Activity ID Activity Name Remaining Start Finish 2016 2017 2018 2019 2020 2021 2022 2023 2024

Duration MA M J J A S O N D J F MA M J J A S ON D J F M A M J J A S ON D J F MA M J J A S O N D J F MA M J J A S O N D J F M A M J J A S ON D J F MA M J J A S O N D J F MA M J J A S ON D J F M
SV-LQ-51110 Blast & Paint HVAC Support Level 1 12 05-Dec-18 18-Dec-18
SV-LQ-51200 Blast & Paint HVAC Support Level 2 15 19-Dec-18 05-Jan-19
SV-LQ-50845 Blast & Paint HVAC Supports Level 3 12 09-Feb-19 22-Feb-19
ARCHITECURAL 50 12-Dec-18 13-Feb-19 13-Feb-19, ARCHITECURAL
SV-LQ-50925 Blast & Paint for Architectural Supports Level 1 12 12-Dec-18 25-Dec-18
SV-LQ-50995 Blast & Paint for Architectural Supports Level 2 18 26-Dec-18 16-Jan-19
SV-LQ-50960 Blast & Paint for Architectural Supports Level 3 20 17-Jan-19 13-Feb-19
TOUCHUP 368 09-Jan-19 27-Mar-20 27-Mar-20, TOUCHUP
SV-LQ-51605 Touchup and Painting for LQ before Jacking Up 176 09-Jan-19 09-Aug-19
SV-LQ-53455 Touchup and Painting for LQ After Jaking Up to CPP Topside 130 23-Oct-19 27-Mar-20
LQ TESTING/ PRE-COM/ COMM 191 11-Jul-19 25-Feb-20 25-Feb-20, LQ TESTING/ PRE-COM/ COMM
LQ Mechanical Completion 181 11-Jul-19 13-Feb-20 13-Feb-20, LQ Mechanical Completion
SVDN-C-12235 MC for LQ System 181 11-Jul-19 13-Feb-20
LQ Precomissioning 102 04-Sep-19 31-Dec-19 31-Dec-19, LQ Precomissioning
SVDN-C-7205 Pre-com for LQ System 102 04-Sep-19 31-Dec-19
LQ Commissioning 131 20-Sep-19 25-Feb-20 25-Feb-20, LQ Commissioning
SVDN-C-7365 Com for LQ System 130 20-Sep-19 24-Feb-20
SVDN-C-7485 LQ Habitation 1 25-Feb-20* 25-Feb-20
HELIDECK 183 07-Jan-19 15-Aug-19 15-Aug-19, HELIDECK
STRUCTURAL 148 07-Jan-19 05-Jul-19 05-Jul-19, STRUCTURAL
PRE-FABRICATION 87 07-Jan-19 23-Apr-19 23-Apr-19, PRE-FABRICATION
SV-LQ-51455 Cut & Prepare Primary Beam of Heli Deck 20 07-Jan-19 29-Jan-19
SV-LQ-51515 Fab Nodes of Helideck 25 07-Jan-19 08-Feb-19
SV-LQ-51660 Cut & Prep Secondary Beams of Helideck 20 16-Jan-19 12-Feb-19
SV-LQ-51820 Cut & Prepare Chord for Helideck Support Panel at (+) 43.500 25 18-Jan-19 20-Feb-19
SV-LQ-51935 Cut & Prep Bracings 20 30-Jan-19 26-Feb-19
SV-LQ-52500 Cut & Prep Deck Plate of Helideck 20 13-Feb-19 07-Mar-19
SV-LQ-51830 Fab Vertical Columns 10 13-Feb-19 23-Feb-19
SV-LQ-51770 Cut & Prepare Stiffener of Helideck 7 13-Feb-19 20-Feb-19
SV-LQ-51870 Fab Safety Net Panel 45 15-Feb-19 08-Apr-19
SV-LQ-51785 Fabricate Tertiary Steel (handrail, Ladder. Walkways....) 50 23-Feb-19 23-Apr-19
SV-LQ-51910 Fab Safety Net Support Framing 35 05-Mar-19 13-Apr-19
ASSEMBLY 136 21-Jan-19 05-Jul-19 05-Jul-19, ASSEMBLY
SV-LQ-51575 Fit up Primary Steels 18 21-Jan-19 14-Feb-19
SV-LQ-51640 Install Nodes of Helideck 12 21-Jan-19 02-Feb-19
SV-LQ-51725 Fit up Secondary Steels 20 02-Feb-19 01-Mar-19
SV-LQ-51860 Assembly Helideck Support Panel at (+) 43.500 25 14-Feb-19 14-Mar-19
SV-LQ-51675 Weld Primary Steels 15 15-Feb-19 04-Mar-19
SV-LQ-51790 Weld Secondary Steels 21 23-Feb-19 19-Mar-19
SV-LQ-51825 Install Stiffeners 15 01-Mar-19 18-Mar-19
SV-LQ-52485 Install Columns and Braces on HeliDeck Support Panel 15 16-Mar-19 02-Apr-19
SV-LQ-51840 Install Deck Plates of Helideck 25 19-Mar-19 17-Apr-19
SV-LQ-51880 Install Safety Net Support Framing 21 18-Apr-19 14-May-19
SV-LQ-51900 Install Safety Netting to Panel 15 26-Apr-19 15-May-19
SV-LQ-51905 Install Safety Netting Panel c/w Safety Netting to Helideck 18 07-May-19 27-May-19
SV-LQ-51920 Install Tertiary Steel (handrail, Ladder. Walkways....) 25 07-May-19 04-Jun-19
SV-LQ-52490 Fab & Install Lifting Padeyes for Heli Deck 15 24-May-19 10-Jun-19
SV-LQ-51960 Dismantle Scaffolder and Prepare transportation to lifting on LQ 7 28-Jun-19 05-Jul-19
PIPING & MECHANICAL 116 30-Mar-19 15-Aug-19 15-Aug-19, PIPING & MECHANICAL
SV-LQ-51460 Fab Piping support On Helideck 15 30-Mar-19 17-Apr-19
SV-LQ-51520 Fab Piping Spools on Helideck 20 11-Apr-19 07-May-19
SV-LQ-51580 Install Piping Support on Helideck 15 18-Apr-19 07-May-19
SV-LQ-51665 Install Piping Spools for Helideck 15 10-May-19 27-May-19
SV-LQ-51775 Hydrotest and Reinstatement for Piping 15 28-May-19 13-Jun-19
SV-LQ-53645 Install HeliDeck Equipment 13 01-Aug-19 15-Aug-19
ELECTRICAL & INSTRUMENTATION 68 30-Mar-19 20-Jun-19 20-Jun-19, ELECTRICAL & INSTRUMENTATION
SV-LQ-51765 Fab E&I support on Helideck 20 30-Mar-19 23-Apr-19
SV-LQ-51845 Install E&I Support on Helideck 20 17-Apr-19 11-May-19
SV-LQ-51875 Install Cable Tray on Helideck 20 25-Apr-19 20-May-19
SV-LQ-51895 Cable Pulling for Helideck 18 09-May-19 29-May-19
SV-LQ-51915 Install Lighting system, Signal system on Helideck 20 17-May-19 08-Jun-19
SV-LQ-51930 Gladding/Dressing/Termination Cables 10 29-May-19 08-Jun-19
SV-LQ-51945 Continuity Check 10 10-Jun-19 20-Jun-19
PAINTING 136 12-Jan-19 27-Jun-19 27-Jun-19, PAINTING
SV-LQ-51525 Blast & Primer & Tie Coat Primary Beams 20 12-Jan-19 08-Feb-19
SV-LQ-51615 Blast & Primer & Tie Coat Nodes 21 15-Jan-19 12-Feb-19
SV-LQ-51695 Blast & Primer & Tie Coat Secondary Beam 20 28-Jan-19 23-Feb-19
SV-LQ-51855 Blast & Prime Chords for Helideck Support Panel at (+) 43.500 20 01-Feb-19 28-Feb-19
SV-LQ-51795 Blast & Primer & Tie Coat Stiffeners 10 21-Feb-19 04-Mar-19
SV-LQ-51850 Blast & Primer & Tie Coat Columns 10 25-Feb-19 07-Mar-19
SV-LQ-51955 Blast & Primer & Tie Coat Bracing 15 27-Feb-19 15-Mar-19
SV-LQ-51890 Blast & Primer & Paint Safety Net Panel 20 27-Feb-19 21-Mar-19
SV-LQ-52505 Blast & Prime & Tie Coat Deck Plate of Helideck 10 02-Mar-19 13-Mar-19
SV-LQ-51815 Blast & Primer & Paint Tertiary Steel (handrail, Ladder. Walkways....) 25 19-Mar-19 17-Apr-19
SV-LQ-51940 Blast & Paint  Safety Net Support Framing 10 22-Mar-19 02-Apr-19
SV-LQ-51530 Blast & Paint for Piping Supports 10 05-Apr-19 17-Apr-19

Actual Work Milestone Page 92 of 103                                     13-Nov-18                                      07:43 APPROVED FOR CONSTRUCTION


Remaining Work Summary Date Revision Checked Approved
Critical Remaining Work SVDN - EPCIC PROJECTED PLAN LEVEL 3 24-Oct-18 Rev. D3