Escolar Documentos
Profissional Documentos
Cultura Documentos
PHASE - I.A.P.
GOVERNMENT OF ANDHRA PRADESH
SoR 2012-2013
The above work has been administratively sanctioned for Rs.113.00 Lakhs. Vide G.O.Ms No.362
dated: 09-11-2012 of Panchayat raj and Rural Development Department under PMGSY-X in IAP Districts.
EXISTING FEATURES
A. Road surface
The proposed road is completely over existing formation.
The Road work estimate is prepared with the following provisions with MORD Specifications as per PMGSY
guidelines.
1 Clearingand grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees
of girth up to 300mm as per technical specification clause 201-1 of MORD.
2 Construction and widening of existing embankment with approved materails deposited at site materail obtained
from roadway cutting as per the requirement of Table 300-1 and 300-2 as per technical specification clause
301.5 of MORD.
3 Construction and widening of existing embankment with approved materails deposited at site obtained from
borrow pits with a lift upto 1.50mtrs, as per the requirement of Table 300-1 and 300-2 with a lead upto
1000mtrs and as per technical specification clause 301.5 of MORD.
4 Construction of granular sub base by providing well graded meterial (i.e Stone aggregates of 9.5 mm to 4.75
mm size Gravel of 66% and sand of size < 2.6mm @ 34% )in uniform layers of loose thickness of not more
than 225mm as per IRC technical specification clause 402 of MORD.
5 Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100
kN in stages to proper grade and camber grading 2 as per Technical Specification Clause 405
6 Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100
kN in stages to proper grade and camber Grading 3 as per Technical Specification Clause 405 with .40-45 mm
metal of HG with Machine Crushing (82 %) and 19-22.40 mm HG metal with Machine Crushing(18 %).
7 Providing and applying Prime Coat with butimen emulsion (Slow Setting- SS-1) as clause 502 of MORD.
8 Providing and applying Tack Coat with butimen emulsion (Rapid Setting- RS-1) using emulsion distributor as
clause 503 of MORD.
9 Providing and laying Open Graded Premix Carpet (OGPC) surfacing material of 20 mm thick composed of
13.20 mm to 5.60 mm size machine crushed hard blasted granite chips using bitumen of 60/70 grade as per
clause 508 of MORD.
10 Providing and laying bituminous liquid seal coat (Type A) comprising of a layer of bitumuneous binder followed
by a cover of stone chipping of grading as defined in table 500.16 of MOST at 0.09 cum/10sqm of chips to be
laid simultaneously along with the bitumunous course using 9.80 kgs of bitumen 60/70 grade as per technical
specification clause 510 of MORD.
11 Construction of Granualar shoulder by providing well graded meterial having soaked CBR not less than 15% s
per IRC technical specification clause 402 of MORD.
12 Actually 3 Nos of CD works are proposed in the approved DPR which is prepared with SoR 2011-12. Now this
estimate is prepared with current SoR2012-13. Due to increase the cost of estimate, no CD works are
proposed in this estimate.
13 Amount proposed for road furniture like KM, HM stones, Sign boards, logo boards, foundation & inaguration
stone.
14 The total length of the road is 2.800kms from 0/0 to 2/80 km there is existing formation . Side drain one side of
the road and C.C. Pavement is proposed at village portions 1/125 to 1/375 & 2/700 to 2/800, Now this estimate
is prepared with current SoR2012-13. Due to increase the cost of estimate,C.C. Pavement is proposed at
village portions 1/125 to 1/375 & 2/700 to 2/800, and one side drain is not proposed
The estimate is prepared with the SoR for the year 2012-2013.
PART - A
1 Road portion 2.800 KM 10171754
2 CD works 0 Nos 0
3 Cost of road furniture 21254
4 Construction of side drain 0 Mts 0
5 Add 5% VAT 10193008 509650
6 Add Seignorage charges 563805
7 Preparation of DPR Rs.10,000/- per KM 2.800 KM 28000
8 Add L.S. for rounding off 5537
PART - A TOTAL 11300000
PART - B
1 Maintenance of BT road per KM for 5 years 2.800 KM 420000
BT renewal coat at the end of 5th year 5.00
2 2.800 KM 1400000
lakhs per KM
PART - B TOTAL 1820000
PART A + PART B 13120000
1 2 3 4 5 6
Total 420000.00
7 Providing and applying tack coat with Bitumen emulsion (RS-1) using
emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the
prepared granular surfaces treated with primer & cleaned with Hydraulic
broom as per Technical Specification Clause 503 MORD,including
overhead charges & Contractors profit but excluding VAT.
10171754
TOTAL 0 0
Type of Cross Drainage work: 1 Vent RCC NP3 pipe culvert (1000mm dia)
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
4 Providing and laying reinforced cement concrete pipe NP3 for culverts on
first class bedding of granular material including fixing collar with
cement mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head wall and parapets. Tech
Specification Clause 1106 MORD ,including overhead charges &
Contractors profit but excluding VAT.
TOTAL : Rs 176407.00
Type of Cross Drainage work: 2 Vent RCC NP3 pipe culvert (1000mm dia)
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
4 Providing and laying reinforced cement concrete pipe NP3 for culverts on
first class bedding of granular material including fixing collar with
cement mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head wall and parapets. Tech
Specification Clause 1106 MORD ,including overhead charges &
Contractors profit but excluding VAT.
TOTAL : Rs 324040.00
Type of Cross Drainage work: 3 Vent RCC NP3 pipe culvert (1000mm dia)
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
4 Providing and laying reinforced cement concrete pipe NP3 for culverts on
first class bedding of granular material including fixing collar with
cement mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head wall and parapets. Tech
Specification Clause 1106 MORD ,including overhead charges &
Contractors profit but excluding VAT.
TOTAL : Rs 362689.00
Cum
Total: 191935
6 Reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm
metal mechanically mixed in substructure complete as per drawings and
technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204
MORD and 1500, 1700 & 2200 MORTH ,including overhead charges &
Contractors profit but excluding VAT upto 5m height.
7 Providing and laying pitching on slopes laid over prepared filter media as
per drawing and technical specifications Clause 1302 MORD / 2504
MORTH
for Approaches 1 x 2 5.00 6.50 0.225 14.63
14.63 1853.12 1Cum 27102
Sl. Description of item Nos L B D Qty in Rate Per Amount
No cum
8 Backfilling behind abutment, wing wall and return wall complete as per
drawings & technical specification Clause 1204.3.8 MORD / 710.14 of IRC,
78 & 2200 MORTH
for Approaches 1 x 2 20.00 6.50 2+0.3 299.00
2
299.00 467.45 1Cum 139768
Total: 1624325
1 2 3 4 5 6 7 8 9 10
1 Earthwork in excavation for structures as per drawing and technical
specifications Clause 305.1 including setting out, construction of shoring
and bracing, removal of stumps and other deleterious material and
disposal upto a lead of 50 m, dressing of sides and bottom and backfilling
in trenches with excavated suitable material as per Technical
Specification 305 MORD / 304 MORTH ,including overhead charges &
Contractors profit but excluding VAT.
1/125 to 1/375 1 0.00 1.00 0.500 175.000
TOTAL : Rs 0
25
SUB ESTIMATE FOR ROAD FURNITURE
21254
2 E/w for widening (Carted 297.19 Cum Earth 297.19 22.00 6538
earth)
3 GSB (35% metal & 65% 3240.90 Cum Gravel 2689.95 22.00 59179
gravel)
Metal 1458.41 50.00 72921
4 WBM Gr-II 0.00 Cum Metal & 0.00 50.00 0
stone dust
5 WBM Gr-III 594.68 Cum Metal 862.29 50.00 43115
6 OGPC 7929.20 Sqm Metal 214.09 50.00 10705
7 Seal coat 7929.20 Sqm Sand 47.575 40.00 1903
8 CC pavement 183.75 Sqm Metal 165.38 50.00 8269
Sand 82.69 40.00 3308
9 Shoulders (100% gravel) 1666.00 Cum Gravel 2015.86 22.00 44349
10 CD Works NIL
11 Side drain
E/W pipe culvert 175.00 Cum Earth 175.00 22.00 3850
M10 for foundations 0.00 Cum Metal 0.00 50.00 0
Sand 0.00 40.00 0
M15 for Body walls 0.00 Cum Metal 0.00 50.00 0
Sand 0.00 40.00 0
12 Road furniture
KM Stones 4 Each Metal 0.86 50.00 43
Sand 0.52 40.00 21
HM Stones 11 Each Metal 0.42 50.00 21
Sand 0.25 40.00 10
LOGO Board 2 Each Metal 0.40 50.00 20
Sand 0.24 40.00 10
Informatory Board 0 Each Metal 0.00 50.00 0
Sand 0.00 40.00 0
Sign Boards 5 Metal 0.50 50.00 25
Sand 0.30 40.00 12
Total Seignorage amount 563805
Index
S. No. Code Description of item Unit Qty Rate Amount
from roadway cutting and excavation from drain (not exceeding 0.6
m depth) and foundation of other structures graded and compacted to
meet requirement of Tables 300.1 and 300.2 as per Technical
Specification Clause 301.5 MORD/ 305 MORTH including overhead
& Contract profit but excluding VAT
Taking Out put = 100 Cum
a) Labour
Mate 260.00 0.00
Mazdoor day 0.52 250.00 130.00
b) Machinery
Dozer D-50 for spreading @ 200 cum per hour hour 0.50 1499.25 749.63
RATE ANALSIS AS PER MORD Data Sheet
Index
S. No. Code Description of item Unit Qty Rate Amount
Tractor with grader for grading @ 25 cum per hour 4.00 361.00 1444.00
hour
Water tanker 6kl capacity hour 2.00 372.00 744.00
Vibratory Roller 80-100 KN @100cum per hour hour 1.00 2384.90 2384.90
Total 5452.53
d) Add 18.00 % for Over head charges & Contractors profit 981.46
Rate for 100 cum 6433.99
Deduct VAT @4.00% -218.10
6215.89
Rate per cum 62.16
Tractor with Grader @ 25 cum per hour hour 4.00 361.00 1444.00
Water tanker 6 KL capacity hour 2.00 372.00 744.00
Vibratory Roller 80-100 KN @100cum per hour hour 1.00 2384.90 2384.90
Basic rate of formation of road with 13607.38
borrow soils per Cum
d) Add 18.00 % for Over head charges & Contractors profit 2449.32
16056.70
Deduct VAT @4.00% -544.29
15512.41
Rate per cum 155.12
Index
S. No. Code Description of item Unit Qty Rate Amount
Index
S. No. Code Description of item Unit Qty Rate Amount
Stone Screening
Type B 11.2 mm for Grading 2 @ 0.18 / 0.20 cum 86.40 526.25 45468.00
cum/10sqm
Binding Material @ 0.06 cum per 10 sqm for cum 28.80 260.00 7488.00
Grading 2 material
Basic rate for 360 Cum 378120.36
Rate per Cum 1050.33
RATE ANALSIS AS PER MORD Data Sheet
Index
S. No. Code Description of item Unit Qty Rate Amount
By Manual means
Taking out put = 360 cum
a) Labour
Mazdoor (Skilled) day 12.08 250.00 3020.00
Mazdoor (unskilled) day 250.00 215.00 53750.00
b) Machinery
Vibratory Roller 80-100 KN @60cum per hour hour 6.00 2384.90 14309.40
Index
S. No. Code Description of item Unit Qty Rate Amount
channel, laying and fixing of 125 mictron thick polythene film, wedges,
steel plates including levelling the formwork as per drawing),
spreading the concrete with sholvels, rakes, compacted using needle,
scareed and plate vibrators and finished in continuous operation
including provision of contraction and expansion, construction joints,
applying debonding strips, primer, sealant, dowel bars, near
approaches to bridge / culvert and construction joints, admixtures as
approved, curing of concrete slabs for 14- days, curing compound
(where specified) and water finishing to lines and grade as per
drawing and Technical Specification Clause 1501 MORD including
overhead charges & Contractors profit but excluding VAT.
Unit = cum
Taking output = 75cum (172.50 t)
(100x3.75 x 0.200)
a) Labour
Mason (1st class) day 5.00 315.00 1575.00
Mason (2nd class) day 5.00 285.00 1425.00
Mazdoor (unskilled) day 150.00 250.00 37500.00
Mazdoor(skilled) day 6.00 250.00 1500.00
Surveyor day 2.00 250.00 500.00
Mazdoor (semi-skilled) day 6.00 250.00 1500.00
Black smith for cutting of dowel bars including day 1.00 315.00 315.00
removal of burrs, fabrications & fixing of dowel
bars
b) Machinery
Concrete mixer 0.28/0.40 cum capacity ( 6 Hour 36.00 370.00 13320.00
mixers) with weight batcher and suitable
capacity calibrated water tank
Needle vibrator Hour 9.00 0.00 0.00
Screed vibrator Hour 9.00 42.00 378.00
Plate vibrator Hour 9.00 42.00 378.00
Water tanker 6 Kl. Capacity Hour 5.00 372.00 1860.00
Air compressor ( 1hour initial + 1 hour final) Hour 2.00 402.00 804.00
c) Material
(I) Crushed stone coarse aggregates, grading will
be as per clause 1501.2.4.1 (Table 1500.1) of
specifications @ 0.90 Cum/cum of concrete
Index
S. No. Code Description of item Unit Qty Rate Amount
Curing compound (if used) @ 0.33 litre per Litre 131.25 60.00 7875.00
sqm
Joint filler board 20mm thick as per IS:1838 sqm 3.00 750.00 2250.00
(4x3.75x0.200 = 3 sqm)
316760.49
(d) Form work @ 3% on (a+b+c) 9502.81
Cost for 75 cum = a+b+c+d 326263.30
Rate per Cum = (a+b+c+d+e)/75 4350.18
(e) Over head charges & contracots profit @ 783.03
18.00% on (a+b+c+d)
Deduct VAT @ 4% 4350.18 -174.01
Add for conveyance of metal Cum 0.90 1126.50 1013.85
Add for conveyance of sand Cum 0.45 74.60 33.57
Rate per cum 6006.63
9 Prime Coat
Low porosity
Providing and applying primer coat with bitumen emulsion (SS-1) on
RBR-BASC-1
Index
S. No. Code Description of item Unit Qty Rate Amount
Water tanker 6 kl capacity 1 trip per hour hour 0.500 372.00 186.00
c) Material
Bitumen emulsion (SS-1) @ 0.85 kg per sqm t 1.480 30667.26 45387.54
Water kl 3.000 0.00 0.00
Cost of 1750 sqm = a+b+c 47578.34
(d) Rate per sqm = (a+b+c)/1750 27.19
(e) d,e)Over head charges & contracots profit 4.89
@ 18.00% on (a+b+c+d)
Deduct VAT @ 4% 27.19 -1.09
Rate per sqm 31.00
10 Providing and applying tack coat with Bitumen emulsion (RS-1) using
emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the
RBR-BASC-2
Index
S. No. Code Description of item Unit Qty Rate Amount
a) Labour
Mate day 0.000 250.00 0.00
Mazdoor (Unskilled) day 10.000 250.00 2500.00
Mazdoor (Skilled) day 3.520 250.00 880.00
b) Machinery
HMP 30/40 t per hour hour 6.000 16626.00 99756.00
Electric generator set 125 KVA hour 6.000 1148.00 6888.00
Front end loader 1 cum bucket capacity hour 6.000 1431.00 8586.00
Tipper 5.5 cum - 10 t capacity hour 3.640 818.30 2978.61
Paver finisher hour 6.000 2664.00 15984.00
Three wheel 80-100 kN static roller hour 16.000 2384.90 38158.40
c) Material
Bitumen (S-65) @ 14.60 kg per 10 sqm t 5.840 36807.49 214955.74
Crushed stone chipping, 13.2 mm to 5.6 mm cum 108.000 808.33 87300.00
@ 0.27 cum per 10 sqm
d&e) Overheads & Contractors Profit 18.00% 477986.75 86037.62
Deduct 4% VAT -4.00% 477986.75 -19119.47
Cost of 4000 sqm = a+b+c+d+e 544904.90
Rate per sqm = (a+b+c+d+e)/4000 136.23
Add for conveyance of metal Cum 0.027 1126.50 30.42
Rate per Sqm 166.65
12 Seal Coat
Providing and laying seal coat sealing the voids in a bituminous
RBR-BASC-17
surface laid to the specified levels, grade and cross fall using Type A,
Excavation of structures:
RBR-FNDN-1
P.C.C grade M 10
Nominal mix 1:3:6
Unit = cum
(a) Material
Cement t 0.22 5000.00 1100.00
Coarse sand cum 0.45 335.00 150.75
40 mm aggregate cum 0.9 732.50 659.25
(CD WORKS) RATE ANALYSIS AS PER MORD
S. Index
Code Description of item Unit Qty Rate Amount
No.
Water kl 1.2 0.00 0.00
(b) Labour
Mate day 0 250.00 0.00
Mason (1st Class) day 0.10 315.00 31.50
Mazdoor (Unskilled) day 1.39 250.00 347.50
(c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity fitted hour 0.40 370.00 148.00
with water measuring device and preferably also with
load cell.
Water tanker 6 kl capacity hour 0.13 372.00 48.36
(d) Formwork @ 4% on cost of material, labour and 4.00% 2485.36 99.41
machinery (a+b+c)
2584.77
Overheads & Contractors Profit @18% 465.26
Deduct 4% VAT 2584.77 -103.39
Add for conveyance of sand cum 0.45 74.60 33.57
Add for conveyance of metal cum 0.90 1126.50 1013.85
Rate per cum = a+b+c+d+e+f 3994.06
Providing and laying reinforced cement concrete pipe NP3 for culverts on
first class bedding of granular material including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete
and masonry works in head wall and parapets. Tech Specification Clause
1106 MORD ,including overhead charges & Contractors profit but excluding
VAT.
Unit = m
Taking output = 7.5 m
34 (3 pipes of 2.5 m length each)
i) 1000 mm dia
a) Labour
Mate day 0.00 315.00 0.00
Mason (1st Class) day 0.25 315.00 78.75
Mazdoor (Unskilled) day 2.09 250.00 522.50
Laying & fixing of Pipes with colors in position including rm
lifting, aligning etc.,
b) Material
Sand at site cum 0.04 335.00 13.40
Cement at site t 0.03 5000.00 150.00
RCC pipe NP3 pipe including collar at site m 7.50 5966.40 44748.00
RCC pipe NP3 collar at site nos 2.00 932.88 1865.76
47378.41
Overheads & Contractors Profit @ 18% 8528.11
Deduct 4% VAT 47378.41 -1895.14
Cost for 7.5 m = a+b+c+d 54011.39
Rate per m = (a+b+c+d)/7.5 7201.52
Add for conveyance of sand cum 0.01 74.60 0.75
(CD WORKS) RATE ANALYSIS AS PER MORD
S. Index
Code Description of item Unit Qty Rate Amount
No.
Rate per m = 7202.00
Note : Water for concrete : A provision for cost of water may be added at 1.2
kl / 1 cum (including curing purpose) keeping the site conditions
Coarse Aggregate : Single grade nominal size can also be used instead of
graded metal, keeping the site conditions in view
For height upto 5 m
Unit = cum
P.C.C grade M 15
Nominal mix (1:2.5:5) using CC Mixer (MORD)
Unit = cum
(a) Material
Cement t 0.275 5000.00 1375.00
Coarse sand cum 0.480 335.00 160.80
40 mm aggregate cum 0.480 732.50 351.60
20 mm aggregate cum 0.240 1183.75 284.10
10 mm aggregate cum 0.080 811.25 64.90
(b) Labour
Mate day 0.000 250.00 0.00
Mason (1st Class) day 0.100 315.00 31.50
(CD WORKS) RATE ANALYSIS AS PER MORD
S. Index
Code Description of item Unit Qty Rate Amount
No.
Mazdoor (Unskilled) day 1.390 250.00 347.50
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 370.00 148.00
(d) Formwork @ 10% on cost of material, labour and 10.00% 2763.40 276.34
machinery (a+b+c)
3039.74
Overheads & Contractors Profit @ 18% 547.15
Deduct 4% VAT 3039.74 -121.59
Add for conveyance of sand cum 0.48 74.60 35.81
Add for conveyance of metal cum 0.80 1126.50 901.20
Rate per cum = a+b+c+d+e+f 4402.31
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day -
Painter (1st Class) day 3.00 350.00 1050.00
Painter Assistant day
Mazdoor (Unskilled) day 2.20 250.00 550.00
b) Material
Cement Primer as per specifications litre 3.00 90.00 270.00
Paint conforming to requirement of Clause 1701.3.8 litre 6.00 200.00 1200.00
18 RBR- Providing and laying pitching on slopes laid over prepared filter media as per
PTWK-5
drawing and technical specifications Clause 1302 MORD / 2504 MORTH
Stone/Boulder
Unit = cum
(a) Material
Stone boulder (25 kg minimum) /(MORTH - 40 kg) cum 1.00 110.00 110.00
Stone spalls of minimum 25 mm size cum 0.20 110.00 22.00
(b) Labour
Mate day 0.00 0.00
Mason 1st Class day 0.35 315.00 110.25
(CD WORKS) RATE ANALYSIS AS PER MORD
S. Index
Code Description of item Unit Qty Rate Amount
No.
Mazdoor (Unskilled) day 0.79 250.00 197.50
Overheads & Contractors Profit @18% 18.00% 439.75 79.16
Deduct 4% VAT -4.00% 439.75 -17.59
Add for conveyance of stone cum 1.20 1126.50 1351.80
Rate per cum = (a+b+c+d) 1853.12
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day -
Painter (1st Class) day 0.60 350.00 210.00
Mazdoor (Unskilled) day 0.65 250.00 162.50
b) Material
Epoxy primer / Red-oxide litre 0.60 110.00 66.00
Epoxy paint litre 1.25 200.00 250.00
Add @ 1 per cent on cost of material for scaffolding
wherever required
c&d) Overheads & Contractors Profit at 18% 688.50 123.93
Deduct 4% VAT 688.50 -27.54
(CD WORKS) RATE ANALYSIS AS PER MORD
S. Index
Code Description of item Unit Qty Rate Amount
No.
Cost for 10 sqm = a+b+c+d 784.89
Rate per sqm = (a+b+c+d)/10 78.49
21 Kilometre Stone
RBR- Reinforced cement concrete M15 grade kilometre stone/local stone of
TSRA-13
standard design as per IRC:8 fixing in position including painting and
printing, etc as per drawing and Technical Specification Clause 1703 MORD /
804 MORTH
as per Clause 1701.3.9 of MORD for Rural Roads of required shade and
colour supported and welded on 47 mm x 47 mm 12 SWG sheet tube firmly
fixed to the ground by means of properly designed foundation with M15
grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground
level as per drawings and Technical Specification Clause 1701 MORD
Unit = Each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.126 83.99 10.58
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.126 4402.31 554.69
(iii) Painting two coats including prime coat on
concrete surface with Epoxy Paint as per
specifications
As per item No. 9 of this Chapter sqm 0.46 78.49 36.10
(a) labour (For fixing at site)
Mate day -
Mazdoor (Unskilled) day 0.26 250.00 65.00
b) Material
Support of M.S. Sheet tube
(I) 47 mm x 47 mm x 12 SWG Sheet 3050 mm long kg 12.40 50.50 626.20
(II) Angle iron 50 x 50 x 6 mm for hold fast including 5% kg 1.06 50.50 53.53
wastage
Add 3% cost of MS Sheet tube 12 SWG and angle irons 3% 679.73 20.39
towards the cost of fabrication, drilling holes, nuts and
bolts etc.
(CD WORKS) RATE ANALYSIS AS PER MORD
S. Index
Code Description of item Unit Qty Rate Amount
No.
(III) 1.5 mm thick M.S. Sheet duly painted with stove sqm 0.36
enameled paint including lettering, signs, border,
message with reflective tape of engineering grade
required size, shade and colour as per Technical
Specifications
(vi) 600 mm x 600 mm square (0.36SQm X 0.0015m X Kg 4.24 40.00 169.60
7850/Kgcum)
(c) Machinery
Tractor with trolley hour 0.08 361.00 28.88
d&e) Overheads& Contractors Profit on a+b+c 18% 963.60 173.45
Deduct 4% VAT 963.60 -38.54
Rate per traffic sign = (i+ii+iii+a+b+c+d+e) 1699.87
Note : 1. Any one area of M.S. Sheet given at (i) to (viii) may be adopted as per site requirement and
in accordance with IRC-67.
2. The rate for excavation, cement concrete M-15, and painting may be taken from respective
Chapters.
3. The depth of foundation and quantity of cement in the foundation are indicative. These may
be increased for areas having higher wind velocities like in coastal area. This is applicable to
all road signs and direction boards.
Unit = each
Take Output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.126 83.99 10.58
Providing and fixing of typical informatory sign board with as per MORD
specifications and drawing. Three MS Plates of 1.6 mm thick, top and middle
plate duly welded with MS flat iron 25mm x 5m size on back on edges. The
lower plate will be we welded with MS angle irone frame of 25 mm x 25 mm x
5 mm. The angle iron frame of the lower most plate and flat iron frame of
middle plate will be welded to 2 nos. 75 mm x 75 mm of 12 SWG sheet tubes
RBR-TSRA-20
Unit = Each
Taking out put = one typical board
i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.252 83.99 21.17
(ii) Cement Concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.252 4402.31 1109.38
(iii) Painting on MS Steel tubes with primer and two
coats of epoxy paint
2x2.05x.30 = 1.23
1x1.10x188 = 0.21
As per item no. 9 of Chapter 10 sqm 1.80 78.49 141.28
(iv) Printing new letters and figures of any shade
with synthetic enamel paint black or any other
approved colour to give an even shade.
Logo Border 60x4x5 = 1200 per cm height per letter
Figure 60x10 = 600 per cm height per letter
(CD WORKS) RATE ANALYSIS AS PER MORD
S. Index
Code Description of item Unit Qty Rate Amount
No.
Middle plate words 28x5 = 140 per cm height per letter
Excavation of structures:
RBR-FNDN-1
NOTE:
ii 3 m to 6 m depth
Mechanical Means
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.00 260.00 0.00
Mazdoor (Unskilled) day 8.32 215.00 1788.80
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2009.50 12057.00
Add seignorage charges cum 210.00 0.00 0.00
(CD WORKS) RATE ANALYSIS AS PER MORD
S. Index
Code Description of item Unit Qty Rate Amount
No.
13845.80
Overheads & Contractors Profit @18% 2492.24
Deduct 4% VAT 13845.80 -553.83
Cost for 210 cum = a+b+c+d 15784.21
Rate per cum = (a+b+c+d)/210 75.16
Note : Cost of dewatering upto 5 per cent of (a+b) may be added, where
required. Assessment for dewatering shall be made as per site conditions.
Clause 305.3.9 MORD & 304 MORTH ,including overhead charges &
Contractors profit but excluding VAT.
Sand filling
Unit = cum
a) Labour
Mate day 0.00 250.00 0.00
Mazdoor (Unskilled) day 0.31 250.00 77.50
b) Material
Sand for filling cum 1.00 248.00 248.00
325.50
Overheads & Contractors Profit @18% 58.59
Deduct 4% VAT 325.50 -13.02
Add for conveyance of sand filling cum 1.00 74.60 74.60
Rate per cum = a+b+c+d 445.67
P.C.C grade M 10
Nominal mix 1:3:6
Unit = cum
(a) Material
Cement t 0.22 5000.00 1100.00
Coarse sand cum 0.45 335.00 150.75
40 mm aggregate cum 0.9 732.50 659.25
Water kl 1.2 0.00 0.00
(b) Labour
Mate day 0 250.00 0.00
Mason (1st Class) day 0.10 315.00 31.50
Mazdoor (Unskilled) day 1.39 250.00 347.50
(c) Machinery
(CD WORKS) RATE ANALYSIS AS PER MORD
S. Index
Code Description of item Unit Qty Rate Amount
No.
Mechanical concrete mixer 0.4/0.28 cum capacity fitted hour 0.40 370.00 148.00
with water measuring device and preferably also with
load cell.
Water tanker 6 kl capacity hour 0.13 372.00 48.36
(d) Formwork @ 4% on cost of material, labour and 4.00% 2485.36 99.41
machinery (a+b+c)
2584.77
Overheads & Contractors Profit @18% 465.26
Deduct 4% VAT 2584.77 -103.39
Add for conveyance of sand cum 0.45 74.60 33.57
Add for conveyance of metal cum 0.90 1126.50 1013.85
Rate per cum = a+b+c+d+e+f 3994.06
Providing and laying reinforced cement concrete pipe NP3 for culverts on
first class bedding of granular material including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete
and masonry works in head wall and parapets. Tech Specification Clause
1106 MORD ,including overhead charges & Contractors profit but excluding
VAT.
Unit = m
Taking output = 7.5 m
34 (3 pipes of 2.5 m length each)
i) 1000 mm dia
a) Labour
Mate day 0.00 315.00 0.00
Mason (1st Class) day 0.25 315.00 78.75
Mazdoor (Unskilled) day 2.09 250.00 522.50
Laying & fixing of Pipes with colors in position including rm
lifting, aligning etc.,
b) Material
Sand at site cum 0.04 335.00 13.40
Cement at site t 0.03 5000.00 150.00
RCC pipe NP3 pipe including collar at site m 7.50 5966.40 44748.00
RCC pipe NP3 collar at site nos 2.00 932.88 1865.76
47378.41
Overheads & Contractors Profit @ 18% 8528.11
Deduct 4% VAT 47378.41 -1895.14
Cost for 7.5 m = a+b+c+d 54011.39
Rate per m = (a+b+c+d)/7.5 7201.52
Add for conveyance of sand cum 0.01 74.60 0.75
Rate per m = 7202.00
RBR-SBST-5
S. Index
Code Description of item Unit Qty Rate Amount
No.
Note : Water for concrete : A provision for cost of water may be added at 1.2
kl / 1 cum (including curing purpose) keeping the site conditions
Coarse Aggregate : Single grade nominal size can also be used instead of
graded metal, keeping the site conditions in view
For height upto 5 m
Unit = cum
P.C.C grade M 15
Nominal mix (1:2.5:5) using CC Mixer (MORD)
Unit = cum
(a) Material
Cement t 0.275 5000.00 1375.00
Coarse sand cum 0.480 335.00 160.80
40 mm aggregate cum 0.480 732.50 351.60
20 mm aggregate cum 0.240 1183.75 284.10
10 mm aggregate cum 0.080 811.25 64.90
(b) Labour
Mate day 0.000 250.00 0.00
Mason (1st Class) day 0.100 315.00 31.50
Mazdoor (Unskilled) day 1.390 250.00 347.50
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 370.00 148.00
(d) Formwork @ 10% on cost of material, labour and 10.00% 2763.40 276.34
machinery (a+b+c)
3039.74
Overheads & Contractors Profit @ 18% 547.15
Deduct 4% VAT 3039.74 -121.59
Add for conveyance of sand cum 0.48 74.60 35.81
Add for conveyance of metal cum 0.80 1126.50 901.20
Rate per cum = a+b+c+d+e+f 4402.31
1002, 1005, 1010 & 1202 MORD / Sections 1600 & 2200 MORTH for Bars
below 36 mm dia including over laps and wastage, where they are not
welded ,including overhead charges & Contractors profit but excluding VAT.
Unit = t
(a) Material
HYSD bars including 5 per cent overlaps and wastage t 1.050 45500.00 47775.00
21 Reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm
metal mechanically mixed in substructure complete as per drawings and
RBR-SBST-5
technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204
MORD and 1500, 1700 & 2200 MORTH ,including overhead charges &
Contractors profit but excluding VAT upto 5m height.
22 RBR- Reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm
SBST-5
metal mechanically mixed in substructure complete as per drawings and
technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204
MORD and 1500, 1700 & 2200 MORTH ,including overhead charges &
Contractors profit but excluding VAT 5 to 10m height.
d) formwork
Add on cost of material, labour and machinery (a+b+c) 11.80% 3889.63 458.98
for Formwork
Add on cost of material, Labour and machinery excluding 1.80% 3889.63 70.01
formwork to cater for extra lift
4418.62
Overheads & Contractors Profit @18% 795.35
Deduct 4% VAT 4418.62 -176.74
Rate perm (a+b+c+d+e+f) 5037.23
Unit = t
(a) Material
HYSD bars including 5 per cent for laps and wastage t 1.05 45500.00 47775.00
23 Providing and laying reinforced cement concrete M25 grade (Design Mix)
using 20 & 10mm metal mechanically mixed in superstructure as per
RBR-SPST-1
drawing and technical specifications Clauses 800, 1205.4 and 1205.5 MORD
/ Sections 1500, 1600 & 1700 MORTH ,including overhead charges &
Contractors profit but excluding VAT upto 5m height.
25 RBR- Providing and laying reinforced cement concrete M25 grade (Design Mix)
SPST-1
using 20 & 10mm metal mechanically mixed in superstructure as per
drawing and technical specifications Clauses 800, 1205.4 and 1205.5 MORD
/ Sections 1500, 1600 & 1700 MORTH ,including overhead charges &
Contractors profit but excluding VAT 5 to 10m height.
Unit = cum
(a) Material
Cement t 0.407 5000.00 2035.00
Sand cum 0.45 335.00 150.75
20 mm aggregate cum 0.54 1183.75 639.23
10 mm aggregate cum 0.36 811.25 292.05
HYSD bar reinforcement including binding wire (Rate as t 0.075 51350.00 0.00
per item 13.2) except OH & CP
(b) Labour
Mate day 0.00 250.00 0.00
Mason (1st Class) day 0.10 315.00 31.50
Mazdoor (Unskilled) day 1.39 250.00 347.50
Mazdoor (Unskilled) for cleaning deck slab concrete day 0.15 250.00 37.50
surface
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 370.00 148.00
Generator 33 KVA. hour 0.40 664.00 265.60
(d) Formwork @ 3% of cost of concrete 3.00% 3681.53 110.45
4057.58
Overheads & Contractors Profit @18% 730.36
Deduct 4% VAT 4057.58 -162.30
Add for conveyance of sand cum 0.45 74.60 33.57
Add for conveyance of metal cum 0.90 1126.50 1013.85
Rate per cum = a+b+c+d+e+f 5673.06
Unit = Running m
Taking output = 4x12 m
Span = 48 m
(a) M 25 grade R.C.C.
No. of vertical posts = (6+1) 4 = 28 nos
Cross-sectional area of vertical post = 0.25x0.275 =
0.069 sqm
Concrete in vertical posts = 0.069x28x1.00 = 1.932 cum
(CD WORKS) RATE ANALYSIS AS PER MORD
S. Index
Code Description of item Unit Qty Rate Amount
No.
Hand rail in 3 tiers = 3x48 = 144 m
Cross-sectional area = 0.17x0.175 = 0.03 sqm
Concrete in hand rails = 0.03 x 144 = 4.32 cum
Total concrete = 1.932+4.32 = 6.252 cum cum 6.252 4744.23 29660.93
(b) HYSD bar reinforcement (Rate as per item 13.2) t 1.36 51350.00 69836.00
99496.93
Overheads & Contractors Profit @18% 17909.45
Deduct 4% VAT 117406.38 -4696.26
Cost for 48 m = (a+b+c+d) 112710.12
Rate per m = (a+b+c+d)/48 2348.13
28 RBR- P.C.C. M 15 ordinary grade (1:2.5:5) using 40,20 & 10mm metal
SPST-12
mechanically mixed leveling course below approach slab complete as per
drawing and technical specifications Clauses 800 and 1211 MORD & 2700
MORTH ,including overhead charges & Contractors profit but excluding VAT.
29 RBR- Reinforced Cement Concrete M 25 grade approach slab using 20 & 10mm
SPST-13
metal mechanically mixed excluding reinforcement complete as per drawing
and technical specifications Clauses 800 and 1211 MORD / 1500, 1600,
1700 & 2704 MORTH ,including overhead charges & Contractors profit but
excluding VAT.
Unit = cum
(a) Material
Reinforced cement concrete M 25 grade
Cement t 0.403 5000.00 2015.00
Coarse sand cum 0.45 335.00 150.75
20 mm aggregate cum 0.54 1183.75 639.23
10 mm aggregate cum 0.36 811.25 292.05
(b) Labour
Mate day 0 260.00 0.00
Mason (1st Class) day 0.1 285.00 28.50
Mazdoor (Unskilled) day 1.39 215.00 298.85
Bhisti day 260.00 0.00
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hr / cum 0.4 345.00 138.00
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day -
Painter (1st Class) day 3.00 350.00 1050.00
Painter Assistant day
Mazdoor (Unskilled) day 2.20 250.00 550.00
b) Material
Cement Primer as per specifications litre 3.00 90.00 270.00
Paint conforming to requirement of Clause 1701.3.8 litre 6.00 200.00 1200.00
27 RBR- Providing and laying pitching on slopes laid over prepared filter media as per
PTWK-5
drawing and technical specifications Clause 1302 MORD / 2504 MORTH
Stone/Boulder
Unit = cum
(a) Material
Stone boulder (25 kg minimum) /(MORTH - 40 kg) cum 1.00 110.00 110.00
Stone spalls of minimum 25 mm size cum 0.20 110.00 22.00
(b) Labour
Mate day 0.00 0.00
Mason 1st Class day 0.35 315.00 110.25
Mazdoor (Unskilled) day 0.79 250.00 197.50
(CD WORKS) RATE ANALYSIS AS PER MORD
S. Index
Code Description of item Unit Qty Rate Amount
No.
Overheads & Contractors Profit @18% 18.00% 439.75 79.16
Deduct 4% VAT -4.00% 439.75 -17.59
Add for conveyance of stone cum 1.20 1126.50 1351.80
Rate per cum = (a+b+c+d) 1853.12
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day -
Painter (1st Class) day 0.60 350.00 210.00
Mazdoor (Unskilled) day 0.65 250.00 162.50
b) Material
Epoxy primer / Red-oxide litre 0.60 110.00 66.00
Epoxy paint litre 1.25 200.00 250.00
Add @ 1 per cent on cost of material for scaffolding
wherever required
c&d) Overheads & Contractors Profit at 18% 688.50 123.93
Deduct 4% VAT 688.50 -27.54
Cost for 10 sqm = a+b+c+d 784.89
(CD WORKS) RATE ANALYSIS AS PER MORD
S. Index
Code Description of item Unit Qty Rate Amount
No.
Rate per sqm = (a+b+c+d)/10 78.49
30 Kilometre Stone
RBR- Reinforced cement concrete M15 grade kilometre stone/local stone of
TSRA-13
standard design as per IRC:8 fixing in position including painting and
printing, etc as per drawing and Technical Specification Clause 1703 MORD /
804 MORTH
as per Clause 1701.3.9 of MORD for Rural Roads of required shade and
colour supported and welded on 47 mm x 47 mm 12 SWG sheet tube firmly
fixed to the ground by means of properly designed foundation with M15
grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground
level as per drawings and Technical Specification Clause 1701 MORD
Unit = Each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.126 83.99 10.58
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.126 4402.31 554.69
(iii) Painting two coats including prime coat on
concrete surface with Epoxy Paint as per
specifications
As per item No. 9 of this Chapter sqm 0.46 78.49 36.10
(a) labour (For fixing at site)
Mate day -
Mazdoor (Unskilled) day 0.26 250.00 65.00
b) Material
Support of M.S. Sheet tube
(I) 47 mm x 47 mm x 12 SWG Sheet 3050 mm long kg 12.40 50.50 626.20
(II) Angle iron 50 x 50 x 6 mm for hold fast including 5% kg 1.06 50.50 53.53
wastage
Add 3% cost of MS Sheet tube 12 SWG and angle irons 3% 679.73 20.39
towards the cost of fabrication, drilling holes, nuts and
bolts etc.
(III) 1.5 mm thick M.S. Sheet duly painted with stove sqm 0.36
enameled paint including lettering, signs, border,
message with reflective tape of engineering grade
required size, shade and colour as per Technical
Specifications
(vi) 600 mm x 600 mm square (0.36SQm X 0.0015m X Kg 4.24 40.00 169.60
7850/Kgcum)
(c) Machinery
Tractor with trolley hour 0.08 361.00 28.88
d&e) Overheads& Contractors Profit on a+b+c 18% 963.60 173.45
Deduct 4% VAT 963.60 -38.54
Rate per traffic sign = (i+ii+iii+a+b+c+d+e) 1699.87
Note : 1. Any one area of M.S. Sheet given at (i) to (viii) may be adopted as per site requirement and
in accordance with IRC-67.
2. The rate for excavation, cement concrete M-15, and painting may be taken from respective
Chapters.
3. The depth of foundation and quantity of cement in the foundation are indicative. These may
be increased for areas having higher wind velocities like in coastal area. This is applicable to
all road signs and direction boards.
Unit = each
Take Output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.126 83.99 10.58
Unit = Each
Taking out put = one typical board
i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.252 83.99 21.17
(ii) Cement Concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.252 4402.31 1109.38
(iii) Painting on MS Steel tubes with primer and two
coats of epoxy paint
2x2.05x.30 = 1.23
1x1.10x188 = 0.21
As per item no. 9 of Chapter 10 sqm 1.80 78.49 141.28
(iv) Printing new letters and figures of any shade
with synthetic enamel paint black or any other
approved colour to give an even shade.
Logo Border 60x4x5 = 1200 per cm height per letter
Figure 60x10 = 600 per cm height per letter
Middle plate words 28x5 = 140 per cm height per letter
Total
Add 25% Deduc
Convey- amount Conveay
Sl. Lead in Initial Blasting extra for t for
Description Quarry ance excluding nce Remarks
No. KM Cost charges machine stocki
Charges conveyan chargs
crushing ng
ce
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
1 60-63 mm IRC HBG Metal x 113.00 378.00 1126.50 70.00 448.00 1126.50 831.17 53-26
2 50-55 mm IRC HBG Metal x 113.00 410.00 1126.50 70.00 480.00 1126.50 981.00 26-4.75
3 40-45 mm IRC HBG Metal x 113.00 530.00 1126.50 70.00 600.00 1126.50 723.13 9.5-4.75
4 25-27 mm IRC HBG Metal x 113.00 874.00 1126.50 70.00 944.00 1126.50
5 19-22 mm IRC HBG Metal x 113.00 998.00 1126.50 70.00 1068.00 1126.50
6 40-45 mm IRC HBG Metal x 113.00 530.00 1126.50 70.00 132.50 732.50 1126.50
7 25-27 mm IRC HBG Metal x 113.00 874.00 1126.50 70.00 218.50 1162.50 1126.50 1070.83
8 19-22 mm IRC HBG Metal x 113.00 998.00 1126.50 70.00 249.50 1317.50 1126.50 832.00 WBMM
9 12-14 mm IRC HBG Metal x 113.00 727.00 1126.50 70.00 181.75 978.75 1126.50 895.00 WMM
10 9.5-11.2 mm for Grading 2 x 113.00 593.00 1126.50 70.00 148.25 811.25 1126.50 723.13 WMM
11 5-7 mm IRC HBG Metal x 113.00 452.00 1126.50 70.00 113.00 635.00 1126.50 808.33 OGPC
12 2.36 mm HBG metal x 113.00 278.00 1126.50 70.00 69.50 417.50 1126.50 526.25 Gr.II
13 40mm HBG chips-SS5 x 113.00 530.00 1126.50 70.00 132.50 732.50 1126.50
14 20mm HBG chips-SS5 x 113.00 891.00 1126.50 70.00 222.75 1183.75 1126.50
15 12mm HBG chips-SS5 x 113.00 727.00 1126.50 70.00 181.75 978.75 1126.50
16 10mm HBG chips-SS5 x 113.00 593.00 1126.50 70.00 148.25 811.25 1126.50
17 2.36mm Below metal x 113.00 260.00 1126.50 260.00 1126.50
18 Rough stone x 113.00 160.00 1126.50 -50 110.00 1126.50
19 Gravel Local 9.00 75.00 119.40 75.00 119.40
19 Sand for mortar y 5.00 335.00 74.60 335.00 74.60
20 Sand for Filling Local 5.00 248.00 74.60 248.00 74.60
21 Bitumen 60/70 Vizag 1020.00 32449.51 3060.00 1297.98 36807.49
Total
Add 25% Deduc
Convey- amount Conveay
Sl. Lead in Initial Blasting extra for t for
Description Quarry ance excluding nce Remarks
No. KM Cost charges machine stocki
Charges conveyan chargs
crushing ng
ce
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
22 Bitumen emulsion (SS-1) Vizag 1020.00 26545.44 3060.00 1061.82 30667.26
23 Bitumen emulsion (RS-1) Vizag 1020.00 27254.84 3060.00 1090.19 31405.03
24 Cement Local 5000.00 5000.00
25 Steel 45500.00 45500.00
26 1000mm dia pipes (Part-I) Z 63.00 5170 589.60 206.8 5966.40
27 700mm dia pipes (Part-I) Z 63.00 2512 311.63 100.48 2924.11
28 600mm dia pipes (Part-I) Z 63.00 2020 271.48 80.8 2372.28
29 1000mm dia collars (Part-I) Z 63.00 897 35.88 932.88
30 700mm dia collars (Part-I) Z 63.00 486 19.44 505.44
31 600mm dia collars (Part-I) Z 63.00 360 14.4 374.40
Certified that the above leads are correct and nearest to the work site to best of my knowledge
The stone quarry is of blasting type. Hence provided blasting charges
Sl. No. Sl. No. Description Units Qty Rate (Rs) Amount
as per (Rs.)
MORD
SDB for
A.Rural
CONSTRUCTION ACTIVITIES
1 Roads Clearing and grubbing road land including Cum 4800.00 1.86 / 8928
uprooting wild vegetation, grass, bushes, S
shrubs, saplings and trees of girth upto 300 q
mm, removal of stumps of such trees cut m
earlier and disposal of unserviceable
materials and stacking of serviceable
material to be used or auctioned, upto a lead
of 1000 m including removal and disposal of
top organic soil not exceeding 150 mm in
thickness as per Technical Specification
Clause 201 MORD/MORTH including
overhead & Contractor profit but excluding
VAT .
WBM Grade-III
5 Providing, laying, spreading and compacting 594.68 3113.59 / 1851590
stone aggregates of specific sizes to water C
bound macadam specification including u
spreading in uniform thickness, hand m
packing, rolling with smooth wheel roller 80-
100 kN in stages to proper grade and
camber, applying and brooming, stone
screening to fill-up the interstices of coarse
aggregate, watering and compacting to the
required density Grading 3 as per Technical
Specification Clause 405 MORD/ MORTH 404.
For compacted thickness of 75 mm,
including overhead charges & Contractor
profit, But excluding VAT
Prime Coat
6 Providing and applying primer coat with 7929.20 31.00 / 245805
bitumen emulsion (SS-1) on prepared surface 1
of granular base including cleaning of road
surface and spraying primer at the rate of s
0.70-1.0 kg/sqm using mechanical means as q
per Technical Specification Clause 502 MORD m
(for use on Wet mix macadam & WBM)
,including overhead charges & Contractors
profit but excluding VAT.
Tack Coat
7 Providing and applying tack coat with 7929.20 11.13 / 88252
Bitumen emulsion (RS-1) using emulsion 1
distributor at the rate of 0.25 to 0.30 kg per
sqm on the prepared granular surfaces s
treated with primer & cleaned with Hydraulic q
broom as per Technical Specification Clause m
503 MORD,including overhead charges &
Contractors profit but excluding VAT.
Seal Coat
9 Providing and laying seal coat sealing the 7929.20 48.69 / 386073
voids in a bituminous surface laid to the 1
specified levels, grade and cross fall using
Type A, Type B and Type C as per Technical s
Specification Clause 510 MORD. (using Three q
wheel 80-100 kN static roller) m
CC pavement
10 Construction of un-reinforced, dowel jointed 183.75 6006.63 / 1103717
at expansion and construction joint only, C
plain cement concrete pavement, thickness u
as per design, over a prepared sub base, m
with 43 grade cement or any other type as
per Clause 1501.2.2 M30 (Grade), coarse
and fine aggregates conforming to IS : 383,
maximum in a concrete mixer of not less
than 0.2 cum capacity and appropeiate
weigh batcher using approved mix design,
laid in approved fixed side formwork (steel
channel, laying and fixing of 125 mictron
thick polythene film, wedges, steel plates
including levelling the formwork as per
drawing), spreading the concrete with
sholvels, rakes, compacted using needle,
scareed and plate vibrators and finished in
continuous operation including provision of
contraction and expansion, construction
joints, applying debonding strips, primer,
sealant, dowel bars, near approaches to
bridge / culvert and construction joints,
admixtures as approved, curing of concrete
slabs for 14- days, curing compound (where
specified) and water finishing to lines and
grade as per drawing and Technical
Specification Clause 1501 MORD including
overhead charges & Contractors profit but
excluding VAT.
Gravel Shoulders
11 Construction of gravel shoulders by 1666.00 352.45 / 587180
providing well graded material, spreading in C
uniform layers with motor grader on u
prepared surface, mixing by mix in place m
method with rotavator at OMC, and
compacting with three wheel 80-100 kN
static roller / Vibratory Roller 80-100 kN
capacity to achieve the desired density,
complete as per Technical Specification
Clause 402 MORD, including overhead
charges & Contractor profit, But excluding
VAT
12 1000mm dia RCC NP3 pipe culvert 1vent 0 0
13 Cost of road furniture 21254
14 Construction of side drain 0
15 Add 4% VAT 509650
16 Add Seignorage charges 563805
17 Preparation of DPR Rs.13,500/- per KM 28000
18 Add L.S. for rounding of 5537
TOTAL 11300000
B. MAINTENANCE ACTIVITIES (YEAR WISE)
1 Provision for 1st year Maintanance 2.80 5.00% 7500 21000
2 Provision for 2nd year Maintanance 2.80 10.00% 15000 42000
3 Provision for 3rd year Maintanance 2.80 15.00% 22500 63000
4 Provision for 4th year Maintanance 2.80 30.00% 45000 126000
5 Provision for 5th year Maintanance 2.80 40.00% 60000 168000
TOTAL 420000
Note:
1.
Rate Analysis shall cover all the items such as Site Clearance, Earthwork, Drainage, Granular
Sub Base, & Surface Course, CD works, Traffic Signs, PMGSY Board & Logo& Maintenance
2. activities
Where local material e used at site and the specif cations a rate analysis are not found in BOS
&SDB. for Rural Roads .the analysis & nomenclature of the item can be suitably used based on
other standards such as PWD Schedule or Rate or assessment based on field observation.
3. Completed items rates including feadfor carriage of materials should be shown
MACHINERY
1 AC Pipe 100 mm dia class 1 188.00
2 Dozer D 80 1881.00 2398.80
3 Paver Finisher Hydrostatic with sensor control 100 2530.00 2664.00
TPH
4 Air Compressor 370.00 402.00
5 Dozer D 50 1081.19 1499.25
6 Electric generator set 125 KVA 1090.00 1148.00
7 Plate Compactor 40.00 42.00
8 Binding Wire 55.00 65.00
9 Emulsion Pressure Distributor 690.00 748.00
10 Smooth wheeled roller 8 tonne 844.40 920.60
11 Tractor with trolley 345.00 361.00
12 Bitumen boiler oil fired 170.00 182.00
13 Front end loader 1320.00 1431.00
14 Stone Boulder 90
15 Tractor with grader 345.00 361.00
16 Vibratory Roller 80-100 1886.90 2384.90
17 Bitumen boiler oil fired, capacity1000 lts fitted with 170.00 182.00
spray set
18 Generator 250 KVA 1550.00 1609.00
19 Tipper 5.5cum 696.40 818.30
20 Tractor with rotavator 345.00 367.00
21 Water Tanker 6 KL 345.00 372.00
22 Bitumen Pressure Distributor 940.00 1016.00
23 Generator 35 KVA 620.00 664.00
24 Wet Mix Plant 1320.00 1431.00
25 Concrete mixer 0.28/0.40 cum 345.00 370.00
26 HMP 40/60 15525.00 16626.00
27 Hydraulic broom @ 1250 290.00 310.00
28 Hydraulic Chip Spreader 2070.00 2232.00
29 Hydraulic Excavator 2009.50 2600.30
30 Joint Filler 540.00
31 Mild Steel - 7/2011 41000.00
32 Mortor Grader 2600.00 2797.00
Paint 184
Painter 300 350.00
Binding Wire 300 65.00
1499.25