Você está na página 1de 16

3 Pole high impedance differential relay 7VH83

Fig 1. High impedance differential protection relay 7VH83


Features Mode of Operation Resetting of tne relay and LED
indication can be performed locally
l Integral CT shorting relay. The 7VH83 relay is a three pole from a push button on the front
l Robust solid state design. sensitive current relay. The AC input panel or electrically from remote.
l Inrush stabilisation through impedance of the relay is regulated
filtering. by a constant current circuit that is Various tripping options can be
l Fast operating time. independent of the voltage setting. selected by setting links LK1, LK2
l LED indicator. and LK3 on the P.C. Board.
l Simple voltage setting. The relay setting voltage pick-up
l Integral buswire supervision. value is set by means of DIL Option 1:
switches located on the front of the
Applications relay module. The voltage setting is Two out of two tripping criteria
determined by adding the base value
The 7VH83 relay is designed for to the sum of the selected setting By selecting links LK1 to position "b"
fast and selective differential pro- switch positions. and LK3 to position "a", the
tection based on the high imped- "differential tripping" circuits are
ance circulating current principle. It The input from the CT’s is enabled when the "external start"
is used for the protection of machine galvanically isolated from the static input is energised from either an
stator windings, busbars and operating circuit. The AC measured instantaneous overcurrent or
transformer and reactor windings current is band pass filtered and undervoltage relay source.
against phase to phase and phase to rectified to a proportional dc voltage.
earth short circuits. This voltage is monitored by Option 2:
switching circuits controlled by zener
Design diodes. When the dc voltage Two out of two tripping
exceeds the set value, the solid
The withdrawable module is housed state amplifiers operate the By selecting links LK1 to position "a"
in a 7XP2020 metal case suitable for command output relays, the LED and LK3 to position "b", additional
flush mounting. The plug connector indication and a latched CT shorting security is obtained where
at the rear of the case has one relay. "differential tripping" circuits are
screw and one snap on terminal for enabled together with the
each connection point. The plug The CT shorting relay is designed to instantaneous pick-up of the buswire
connector is marked with a co- short circuit the CT buswires supervision circuit.
ordinated system depending on the instantaneously removing the high
mounting location e.g. 4A1 denoted voltage across the relay CT input. Option 3:
row 4, block 1, column 1. The
individual connections are marked The reason for shorting out the CT’s One out of one tripping criteria
sequentially from left to right (viewed after the relay operation is to reduce
from the rear). See Fig. 3. the high voltage stress on the By selecting links LK1, LK2 and LK3
insulation and MOV especially to positions "a", "differential tripping"
during commissioning and circuits are permanently enabled and
maintenance when the primary will operate immediately once the
current can be injected for long voltage setting is exceeded.
periods.

1
3 Pole high impedance differential relay 7VH83

Fig 2. Connection diagram for 7VH83 relay

2
3 Pole high impedance differential relay 7VH83

Technical Data

CT Circuits 50 Hz or 60 Hz
Normal frequency

Thermal Withstand
2 sec 505 volt
Continuous 400 volt

Measuring Circuit

Setting range
Differential protection 10 to 280 volts in 10 volt steps
Buswire supervision 5 to 160 volts in 5 volt steps
Buswire supervision timer 0 to 15 seconds in 1 second steps

Tripping Time

1,1 x setting 56 ms
1,2 x setting 43 ms
1,5 x setting 30 ms
5 x setting 21 ms

Pick up to drop out ratio 0.95

Reset Time 20 ms

Supply and Reset Voltage 24/48V dc 19 to 56 V dc


110/125V dc 48 to 144V dc
220/250V dc 176 to 288V dc

Supply Burden (at rated voltage)

For all voltages


Quiesent 4W
Picked up 5W

Contacts Command Output Alarm

Number of Contacts 2 N/O 1 N/C


Make 1000 W/VA 30 W/VA
Break 30 W/VA 30 W/VA
Carry 30A for 0,5s and 5A continuous
Max Switching Voltage 250V AC/dc

Indication LED trip indication per phase


LED indication for CT buswire supervision

3
3 Pole high impedance differential relay 7VH83

Environmental Withstand

Max. Temperatures, during


Service - 10°C to + 55°C
Storage - 25°C to + 55°C
Transport - 25°C to + 70°C

Humidity, acc. to DIN 40 040 class F

Vibration, service 0.5g between


60 to 500 Hz
0.035 mm amplitude
between 10 to 60 Hz

Vibration, transport 2 g between


8 to 500 Hz
7,5 mm amplitude
between 5 to 8 Hz

Insulation Tests
HV Test IEC 255-5 2kV (rms); 50/60 Hz; 1 min
Impulse Test IEC 255-5 5kV (peak); 1,2/50 µs; 0,5J; sec
3 positive and 3 negative
shots at intervals of 5s

High Frequency Test 2, 5 kV (peak); 1 MHz;


IEC 255-22-1 π = 1,5 µs; 400 shots/s
Class Ill duration 2s

EMI Test

IEC 801-3 20 MHz to 1000 MHz at 10V/m


ANSI/IEEE C37.90.2 field strength

Weight Dimensions

Withdrawable Module 3U; 12 slots of 5.08 mm

Case

Standard metal case for 7XP201 0-2C


flush mounting

Size 1/6 of 19" rack

Extra frame for surface mounting 7XP21

Enclosure protection IP51


Mass Approx. 1kg

Modular Terminal Block


2
Each terminal provides one snap-on 1.5 mm wire
connection one tunnel type screw
connection
4
3 Pole high impedance differential relay 7VH83

Ordering Data

Order No.
3 Pole High-Impedance Differential Relay 7VH8300 - A
With CT Shorting Input Relay
Auxiliary Supply Voltage

24/48V dc 3
60/110/125V dc 4
220/250V dc 5

Mechanical Construction

Plug-in Module in a 7XP20 case


C
External Varistors
With 3 Varistors as loose items 0
Without varistors
1

Reset Voltage
3
24/48V dc 4
60/110/25V dc 5
220/250V dc

ORDERING DATA
Please specify the varistor type required ( see page 10) for your application or consult your
nearest Siemens office.

5
3 Pole high impedance differential relay 7VH83

Fig 3. 7VH83 relay in flush mount case

6
3 Pole high impedance differential relay 7VH83

Fig 4. Phase and earth fault protection

7
3 Pole high impedance differential relay 7VH83
Relay setting

List of abbreviations

IE = Current transformer exciting current at relay setting voltage.


(referred to the CT secondary current)
IF = Maximum value of primary through fault current for which protection must remain stable.

IFM = Maximum value of primary fault current for internal fault.

lp = Primary current for operation of protection.

IR = Relay operating current.

ISH = Current in shunt resistor at relay setting VR.

N = Turns ratio of current transformer.

n = No. of current transformers in parallel with relay.

RCT = Secondary resistance of current transformer.

RL = Lead resistance between furthest current transformer and relay connection point.

RR = Relay impedance.

RSH = Value of shunt resistor.

VF = The theoretical voltage which would be produced across the relay circuit
under internal fault conditions.
I FM
VF = ( RCT + 2 R L + RR )
N

VK = Knee point voltage of current transformer.

VP = Peak voltage across relay circuit under maximum internal fault conditions.

VS = Minimum Setting voltage. (Calculated)

VR = Relay setting voltage.

K = Varistor constant.

B = Varistor constant.

8
3 Pole high impedance differential relay 7VH83

Calculation of relay protection l accidental open or short shown. From this curve, it is
setting circuit of the secondary of easy to determine the mag-
one or more CT’s. netising current IE for a sec-
The minimum setting voltage to ondary voltage of V.
ensure stability is The operating current of the
relay is 5mA irrespective of the CT supervision circuit
I voltage selected excluding the
VS ≥ FM ( RCT + 2 R L ) current drawn by the external If the CT’s have broken or
N varistor. shorted connections, the
protective relay may detect this
The relay plug setting voltage Configuration are generally condition as a busbar fault and
VR must be set to the nearest provided therefore trip all the circuit
tap above VS. The minimum breakers in that zone. If several
knee point voltage must be l polyphase faults; requiring a CT’s are associated in the zone,
three relay type 7VH83 the disconnection of one of them
VK≥2VR phase. Current transformer (corresponding perhaps to a
supervision, protects against lightly loaded feeder) will result
The primary current for operation the accidental opening of a CT in a very low fault current
is given by connection. This occurrence measurement. If this unbalance
normally causes a fault current is lower than the 7VH83
IP=N(IR+nIE) that is too low to activate the protection setting, this condition
relay circuits, however the will not be detected. Therefore a
If the resultant value of lP is too condition should be signalled more sensitive monitoring circuit
low it may be increased by the before the appearance is required for CT supervision.
addition of a shunt resistor RSH of an actual fault . This monitoring circuit is integral
to give a current of The supervision would to the 7VH83 relay.
register the low unbalanced
ISH=VR/RSH current and control a time CT Requirements
delayed output alarm.
The new increased value of The correct operation of the high
primary current Knee-point voltage of current impedance circulating current
transformers protection is largely dependant
on the CT dimensioning.
lP = N(IR+nIE+ISH)
The CT’s will not be saturated by
the short-circuit current if the To enable the CT manufacturer
Setting advice
knee-point voltage is greater to design an appropriate CT, a
than twice the maximum voltage class X specification, as outlined
With particular reference to high
likely to be applied across the in the BS3938 or similar should
impedance busbar protection,
terminals of the relay during the be specified and would include:
the plant and equipment should
fault. 1 . CT Knee point voltage (VK)
have protection with the
2. CT secondary resistance
following features:
(RCT)
V RMAX = 2 2VK (VF − VK ) 3. CT magnetisation/excitation
l adequate sensitivity
current(IE)
l fast response time
4. Turns ratio (N)
l stability, when external
At the maximum secondary 5. Thermal rating of the
faults occur
secondary turns to primary
l selectivity to allow
through fault current the varistor
should limit the voltage to load current.
disconnection of only
< 1 OOOV rms if possible.
the faulted section
In the case of existing current
l permanent supervision of
Determination of magnetising transformers the above details
the current transformers
current IE can be obtained either from the
manufacturers design test
Relay operation shall not sheets, or by carrying out a
occur on: The manufacturer of the current
transformer supplies the magnetising characteristic test
comparing excitation current to
l saturation of the CT’s by
magnetic characteristics from
which the magnetising current the applied voltage, a resistance
the transient dc compo- measurement and a primary to
curve versus the secondary
nent when a serious fault secondary ratio check.
voltage is
occurs outside the zone

9
3 Pole high impedance differential relay 7VH83

Varistor Selection

Each 7VH83 relay is normally tance and applied voltage is If the current transformer
applied with an external varistor non-linear, i.e. an increase in the secondary voltage is to be limit-
which must be connected applied voltage will result in a ed to a safe level during max-
across the relay input terminals. decrease in the resistance and imum internal fault conditions
The varistor limits the voltage hence an increase in the cur- then a varistor may be required.
developed across the CT and rent. The change in resistance Generally if
relay terminals under fault con- occurs instantaneously.
ditions. VRMAX > 2KV
The electrical characteristics can
B
A varistor is a non-linear or be expressed as V = KI where then a varistor is required
voltage dependent resistor. It is K and B are constant for any
a ceramic semi-conducting one varistor.
resistance material in which the
VRMAX = 2 2VK (VF − VK )
relationship between resis-

Relay Voltage Setting K B Varistor type


Up to 125V rms 450 0.25 600A/S3/I/S802

Table 2

K Characteristic Max. Continuous Rating – rms


450 2OOV
900 35OV
Varistor Assembly Type Unit K Value Short Time Rating
Standard 600A/S3/I/S802 450 22A for 3 seconds
30A for 2 seconds
45A for 1 second

Table 3

Installation and Commissioning Instructions


Installation
Protective relays, although The relays are either despatched sustained in transit. If damage
generally of robust construction, individually or as part of a due to rough handling is
require careful treatment prior to panel/rack mounted assembly in evident, a claim should be
installation. By observing a few cartons specifically designed to made to the Transport
simple rules the possibility of protect them from damage. Company concerned
premature failure is eliminated Relays should be examined immediately and the nearest
and a high degree of immediately to ensure that no Siemens Office should be
performance can be expected. damage has been promptly notified.

10
3 Pole high impedance differential relay 7VH83
Relays which are supplied tests, must subsequently be
unmounted and not intended for Commisioning preliminaries replaced.
immediate installation should be Inspection It is only necessary to check the
returned to their protective relay at the setting on which it is
cartons. Carefully examine the module to be used. The relay must not
and case to see that no damage be used at any setting other than
Care must be taken when has occurred during transit. that for which the setting has
unpacking and installing the Check that the relay serial been calculated.
relays so that none of the parts number on the module, case
are damaged or their settings and cover are identical, and that Commissioning Tests
altered and must at all times be the model number and rating Test Equipment
handled by skilled persons only. information are correct.
1 Secondary injection test
Relays which have been Check that the external wiring is equipment capable of
removed from their cases should correct to the relevant relay providing an AC voltage
not be left in situations where diagram or scheme diagram. supply of up to at least
they are exposed to dust or 120% of the relay setting.
damp. This particularly applies Particular attention should be 1 Test plug for use with test
to installations which are being paid to the correct wiring and block if fitted.
carried out at the same time as value of any external resistors 3 Calibrated multimeters 0-10
construction work. indicated on the wiring amp AC 0 - 400 volt AC.
diagram/relay rating information. 1 Set of primary injection
If relays are not installed testing equipment.
immediately upon receipt they Note that shorting switches
should be stored in a place free shown on the relay diagram are General
from dust and moisture in their fitted internally across the
original cartons and where relevant case terminals and If the relay is wired through a
dehumidifier bags have been close when the module is test block it is recommended
included in the packing they withdrawn. It is essential that that all secondary injection tests
should be retained. such switches are fitted across should be carried out using this
all CT circuits. block.
The action of the de-humidifier
crystals will be impaired if the If a test block is provided, the Ensure that the main system
bag has been exposed to damp connections should be checked current transformers are shorted
ambient conditions and may be to the scheme diagram, before isolating the relay from
restored by gently heating the particularly that the supply the current transformers in
bag for about an hour, prior to connections are to the ’live’ side preparation for secondary
replacing it in the carton. of the test block. injection tests.

Dust which collects on a carton Earthing Danger


may, on subsequent unpacking,
find its way into the relay; in Ensure that the case earthing Do not open circuit the
damp conditions the carton and connection at the rear terminal secondary circuit of a current
packing may become block, is used to connect the transformer since the high
impregnated with moisture and relay to a local earth bar. voltage produced may be
the de-humidifying agent will
lethal and could damage
lose its efficiency. Insulation
The storage temperature range insulation.
is -25° and +55°C. The relay, and its associated Secondary injection testing
wiring, should be insulation
The installation should be clean, tested between:
dry and reasonably free from Connect the circuit as shown in
• all electrically isolated circuits Figure 5 and ensure that the
dust and excessive vibration. • all circuits and earth
The site should preferably be current transformer primary is
well illuminated to facilitate open circuit and that if any
An electronic or brushless earthing connections are fitted,
inspection. The relay should be insulation tester should be used,
mounted in the cut-out or rack they do not short out the
having a dc voltage not primaries of any current
provided (Fig 3.) and wired exceeding 1000V. Accessible
according to Figure 2 or the transformers.
terminals of the same circuit
relevant drawing or schematic should first be strapped
diagram. Increase the voltage until the
together. Deliberate circuit relay just operates.
earthing links, removed for the

11
3 Pole high impedance differential relay 7VH83

Record the current at which the is injected into each current be very low, only a few milliamps
relay operates (A2). It should be transformer in turn and if the connections are correct. A
approximately 5mA at setting. increased until the relay high reading (twice the injected
operates. The voltage at which current, referred through the
Note also the voltage at which the relay operates should be current transformer ratio)
the relay operates which should within ± 10% of the relay setting indicates that one of the current
correspond to the setting VR of voltage VR. The primary current transformers polarity is reversed.
the relay with a tolerance of for operation and relay current
± 10%. The total secondary should be noted. Injection should be carried out
current for operation will be through each phase to neutral.
given on ammeter A1.This test
should be repeated for each For large machines the machine In the case of machine protec-
pole of the relay. itself can be used to provide the tion similar stability tests must
fault current to check the primary be carried out by injecting into
Record the value at which the fault setting as shown in Figure 8. one and out of another current
relay picks up and then reduce The machine should be run up to transformer connected on the
the voltage until it drops off. speed with no excitation. The same phase.
From these two values calculate excitation should then be
the drop off/pick up value. It increased until the relays have all For large machines, the machine
should be approximately 0,95. operated. The primary current, itself can be used to provide the
relay current and relay voltage fault current, but the short circuit
Primary injection testing should be noted as each relay must now be fitted as shown in
operates. Figure 9. The machine should
It is essential that primary be run up to normal speed and
injection testing is carried out to Through fault stability the excitation increased until the
prove the circuit is dead, isolated primary current is approximately
from the remainder of the With any form of unbalanced full load, when the spill current
system and that only those earth protection it is necessary to should be checked.
connections associated with the check that the current trans-
primary test equipment are in formers are correctly connected. All other types of balanced
position. For this purpose the circuit protection should be tested in a
shown in Figure 7 may be used. similar manner.
Primary fault setting During this test the relay is
shorted out and the spill current At the conclusion of the tests
The primary fault setting of any through the relay circuit A2 is ensure that all connections are
balanced scheme can be measured. The current is correctly restored and any
checked using the circuit shown increased up to as near full load shorting connections removed.
in Figure 6. The primary current as possible and the spill current
noted. The spill current should

ADDENDUM COMMISSIONING TEST RECORD DATE


HIGH STABILITY
CIRCULATING CURRENT RELAY
TYPE 7VH83
STATION CIRCUIT
RELAY MODEL NO. SERIAL NO.
SETTING RANGE CT RATIO
SETTING VOLTAGE RELAY SETTING
SHUNT RES.
OHMS (if fitted)
TYPE OF EXT. VARISTOR CALCULATED PRI.
OP CURRENT

12
3 Pole high impedance differential relay 7VH83

TEST RESULTS
Relay CT Shorting Switch
Secondary Voltage to operate relay

Phase Total Current A1 Relay Current (A2) P.U. Volts D.O. Volts
A
B
C

Drop off / Pick up ratio check

Table 5

Primary Current to operate relay


Phase Primary Current A1 Relay Current A2 Relay Voltage
A
B
C
N

Table 6

Stability check by primary injection

Restricted Earth Fault


Phases A1 Primary Current A2 Spill Current
A-N
B-N
C-N

Table 7

Circulating Current between two or more sets of current transformers


Phases A1 Primary Current A2 Spill Current
Al -A2
Bl - B2
Cl -C2

Table 8

Where more than two sets of


current transformers are
involved, injection should be
carried out between set 1 and
each other set in turn.

Maintenance

Periodic maintenance is not mounted in poor environmental


necessary. However, periodic conditions.
inspection and test is Repeat secondary injection tests
recommended. This should be to prove correct operation,
carried out every 12 months or making sure the circuit breaker
more often if the relay is trips when the relay operates.
operated frequently or is

13
3 Pole high impedance differential relay 7VH83

Fig 5. Secondary injection test

Fig 6. Primary fault setting test

14
3 Pole high impedance differential relay 7VH83

Fig 7. Primary fault setting test

Fig 8. Through fault stability test

15
3 Pole high impedance differential relay 7VH83

Fig 9. Primary fault setting test

The information contained in this publication is subject to change without prior notice.

Siemens Limited
P O Box 207 lsando 1600
South Africa
Telephone (011) 921-7000

Issued by Energy and Automation Group - Power Transmission and Distribution

16

Você também pode gostar