Você está na página 1de 122

An NZGS 1 day short course

Ground movement control

Deep excavations

Antonio Gens
Technical University of Catalonia, Barcelona, Spain
Outline
 Introduction. Generation of ground movements by deep
excavations
 Empirical methods for estimating ground movements
 Methods for calculating ground movements
 Procedures for control and reduction of movements
 A case history
 Excavations with large movements: announcing failure?
 Conclusions
Excavation-induced ground movements

 The performance of an excavation with retaining walls


inevitably causes movements in the wall and surrounding
ground
 We will mainly focus on “normal” movements (i.e. on those
corresponding to an adequate construction not on those
arising from accidents)

 We will focus on movements associated basically to the


excavation process

 Tolerance concerning the acceptable deformation level (in


urban environment) has reduced significantly in recent years
 It means enhanced requirements for estimation and control of
movements
Deformation mechanisms
 Two basic deformation modes

Cantilever wall Propped wall Total displacements


Deformation mechanisms

 Surface horizontal displacements often ignored


 they are more difficult to measure (less experience)

Lion Yard excavation (Ng, 1998)


Deformation mechanisms
 Tension horizontal deformation contributes significantly to damage of
buildings and structures

Boscardin & Cording (1989) Burland (1998)


Deformation mechanisms
 Tension horizontal strains contribute significantly to the damage of
buildings and structures
 the majority of horizontal strains associated to deep excavations are tension strains
(more unfavourable than in the tunnelling case)
 the response of a building may depend significantly on its horizontal stiffness

Tension

Hor.
Tension Compression Tension

Vert.

Tension
Hor.

Vert.

Tunnels Excavations
Deformation mechanisms
 Factors that influence ground movements caused by excavations
 stress changes in the ground (due to excavation and construction)
 excavation size (depth and width)
 ground properties
 initial horizontal stresses in the ground
 hydraulic conditions and their variation
 wall and prop stiffness
 preloading of propos and anchors
 external loads
 construction procedure
 construction quality
 others...
Esquema de la presentación
 Introduction. Generation of ground movements by deep
excavations
 Empirical methods for estimating ground movements
 Methods for calculating ground movements
 Procedures for control and reduction of movements
 A case history
 Excavations with large movements: announcing failure?
 Conclusions
Empirical methods for evaluating movements

 Settlements

I: sands and soft clays, standard construction quality


II: soft and very soft clays
III: soft and very soft clays reaching below excavation depth

(Peck,1969)

 Curves obtained from excavations with sheet pile walls or soldier piles.
Reduced embedment
Empirical methods for evaluating movements

 Support: soldier pile lagging with struts

Medium to dense sand with interbedded stiff clay


Excavations en Washington D.C. (O´Rourke, 1976)
Empirical methods for evaluating movements

 Stiff clays, residual soils and sands (Clough & O’ Rourke, 1990)

Maximum lateral movement Maximum settlement


 The mean of maximum lateral movements measured around 0.2%
 The mean of maximum settlements measured around 0.15 %
 Large scatter, more in horizontal movements
 No significant differences between different wall types
Empirical methods for evaluating movements

 Soft clays (Mana & Clough, 1981)

Maximum horizontal movement

Bottom instability

 Movements associated to bottom instability are dominant when the factor of safety is
low
Empirical methods for evaluating movements

 Soft clays (Clough & O’ Rourke, 1990)

Maximum lateral movements Settlements

 System stiffness: (EI)/(wh4)


 Addenbrooke et al. (2000) defined system stiffness as (EI)/(wh5)
Empirical methods for evaluating movements

 Other databases

 Karlsrud (1986): Oslo soft clay


 Ou et al. (1993): Taipei soft clay
 Wong et al. (1997): Singapore
 Carder (1995): UK
 Fernie and Suckling (1996): UK
 Long (2001): 296 cases! (COST Action C-7)
Empirical methods for evaluating movements

 Long (2001) database. Excavations in medium and stiff soils

Maximum lateral movement Maximum settlement

 Large scatter
 Generally values smaller than those collected by Clough & O’Rourke (1990)
 Little influence of the type of bracing (props, anchors, top-down)
Empirical methods for evaluating movements

 Long (2001) database. Excavations in stiff and medium soils

h < 0.6H

System stiffness: (EIs4 (Clough & O’Rourke, 1990)

Maximum lateral movement

 System stiffness does not appear to be a critical parameter in these cases


Empirical methods for evaluating movements

 Long (2001) database. Excavations in stiff and medium soils

h < 0.6H

Flexibility number: (s5)/(EI) (Addenbrooke et al., 2000)

Maximum lateral movement

 System flexibility does not appear to be a critical parameter in these cases


Empirical methods for evaluating movements

 Long (2001) database. Excavations in soft soils

h > 0.6H
Low FS

Maximum lateral movement


Empirical methods for evaluating movements

 Long (2001) database. Excavations in soft soils

h > 0.6H
Low FS

Maximum lateral movement


Empirical methods for evaluating movements

 Long (2001) database: causes of excessive movements (with respect to the


majority of works in similar circumstances). 36 cases examined

 Excessive movements in cantilever mode: 12 cases


 Wall too flexible: 8 cases
 Creep of anchors/props: 3 cases
 Structural yielding: 2 cases
 Water inflow: 1 case
 Pile driving: 1 case
 Unknown: 9 cases
Empirical methods for evaluating movements

 Distribution of surface settlements (Clough & O’Rourke, 1990)

Sands
Empirical methods for evaluating movements

 Distribution of surface settlements (Clough & O’Rourke, 1990)

Stiff to hard clays


Empirical methods for evaluating movements

 Distribution of surface settlements (Clough & O’Rourke, 1990)

Chicago excavations (O´Rourke, 1976)


Empirical methods for evaluating movements

 Distribution of surface settlements (Clough & O’Rourke, 1990)

Soft to medium clays


Empirical methods for evaluating movements

 Distribution of surface settlements (Clough & O’Rourke, 1990)

Sands Stiff to hard clays

Soft to medium clays


Empirical methods for evaluating movements

 Distribution of surface settlements (Hsieh and Ou, 1998)


 They suggest that the shape of the settlement distribution is related to the type
of wall deformation

Spandrel
Ac (cantilever) type

Concave type

As
Empirical methods for evaluating movements

 Distribution of surface settlements (Hsieh and Ou, 1998)


 Estimation method

Spandrel (cantilever) type Concave type


Empirical methods for evaluating movements

 Distribution of surface settlements (Hsieh and Ou, 1998)


 Excavation in soft silty clay near the centre of the Taipei basin

Concave type
Empirical methods for evaluating movements

 Distribution of surface settlements (Hsieh and Ou, 1998)


 Excavation in silty clay for the Far-East Enterprise Center project in Taipei

Spandrel (cantilever) type


Empirical methods for evaluating movements

 Relationship between maximum vertical and lateral movement (Hsieh and


Ou, 1998)

Independent of settlement distribution type


Empirical methods for evaluating movements

 Settlements caused by the installation of concrete diaphragm wall (Clough &


O’Rourke, 1990

 Hong Kong, Charter Station: 50mm settlements for a 37m deep trench
 Normally 5 – 15 mm settlement in soft ground
Esquema de la presentación
 Introduction. Generation of ground movements by deep
excavations
 Empirical methods for estimating ground movements
 Methods for calculating ground movements
 Procedures for control and reduction of movements
 A case history
 Excavations with large movements: announcing failure?
 Conclusions
Methods for calculating ground movements

 Calculation methods
 Limit equilibrium (no information on ground movements)
 Diaphragm walls considered as elastic beams on springs (Winkler’s
model): RIDO, PARATIE, WALLOP…


i

 Simualtion using finite elements or finite differences: ABAQUS,


FLAC, PLAXIS
Methods for calculating ground movements

 Diaphragm wall considered as beams supported by springs


 Relatively simple, they require a limited number of hypotheses and data
 There is a wide experience of their use in practice
 They allo the introduction of some nonlinearity
 The subgrade modulus (a key parameter in this type of calculations) is a
parameter with serous limitations
 The global soil-interaction problem is not considered
 The horizontal movements of the wall are computed, ground movemnts
must be calculated separately
Methods for calculating ground movements

 Finite elements / Finite differences


 More complex, they require a larger number of hypotheses and decisions
(constitutive model, type of analysis, initial stresses, boundary conditions.
domain size…)
 There is less experience of use in practice (rapidly changing but…
 Some models require an information level not always available
 The allow the consideration of the global problem, they contribute to the
better understanding of deformation and failure mechanisms
 They provide a quite complete information on stresses, stains,
displacements
 They are progressively replacing simplified methods
 Validation/calibration with field measurements are essential
Methods for calculating ground movements
 Effect of constitutive model (Schwiger, pers. comm.)

30 m 2 - 3 x width of excavation
x 0.00m

GW = -3.00m below surface


excavation step 1 = - 4.80m
27°
z
excavation step 2 = - 9.30m 19.
27° 8m 8.0
m

excavation step 3 = -14.35m 23.


27° 3m
8.0
m
excavation step 4 = -16.80m
23.
-17.90m 8m
8.0
m

top of hydraulic barrier = -30.00m


-32.00m = base of diaphragm wall

0.8m
'='sand Specification for anchors:
2 - 3 x width of excavation

prestressed anchor force: 1. row: 768KN


2. row: 945KN
3. row: 980KN

distance of anchors: 1. row: 2.30m


2. row: 1.35m
> plane strain cross section area: 15 cm2
3. row: 1.35m

> wall "wished-in-place" Young's modulus E = 2.1 e8 kN/m2

sand
Methods for calculating ground movements
 Effect of constitutive model
 Mohr Coulomb vs. Hardening Soil

Mohr-Coulomb Hardening Soil


Methods for calculating ground movements
 Effect of constitutive model
 Mohr Coulomb vs. Hardening Soil
-60 -55 -50 -45 -40 -35 -30 -25 -20 -15 -10 -5 0
0

2
Hard. Soil
4

6
distance from wall [m]
8 0 10 20 30 40 50 60 70 80 90 100
30

vertical displacements of surface [mm]


10 25
20
12

depth below surface [m]


15

14 10
5
16 0
-5
18
-10 MC_1
20 -15 Poisson = 0.2
Poisson = 0.4
-20
Rinter = 0.5
22
-25 reference solution
-30 (Hardening Soil)
24

MC_1 26
Poisson = 0.2
Poisson = 0.4
Rinter = 0.5 28
reference solution
(Hardening Soil) 30

32
-60 -55 -50 -45 -40 -35 -30 -25 -20 -15 -10 -5 0

horizontal displacement [mm]


Methods for calculating ground movements

Wesminster Palace, London


Methods for calculating ground movements

 Clock Tower inclination


 Prediction: 1:8000
 Observation: - 1:8600

Westminster Palce, London


Methods for calculating ground movements

Horizontal and vertical displacements


Methods for calculating ground movements

 Mohr-Coulomb model (or any other that incorporates a linear


elastic component)
 Although reasonable wall lateral movements can be obtained,
computed settlements are often in error
 Excavation bottom heave are considerably overestimated
 The location of the lower boundary of the calculation domain has an
decisive influence on computed displacements
 In the case of excavations in soft soils, the effects are less marked
because the soil shear strength plays a dominant role
Methods for calculating ground movements
 Effect of the friction between soil and wall
-70 -65 -60 -55 -50 -45 -40 -35 -30 -25 -20 -15 -10 -5 0
0
R=0.5
2

4 R=0.8
6
distance from wall [m]
8
0 10 20 30 40 50 60 70 80 90 100
10

vertical displacement of surface [mm]


10
5
12 0

depth below surface [m]


-5
14
R=0.8
-10
16
-15
18
-20

-25
R=0.5
20

-30
22 reference solution
reference solution Rinter = 0.5
Rinter = 0.8 (final stage)
-35
Rinter = 0.5 (final stage) 24
-40
Rinter = 0.8 t_virt = 0.01
(final stage) 26
reference solution
(1. excavation stage)
28
Rinter = 0.5
(1. excavation stage)
Rinter = 0.8 t_virt = 0.01 30
(1. excavation stage)
32
-70 -65 -60 -55 -50 -45 -40 -35 -30 -25 -20 -15 -10 -5 0

horizontal displacement [mm]


Methods for calculating ground movements
 Benchmark (Schwiger, 2006)

 17 participants
x
30 m
0.00m
2 - 3 x width of excavation
 domain size
GW = -3.00m below surface

z
excavation step 1 = - 4.80m

excavation step 2 = - 9.30m


27°

19.
 structural elements, interfaces
27° 8m 8.0

 Constitutive models: Mohr-


m

excavation step 3 = -14.35m 23.


27° 3m
8.0
m
excavation step 4 = -16.80m
-17.90m
23.
8m
8.0
m
Coulomb, nonlinear
elastoplastic, hypoplastic
top of hydraulic barrier = -30.00m

 similar strength parameters, more


-32.00m = base of diaphragm wall

0.8m
'='sand Specification for anchors:
differences in stiffness parameters
2 - 3 x width of excavation

prestressed anchor force: 1. row: 768KN


2. row: 945KN
3. row: 980KN

distance of anchors: 1. row: 2.30m


2. row: 1.35m
3. row: 1.35m
cross section area: 15 cm2
Young's modulus E = 2.1 e8 kN/m2

sand
Methods for calculating ground movements
 Benchmark (Schwiger, 2006)
-250 -225 -200 -175 -150 -125 -100 -75 -50 -25 0 25 50
0

6 distance from wall [m]


0 10 20 30 40 50 60 70 80 90 100
8 50
B1
10
25 B2

vertical displacement of surface [mm]


0 B2a
12 B3

depth below surface [m]


-25
B3a
14 -50 B4
B5
-75
B1 B6
16
B2 -100 B7
B2a
-125 B8
18
B3 B9
B3a -150 B9a
B4 20
-175 B10
B5
B6
B11
22 -200 B12
B7
B8 -225 B13
B9 24 B14
B9a -250 B15
B10 B16
B11
26 -275
B17
B12 -300
B13 28
B14
B15
B16
B17
30
Surface settlements
32
-250 -225 -200 -175 -150 -125 -100 -75 -50 -25 0 25 50

horizontal displacement [mm]

Horizontal wall displacements


Esquema de la presentación
 Introduction. Generation of ground movements by deep
excavations
 Empirical methods for estimating ground movements
 Methods for calculating ground movements
 Procedures for control and reduction of movements
 A case history
 Excavations with large movements: announcing failure?
 Conclusions
Procedures for control and reduction of movements
 Taking adequate measures, it is possible to minimize movements even
in soft soils
 A recent example: Shanghai metro
d
h
17 - 23 m

Fill Level 1
Medium clay
Level 2
Soft silty clay Level 3
h = 15 – 21 m
Level 4

Level 5
Soft to medium clay
Final level
Compaction grouting

Diaphragm
Medium to stiff clay
wall

Bored pile
Stiff silty clay or silt

u max
v h %
Wong et al. (2005)
Procedures for control and reduction of movements

1. Increase stiffness of the retaining system (wall / bracing)


2. Early installation of bracing (especially the top one)
3. Attention to the contact between bracing and wall
4. Preloading the bracing
5. Avoid overexcavations
6. Embedding the wall in a stiff layer
7. Bracing below the maximum excavation depth
8. Impervious wall and water flow control
9. Compensation / correction grouting?
Procedures for control and reduction of movements
 Increase the stiffness of the retaining system
 increase wall stiffness (thickness, counterforts)
 increase bracing system (prop separation, prop stiffness)

System stiffness: (EI)/(ws4) (Clough & O’ Rourke, 1990)


Flexibility number: (s5)/(EI) (Addenbrooke et al., 2000)

Addenbrooke
et al. (2000)

Clough & O’ Rourke (1990)

 based on finite elements calculations


(nonlinear model with small strain stiffness)
Procedures for control and reduction of movements

 Influence of system stiffness


 Long (2001) database. Excavations in stiff and medium soils

h < 0.6H

Maximum lateral wall movement

 System stiffness does not appear to be a dominant factor in these cases


Procedures for control and reduction of movements

 Influence of system stiffness


 Long (2001) database. Excavations in soft soils

h > 0.6H
Low FOS

Maximum lateral movement

 There appears to be some influence of the system stiffness for low factors fo safety
Procedures for control and reduction of movements
 Early installation of bracing
 top-down construction

Buen Pastor Cathedral, San Sebastián, Spain


Procedures for control and reduction of movements
 Early installation of bracing
 top-down construction

Section Plan view

Buen Pastor Cathedral, San Sebastián, Spain


Procedures for control and reduction of movements
 Early installation of bracing
 top-down construction

Buen Pastor

Buen Pastor

Maximum lateral movement Maximum settlement

Buen Pastor Cathedral, San Sebastián, Spain


Procedures for control and reduction of movements
 Attention to the contact between bracing and wall

Lisbon Metro Circle Line, Singapore Metro


Procedures for control and reduction of movements
 Preloading the bracing (props and anchors)

Lisbon Metro Diagonal Mar, Barcelona

 prestressing reduces the movements caused by excavation


 prestressing does not increase the stiffness of the bracing
Procedures for control and reduction of movements
 Preloading of the bracing (props and anchors)
 anchors with a considerable free length exhibit a significant deformability

 Pile wall (65 cm diameter)


 Wall length: 80 m
 Max. excavation depth: 20 m
 Excavation in weathered granite

Science Museum, Barcelona


Procedures for control and reduction of movements
 Preloading of the bracing (props and anchors)
 anchors with a considerable free length exhibit a significant deformability

-10.000 0.000 10.000 20.000 30.000 40.000 50.000 60.000 70.000 80.000 90.000

70.000

60.000

50.000

40.000

30.000

Science
20.000 Museum
-10.000 0.000 10.000 20.000 30.000 40.000 50.000 60.000 70.000 80.000 90.000
10.000

70.000

60.000

50.000

40.000

30.000

20.000 Maximum lateral


10.000
displacement
Science Museum, Barcelona
Procedures for control and reduction of movements

 Bracing below the maximum excavation depth


 Procedures:
 Props placed in trenches or tunnels previously excavated
 Rows of barrettes (diaphragm walls segments)
 Jet grouting slabs or props
 Slabs of props constructed with deep soil mixing
 Slabs of props constructed with compaction grouting

 For bracing constructed using soil improvement techniques


 There is no consensus whether it is better to use slabs or thicker
discontinuous props
 Ground improvement techniques often produce brittle materials that
can lose strength if failure strain is exceeded
 Constructing the bracing may weaken the overlying soil
Procedures for control and reduction of movements
 Bracing below the maximum excavation depth
 Props placed in pre-excavated trenches or tunnels

Westminster Station
London

Barbican Arts Centre


London
Procedures for control and reduction of movements
 Bracing below the maximum excavation depth

Studenterlinden
Oslo

Diaphragm wall segments Lime-cement columns


Procedures for control and reduction of movements
 Bracing below the maximum excavation depth
 Jet grouting slabs or props

No jet
grouted slab

Lateral excavation movements


in Singapore (Shirlaw, 2006)

Race Course Road Metro


Singapore
Procedures for control and reduction of movements
 Impervious wall and water flow control
 The lack of water flow control or the changes in hydraulic conditions
cause sort and long term ground movements

Pumping

Sealing defects
Procedures for control and reduction of movements
 Amsterdam. North-South line
 Vijzelgracht station
 250 m long, 22 m wide, 31
m deep
 Top down construction
 1.2 m thick diaphragm
walls 45 m deep
 5.1 m long panels with
steel stop ends
Procedures for control and reduction of movements
 Vijzelgracht station, North-South line, Amsterdam
 Vijzelgracht, 26. Leakage due to a steel stop not being removed

(Korff et al., 2009)


Procedures for control and reduction of movements
 Vijzelgracht station, North-South line, Amsterdam
 Vijzelgracht, 26. Leakage due to a steel stop not being removed

 Settlement due to ground loss


 Tilt 1/78 and 1/184. Severe to very severe damage
(Korff et al., 2009)
Procedures for control and reduction of movements
 Vijzelgracht station, North-South line, Amsterdam
 Vijzelgracht, 4. Leakage due a large bentonite inclusion in the wall

 Settlement due to ground loss


 Tilt 1/38 and 1/70. Severe to very severe damage
(Korff et al., 2009)
Procedures for control and reduction of movements
 Compensation grouting
 Excavation in soft clay in Shanghai (Liu, 2003)
 Risk of affecting the wall (injection is performed after the props have been
installed)
 It is generally counterproductive to perform compensation grouting in soft
clays
Procedures for control and reduction of movements
 Vijzelgracht station, North-South line, Amsterdam
 Corrective grouting at Vijzelgracht, 22, 24, 26

(Bezuijen et al., 2009)


Procedures for control and reduction of movements
 Vijzelgracht station, North-South line, Amsterdam
 Corrective grouting at Vijzelgracht, 22, 24, 26

(Bezuijen et al., 2009)


Esquema de la presentación
 Introduction. Generation of ground movements by deep
excavations
 Empirical methods for estimating ground movements
 Methods for calculating ground movements
 Procedures for control and reduction of movements
 A case history
 Excavations with large movements: announcing failure?
 Conclusions
Procedures for control and reduction of movements

Prat de Llobregat cut-and-cover tunnel


Procedures for control and reduction of movements

Prat de Llobregat cut-and-cover tunnel


Procedures for control and reduction of movements

Prat de Llobregat cut-and-cover tunnel


What the papers say…
Procedures for control and reduction of movements
Desplazamientos verticales de la superficie del terreno
en calle M. Bertrand (pk 201+525)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
0.000

-0.005

Desplazamiento vertical [m]


-0.010

-0.015

-0.020

-0.025

-0.030

-0.035

Inclinometer Distancia al centro de la estructura del IB [m]

Computed settlements

Desplazamientos horizontales de la superficie del terreno


en calle M. Bertrand (pk 201+525)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
0.000

Desplazamiento horizontal [m]


-0.005
Fill
Relleno -0.010

Sands
Arenas -0.015

-0.020

-0.025

Limos
Silts y
and -0.030
clays
arcillas
-0.035
Distancia al centro de la estructura del IB [m]

Computed horizontal displacements


Procedures for control and reduction of movements
Procedures for control and reduction of movements
Desplazamientos verticales de la superficie del terreno
en calle M. Bertrand (pk 201+525)  Project 0
0,000
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
 No additional measures
-0,005
Desplazamiento vertical [m]

-0,010

-0,015

-0,020 actual

-0,025

-0,030 proyecto 0

-0,035
Distancia al centro de la estructura del IB [m]

Computed settlements

Desplazamientos horizontales de la superficie del terreno


en calle M. Bertrand (pk 201+525)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
0,000
Desplazamiento horizontal [m]

-0,005

-0,010

-0,015

-0,020 actual

-0,025

-0,030 proyecto 0

-0,035
Distancia al centro de la estructura del IB [m]

Computed horizontal displacements


Procedures for control and reduction of movements
 Possible additional measures
 Increase wall thickness
 Install additional props
 Increase wall length
 Embed the diaphragm wall in a stiff layer
 Install bracing below the maximum excavation depth (jet grouting)

 Cases examined
 Project 0: No additional measure
 Project 1: 1.20 m wall thickness (UIC2)
 Project 2: Project 1 + Temporary intermediate prop
 Project 3: Project 2 + wall depth to elevation -27
 Project 4: Project 2 + wall depth to elevation -34
 Project 5: Project 3 + bracing below the maximum excavation depth
Procedures for control and reduction of movements
Desplazamientos verticales de la superficie del terreno
en calle M. Bertrand (pk 201+525)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75  Project 0
0,000
 No additional measures
-0,005
 Project 1
Desplazamiento vertical [m]

-0,010

-0,015
 Wall thickness:1.2 m
actual
-0,020

-0,025 proyecto 0

-0,030
proyecto 1

-0,035
Distancia al centro de la estructura del IB [m]

Computed settlements

Desplazamientos horizontales de la superficie del terreno


en calle M. Bertrand (pk 201+525)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
0,000
Desplazamiento horizontal [m]

-0,005

-0,010

-0,015
actual
-0,020

-0,025 proyecto 0

-0,030
proyecto 1

-0,035
Distancia al centro de la estructura del IB [m]

Computed horizontal displacements


Procedures for control and reduction of movements
Desplazamientos verticales de la superficie del terreno
en calle M. Bertrand (pk 201+525)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75  Project 0
0,000
 No additional measures
-0,005
 Project 1
Desplazamiento vertical [m]

-0,010

-0,015
 Wall thickness: 1.2m
-0,020
actual
 Project 2
-0,025
proyecto 0
 Project 1 + additional prop
proyecto 1
-0,030
proyecto 2
-0,035
Distancia al centro de la estructura del IB [m]

Computed settlements

Desplazamientos horizontales de la superficie del terreno


en calle M. Bertrand (pk 201+525)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
0,000
Desplazamiento horizontal [m]

-0,005

-0,010

-0,015
actual
-0,020
proyecto 0
-0,025
proyecto 1
-0,030
proyecto 2
-0,035
Distancia al centro de la estructura del IB [m]

Computed horizontal displacements


Procedures for control and reduction of movements
Desplazamientos verticales de la superficie del terreno
en calle M. Bertrand (pk 201+525)  Project 0
 No additional measures
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
0,000

-0,005  Project 1
Desplazamiento vertical [m]

-0,010
 Wall thickness: 1.2m
 Project 2
-0,015
actual
-0,020
proyecto 0
 Project 1 + additional prop
-0,025 proyecto 1

-0,030
proyecto 2  Project 3
-0,035
proyecto 3
 Project 2 + wall to elevation -27
Distancia al centro de la estructura del IB [m]

Computed settlements
Desplazamientos horizontales de la superficie del terreno
en calle M. Bertrand (pk 201+525)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
0,000
Desplazamiento horizontal [m]

-0,005

-0,010

-0,015
actual
-0,020
proyecto 0

-0,025 proyecto 1

proyecto 2
-0,030
proyecto 3
-0,035
Distancia al centro de la estructura del IB [m]

Computed horizontal displacements


Procedures for control and reduction of movements
Desplazamientos verticales de la superficie del terreno
en calle M. Bertrand (pk 201+525)

0,000
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
 Project 0
-0,005
 No additional measures
Desplazamiento vertical [m]

-0,010  Project 1
-0,015
actual
 Wall thickness: 1.2m
-0,020
proyecto 0  Project 2
-0,025 proyecto 1
 Project 1 + additional prop
proyecto 2
-0,030

-0,035
proyecto 4  Project 4
Distancia al centro de la estructura del IB [m]  Project 2 + wall to elevation -34
Computed settlements

Desplazamientos horizontales de la superficie del terreno


en calle M. Bertrand (pk 201+525)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
0,000
Desplazamiento horizontal [m]

-0,005

-0,010

-0,015
actual
-0,020
proyecto 0

-0,025 proyecto 1

proyecto 2
-0,030
proyecto 4
-0,035
Distancia al centro de la estructura del IB [m]

Computed horizontal displacements


Procedures for control and reduction of movements
Desplazamientos verticales de la superficie del terreno
en calle M. Bertrand (pk 201+525)  Project 0
0,000
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75  No additional measures
-0,005  Project 1
Desplazamiento vertical [m]

-0,010  Wall thickness: 1.2m


-0,015
actual
 Project 2
-0,020 proyecto 0
 Project 1 + additional prop
proyecto 1

 Project 3
-0,025
proyecto 2

 Project 2 + wall to elevation -27


-0,030 proyecto 3

proyecto 5
-0,035
Distancia al centro de la estructura del IB [m]  Project 5
Computed settlements  Project 3 + Jet grouting prop
Desplazamientos horizontales de la superficie del terreno
en calle M. Bertrand (pk 201+525)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
0,000
Desplazamiento horizontal [m]

-0,005

-0,010

-0,015
actual
-0,020 proyecto 0
proyecto 1
-0,025
proyecto 2

-0,030 proyecto 3
proyecto 5
-0,035
Distancia al centro de la estructura del IB [m]

Computed horizontal displacements


Procedures for control and reduction of movements

Trial sections
Procedures for control and reduction of movements

Adopted construction procedure


Procedures for control and reduction of movements

Jet grouting props below maximum excavation depth


Procedures for control and reduction of movements

Fill

Sands

Silts and
clays

Finite element model

 “Hardening Soil model” for all layers


Procedures for control and reduction of movements
 Observations and model calibration. Ground inclinometers
Excavation Ground Excavation Ground Excavation Ground
10 10 10

5 5 5

0 0 0

-5 -5 -5

-10

Elevation (m)
-10 -10
Elevation (m)

-15 -15 -15

-20 -20 -20

-25 -25
-25

-30 -30
-30

-35 -35
-35

-40 -40
-40
-0,020 -0,010 0,000 0,010 0,020
-0,020 -0,010 0,000 0,010 0,020 -0,020 -0,010 0,000 0,010 0,020
Horizontal displacement (m)
Horizontal displacement (m) Horizontal displacement (m)

Jet-grouting Excavation from top Total excavation


to bottom slab
Procedures for control and reduction of movements

Maragall St. section


Procedures for control and reduction of movements
 Predictions of the calibrated model. Wall inclinometer

Excavation Ground Excavation Ground Excavation Ground


10 10 10

5 5 5

0 0 0

-5 -5 -5
Elevation (m)

-10 -10 -10

-15 -15 -15

-20 -20 -20

-25 -25 -25

-30 -30 -30

-35 -35 -35

-40 -40 -40


-0,020 -0,010 0,000 0,010 0,020 -0,020 -0,010 0,000 0,010 0,020 -0,020 -0,010 0,000 0,010 0,020

Horizontal displacement (m) Horizontal displacement (m) Horizontal displacement (m)

Excavation of first Excavation of Total excavation


tunnel second tunnel
Procedures for control and reduction of movements
 Estimation of potential damage
Displacements from phase 7 to phase 16
3.5

3.0

Severe to very
2.5
severe
Horizontal strain (‰)

2.0

1.5 Moderate

1.0

Slight

0.5 Very slight

Negligible
0.0
0.000 1.000 2.000 3.000 4.000 5.000 6.000 7.000

Angular distortion (‰) model M35_0

Excavation of the second tunnel


Procedures for control and reduction of movements
 Estimation of potential damage
Displacements from phase 0 to phase 16
3.5

3.0

Severe to very
2.5
severe
Horizontal strain (‰)

2.0

1.5 Moderate

1.0

Slight

0.5 Very slight

Negligible
0.0
0.000 1.000 2.000 3.000 4.000 5.000 6.000 7.000

Angular distortion (‰) model M35_1

Total excavation
Procedures for control and reduction of movements

Construction of tunnel UIC


Procedures for control and reduction of movements

7-06-2007 15-10-2007
Procedures for control and reduction of movements
 Observations Maragall St.

d=7m d=32m d=55m


Horizontal displacements
Esquema de la presentación
 Introduction. Generation of ground movements by deep
excavations
 Empirical methods for estimating ground movements
 Methods for calculating ground movements
 Procedures for control and reduction of movements
 A case history
 Excavations with large movements: announcing failure?
 Conclusions
Excavations with large movements: announcing failure?
 Diagonal Mar
 Surface: 40,000 m2
 Excavation depth: 20 m
 Excavation volume: 800,000 m3
 Water level: 1.5 m deep

330 m
Excavations with large movements: announcing failure?
 Diagonal Mar
Excavations with large movements: announcing failure?
 Diagonal Mar
Excavations with large movements: announcing failure?
 Diagonal Mar
Anchor head

- 4.50 m
Cantilever excavation
- 7.50 m
to -4.50 m
- 9.00 m

Excavation with
1 anchor

Wall horizontal displacements


Excavations with large movements: announcing failure?
 Diagonal Mar: numerical model
-90.000 -60.000 -30.000 0.000 30.000 60.000

60 m

Symmetry axis
0.000

Sands (upper aquifer)

Silty fine sands


(intermediate
layer)
-30.000

Gravel (lower aquifer)

-60.000

Still clayey silt

-90.000
Excavations with large movements: announcing failure?
 Diagonal Mar: calculations and observations
10 10

5 5

0 0

-5 -5

-10 -10

-15 -15

-20 -20
Elevation (m)

Elevation (m)
-25 -25

-30 -30

-35 -35

-40 -40

-45 -45

-50 -50

-55 -55

-60 -60

-65 -65

-70 -70
-0.20 -0.15 -0.10 -0.05 0.00 0.05 0.10 0.15 0.20 0.25 -0.20 -0.15 -0.10 -0.05 0.00 0.05 0.10 0.15 0.20 0.25

Horizontal displacement (m) Horizontal displacement (m)

model p75b i75p (04.11.97 to 19.01.98) model p75b i75p (04.11.97 to 17.07.98)

Cantilever excavation to -4.50 m Anchored excavation to -7.50 m

Horizontal wall displacements


Excavations with large movements: announcing failure?
 Diagonal Mar: numerical model

-50.000 -40.000 -30.000 -20.000 -10.000 0.000 10.000 20.000 30.000 40.000 50.000 60.000 -50.000 -40.000 -30.000 -20.000 -10.000 0.000 10.000 20.000 30.000 40.000 50.000 60.000

10.000 10.000

m m
0.000 0.000
0.200 0.200

0.180 0.180

-10.000 -10.000
0.160 0.160

0.140 0.140

-20.000 0.120 -20.000 0.120

0.100 0.100

0.080 0.080
-30.000 -30.000

0.060 0.060

0.040 0.040

-40.000 -40.000
0.020 0.020

0.000 0.000

-50.000 -0.020 -50.000 -0.020

-0.040 -0.040

-0.060 -0.060
-60.000 -60.000

-70.000 -70.000

Cantilever wall Anchored wall

Horizontal displacements contours


Excavations with large movements: announcing failure?
 Diagonal Mar: field observations

Surface crack 35 m away from the wall


Excavations with large movements: announcing failure?
 Diagonal Mar

Excavation trial
Excavations with large movements: announcing failure?
 Diagonal Mar

-100
-110
-120
-130
-140
-150
-160
-170
-180
-190
-200
-210
-220
-230
-240
-250
-260
-270
-10
-20
-30
-40
-50
-60
-70
-80
-90
0
2

-2

-4

-6

-8

-10

-12

-14

-16

Level (m)
-18

-20

-22

-24

-26
102 P75 Panel 19-ene-98 -2.0
-28 107 P75 Panel 20-feb-98 -5.0
406 P75 Panel 26-mar-98 -7.5
439 P75 Panel 18-dic-98 -7.5
-30 442 P75 Panel 15-ene-99 -7.5
475 P75 Panel 07-abr-99 -10.8
723 P75 Panel 07-jun-99 -10.8
-32 492 P75 Panel 18-ago-99 -10.8
731 P75 Panel 09-sep-99 -10.8
753 P75 Panel 31-may-00 -10.8
-34 755 P75 Panel 20-jun-00 -10.8
758 P75 Panel 21-jul-00 -10.8
-36 761 P75 Panel 25-ago-00 -10.8
762 P75 Panel 27-sep-00 -10.8
769 P75 Panel 16-oct-00 -14.0
-38 773 P75 Panel 25-oct-00 -14.0
775 P75 Panel 30-oct-00 -14.0
781 P75 Panel 22-nov-00 -14.0
-40 788 P75 Panel 20-dic-00 -14.0
789 P75 Panel 22-dic-00 -14.0
797 P75 Panel 26-ene-01 -14.0
-42 799 P75 Panel 02-feb-01 -14.0

Horizontal Displacement (mm)

Excavation trial
Excavations with large movements: announcing failure?
 Diagonal Mar: observations and calculations
10

-50.000 -40.000 -30.000 -20.000 -10.000 0.000 10.000 20.000 30.000 40.000 50.000 60.000 -5
10.000
-10

m -15
0.000
0.200
-20
0.180

Elevation (m)
-10.000
0.160
-25

0.140
-30
-20.000 0.120
-35
0.100

0.080 -40
-30.000
0.060
-45
0.040

-40.000 -50
0.020

0.000 -55

-50.000 -0.020
-60
-0.040

-65
-0.060
-60.000

-70
-0.20 -0.15 -0.10 -0.05 0.00 0.05 0.10 0.15 0.20 0.25
-70.000

Horizontal displacement (m)

model p75b i75p (04.11.97 to 07.04.99)

Anchored excavation to -18.0 m. Horizontal displacements


Excavations with large movements: announcing failure?
 Diagonal Mar

Maximum lateral wall displacements


Excavations with large movements: announcing failure?
 Diagonal Mar 0.000

Safety
Phase
factors -30.000

2 1.68

-60.000

8 3.09
Cantilever excavtion to -4.50 m. SF = 1.68

16 >1.88 0.000

19 1.99
-30.000

21 2.34

-60.000

Maximum excavtion. SF = 1.99


Excavations with large movements: announcing failure?
 Diagonal Mar
Excavations with large movements: announcing failure?
 Nicoll Highway excavation, Singapore

20/4/04
Excavations with large movements: announcing failure?
 Nicoll Highway excavation, Singapore

Fill
Kallang Formation
Old Alluvium
Excavations with large movements: announcing failure?
 Nicoll Highway excavation, Singapore
Excavations with large movements: announcing failure?
 Nicoll Highway excavation, Singapore
Excavations with large movements: announcing failure?
 Nicoll Highway excavation, Singapore

North wall South wall


Excavations with large movements: announcing failure?
 Nicoll Highway excavation, Singapore
South wall

North wall

Maximum lateral wall displacements


Excavations with large movements: announcing failure?
 Nicoll Highway excavation, Singapore

9
Excavations with large movements: announcing failure?
 Nicoll Highway excavation, Singapore
Excavations with large movements: announcing failure?
 Nicoll Highway excavation, Singapore

Strut 338-9 north wall

Strut 335-9 south wall


Summary & conclusions
 Performing a deep excavation inevitably produces movements in the retaining
walls and surrounding ground. The tolerance concerning acceptable
deformation levels (in urban conditions) has reduced significantly in recent
years
 The mechanisms of excavation-induced deformations are well identified.
Horizontal movements are mainly tension ones, more unfavourable than in the
tunnelling case
 There exists a wide documented experience providing useful information to
estimate excavation-induced ground movements and heir possible effects on
nearby structures
 Numerical analyses of excavations are becoming widespread. Those methods
provide a more complete perspective of the problem but must be validated and
calibrated if used for prediction purposes.
 There is a large range of construction procedures to reduce the excavation-
induced ground movements to the required levels.
 Although it is advisable to try to prevent large deformations of the retaining
walls, they are not necessarily signs of impending failure.

Você também pode gostar