Department of Education

Region VI – Western Visayas


Division of San Carlos City
San Carlos City, Negros Occidental
District II – Cluster 4
GIGALAMAN ELEMENTARY SCHOOL

ALLAN B. YAP, Ph.D., CESO VI


Schools Division Superintendent

Thru: MARIA CRISTINA F. BAHINTING


CES – SGOD

Submitting herewith is the actual status of accomplishment of works of Gigalaman ES pertaining


to the installation of off-grid solar energy system.

For your information and guidance.

Thank you very much and God bless.

JOVITO P. LIMOT
ESHT-III

ACCOMPLISHMENT OF WORKS REPORT


Project: INSTALLATION OF SOLAR PV ENERGY SYSTEM
School: GIGALAMAN ELEMENTARY SCHOOL - 117759
Location: SITIO GIGALAMAN, BRGY. GUADALUPE, SCC, NEG. OCC.
Electricals per classroom (8 classrooms)
Quantity based on Quantity based on
# Description Unit Remarks
ABC actual installations
1x18 W (T8) Led Fluorescent Lighting Fixture (Box
1 set 48 32 Lacking of 16 sets
Type-Surfaced Ceiling Mounted)
Complete and
2 Solar DC Wall Fan (Energy Efficient Fan) set 16 16
functional
Solar PV System per Classroom
1.2 KW off-grid solar panels (complete set including installation (1 set per classroom)
Complete but only 11
1 12x100 W monocrystalline Solar Panels panel 12 12
is functional
1440 Max. PV Capacity PWM Solar Charge
Complete but 1 is not
2 Controller box 8 8
functional (defective)
1000 watts PSW Inverter
Complete but the
actual storage
3 9600 WH Max. Capacity Lead Acid Battery bat 16 16
capacity per battery is
200 AH Gel Battery
4 Complete Roof Mounting Kit complete
5 PV Combiner Box box 8 8 complete
6 MC4 Connectors cannot define
7 12 way CB Distribution Box box 8 7 Lacking of 1 box
8 AC circuit breaker cannot define
9 DC circuit breaker cannot define
10 AC Surge and Lighting Protective Device cannot define
11 DC Surge and Lighting Protective Device cannot define
12 20 meters Single Core AWG 8 Stranded Wire cannot define