UR9000 UMTS Dimension (V4.

16)
Contents

 UR9000 UMTS Hardware Introduction


 UR9000 UMTS Dimension Input
 UR9000 UMTS Hardware Dimension
 UR9000 Dimension Output

2
UR9000 UMTS Rack and Shelf Introduction

Slave
Sub-rack 1

ZXUR 9000 shelf (Front, Rear, Side view)

 ZXUR9000 Rack:600mm*800mm*2200mm(W*D*H)
Slave  Supports 3 shelves configuration including two
Sub-rack 2 types of sub-racks:
 Main sub-rack, service handling, O&M and clock function,
compulsory for configuration.

 Extension sub-rack, service handling, configured based


on capacity requirement, configured from 0-2.
Master  Each shelf has 28 slots, configuration including
Sub-rack front and rear plug-in shelf.
 Processing boards and O&M boards in front shelves.
 Interface boards and switching boards in rear shelves.

© ZTE All rights reserved 3


UR9000 UMTS Boards Overview

Interface Unit
10GE O&M Unit
EXGB1b Switch Unit
FE/GE
EGPB
UMP
IP E1 EGBS
EDTI
IP CSTM1
ESDTI
Processing Unit
ATM E1
EDTA
ATM CSTM1
ESDTA EGFS USP
ATM STM1
EAPB

In ZXUR 9000, process boards are responsible for the control plane and user plane
processing. Switch boards provide system control, data switch, system operation
and maintenance. Interface boards are responsible for the transmission interface
and protocol processing.

© ZTE All rights reserved 4


Processing and Switching Board
Processing Board
Physical Full Logical Function Description Conf. Principle
Boards Name Boards
Universal
Service 1+1 backup
USP1b Process CDR Fulfills service processing function and load sharing
board 1b

Universal OMP Overall management


Managemen
UMP1c t Process .1+1 backup
OMM Local O&M
board

Switching Board
Boards Full Name Function Description Conf. Principle
Enhanced GE Handles switching in BASE, namely control plane;
EGBS Base Switch provides switching channels for all intra-shelf and load sharing
board inter-shelf communication in control plane.
Handles switching in FABRIC, namely media
The Enhanced
plane; provides switching channels for all intra- load sharing
EGFS GE Fabric
shelf and inter-shelf communication in media
Switch board 1a
plane. Provides clock function.

© ZTE All rights reserved 5


Interface Board
Interface Board
Boards Full Name Function Description GSM or UMTS

EAPB Enhanced ATM Process Board Offer interface for ATM over STM-1 Apply to UMTS only

Enhanced Digital Trunk board


EDTA Offer interface for ATM over E1 Apply to UMTS only
ATM version

Enhanced SDH Digital Trunk Offer interface for ATM over


ESDTA Apply to UMTS only
board ATM version channelized STM-1

Enhanced Digital Trunk board


EDTI Offer interface for IP over E1 Apply to GSM and UMTS
IP version

Enhanced SDH Digital Trunk Offer interface for IP over


ESDTI Apply to GSM and UMTS
board IP version channelized STM-1

EGPB Enhanced GE Process Board Offer GE interfaces Apply to GSM and UMTS

Enhanced XGE Process Board


EXGB1b Offer 10GE interfaces Apply to GSM and UMTS
1b

Abundant interfaces for different networking requirements

© ZTE All rights reserved 6


Contents

 UR9000 UMTS Hardware Introduction


 UR9000 UMTS Dimension Input
 UR9000 UMTS Hardware Dimension
 UR9000 Dimension Output

7
Dimensioning Introduction

 The UR9000 Dimensioning follows the process shown in the


following figure Dimensioning
Methodology

Traffic Profile

Equipment
Configuration

Transmission Type C

Interface Bandwidth

Default Parameter

© ZTE All rights reserved 8


Traffic Profile
Parameters Provided by
Abbreviation Value
Operators
N_Erl
Number of Erl

Bidirectional throughput of PS
T_PS
service
Number of Cell N_Cell

N_Site
Number of NodeB

Number of Equivalent BHCA N_eBHCA


(K/Busy hour)

Number of Online User (D/F) N_DF

Number of Online User (P/D/F) N_PDF

© ZTE All rights reserved 9


Traffic Profile
Typical Traffic Model of Control Plane for UMTS
Control Plane Messages Recommended Weight
Category Unit
Overview Value in eBHCA
CS RAB Assignment in Busy Hour,
Times/BH
including RRC and Direct transfer
RAB 10.8/subscriber 100%
PS RAB assignment in Busy Hour,
Times/BH
including RRC and Direct Transfer
CS Handover in busy hour Times/BH
HO 19.6/subscriber 40%
PS handover in busy hour Times/BH
PS channel migration, including
CC Times/BH 30/subscriber 38%
DRBC
RRC connection times without
RAB assignment (e.g, SMS, LAU,
RRC Times/BH 3.8/subscriber 55%
RAU, Attach, Detach, Paging and
etc)
 Based on the above table, the eBHCA per user can be calculated:
 eBHCA per user =10.8×100% + 19.6×40% + 30×38% + 3.8×55%
= 32.2

© ZTE All rights reserved 10


Traffic Profile : Online User Number

 D/F online user


 The online user is in DCH (HS-DSCH included) or FACH status. The number of D/F
online user will be used as a limitation of process board dimensioning.
 D/F online user number = PS_Thrupt/ Average_data_rate
 Average data rate calculation only considers DCH and FACH online users, and D/F
online user number is noted as N_DF in this document formula.
 P/D/F online user
 The online user is in DCH (HS-DSCH included) or FACH, or PCH status. The
number of P/D/F online user will be used as a limitation of process board
dimensioning.
 P/D/F online user number is noted as N_PDF in this document formula.
 N_PDF = N_DF (PCH not activated)
 N_PDF = N_DF * 2.5 (PCH activated)
 ZTE recommends N_PDF equals to N_PDF times 2.5 if PCH activated based on live
network statistics.
© ZTE All rights reserved 11
Transmission type

Item Transmission Type

Iub interface

IuCS interface

IuPS interface

Iur interface

© ZTE All rights reserved 12


Default Parameter

Default Parameter Abbreviation Default Value


Soft Handover Ratio R_SHO 35%
Iur ratio vs Iub interface R_Iur 10%
Ratio of signaling vs service in Iub
R_Sig 6%
Service
Ratio of downlink service Rd 80%
Average data rate for D/F online V_Act
32Kbps
user
Average Payload Packet length of PL_DL
800Byte
PS in downlink
Average Payload Packet length for PL_UL
240Byte
PS in uplink
Transmission redundancy RelayT 20%
Process redundancy RelayP 10%

Voice activation factor VAF 0.5

© ZTE All rights reserved 13


Contents

 UR9000 UMTS Hardware Introduction


 UR9000 UMTS Dimension Input
 UR9000 UMTS Hardware Dimension
 Shelf Dimension
 Process Board Dimension
 Switch Board Dimension
 Interface Board Dimension

 UR9000 Dimension Output

14
Shelf Dimension

 Each shelf has 28 slots, 14 slots in front and 14 slots in rear.


Interface boards and switch boards locate at the rear and the
process boards locate at the front.
 N_Shelf = Roundup (Max (N_IB/ 10, N_PB/ 14), 0)
 In which:
 N_Shelf: Number of ZXUR 9000 shelf
 N_IB: Number of interface board
 N_PB: Number of process board
 There are 14 slots in rear, and 4 slots are mandatory for EGBS and
EGFS. Only 10 slots available for interface boards. And all slots in
front can be used for service board, and the O&M board is
included in the number of service board.
© ZTE All rights reserved 15
Contents

 UR9000 UMTS Hardware Introduction


 UR9000 UMTS Dimension Input
 UR9000 UMTS Hardware Dimension
 Shelf Dimension
 Process Board Dimension
 Switch Board Dimension
 Interface Board Dimension

 UR9000 Dimension Output

16
UMP1c

Board name Dimension princple

UMP1c 4 pieces per UR9000

 UMP1c provides global management processing and


maintenance function.
 UMP1c will take the place of UMP. The capacity of the two
boards is the same. They can be installed into one shelf,
but each cannot be used as the standby board for the
other one.
 The number of UMP1c is fixed for 4, 2 for OMM and 2 for
OMP. The slot number for OMM is 5-6, and for OMP is 7-8
in master shelf.
© ZTE All rights reserved 17
USP1b
N_USP=EVEN (MAX (N_USP_CU, N_USP_DU, N_PDF/ N_PDF_USP, N_Cell/
N_Cell_USP)/ (1-RelayP))
Index Code Capacity
CU Number N _CU_USP 1
DU Number N_ DU_USP 12
P/D/F user Number N_PDF_USP 22500
Cell N_Cell_USP 600

Code
Index Capacity

USP1b board is divided 1.CU eBHCA (K)


N_BHCA_CU
2400

into three parts: CU 150K (IP transmission of


Iub)
(Common Unit), DUc 2.DUc eBHCA (K) N_BHCA_DUc
105K (ATM transmission
(Dedicate Unit control of Iub)

plane), DUm (Dedicate PS Throughput (Mbps) T_PS_DUm 115

Unit media plane). 3.DUm


CS Erl N_Erl_DUm 515
P/D/F user Number N_PDF_DUm 2500
D/F user Number N_DF_DUm 910

© ZTE All rights reserved 18


USP1b
N_USP2a_CU= N_CU/ N_CU_USP* 2

N_CU= ROUNDUP (N_eBHCA/ N_eBHCA_CU, 0)

N_USP_DU=ROUNDUP ((N_ DUc+N_DUm)/ N_DU_USP, 0)

N_ DUc= ROUNDUP (N_eBHCA/ N_eBHCA_DUc, 0)


N_DUm= ROUNDUP (MAX (T_PS/ T_PS_DUm+ N_DF/ N_DF_DUm+ N_Erl/ N_Erl_DUm, N_PDF/
N_PDF_DUm), 0)

•T_PS: Bidirectional throughput of PS •N_DUc: Number of DUc


service •N_DUm: Number of DUm
•N_Erl: Number of CS Erl •RelayP: Process redundancy
•N_Cell: Number of cell
•N_eBHCA: Number of eBHCA
•N_PDF: Number of PCH, DCH and
FACH user
•N_DF: Number of DCH and FACH user
•N_USP: Number of USP
•N_USP_CU: Number of USP decided
by CU
•N_USP_DU: Number of USP decided
by DU
© ZTE All rights reserved 19
Calculation example

traffic model

Registered
Throughput of PS service NO.of No. of eBHCA
No. of Erl/RNC User
(Mbps)/RNC cell/RNC (K/BH)/RNC
(k)/RNC

123950 12395 3462 37650 1549

No. of eBHCA (K/BH) eBHCA per user

37650 24.3

© ZTE All rights reserved 20


Detail Calculation ( USP1b)

N_USP_CU
N_CU= ROUNDUP (N_eBHCA/ N_eBHCA_CU, 0)
=ROUNDUP (37650/2400,0) = 16

N_USP2a_CU= N_CU/ N_CU_USP2a* 2 = 16/2*2=16

N_USP_DU

N_USP2a_DU=ROUNDUP ((N_ DUc+N_DUm)/ N_DU_USP2a, 0)

N_ DUc= ROUNDUP (N_eBHCA/ N_eBHCA_DUc, 0) = ROUNDUP ( (37650/150),0) = 251

N_DF= PS_Thrupt/ Average_data_rate = 12395 / 0.2 = 61975

N_PDF= N_DF*2.5 = 61975*2.5 = 154938

N_DUm= ROUNDUP (MAX (T_PS/ T_PS_DUm+ N_DF/ N_DF_DUm+ N_Erl/ N_Erl_DUm,


N_PDF/ N_PDF_DUm), 0)
= Roundup ( MAX ((12395/115) +(61975/910) + (123950 / 515), (154938/2500)))
= ROUNDUP ( MAX (( 108+ 68+ 240) , (62) )
= Roundup ( MAX ( 416, 62))= 416
© ZTE All rights reserved 21
Detail Calculation ( USP1b)

 N_USP_DU

 N_USP2a_DU=ROUNDUP ((N_ DUc+N_DUm)/ N_DU_USP2a, 0)


=roundup (( 251+416)/24) = 28

 N_USP
 N_USP2a=EVEN (MAX (N_USP2a_CU, N_USP2a_DU, N_PDF/ N_PDF_USP2a, N_Cell/
N_Cell_USP2a)/ (1-RelayP))
 MAX( 16, 28, 154938/32500, 3462/900) = 28

© ZTE All rights reserved 22


Contents

 UR9000 UMTS Hardware Introduction


 UR9000 UMTS Dimension Input
 UR9000 UMTS Hardware Dimension
 Shelf Dimension
 Process Board Dimension
 Switch Board Dimension
 Interface Board Dimension

 UR9000 Dimension Output

23
EGBS and EGFS

 EGBS is the switch board of control plane, and 2 pieces EGBS


provide intra-shelf (52G) and inter-shelf (4G) control plane switch
channel. The slot number for EGBS is 19-20.
 EGFS is the switch board of user plane, and 2 pieces EGFS
provide intra-shelf (68G) and inter-shelf (20G) user plane switch
channel. The slot number for EGFS is 21-22.

Board name Dimension princple

EGBS 2 pieces per shelf. Load sharing

EGFS 2 pieces per shelf. Load sharing

© ZTE All rights reserved 24


Contents

 UR9000 UMTS Hardware Introduction


 UR9000 UMTS Dimension Input
 UR9000 UMTS Hardware Dimension
 Shelf Dimension
 Process Board Dimension
 Switch Board Dimension
 Interface Board Dimension

 UR9000 Dimension Output

25
Transmission Overhead

Abbreviation ATE IP PPP


Iu CS transmission C_IuCS
40% 66% 54%
overhead
Iu PS uplink C_IuPS_UL
25% 19% 12%
transmission overhead
Iu PS downlink C_IuPS_DL
21% 7% 4%
transmission overhead
Iub CS transmission C_IubCS
40% 62% 47%
overhead
Iub PS uplink C_IubPS_UL
25% 20% 13%
transmission overhead
Iub PS downlink C_IubPS_DL
21% 7% 4%
transmission overhead
Iub Uu Sig C_IubSig
60% 73% 60%
transmission overhead

© ZTE All rights reserved 26


Bandwidth of Iub Interface

 B_Iub_DL = (B_IubCS_Ui + B_IubPS_DL + B_IubSig_Site_Ui +


B_IubSig_Cell_Ui + B_IubSig_Uu_DL)
 B_IubCS_Ui=T_CS_Ui* (1+ R_SHO)/ (1- C_IubCS)
 T_CS_Ui= N_Erl* 12.2K* VAF
 B_IubPS_DL= T_PS* Rd/ (1- C_IubPS_DL)
 B_IubPS_UL= T_PS* Ru* (1+ R_SHO)/ (1- C_IubPS_UL)
 B_IubSig_Site_Ui= N_Site* (B_OMCB_Site+ B_NBAP_Site+ B_1588_Site)
 B_IubSig_Cell_Ui = N_Cell* V_Com
 B_IubSig_Uu_DL = (T_CS_Ui+ T_PS* Rd)* R_Sig* (1+ R_SHO)/ (1- C_IubSig)

 which:
 T_CS: Total throughput of CS
 N_Erl: Number of Erl for CS 12.2K
 Rd: Ratio of DL
 The formula has not yet considered the transmission redundancy (RelayT), same as the following
calculation of other interface.

© ZTE All rights reserved 27


Bandwidth of Iub Interface

 IUB bandwidth
 B_IubCS= T_CS* (1+ R_Iub)/ (1- CIubCS)
 T_CS_Ui= N_Erl* 12.2K* VAF = 123950*12.2*0.5 = 756095 kbps = 738.4 Mbps
 R_Iub = 0.2
 B_IUbCS = 738.4 * (1+0.2)/(1-0.62) = 2331.789 Mbps

 B_IubPS=B_IubPS_DL+ B_IubPS_UL= T_PS* Rd/ (1- C_IubPS_DL)+T_PS* Ru* (1+


R_SHO)/ (1- C_IubPS_UL)
 B_IubPS_DL = = T_PS* Rd/ (1- C_IubPS_DL) = 12395* 0.8 /(1-0.07) = 10662.37
Mbps
 B_IubPS_UL= T_PS* Ru* (1+ R_SHO)/ (1- C_IubPS_UL)= 12395*0.2*(1+0.35)/(1-0.2)
 B_IubPS_UL= 4183.313 Mbps
 B_IuBPS= 10662.37+4183.313= 14846 Mbps

© ZTE All rights reserved 28


Bandwidth of Iub Interface

 IUB bandwidth
 B_IubSig= Rsig * ( B_IubCS + B_IubPS ) = 0.06 (14846+ 2332 ) = 1030 Mbps

 B_Iub= (B_IubCS+ B_IubPS+ B_IubSig)/ (1- RelayT )


 B_Iub= ( 2332+14846+1030)/(1-0.1) = 20231.11 Mbps

© ZTE All rights reserved 29


Bandwidth of Iu Interface

 IuCS Interface
 B_IuCS_Ui=T_CS_Ui/ (1- C_IuCS)
 In which:

 B_IuCS: Bandwidth of Iu interface CS service

 IuPS Interface
 B_IuPS_DL= T_PS* Rd/ (1- C_IuPS_DL)
 B_IuPS_UL= T_PS* Ru/ (1- C_IuPS_UL)
 In which:
 B_IuPS_DL/ B_IuPS_UL: Bandwidth of Iu interface PS downlink/ uplink service

 B_IuCS= 123950*12.2*0.5/(1-0.66)= 2223809 kbps = 2172Mbps

© ZTE All rights reserved 30


Bandwidth of Iu Interface

B_IuPS_DL= T_PS* Rd/ (1- C_IuPS_DL) = 12395*0.8/(1-0.07)


B_IuPS_DL= 10662.37 Mbps
B_IuPS_UL= T_PS* Ru/ (1- C_IuPS_UL) = 12395*0.2/(1-0.19)
B_IuPS_UL= 3060.494 Mbps

B_IuPS= 10662.37+3060.5= 13722 Mbps

© ZTE All rights reserved 31


Bandwidth of Iur Interface

 B_Iur= B_Iub* R_Iur


 In which:
 B_Iur: Bandwidth of Iur interface

 The Iur interconnects different ZXUR 9000s in order to support


handover procedures between two different ZXUR 9000 service
areas. This specific handover is called drift handover (DHO). The
user data traffic and signaling traffic are transmitted over the Iur
interface. for practical project experiences, the transmission
bandwidth of Iur is set as 10% of Iub interface.

© ZTE All rights reserved 32


Interface Board Dimensioning
 EGPB board capactiy

Interface
PORTS BTS Capacity
Board
IubPS: 4500Mbps(UL+DL)/ 4500 Mbps(DL)
400 NodeB
EGPB 4* GE IuPS: 4800Mbps(DL+UL)/ 4800Mbps(DL)
(1588V2)
CS: 20000Erl

Index Abbreviation Capacity


IubPS Throughput (bidirectional) B_EGPB _IubPS_Bi 4500Mbps
Iub Signaling Throughput (bidirectional) B_EGPB _IubSig_Bi 600Mbps
IuPS Throughput (bidirectional) B_EGPB _IuPS_Bi 4800Mbps
CS12.2K Erl N_Erl_EGPB 20000
Site number (1588V2) N_Site_EGPB 400
Unidirectional Bandwidth B_EGPB_Ui 3000Mbps
10GE number N_GE_EGPB 4

© ZTE All rights reserved 33


Interface Board Dimensioning
 EGPB board capactiy
 EGPB boards can be used for all the interfaces:

 N_EGPB_Iub= ROUNDUP( Max( N_Site/ N_Site_EGPB, N_Erl* (1+


R_SHO)/ N_Erl_EGPB+ Max((B_IubPS_DL+ B_IubSig_Cell_Ui+
B_IubSig_Uu_DL)/ B_EGPB_Ui, B_IubPS_Bi/ B_EGPB_IubPS_Bi+
(B_IubSig_Cell_Bi+ B_IubSig_Uu_Bi)/ B_EGPB_IubSig_Bi ))/ (1-
RelayT), 0)
 N_EGPB_IuCS= ROUNDUP( N_Erl/ N_Erl_EGPB/ (1-RelayT), 0)
 N_EGPB_IuPS= ROUNDUP( Max( B_IuPS_DL/ B_EGPB, B_IuPS_Bi/
B_EGPB_IuPS_Bi)/ (1- RelayT), 0)

© ZTE All rights reserved 34


Interface Board Dimensioning
 EXGB1b board capactiy

Interface
PORTS BTS Capacity
Board
IubPS: 11200Mbps(UL+DL)/ 11200 Mbps(DL)
1000 NodeB
EXGB1b 2* 10GE IuPS: 12000Mbps(DL+UL)/ 12000Mbps(DL)
(1588V2)
CS: 50000Erl

Index Abbreviation Capacity


IubPS Throughput (bidirectional) B_EXGB1b _IubPS_Bi 11200Mbps
Iub Signaling Throughput (bidirectional) B_EXGB1b _IubSig_Bi 1500Mbps
IuPS Throughput (bidirectional) B_EXGB1b _IuPS_Bi 12000Mbps
CS12.2K Erl N_Erl_EXGB1b 50000
Site number (1588V2) N_Site_EXGB1b 1000
Unidirectional Bandwidth B_EXGB1b_Ui 3000Mbps
10GE number N_10GE_EXGB1b 2

© ZTE All rights reserved 35


Interface Board Dimensioning
 EXGB1b board capactiy
 EXGB1b boards can be used for all the interfaces:

 N_EXGB1b_Iub= ROUNDUP(Max(N_Site/ N_Site_EXGB1b, N_Erl*


(1+ R_SHO)/ N_Erl_EXGB1b+ Max((B_IubPS_DL+
B_IubSig_Cell_Ui+ B_IubSig_Uu_DL)/ B_EXGB1b_Ui, B_IubPS_Bi/
B_EXGB1b_IubPS_Bi , (B_IubSig_Cell_Bi+ B_IubSig_Uu_Bi)/
B_EXGB1b_IubSig_Bi ))/ (1- RelayT), 0)
 N_EXGB1b_IuCS= ROUNDUP(N_Erl/ N_Erl_EXGB1b/ (1- RelayT), 0)
 N_EXGB1b_IuPS= ROUNDUP(Max(B_IuPS_DL/ B_EXGB1b,
B_IuPS_Bi/ B_EXGB1b_IuPS_Bi)/ (1- RelayT), 0)

© ZTE All rights reserved 36


Interface Board Dimensioning(example)

 EXGB1b for Iub


 N_EXGB1b_Iub= ROUNDUP(Max(N_Site/ N_Site_EXGB1b, N_Erl*
(1+ R_SHO)/ N_Erl_EXGB1b+ Max((B_IubPS_DL+
B_IubSig_Cell_Ui+ B_IubSig_Uu_DL)/ B_EXGB1b_Ui, B_IubPS_Bi/
B_EXGB1b_IubPS_Bi , (B_IubSig_Cell_Bi+ B_IubSig_Uu_Bi)/
B_EXGB1b_IubSig_Bi ))/ (1- RelayT), 0)
 N_EXGB1b_Iub= ROUNDUP (Max(1154/1000,
123950*(1+0.35)/50000, 14846/ 11200, 1030/1500)/(1-0.1),0)
 N_EXGB1b_Iub = 4

© ZTE All rights reserved 37


Interface Board Dimensioning(example)

 EXGB1b for IUCS


 N_EXGB1b_IuCS= ROUNDUP(N_Erl/ N_Erl_EXGB1b/ (1-RelayT), 0)
 N_EXGB1a_IuCS= ROUNDUP(123950/50000/(1-0.1),0) =3

 N_EXGB1b_IuPS= ROUNDUP(Max(B_IuPS_DL/ B_EXGB1b,


B_IuPS_Bi/ B_EXGB1b_IuPS_Bi)/ (1-RelayT), 0)
 N_EXGB1a_IuPS= ROUNDUP(Max(10662.37 /3000, 13722
/12000)/(1-0.1),0) =4

© ZTE All rights reserved 38


Contents

 UR9000 UMTS Hardware Introduction


 UR9000 UMTS Dimension Input
 UR9000 UMTS Hardware Dimension
 Shelf Dimension
 Process Board Dimension
 Switch Board Dimension
 Interface Board Dimension

 UR9000 Dimension Output

39
Dimension Output

 According to the interface bandwidth and board capacity, get the


quality of the boards as the following:
 Number of boards per RNC

ZXUR9000 Configuration
Rack 1
Shelf 3
UMP1c 4
EGFS 6
EGPB 11
EGBS 6
USP1b 28

© ZTE All rights reserved 40


Thank you