Escolar Documentos
Profissional Documentos
Cultura Documentos
Assignment 2
Prepared by
1. Alif Akhmizan bin Mohd Jaya (2016209982)
2. Evllynn Suezelynn Dolian (2016209974)
3. Azizah binti Abdul Nassir (2016209732)
Detail background • Construction of Sekolah Menengah Kebangsaan Bertam
Why the precast Putra; which consists of 24 classrooms.
information of
construction type is • Located at Lot 7159, Jalan Seksyen 4 Putra Bertam, Mukim
chosen? chosen
6, Bandar Bertam Putra, Seberang Perai Utara, Pulau
• Only need a few workers construction site. Pinang.
to be in site to transport • Client for this construction project were Ministry of
using machinaries and Education Malaysia and Contractor assigned in completing
install these prestressed the construction were The One PMC Sdn. Bhd.
members, suitable with • Construction works were started from 27th April 2018 and
limited space of the estimated to be completed 24th April 2020.
construction site. • Around 40% of the whole construction were completed
• Symmetrical and boxy during our second visit.
design of the project
makes it easier to use
with prestressed
construction as it is
using the same
Question 1 Prestressed concrete.
prestressed structures • It is a form of reinforced concrete that builds in
from the same mould compressive stresses during construction to
along the span. oppose those found when in use.
• However, some of the • Refers to concrete that has applied stresses
structures were using induced into the member. Wires or tendons were
conventional reinforced stretched and then locked at the ends creating
concrete constuction compressive stresses throughout the entire
due to different cross members' cross-section.
sections of the concrete • For this project, prestressed concrete were
Type of precast
structures. Examples precasted in site; having several same moulds
construction that is provided by the precast factory for entire
can be observed in
applied? construction uses.
classroom toilet.
Figures
Backhoe
• Backhoe loaders are general-purpose tools and being displaced to some
extent by multiple specialist tools.
• For example, the excavator and the specialty front end loader with the rise
of the mini-excavator.
• In this project, backhoe crane was used as transportation of elements from
in-situ fabrication area to the construction area.
• Backhoe crane was used instead of other crane because it can move faster.
Question 5 Table 1
Description First visit - 29 April 2019 Second visit - 17 May 2019
i) Construction Construction-phase or work- For the first visit, the construction work On the second visit, the construction
work phase. phase, a typical building phase was completed from mobilization, work phase has move to the initial part
construction involves ground work and most of sub-structure of super structure work for first floor.
following sequence of work- work.
phase:
1. Mobilization,
2. Ground work,
3. Sub-Structure work,
4. Super Structure work,
5. Masonry work,
6. Services work,
7. Finishing work and
8. Completion.
ii) The In contracts for the provision of goods and services; and subject to express provisions
completion of to the contrary, performance under the contract is not complete until all of the obligations
the construction imposed by the contract have been satisfied. In other words the contract is not complete if
work. there are still works to be done or repairs to be made or documents to be provided.
Hollowcore.com.au. (2019). Hollowcore Concrete: Manufacture, design and install, precast hollow core concrete floor &
wall slabs to Melbourne. Retrieved from http://www.hollowcore.com.au/.
The Constructor. (2019). CONNECTIONS FOR PRECAST FLOOR SLABS. Retrieved from
https://theconstructor.org/concrete/connections-for-precast-floor-slabs/6332/.
Peikko.com. (2019). 3 ways to connect precast columns to foundation – choose yours!. Retrieved from
https://www.peikko.com/blog/3-ways-to-connect-precast-columns-to-foundation-choose-yours/.