Piping Route Line Hot Air Drying System

10" C/S
Existing 10" C/S

6" C/S

To Rotary kiln

AUTHOR NAME
6" C/S

Drying Room

10" C/S
To Gas Cooler

Heat Exchanger

2" C/S

Estimate Line Lenght

Carbonization Kiln Item Description Q'ty Unit


1 2" Hot Air 12 m.
2 6" 48 m.
3 10" 24 m.
4 10" To Gas Cooler 20 m.

Design By. K.Piping