CONTENTS

SECTION - A

Page
Sl.No. Description
No.
1.0 Scope of Work
2.0 Definition of Terms &Specification
Documents
2.1 Definition of terms
2.2 Specification Documents
3.0 Instruction to Bidders
3.1 Information Furnished
3.2 Time of completion and work schedule
3.3 Night Work
3.4 Inspection of site by bidders
3.5 Work Execution and Supervision
3.6 Services & Facilities by the Owner
3.7 Prices and Rates
3.8 Validity of Bid
3.9 Demobilisation
3.10 Security & Safety Rules of Owner
3.11 Payment
3.12 List of Works
3.13 Drawings
3.14 Discrepancies between Drawing &
Specification
3.15 Bid Documents
4.0 Submission of Bid (Two Part tender
System)
5.0 Bid Qualification Requirements
6.0 Return of Bid Document
6.1 Owner Reserves Right
7.0 Materials Supplied By Contractor
8.0 Surveying and Layout
9.0 Quantities
10.0 Equipment
11.0 Delivery and Prices
SECTION - A

Page
Sl.No. Description
No.
12.0 Cement and Steel
12.1 Cement
12.2 Steel
13.0 General Note
14.0 Other Works
15.0 Controlled Concrete
16.0 Contract Document
17.0 Sub-Contractor
18.0 Bid Evaluation

SECTION - B

Sl.No. Description Page


No.

1.0 Project Information


SECTION – C

Sl. No. Description Page No.


1.0 Submission of Tender
2.0 Certificate of Income Tax
3.0 Earnest Money Deposit
4.0 Validity of Tender
5.0 Security Deposit
6.0 Instructions to Tenderers
7.0 Employment of technically qualified
Personnel by the contractors in the
execution of works.
8.0 Guarantee
8.1 Failure to meet guarantee
9.0 Insurance
10.0 Schedule of Quantities
11.0 Completion of works
12.0 Sub-letting
13.0 Further information
14.0 Evidence of Previous experience
15.0 Supply of compressed air
16.0 Power Supply for works
17.0 Alternate Supply
18.0 Water Supply for works
19.0 Erection of Sheds
20.0 Rates of Contract
20.1 Completeness of scope
21.0 Liquidated Damages
22.0 Force Majeure
23.0 Terms of payment

SECTION – C

Sl. No. Description Page No.

24.0 Contractor not to dispose off soil, etc.

25.1 Liability for accidents to persons


25.2 Liability for Damage to Works or Plants
26.0 Power for Engineer to decide order of
works
27.0 Contractor to inform Engineer for
arrangements for execution of work
28.0 Sunday Work
29.0 Suspension of work
30.0 Inspection of works
31.0 Patent Rights
32.0 Access to site and work on site
33.0 Supply of Cement
34.0 Supply of Steel
35.0 Materials brought to the site of works
36.0 Contractor to keep inventory of plant, etc.
37.0 Tools and Plants for the execution of the
contract
38.0 Maintenance
39.0 Completion Certificate
40.0 Final Certificate
41.0 Certificate to be Provisional and Subject
to correction
42.0 Negligence
43.0 Death, Bankruptcy etc.
44.0 Measuring, valuing and certifying by
Engineer
45.0 Arbitration
46.0 Cleaning up

SECTION – C

Sl. No. Description Page No.

47.0 Jurisdiction
48.0 Submission of PERT Chart
49.0 Quality of Materials
50.0 Waste Materials
51.0 Recovery of money from Contractor
52.0 Weekly Progress Reports

53.0 Gold, Silver, Minerals, Oil, Relics etc.


found on the site.
54.0 Interest on money due to the contractor
55.0 Deviation, alterations etc. in the materials
56.0 Deviations, alterations and additions to
the works
57.0 Claims for extra work or for deductions
58.0 Measurement of Extra works
58.1 Rates for Supplemental Items
59.0 Work executed by day labour
60.0 Application for retention sum
61.0 Breach on part of Purchaser not to annul
contract
62.0 Regulations of local authorities
63.0 Notices : How to be given
64.0 Construction of contract
65.0 Contractor's Representatives and
workmen
66.0 Right of Engineer to order withdrawal of
labour
67.0 Works materials, works and workmanship
to be executed to the satisfaction of the
Engineer

SECTION – C

Sl. No. Description Page No.

68.0 Execution of works in conformity with the


contract documents
69.0 Contract includes all necessary operation
69.1 Location of contractor’s plants
70.0 Contractor to supply and be responsible
for the sufficiency of the means employed
71.0 Fencing and Lighting
72.0 Discrepancies between drawing and
specification
73.0 Terms of Payment
74.0 Documents Confidential
75.0 Tender Document not returnable
76.0 Filling up of Tender Proforma
77.0. Illumination
78.0 Communication facilities
79.0 Health and Sanitary Rules for workers
79.1 First Aid
79.2 Drinking Water
79.3 Washing and Bathing places
79.4 Latrine and Urinals
79.5 Shelters during rest
79.6 Crèches
79.7 Canteen
79.8 Shed for Workers
80.0 Provisional Laws
81.0 Taxes and Duties
81.1 Excise Duty
81.2 Works Contract Tax
81.3 Service Tax
82.0 Seignorage Charges
83.0 Precaution during working
83.1 Inclement weather
84.0 Deduction for Labour Welfare Fund

SECTION – D

Sl.No. Description Page no.

1) Earth work excavation and back filling

2) Timber shoring
3) Dewatering
4) Concrete and allied works

5) Specific Technical Requirements


SECTION – E

Sl.No. Description Page no.

1) Schedule-1 Summary of Price proposal

2) Schedule-2 Summary of Price break upl

SECTION - F

ANNEXURE- I to IX

Sl.No. Description Page no.

I Lead particulars for construction materials

II Proforma for submission of tender

III Particulars of employment of ex-service


personnel
IV Undertaking in-lieu of payment of EMD

V Schedule of equipment

VI Bidders experience

VII Schedule deviation from technical


specification
VIII Schedule of deviation from general
conditions
IX Details of technical personal of the
tenderers organization
SECTION – G

Sl.No. Description Page no.

1) Alignment of proposed cooling water


channel
2) General arrangement of cooling water
pump house
3) Annexure to technical details

Você também pode gostar