
minimum requirement.
2.3.4. Welding
a. Conformance to Standards
Welding works must conform to AWS D1.1 for Steel and AWS D1.6 for Stainless Steel.
Surface preparation must conform to BS EN 1011-1.
b. Welder Qualification
Welders shall have qualification as required by BS EN 287-1 and/or BS 4872: Pt 1.
c. Provisions for Quality Control
• Fusion faces shall be properly prepared;
• Preheating of temperature and post heated treatment if required;
• Electrodes shall be approved and as per shop drawings;
• Number and sequence of runs to build up the weld bead must be as prescribed;
• Welding procedure must be as per DIN EN ISO 15614-1.
d. Testing
Results for the following tests are required for welding works:
• Transverse tensile test thru BS EN 10002-1;
• Transverse bend test thru BS EN ISO 7438;
• Side bend test;
• Macro Examinations;
• Fracture test (for Fillet Welds).
2.3.6. Fasteners
a. Code Compliance
All fasteners shall conform to AAMA MCWM-1 for application on dissimilar metals and
AAMA TIR-A9 for design and selection.
b. Grade/Alloy
• Steel Bolts - Galvanised High Strength Class 8.8 to ASTM A325
• Screws - Stainless Steel A4 Grade (exposed to weather), A2 (not exposed to
weather)
c. Size
• Rivets – 2.5 mm
• Screws - #10 (4.8 mm) to #14 (6.3mm)
• Bolts & Nuts – 8 mm to 16 mm
Screws which are visible from the exterior shall be countersunk. Nuts and washers
shall have the appropriate grade and size based on referenced standards.
Any manufacturers are acceptable provided that fasteners are marked with their Grade
and/or certified to have the correct strengths, chemical composition, and finish.
2.3.7. Connectors
a. Friction Reducing Pads
Friction reducing pads shall have a minimum thickness of 3 mm. Pads shall:
• Sufficiently reduce friction;
• Be resistant to wear;
• Positively retained in position;
• Not to be subjected to heat damage or excessive pressure.
b. Shim Stacks Transferring Shear Force
Polypropylene Shim stacks shall have a maximum height equivalent to 4 shims high or
twice the diameter of the fastener. If there is a need to provide shim stacks higher than
the mentioned limit, provide steel plates (welded together if multiple stacks) having a
hole clearance of less than fastener diameter plus 0.8 mm.
2.3.8. Anchorage
a. General
All anchorage must be corrosion resistant and its holding power shall have a minimum
of 5 times the design load.
b. Type & Manufacturer for Cast-in Plates
40
Cast-in plates shall have a strength of Grade 43 with welded studs or mild steel
reinforcements. Acceptable manufacturers are Halfen, Jordahl, Fischer and HILTI. All
cast-ins must be galvanized for protection.
In case cast-in plates with stud bolts are used, acceptable manufacturers for stud bolts
are Nelson or SINOARS. Fusion welding shall be in accordance to AWS D1.5 and all
testing requirements shall be satisfied.
c. Type & Manufacturer for Anchor-Bolts
Mechanical and Chemical Anchor bolts shall be as per computed design requirement.
Acceptable manufacturers are HILTI, Fischer, and RAWLPLUG. Test result
requirements shall be as per section 1.13.3 of this specification.
d. Provisions for Quality Control
• No installation in post tensioned concrete structures, void sections of precast
concrete panels, and other non-conventional concrete structure;
• Explosive shot fired devices shall not be permitted;
• Maximum deviation from correct position shall be +/- 12mm;
• Minimum edge distance (clear) shall be as specified by the manufacturer.
e. Performance Requirement/s during Testing
Anchor bolts shall be tested thru ASTM E488 and shall meet the following
requirements:
• No permanent deformation at 1.5 times the design load (proof load);
• No failure of the anchor at 2 times the design load;
• No failure of the structural concrete at 3 times the design load.
f. Cementitious Non-Shrink Grout
Cementitious Non-Shrink Grout shall conform to ASTM C1107 and shall have a
minimum compressive strength of 40 MPa to properly support the base plate.
2.3.9. Finish
a. Aluminum – PVDF
All aluminum surface exposed to outdoor view shall have Oven-cured 3 coat w/ 2 bake
finish. Resin shall be Kynar 500 or Hylar 5000 70% fluoropolymer resin. Thickness of
the coating shall be as follows:
• Primer - 5 to 10 microns;
• Topcoat - 25 to 30 microns;
• Clear - 10 to 20 microns.
Dry film thickness shall conform to ASTM D1400 (80% of measurements on primary
exposed shall meet 30 microns) while paint finish shall conform to AAMA 2605.
Provisions or requirement for quality control shall be:
• Color difference not exceeding 5E NBS units as per ASTM D2244;
• Chalking not exceeding No. 8 rating as per ASTM D4214;
• No visible flow lines, streaks, blisters, or other surface imperfections in the dry film
state when observed 3 m away.
b. Aluminum - Powder Coating
Alternative for PVDF finish shall be Powder Coating (Subject for approval from the
Architect). Acceptable manufacturer shall be Interpon Ultriva D2015. Application shall
be Super durable polyurethane or polyester coating, factory applied by electrostatic
spray and oven cured with greater than or equal to 40 micrometers dry film thickness
and 65 to 100 microns super durable polyester grade.
Conformance to referenced codes are as follows:
• Pretreatment - ASTM B449 under chromate class 1;
• Measurement of thickness - ASTM B244;
• Paint Finish – AAMA 2605
41
The following performance criteria must be met for the powder coating to be deemed
acceptable:
• Thermosetting and superdurable powders;
• Lead, Cadmium & TGIC free;
• Initially tested for 3000 hrs QUV A test and with at least 80%;
• gloss retention and color change not exceeding 5 delta units.
c. Steel
Finish and protection of steel shall 2.3.3-b. Painted finish shall be in accordance to the
Architect’s requirement.
d. Touch-up Paint
Field touch-up painting shall generally be Air Dried Coating in conformance with AAMA
2604 for internal application and AAMA 2605 for external application.
2.3.13. Tapes
Tapes used for glazing shall be compatible with all proposed sealants, non-gassing and
non-staining. It shall comply with the following quality control provisions:
• Tapes shall be aligned with glass edge with only +/- 1 mm deviation from its
straightness;
• Tapes shall not be a permanent holding component for the window wall;
• Tapes shall not act as air seal or rain screen for the window wall.
2.3.21. Hardwares
a. General
Hardwares shall conform to design & testing requirements stipulated in AAMA SFM-1-
87. Material to be used shall be Stainless Steel AISI Grade 304 or 316 with the latter
strictly for sliding doors and automatic doors.
b. Performance Requirements
Hardwares shall be Capable of withstanding barrier load of 0.75 kN/m at 1.1 m above
FFL both in opened and closed position.
c. Door Hinge
Door hinges shall be concealed spring comparable to the products of the following
manufacturers:
• Jackson Door Control;
• DORMA;
• Hager Companies;
• McKinney Products Company, an ASSA ABLOY Group Company;
• Stanley Commercial Hardware, a division of Stanely Security Solutions
d. Door Locks
Locking mechanism, Bored and Mortise Locks, shall be comparable to the products of
the following manufacturers:
• Hager Companies;
• Schlage Commercial Harware;
• Yale Security Inc.
3.3. Installation
Materials and components used in the façade system shall be in accordance to the approved shop
drawings. Any change or substitution shall be submitted for approval.
All window panels, materials, and components of the façade system must be new and in pristine
condition. Damaged materials must never be used.
The Façade Contractor shall postpone complete enclosure of the façade system.
Workmen, installers, and specialty craftsmen shall be properly trained, well experienced and briefed
before foregoing any works. The client and its representatives has the right to check the credentials of
the people engaged in the façade works. If at any time, a personnel shows incompetence regarding
his respective job, the client or its representative has right to dismiss the personnel off the job site and
request a replacement without incurring additional cost to the client and without causing delay to the
project.
Shall there be a need for an open access within the area of the façade, the Façade Contractor shall
postpone installation at that area until directed by the Main Contractor. Alternate detailing at this area
may also be provided such that later installation may be accommodated.
3.3.1. Window Wall, Glazing or Stick Type System
49
For a more consistent quality of façade works, factory assembled systems are preferred
over site glazing. Hence, site glazing shall only be permitted if it is established that off-site
glazing is impossible. Approval for on-site Structural Glazing shall only be given if the
Façade Contractor submitted a Glazing Method Statement complete with activities such
as deglazing, cleaning, priming, sealant application, provision of temporary support, and
testing. The Glazing Method Statement may be provided as a section of the Project
Manual stated in section 1.7.9.
Installation of glass must ensure watertightness, airtightness, and structural adequacy
against loads and movements without causing failure or deterioration to any glazing
component.
The façade contractor shall check the opening for its squareness, plumbness, and
adherence to accepted tolerances. If found non-compliant, glazing shall only pursue upon
corrections.
a. Glazing Logbook
The glazing team of the Façade Contractor must document all of their works as written
in the glazing logbook. It must have the following requirements as a minimum:
1) At the initial pages, the details and experience of each glazing team member
including their certification from the sealant supplier;
2) Date and names of glazing personnel working on the said date;
3) Tag/identity/sequence number of glazed panel as well as the intended area for
glazing and a graphical representation of the working area with respect to the
whole building;
4) Sealant details such as manufacturer, type, color, and batch number;
5) Temperature inside and outside the glazing area (or factory);
6) Manufacturers and types of accessories used (e.g. tape, backing rod, setting
block, etc…);
7) Test results based on QC requirements (adhesion test, deglazing test); and
8) Signature and certification of supervisor.
The Façade Contractor must provide separate glazing logbook for structural glazing
having the same details listed above.
b. Setting Blocks
Weight of glass units must be supported by setting blocks, fully engaged to the glass
before application of structural sealant. In no case shall the structural silicone be
allowed to support the weight of the glass panel.
c. Certification
Assembled frames for the glazing must be certified to accommodate all glazing
clearances and tolerances related to bow, warp, and twist characteristics of the glass.
The adhesive bond between the structural adhesives and the contact surface must be
certified as adequate or if primers are required for adequacy.
The structural glazing adhesive must be certified and tested through ASTM C1087 for
its compatibility with the adjacent materials. It must not cause defects or any detrimental
damage to all adjacent materials as well.
Calculation requirements as listed in section 1.7.7.b.4 as well as clearances provided in
shop drawings must certified by the sealant manufacturer. 50
d. Cleaning
Joint surfaces must be cleaned before installation of backer rod and before application
of sealant. All deleterious and foreign objects, including protective tapes and removable
films, must be removed to ensure bond of sealant.
Surfaces to be masked must also be cleaned before application of film or tape.
Glass and aluminum surfaces must only be cleaned using clean and lint-free cloths and
mild cleaning compounds. Façade Contractor must apply two-wipe method of cleaning
– first wipe is to dry and clean the surface while the second wipe is to apply the cleaning
compound. In no case shall the cleaning compound be allowed to air-dry on the
substrate.
Porous substrates such as concrete and masonry must be cleaned where necessary by
grinding, mechanical abrasion, and/or detergent washing. Concrete laitance must be
removed mechanically and formwork oils must be removed by blast cleaning.
Acid washing shall only be allowed if approved through writing. The sealant
manufacturer shall recommend the manner of sealant application to ensure proper
adhesion.
e. Priming
Primer must be applied as recommended by the sealant manufacturer. Also, other
preparatory works such as surface roughening and removal of protective coating is
allowed as recommended by the sealant manufacturer.
f. Contamination of Adjoining Surfaces
The Façade contractor must not allow primer or sealer to migrate unto adjoining
surfaces. Thoroughly clean and apply ample protection to surfaces or joints prone to
contamination.
g. Sealant Accessories
Backer rods must be installed as approved in shop drawings and recommended by the
sealant manufacturer. It must be of proper depth to ensure sealant dimensions as
indicated in the shop drawings. It must be compressed between 25% to 50% when
installed.
Bond breakers must be applied to ensure there are no three-way adhesion as
recommended by the sealant manufacturer.
h. Sealant Expiration Dates
The Façade Contractor, through documents such as purchase dockets and confirmation
from the sealant manufacturer, must ensure that the applied silicone is within its
remaining shelf life.
i. Sealant Dimensions
Sealant bite or width shall be in accordance with the structural calculation and shown in
the shop drawings. Sealant depth must be the minimum of 6mm or half the joint width or
as specified by the Sealant Manufacturer.
j. Sealant Application
Before application of sealant, ambient temperature and humidity conditions must be
checked and must be within conditions recommended by the sealant manufacturers.
Sealant must be applied under pressure uniformly and continuously without gaps and/or
air pockets. Vertical joints must be slightly concave and below adjoining surfaces while 51
horizontal joints must convex. Tooling is a must to ensure formation of a compacted
bead. Tooling aid or lubricant must not be used unless specified by the sealant
manufacturer. Excess sealant must be removed to provide neat and smooth adjacent
surfaces. Masking materials must be removed after cleaning of excess sealants.
k. Curing
Curing must be compliant with the supplier’s recommendations for both off and on site
applied sealant. Temporary fixings must not be removed until sealant is fully cured.
The Façade Contractor must provide a site QA/QC representative all throughout the installation works.
Any deviation from approved from shop drawings must be noted and incorporated in the as-built
drawings. Proper filing of site documents must be observed.
The Façade Contractor shall maintain cleanliness at the work area and regularly remove all debris,
waste, rejected or excess materials at a manner prescribed by the Main Contractor. Upon completion
of installation, the façade system must undergo final cleaning to remove all marks, stains, laitance,
etc… Final cleaning must include a pre-rinse water spray removing abrasive particles before using
squeegee with mild soap. Finished work must be free from physical defects such as scratches, dents,
and abrasion as well as foreign objects such as labels and stickers. Diluted acids, in any ratio, must
not be used in cleaning the façade system. Any dirt or residue which cannot be cleaned with potable
water and soft brushes can be cleaned by other prescribed solution provided that it is proven and
tested to cause no harm or defects to each façade components.
The Façade Contractor is responsible in providing all materials including a temporary BMU for the
cleaning of the external façade.
Upon completion of adjacent works done by others, the Façade Contractor shall inspect the work
area, repair all damage or defects, and if applicable, apply proper trimming and sealant. Damaged due
to works done by others, direct and directly, can be recompensed at a reasonable cost from that
specific contractor.
The Façade Contractor shall be responsible for the protection and handling of their products and its
respective components through all stages of the façade works.
All exposed components of the window wall system must be provided with protective covering by the
Façade Contractor. Markings and notice to other contractors must also be provided on exposed
components to help in preventing damages.
C.
60
(+0.3/-2.0) kPa
61
(+0.3/-2.0) kPa
62
(+0.3/-2.0) kPa
D. Materials and Finishes Schedule
1) Glass
2) Finishes
Interior Exterior
Wall Type Component
Color Coating Color Coating
1 Aluminum Surfaces PVDF PVDF
2 Steel Sections HDG HDG
Check with Check with
3 Stainless Steel
Architect Architect
E. Proposed Façade System Material List
64
(To be filled up by the Façade Contractor)
Included?
Item Submittal Content Verified
Yes No
Partial Elevation 1 ☐ ☐ sign
Partial Elevation 2 ☐ ☐ sign
Drawing Registry ☐ ☐ sign
Material List ☐ ☐ sign
1 Shop Drawings
Wall type 1 Details ☐ ☐ sign
Wall type 2 Details ☐ ☐ sign
Wall type 3 Details ☐ ☐ sign
Wall type 4 Details ☐ ☐ sign
Design Criteria ☐ ☐ sign
Loadings ☐ ☐ sign
Glass & Glazing ☐ ☐ sign
Cladding ☐ ☐ sign
Structural
2 Vertical Frames ☐ ☐ sign
Calculations
Horizontal Frames ☐ ☐ sign
Connections ☐ ☐ sign
Anchoring to Concrete ☐ ☐ sign
Software Model Softcopy ☐ ☐ sign
3 General Programme ☐ ☐ sign
4 Quality Plan Outline ☐ ☐ sign
5 Materials Schedule (see attachment) ☐ ☐ sign
Written Confirmation of providing Warranty for the
6 ☐ ☐ sign
Façade Components
7 Organizational Chart & Curriculum Vitae of Key Staff ☐ ☐ sign
8 Installation Method Statement ☐ ☐ sign
9 Installation Manpower & Equipment Loading ☐ ☐ sign
10 List of current and completed jobs within past 5 years ☐ ☐ sign
Written Conformance to the Façade Tenchical
11 ☐ ☐ sign
Specification
2) Post-Award Requirements
66
Projected
Activity Verified
Submission Date Date Submitted
PROGRAMME
Material Sample Approval Click or tap to enter a date. Click or tap to enter a date. sign
VMU Click or tap to enter a date. Click or tap to enter a date. sign
PMU Click or tap to enter a date. Click or tap to enter a date. sign
Procurement Click or tap to enter a date. Click or tap to enter a date. sign
Manufacturing Click or tap to enter a date. Click or tap to enter a date. sign
Assembly Click or tap to enter a date. Click or tap to enter a date. sign
Shipment to Site Click or tap to enter a date. Click or tap to enter a date. sign
Installation of Embeds Click or tap to enter a date. Click or tap to enter a date. sign
Installation of Panels Click or tap to enter a date. Click or tap to enter a date. sign
Cleaning Click or tap to enter a date. Click or tap to enter a date. sign
Handover Click or tap to enter a date. Click or tap to enter a date. sign
MATERIAL SAMPLES
GL-01 Click or tap to enter a date. Click or tap to enter a date. sign
GL-02 Click or tap to enter a date. Click or tap to enter a date. sign
GL-03 Click or tap to enter a date. Click or tap to enter a date. sign
GL-04 Click or tap to enter a date. Click or tap to enter a date. sign
Backpan Click or tap to enter a date. Click or tap to enter a date. sign
Cladding Click or tap to enter a date. Click or tap to enter a date. sign
Extrusion Click or tap to enter a date. Click or tap to enter a date. sign
Gasket Click or tap to enter a date. Click or tap to enter a date. sign
Fixings Click or tap to enter a date. Click or tap to enter a date. sign
Anchors Click or tap to enter a date. Click or tap to enter a date. sign
Embeds Click or tap to enter a date. Click or tap to enter a date. sign
Firestop Click or tap to enter a date. Click or tap to enter a date. sign
67
Smokeseal Click or tap to enter a date. Click or tap to enter a date. sign
PMU
Shop Drawings Click or tap to enter a date. Click or tap to enter a date. sign
Structural Calculations Click or tap to enter a date. Click or tap to enter a date. sign
Steel Chamber Drawings Click or tap to enter a date. Click or tap to enter a date. sign
Final Report Click or tap to enter a date. Click or tap to enter a date. sign
SHOP DRAWINGS
General Notes Click or tap to enter a date. Click or tap to enter a date. sign
Materials List Click or tap to enter a date. Click or tap to enter a date. sign
Elevations and Plans Click or tap to enter a date. Click or tap to enter a date. sign
Setting Out for Façade Works Click or tap to enter a date. Click or tap to enter a date. sign
Die List with Paint Area Illustrated Click or tap to enter a date. Click or tap to enter a date. sign
Vertical and Horizontal Details Click or tap to enter a date. Click or tap to enter a date. sign
STRUCTURAL CALCULATIONS
Design Criteria Click or tap to enter a date. Click or tap to enter a date. sign
Load Derivation Click or tap to enter a date. Click or tap to enter a date. sign
Glass & Glazing Click or tap to enter a date. Click or tap to enter a date. sign
Aluminum Sheet Cladding Click or tap to enter a date. Click or tap to enter a date. sign
Stone Cladding (if any) Click or tap to enter a date. Click or tap to enter a date. sign
Typical Wall Mullions & Transoms Click or tap to enter a date. Click or tap to enter a date. sign
Corner Mullion & Transoms Click or tap to enter a date. Click or tap to enter a date. sign
68
Balusters and Railings Click or tap to enter a date. Click or tap to enter a date. sign
Connections Click or tap to enter a date. Click or tap to enter a date. sign
Operable Sash Click or tap to enter a date. Click or tap to enter a date. sign
Anchors Click or tap to enter a date. Click or tap to enter a date. sign
Bmu Pins/Tie Backs Click or tap to enter a date. Click or tap to enter a date. sign
SITE DRAWINGS
Embed Layout Click or tap to enter a date. Click or tap to enter a date. sign
Panel & Cladding Tag Elevation Click or tap to enter a date. Click or tap to enter a date. sign
Sealant Schedule Click or tap to enter a date. Click or tap to enter a date. sign
PROJECT MANUAL
Installation/Method Statement
Click or tap to enter a date. Click or tap to enter a date. sign
Manual
Operations & Maintenance Manual Click or tap to enter a date. Click or tap to enter a date. sign
Factory Inspection and Test Plan Click or tap to enter a date. Click or tap to enter a date. sign
Project Quality Plan Click or tap to enter a date. Click or tap to enter a date. sign
Embed Layout Click or tap to enter a date. Click or tap to enter a date. sign
Elevations and Plans Click or tap to enter a date. Click or tap to enter a date. sign
Modified Details Click or tap to enter a date. Click or tap to enter a date. sign