Você está na página 1de 15

Safety Science 76 (2015) 175–189

Contents lists available at ScienceDirect

Safety Science
journal homepage: www.elsevier.com/locate/ssci

Development and validation of three-step risk assessment method


for ship recycling sector
Karin Garmer a, Hasse Sjöström a, Anand M. Hiremath b, Atit K. Tilwankar b, George Kinigalakis c,
Shyam R. Asolekar b,c,⇑
a
Swerea IVF AB, Mölndal, Sweden
b
Centre for Environmental Science and Engineering, Indian Institute of Technology Bombay, Mumbai, India
c
Medimetal Limited, Uppsala, Sweden

a r t i c l e i n f o a b s t r a c t

Article history: Disposal of end-of-life vessels in an environmentally sound and safe manner is a major challenge today.
Received 10 April 2014 In the present study an attempt has been made to develop a three-step risk assessment method – which
Received in revised form 5 January 2015 offers a systematic pedagogic approach for the ‘‘analysis team’’ comprising of production managers,
Accepted 12 February 2015
safety officers, safety supervisors and the designated expert monitor to reduce risks and enhance safety
Available online 24 March 2015
at ship recycling yards. The three-step risk assessment was performed in 35 ship recycling yards through
questionnaire surveys and door-to-door communication. Thus, 35 data sets from field personnel at the
Keywords:
ship recycling yards, each data set with 8 risk indexes (4 risk indexes each, before and after implementing
Ship recycling
Ship breaking
corrective actions) were collected. In addition, 9 data sets were collected to document the perceptions of
Risk assessment experts. In all, a total of 44 data sets were collected and used to validate the risk assessment method.
End-of-life vessels Validation of the three-step method, essentially addresses the differences (or similarities) in ‘‘perception
Occupational risk of risk’’ by several health, safety and environment (HSE) managers who volunteered for the risk assess-
ment exercise. In order to validate the risk assessment method, three validation protocols were devel-
oped. Consistency check on the data sets was also performed and it was found that the relationship
was linear with the slope close to unity. The example illustrating the application of Three Step Method
in identifying and minimizing risks provides clear understanding for the users of this method.
Evidently, the three-step risk assessment method developed in this research appeared to give consistent
results in a variety of scenarios of validation.
Ó 2015 Elsevier Ltd. All rights reserved.

1. Introduction Disposal of end-of-life vessels was initially started by USA and


some of the European Countries by dismantling them (typically
As per the estimation of International Maritime Organization, as referred to as ‘‘ship breaking’’) as an on-shore business in the fifties
on 2010, nearly 150 nations contributed to total 104,304 world (Demaria, 2010). Eventually, the industry moved to developing
fleet of merchant ships; which were involved in international trad- countries on account of the availability of cheaper labor as well as
ing activity. Vessels or ships are typically disposed off after a life potential market for recycled scrap steel and sheet metal – which
span of 22–25 years (Deshpande et al., 2012). Typically, the need helped in improving economics of the ship breaking sector in
for disposal of ship arises under two circumstances. (1) When India, China, Bangladesh and Pakistan. Most of the ocean-going ships
the cost of operation of the ship becomes greater than the revenue are owned and operated for trade by the developed countries; but,
which it can generate. (2) When the age or market conditions make the dismantling and recycling of the ships at the end-of-life is being
a ship less profitable to operate for the owner (Asolekar, 2012; transferred to the developing countries (Deshpande et al., 2012).
Moen, 2008). Ship recycling industry can be considered as a green industry as
almost entire product can be reused, recycled and resold (Sarraf
et al., 2010). It provides direct employment to approximately
50,000 workers in Bangladesh and 60,000 in India. It provides indi-
⇑ Corresponding author at: Centre for Environmental Science and Engineering, rect employment to approximately half a million workers in both
Indian Institute of Technology Bombay, Mumbai, India. Tel.: +91 22 2576 7867; fax:
countries combined. Country like Bangladesh is scarce in terms of
+91 22 2572 3480.
Iron ore. Hence, it relies heavily on imported steel scrap for steel
E-mail address: asolekar@iitb.ac.in (S.R. Asolekar).

http://dx.doi.org/10.1016/j.ssci.2015.02.007
0925-7535/Ó 2015 Elsevier Ltd. All rights reserved.
176 K. Garmer et al. / Safety Science 76 (2015) 175–189

production to meet the infrastructural and other requirements of housekeeping, by infusing low-risk and high efficiency technolo-
the country. In the year 2004, Bangladesh ship breaking industry gies and practices (Asolekar, 2012). It appears as though the ship
contributed as high as 80% to the country’s steel production dismantlers in Alang, India are keen to improve themselves and
(Kumar, 2009). Though a minuscule fraction when compared to want to co-operate with the national and international regulatory
India’s steel production, the ship recycling sector typically recovers agencies by promoting safe and environmentally sound ship recy-
nearly 100% steel from dismantling of obsolete ships and thereby cling in India (Deshpande et al., 2012). While every nation would
reduces the load on iron ore mining and ultimately avoids CO2 emis- like to have their obsolete vessels dismantled, it would be expected
sions to that extent (Hiremath et al., 2014). Thus, the contribution of that the ship breaking activity does not create polluted yards and
this industry has been significant in the context of India in terms of deteriorate beaches and coastal marine environment further.
employment generation as well as production of steel with nearly This awareness and sense of responsibility has led the interna-
2.8 times smaller CO2 emissions (findings from a project on life cycle tional stakeholders including European Commission (EC) as well
assessment of steel recycling sector in progress). as International Maritime Organization (IMO) to initiate dialog
Nearly half of the world’s ships are being dismantled and among stakeholders and forge international convention and leg-
recycled on India’s west coast along the Alang-Sosiya beach in islation, respectively. Recently, the European Parliament passed
the Gulf of Cambay; located around 56 km from the City of Legislation entitled ‘‘Ship Recycling Regulation’’ published in
Bhavnagar, State of Gujarat. The Alang-Sosiya cluster has around Official Journal of the European Union on 10 December, 2013. Also,
160 active ship recycling yards spanning along its 12 km stretch the draft of ‘‘Hong Kong Convention’’ (HKC), which addresses ‘‘Safe
of beach. The natural energy of tidal motion combined with some and Environmentally Sound Recycling of Ships’’, is being negotiated
unique geographical and coastal conditions at Alang (e.g. a slope of multilaterally since May 2009 at the IMO Headquarters in London.
10 degree of sandy beach and the relatively quiet ocean) has Highpoints of the Draft HKC include its insistence on prepara-
helped the Alang-Sosiya cluster to achieve the objective of disman- tion of yard-specific Ship Recycling Facility Plan (SRFP) as well as
tling obsolete vessels for the past three decades without undertak- ship-specific Ship Recycling Plan (SRP). Unfortunately, there exists
ing any ecologically damaging construction or installing expensive inadequate guidance on preparation of these plans in the present
equipments (Reddy et al., 2003; Asolekar, 2006; Mahindrakar et al., draft of HKC – which may eventually be seen as the striking lim-
2008; Demaria, 2010; Asolekar and Hiremath, 2012;Deshpande itation of the draft. This deficiency can be remediated by devising
et al., 2012; Hiremath et al., 2014). Cumulatively, more than one a methodology to identify and assess the occupational risks posed
ship of nearly 30,000 LDT (light displacement tonnage) is broken during a variety of activities during the course of ship breaking and
every day in the Alang ship recycling yards. It is the destiny of recycling.
ocean-going ships like oil tankers, bulk carriers, general cargo, con- It is well known that the high-tech industrial sectors (e.g. air-
tainer ships and others like passenger and cruise ships Reddy et al. craft and automobile manufacturing, electronics hardware manu-
(2004). In 1990s the Alang-Sosiya established as largest ship recy- facturing, sophisticated machines and tool manufacturing,
cling yard in the World (Demaria, 2010). manufacturing of high value drugs and pharmaceutical, dyestuff,
There is a downside of the ship recycling sector involving expo- paints and pigments, textiles, printing, etc.) as well as high-tech
sure to workers to a wide range of hazards and conditions that cause service and logistics sectors (e.g. aviation, freight transportation,
a large number of near accidents resulting in ill health, injuries and logistics and ground-activity management, operation and mainte-
fatal accidents as well as contamination of surrounding environ- nance of commercial vessels through trained marine crew, ware-
ment Deshpande et al. (2012). For example, nearly 70% of the total house management, just-on-time delivery of spare parts as well
workforce is involved in the plate cutting activity at the yards using as finish products, etc.) have successfully employed risk assess-
the Oxy-LPG torches for plate cutting (Deshpande et al., 2013). ment approach for improving occupational health and safety as
Most of the labor force for breaking obsolete ships is hired on a well as minimization of risk of accidents during the industrial
short-term contract-basis and the entire operations are labor activity. These industrial sectors have organized educated work-
intensive. The work place is temporary and workers are not highly force, nearly continuous operations and often are governed by pro-
educated (Asolekar, 2006). To add to the complexity, the ship dis- fessional management systems. Such sectors are known for their
mantling yards in India is typically small and 150–200 workers work diligent data collection on consumption of resources, occupational
on site and inside beached ship in almost every plot (Deshpande safety and health and workplace accidents.
et al., 2013). The unsafe work place conditions, episodic nature of Thus, it is not a coincidence that the high-tech modern indus-
the ship dismantling and recycling activity, use of unskilled and trial sectors worldwide are engaged in implementation of strate-
uneducated workers for executing manual activities in ship gies to minimize work place accidents and enhance occupational
breaking as well as proximity of work place to ocean-land interface safety through periodic assessments of occupational risks. It will
(beach, dry dock, floating platform, etc.) are some of the complicat- be interesting to notice such efforts in those industrial sectors, as
ing factors associated with modernization of the ship dismantling referenced by Kurt-Karakus (2012) (indoor air pollution), Ehsani
and recycling sector throughout the world (Asolekar, 2012). et al. (2013), Bahn (2013), Zhang et al. (2014), Grant and Hinze
However, the unorganized sector and several not-so-profitable (2014), Hardison et al. (2014), Amponsah-Tawiah et al. (2014),
small and medium industries have not been able to adopt risk- Fruhen and Keith (2014), Mohammadzadeh Moghaddam and
based approaches for improvement in the third world – especially Ayati (2014) (workplace accidents), Li et al. (2012), Cao et al.
those sectors which are known for ‘‘risky’’ activities and hazard- (2014) (heavy metals exposure in industry), etc.
prone work environment. To complicate the process of up grada- The literature review was carried out to discover whether any
tion and improvement further, a variety of social, cultural and previously recorded methods were available to carry out risk
enabling legal as well as bureaucratic strength may not be there assessment specifically suitable for a low-tech and labor intensive
in the first place. In such instances, neither relevant data on work- sector such as ship recycling industry. Interestingly, none among
place accidents and exposure are available nor there exist intra- the European Commission, International Labor Organization
sectoral collaboration to crank-start the process of improvement. (ILO), the International Maritime Organization (IMO), British
For example, the sector of ship dismantling is warming up in the Standard (BS), Occupational Health and Safety Assessment
recent times to initiating the process of change. (OHSAS) 18001:2007, and International Organization for
Clearly, there is a room to improve such workplace through Standardization (ISO) 30000:2008 has provided useful guidelines.
implementation of modern management techniques, better Ideally we wanted to use the approach of applying conventional
K. Garmer et al. / Safety Science 76 (2015) 175–189 177

tools including what-if-analyses, check-lists, HAZOP, fault tree and though the ‘‘external experts’’ would assess the risks more profi-
event tree methods to identify, classify and index risks and hazards ciently; there may not be sufficient number of such experts to go
in ship dismantling sector (Harms-Ringdahl, 2001; Ayyub, 2003; around in the yards in Alang. As a result, management personnel
Reniers et al., 2005; Marhavilas et al., 2009, 2011). Our initial in the yards had to be motivated and placed on the locus of self-
efforts did not bear any fruits because there was no data available help for implementing the spirit and substance of articulated
and the sector happens to be informal and truly managed with the strategies. To achieve this, therefore, it was envisaged that the risk
help of traditional work-force, underdeveloped management prac- assessment protocol will be developed and implemented with the
tices and primitive technologies. help of the ‘‘analysis team’’ comprising of production managers,
In summary, in light of the efforts initiated by the EC and IMO to safety officers, safety supervisors and the designated expert moni-
make the ship dismantling sector ‘‘safer and greener’’; there is a tor. The real benefit related to risk reduction and enhancement of
need for a tool that can, on the one hand, help the sector to assess health and safety conditions would be accrued by those yards
the threats to work place safety and environment through a sim- which embark on self-improvement exercise by undertaking
pler and manageable risk assessment exercise. On the other hand, repeated cycles of risk assessment followed by implementation
the risk assessment tool should be devised in a manner so that it of the interventions in the Alang ship dismantling yards. Fig. 1
will help the sector in development of corrective measures through depicts the steps involved in the ‘‘three-steps of the risk assess-
repeated applications of the risk assessment exercise. Thus, the ment method’’.
present study focuses on the development and validation of a risk It is to be noted that the three-step risk assessment method
assessment method which is easy to understand and implement in covers all aspects of ship breaking and recycling starting from pre-
the ship recycling sector. The specific objectives were as follows: paration of the safe plan for ship recycling leading to the quan-
tification of risks and further suggesting the measures to
(1) to develop the three-step method to identify the occupa- minimize those risks. The details of the three-steps are discussed
tional risks in ship recycling activities, below.
(2) to conduct the risk assessment exercise in ship recycling
yards in Alang using the three-step method and 2.1. First step: Preparation of plan for safe ship recycling
(3) to validate the three-step risk assessment method using the
data from the Alang ship recycling yards. When the ship recycler takes over the vessel from a ship owner,
a certificate for dismantling should be available. It must be secured
In order to address these objectives, observations were made in that the basic requirements for ship recycling are fulfilled as well
ship dismantling yards situated along the Alang-Sosiya Beach. as work activities and job tasks are identified (Document A) and
These observations were used in conjunction with an elaborate also safe ship recycling plan should be prepared (Document B).
consultation process and a novel three-step risk assessment Based on the literature review, important requirements stipulated
method was developed and employed in the yards for assessing in various applicable international and national regulations and
the risk of some critical steps. Further, the proposed three-step conventions including the MARPOL (1973), ILO (2004), IMO
assessment method was validated using the primary data specifi- (2009), EU Ship Recycling Legislation (2013) were organized in
cally collected to serve the purpose. preparation of the documents A and B. The preparation of a safe
recycling plan should be led by a competent person who possesses
2. The three-step risk assessment method a thorough knowledge of safe ship breaking practices and proce-
dures (adapted to specific ships). The plan should be developed
The first objective has been to articulate and implement work- for preparation, deconstruction and for the material (scrap) stream.
able strategies for minimization of risks in the work place as well A drawing showing the general arrangements of decks, fire-fight-
as to the surrounding environment. Therefore, a simplified yet ing equipment, position of cargo handling equipment, location of
scientifically defendable protocol had to be evolved. It was felt that holds, tank disposition, logbooks of tank substances, hydrostatic

FIRST STEP SECOND STEP THIRD STEP

Make a Work Procedure: Deeper Risk


Safe Ship 1. Identify the most hazardous Assessment
Breaking Plan Work Activities and Action when
2. Start with the most hazardous assessed NOK
Work Activity (e.g. work in confi- Document F
Document B ned space) and identify its detailed
Use Risk Matrix
Job Tasks (Document C) Document G
3. Use Screening Tool (Document D)
4. Fill in all Job Task No. (use Go back to 2nd
letters) and Job Task Names in step and continue
The Base the two first columns. Put the with the next
For Safe Job Tasks in sequential order hazardous Work
Ship (Document D) Activity
Recycling 5. Use the Checklist Job Task and so on
Hazards for Hazard Screening
Document A
(Document E). Assess each Job
Task Name, fill in horizontally Asssessment
OK/NOK/NA from 1-18. Report
(Document D)

Fig. 1. The schematic representation of the steps involved in the ‘‘three-step risk assessment method’’ developed for ship dismantling and recycling yards.
178 K. Garmer et al. / Safety Science 76 (2015) 175–189

Table 1
Document D – Screening tool used for assessing the job tasks to be OK or Not OK with the associated hazard.

Template for each team member Name:


Position:

Job task Sr. no. Job task name Hazard description


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
a
b

information, accommodation, etc., should be given consideration particular accident is determined, probability ‘‘P’’ of occurrence of
when deciding the cutting plan. accident is judged and probability number is taken from risk
matrix. Finally, the risk level ‘‘R’’, is found out from matrix on the
2.2. Second step: Identification of hazardous job tasks basis of S and P number. Based on the determined risk level, next
task is to suggest the safety measures to be taken to reduce the risk.
According to the principles of the ‘‘Job Safety Analysis’’ (Harms- Several iterations might be needed to find final measures that
Ringdahl, 2001), it is important to identify the most hazardous work work in practice after actions are decided and responsible execu-
activity initially and then identify the less important. Within each tors must be appointed. It is recommended to start the risk reduc-
hazardous work activity the different Job Tasks contained in it tion process with the identified most hazardous work activity and
should also be identified (Document C). The sequence of work then continue with less hazardous work activities.
activities may vary depending upon the type of ship and nature of
recycling work. After identifying the hazardous work activity and
job tasks associated with it, the job tasks are systematically inserted 3. Methodology for conducting risk assessment
into the table called screening tool (Document D) as represented in
Table 1 which will be used for assessing the job tasks to be OK or The complexities associated with ship breaking and recycling
Not OK with the associated hazard. sector around the world in general and as practiced in Alang in par-
In the present work, a hazard screening list (Document E) was ticular; the field investigation team of IIT Bombay embarked upon
developed with the intention to find the causal risk factors for a comprehensive door-to-door interview-campaigns. The safety
the identified hazard. This hazard screening list is based on Job officers, yard owners and safety supervisors as well as production
Safety Analysis (Harms-Ringdahl, 2001), safety and health in ship managers from more than 50 ship recycling yards in Alang were
breaking, Guidelines for Asian Countries and Turkey, ILO, 2004, interviewed to articulate the work activities and the corresponding
occupational safety and health manual, for the ship recycling job tasks (associated with each work activity). The data were brain-
workers in Bangladesh, ILO, Ministry of Labor and Employment stormed, deliberated and ground truths were established with
Bangladesh and United Nations Development Fund (UNDF) within regard to each job task typically carried out during breaking and
the Safe and Environment Friendly Ship Recycling (SAFEREC) pro- recycling of obsolete vessels. The results were finally depicted in
ject, 2007 (see Table 2). The checklist (Document E) should be seen a form of a flow diagram of work activities as shown in Fig. 3.
as a reference when identifying hazards for filling Table 1. It would be interesting to notice that the time frames and frac-
tion of work force deployed for conducting different work activities
2.3. Third step: Deeper risk assessment and recommendations for risk differ greatly (for further details, refer to Hiremath et al., 2014).
minimization The work activities and job tasks obtained from the study were
used as a base for preparing ship recycling plan (Document A).
When hazards are considered as Not OK, there is always a need Also, the ship structure diagrams acquired from ship owner were
to go further into deeper analyses in the Third Step (Document F) used for preparing the safe ship breaking plan (Document B).
as shown in Table 3. Further, three-half day long workshops on risk assessment popu-
Once the hazardous job tasks are identified, the next task is to lated by (say) 60 persons in every session were conducted, where
quantify the risk in systematic way. The risk matrix frequently used people were asked to vote for identification of risky tasks as well
in a car manufacturing production plant (Volvo Cars AB, Sweden) as casual risk factors and safety measures to minimize the risk
was chosen as a base and then refined further. It is based on proba- for vital work activities. In this exercise, Document C was provided
bility and severity. Risk is defined as the combination of the proba- to identify the hazardous work activities.
bility of occurrence of harm and severity of that harm (Høj and The in-depth follow-up information obtained from ship recy-
Kroger, 2002). According to International Standard ISO 14121- cling yards, the field personnel involved in risk assessment when
1:2007, risk assessment can be effectively performed for every they indicated in Document C (in the interviews) that certain
identified hazardous job task (i.e. actions, situations, or practices) activities posed unacceptable levels of risk. The separate section
by use of a risk level matrix. This risk can be mapped with the of data sheets (Document D) was prepared to use as screening tool
experience of field personnel and utilized in assessing the risk in identifying OK and NOT OK situations in performing each job
associated with prevailing practices of ship dismantling. tasks in that work activity. In order to fill Document D, the support-
Consequently, the same approach can be used by the expert or ing Document E was prepared to find the causal risk factors for an
experienced personnel to estimate risk associated with alternate identified hazard. The NOT OK tasks identified in Document D were
potential improved actions/solutions or alternatively the options further analyzed in-depth using Document F. The conventional risk
can be prioritized on the basis of risk assessment. The risk matrix level matrix (Document G) was used to fill Document F.
(Document G) as shown in Fig. 2 helps in finding relevant risk levels Finally, with the help of assessment documents in conjunction
and also gives a help for prioritization of actions needed. Firstly, the with conventional risk level matrix are organized in a simple three
severity ‘‘S’’ of accident which can be divided starting from negligi- step manner. First step was, preparation of safe ship breaking plan
ble injury till death of worker. Once the severity number for (Document A and B), second step was, identification of hazardous
K. Garmer et al. / Safety Science 76 (2015) 175–189 179

Table 2
Document E – Job task hazards and associated causal risk factors (adapted from ILO, 2004, Harms-Ringdahl, 2001; SAFEREC, 2007).

Hazard screening Causal risk factors


a a
S,E 1. Burning, explosion, gas – Hot work, lack of legal and updated gas free certificate,
Fire – from ignited insulation, matting, lagging, and residual fuel; and lubricants and other lack of gas meter
flammable liquids – Lack of tanks being properly ventilated, cleaned and
tested for explosive gas before commencing work
– Explosive materials
– Explosive gases
– Flammable materials
– Chemical reactions
– Dust
– Ballast water
– Evaporated rests in tank or mud bed
– Pipes containing gas
– Inadequate fire protection measures
– Lack of appropriate emergency response, rescue and first-
aid personnel services
– Uncoated tools when there is a risk for sparks
– Lack of explosion proof light or/and equipment
– Use of cylinders (dragged cylinders over the ground,
dropped or rolled or pulled cylinders, heat, valve used
as hold when carrying, standing in front of a valve when
it is being opened.
– Unprotected disposal/storage place of e.g. fuel, oil, grease
S 2. Falling on the same level-stumbling, slipping, etc. – Slipping on wet surfaces or on something laying or fas-
tening on the walking surface
S 3. Falling to a lower level – Falls from height inside ship structures or on the ground
– Access in progressively dismantled vessels (floor, stairs,
passageways)
– Collapse of structure
– Scaffolding, platforms, fixed and portable ladders
S 4. Impact with a falling object – Being stuck by falling objects
– Snapping of cables, ropes, chains, slings
– Wire and rope breakage, wear and corrosion of wire ropes
S 5. Impact with a flying object
S 6. Squeezing or crushing – Stuck by moving objects
– Caught in or compressed
– Shackles, hooks, chains
– Cranes, winches, hosting and hauling equipment
– Impact by tools
S 7. Hazardous Mechanical situations due to for example equipment/machinery – Failure of machinery and equipment
– Poor maintenance of machinery and equipment
– Rotation of machinery part or linear movement
– Lack of safety guards in machines
– Power driven hand-tools, saws, grinders abrasive cutting
wheels
– Structural failures
– Stored pressure (gas, steam, liquid, feathers, etc.)
a
H 8. Hazardous handling, overloading of part of the body – Handling heavy objects
– Repetitive strain injuries
– Awkward postures
– Repetitive work and monotonous work
– Excessive work load
S, H 9. Penetration of sharp objects – Sharp objects
– Sharp-edged tools
E 10. Vehicles – Trucks
– Transport vehicles
– Cranes
S 11. Electrical energy available – Electricity/electrocution
– Electrostatic recharging (could happen when using
powerful jet of water
H 12. Poisoning – Inhalation
H 13. Suffocating or drowning – Lack of control of Oxygen deficiency in confined spaces
(should be 20–22 volume percentage (less than 19.5 is
dangerous and one should not enter without PPE, if
higher than 22% there can be an explosive mixture))
– Lack of proper ventilation
– Lack of proper training when entering a confined space,
etc.
– Drowning for floating or partially floating structures
– Gases and fumes heavier than air which presses the oxy-
gen away
– Oxidation processes that consume oxygen (e.g. open
flame or welding)
– Closed entry to space

(continued on next page)


180 K. Garmer et al. / Safety Science 76 (2015) 175–189

Table 2 (continued)

Hazard screening Causal risk factors


– Lack of rescue team standing standby and no attendant
(with correct PPE) being in constant contact with workers
inside a confined space)
H, E 14. Hazardous persons or animals – Toxic marine organisms
– Animal bites
– Risk of communicable diseases transmitted by pets, ver-
min, rodents, insects and other animals that may infest
the ship
– Vectors of infectious diseases (TB, malaria, dengue fever,
hepatitis, respiratory infections, etc.)
E 15. Exposure that can give effects in a long term: Hazardous substances and wastes – Asbestos fibers
– Asbestos – in hanger liners, mastic under isolation, cloth under isolation, cable, lagging and – PCBs and PVC and CFC’s
insulation on pipes and hull, adhesive, gaskets on piping connections, and valve packing – Heavy and toxic metals (lead, mercury, cadmium, copper,
– Polychlorinated biphenyls (PCBs) – in rubber products such as hoses, plastic foam isolation, zinc, etc.)
cables, silver paint, habitability paint, felt under septum plates, plates on top of the hull – Dusts
bottom and primary paint on hull steel – Paints and coatings
– Hazardous materials and chemicals – including heavy metals in ship transducers, ballast, and – Combustible Materials
paint coatings; mercury in fluorescent light tubes, thermometers, electrical switches, light – Foam Insulation
fittings, fire detectors and tank level indicators; and chlorofluorocarbons (CFCs) in self- – Welding fumes
contained refrigeration devices such as water coolers and freezer units. – Organic substances (TBT, isocyanates, etc. in marine
paint)
– Volatile organic compounds (solvents)
– Hydrogen sulfide H2S (has a distinctive smell-like rotten
eggs)
– Carbone monoxide (CO) has no smell, measured by
testing)
– Batteries
– Fire-fighting liquids
– Compressed gas under pressure
– Exposure to hazardous liquids or gases or material
substances
– Redundant gases
– Oil and fuel
– Cleaning compounds
– CO2
– Bilge and ballast water
– Radiation sources
– Timber
– Corroding
– Other chemicals
– Evaporated rests in tank or mud bed or leaking packing or
valves
– Hydrogen sulfide at microbiological activity or breaking
down
H, E 16. Exposure that can give effects in a long term: Hazardous Physical situation – Poor illumination
– Excess noise – associated with grinding, hammering,
metal cutting, and other activities
– Vibrations
– Extreme temperatures
– Radiation (UV, radioactive materials)
H, E 17. Hazardous psychosocial-situations – Mental stress
– Human relations (aggressive behavior, alcohol and drugs
abuse, violence)
– Long working hours
– Shift work
– Night work
– Temporary employment
– Poverty
– Low wages
– Minimum age
– Lack of education and social environment
– Poor work organization
S 18. Hazardous standard of work place – Lack of PPE (helmet, safety shoes (oil resistant), safety
goggles, gloves, ear plugs/ear muffs, dust mask or/and
gas mask (fresh air), safety belt and life line, apron, face
shield with color glass, fire extinguisher near cutting, fire
guard, when cutting: leather used as material PPE
– Lack of special routines and PPE when collect and dispose
fuel oil, grease and other combustible products, asbestos,
etc.
– Inadequate maintenance of PPE
– Housekeeping practices
– Safety signs
– Lack of health and safety training to carry out the work in
a safe manner
K. Garmer et al. / Safety Science 76 (2015) 175–189 181

Table 2 (continued)

Hazard screening Causal risk factors


– Inadequate accident prevention and inspection
– Inadequate emergency
– Lack of regular exercises in emergency prevention, pre-
paredness and response procedures
– Escape routes not free for possible evacuation
– First-aid and rescue facilities
– Inadequate housing and sanitation
– Lack of medical facilities and social protection
– Lack of hazard communication (storage, labeling, mate-
rial safety data sheets
– Lack of standard work area and procedures. (There can-
not be a work system, which is standard but unsafe. Stan-
dard way of doing a work is definitely the safest way too.
Occupational safety ensures higher productivity).
a
S = Safety, H = Health and E = Environment.

Table 3
Document F – Third step – Deeper risk assessment and action plan.

Co-ordinate Causal risk Location in Potential effects, Risk level (R) Hazard Risk level (R) Responsible authority
of job task factor ship or e.g. harm before risk control/Safety after risk and finish date
ship yard reduction measure reduction
S P R S P R
a1
a2

Fig. 2. Risk matrix to estimate the risk level used in third step of three-step risk assessment method.

job tasks, associated with ship breaking and recycling (Document It must be pointed out that there is always a need for validation,
C, D and E) and third step was deeper risk assessment and action determining that the implemented measures functioning as
plan for safe ship recycling using risk matrix (Document F intended. In the three-step method all these checklists and
and G). This combination of three steps was named as the documents are combined in a logical order. It is most important to
‘‘Three-Step Method’’ which is developed for the risk assessment keep a record in a protocol all through the different steps of the
in ship recycling sector. method.
182 K. Garmer et al. / Safety Science 76 (2015) 175–189

Fig. 3. Typical ship recycling plan practiced at Alang ship recycling yards and time required to accomplish each work activity.

3.1. Validation of the three-step risk assessment method Input Data


Xobs
Validation of the Three-Step Method, essentially addresses the
differences (or similarities) in ‘‘perception of risk’’ by several
Health Safety Environmental (HSE) managers who volunteered
for the risk assessment exercise. Although, their opinions differed
Assumpons Mathemacal Model Limitaons
person-to-person due to the fact that they belong to different yards
or have different years of experience; would they still collectively
suggest a similar level of risk in a given job task? Validation of
the risk assessment model was used to answer this question from
a statistical stand point. Output is the “Parameter”
As represented in Fig. 4 a validation protocol, in the context of
this study, may be conceptualized as a two-stage process. Input of independent
Terminologies used are listed in Table 4. In the first stage, a mathe- data set (Xobs)
Mathemacal Model
matical model is developed based on data sets listed in Table 5. In
the second stage, a different data set from same table is used to
validate the mathematical model developed in the first stage.
Using the appropriate statistics, the model is either confirmed or
Output is Ymodel
considered invalid at a specified level of statistical significance
(say 0.05 or 95% confidence).
In order to validate the risk assessment method, two validation
protocols were developed. Each of these protocols is framed as a Is Ymodel = Yobs
hypothesis as shown below: NO at acceptable level of
stascal significance?
Hypothesis 1. There is no significant difference between the
observed average risk index based on the field data and
the assigned risk index corresponding to the averaged YES
values when average is based on ‘‘large enough’’ number of
observations.
Fig. 4. Schematic representation of conceptualization of two-stage process of
validation protocol.
Hypothesis 2. There is no significant difference between the per-
ception of risk by experts and the perception of risk by the ‘‘analy- Hypothesis 3. There is no significant difference between an
sis team’’ comprising of production managers, safety officers, individual’s perception and the perception of the entire group as
safety supervisors and the designated expert monitor. long as the data set is large enough.
K. Garmer et al. / Safety Science 76 (2015) 175–189 183

Table 4 One other shortcoming of the methodology adopted for con-


Terminology and definitions for the validation of three-step risk assessment method. ducting risk assessment exercise was that the workers were not
Variable Definition interviewed. This limitation was circumvented by interacting with
Yobserved average Average of risk index values obtained from field the ‘‘analysis teams’’ comprising of production managers, safety
personnel officers, safety supervisors and the designated expert monitor from
Yassigned for average Rounded off integer for average risk index values each participating dismantling yard. They were briefed by the
obtained from field personnel external experts (posted by the researching team by IIT Bombay)
Yassigned for average using model Average assigned risk index values calculated
from the regression model between Y averages
and encouraged to think, discuss with their work-force and col-
observed versus Y assigned for average leagues and articulate their opinions before presenting themselves
Yexpert average Average risk index values obtained from experts to participate in the risk assessment exercise.
Dobserved Absolute number obtained by subtracting
individual risk index assigned by field personnel
with average of individual risk index
4. Validation of the method
Dassigned Absolute number obtained by subtracting
individual risk index assigned by field personnel Risk can be mapped with the experience of field personnel and
with rounded off integer of average of assigned utilized in assessing the risk associated with prevailing practices of
risk index values calculated from the regression
ship dismantling. Consequently, the same Three Step Method
model
approach can be used by the expert or experienced personnel to
estimate risk associated with alternate potential improved
Table 5
actions/solutions or alternatively the options can be prioritized
Classification of risk data for application of validation protocols. on the basis of risk assessment. In order to validate the developed
three-step method following two validation protocols as well as
Group No. of No. of risk Description
data indexes
consistency check were carried out.
sets
Before After 4.1. Validation Protocol 1
A 12 4 4 Risk index as per field personnel
B 12 4 4 perception
C 11 4 4 Hypothesis: There is no significant difference between the
E 9 4 4 Risk index as per the expert’s perception observed average risk index based on the field
data and the assigned risk index corresponding
to the averaged values when average is based on
The risk assessment data were collected by interviewing several ‘‘large enough’’ number of observations.
field personnel at a number of ship recycling yards. Risk was deter-
mined before and after taking corrective action to reduce risk. The Model : Y assigned for average ¼ a  Y observed average where ideally a ¼ 1:
research group was able to collect 35 data sets from field personnel
at the ship recycling yards, each data set with 8 risk indexes (4 risk Calibration (i.e. Estimation of a): Data from Group A were used
indexes each, before and after implementing corrective action). In for calibration. As shown in Fig. 5, Yassigned for average for Group A was
addition, 9 data sets were collected to document the perceptions of plotted against the Yobserved average of Group A which yielded a straight
experts. Thus a total of 44 data sets were available to carry out the line with the slope of 1.064 and R2 = 0.918 by forcing it through
validation exercise. the origin. The 95% confidence interval for the slope was deter-
For the purpose of validation, all 44 data sets are divided into 4 mined to be ±0.217. The area between dashed lines on the graph
groups: Group A, B, C and E as shown in Table 5. Groups A and B represents the 95% confidence interval zone. The error bars for
consist of 12 data sets each, Group C consists of 11 data sets and individual data points are also shown.
Group E consists of 9 data sets. The 12 data sets of Group A in Validation: Validation was carried out using Group B data set.
Table 2 represent 12 field personnel, and each of the 12 data sets The ordinate for Fig. 6 (i.e. Yassigned for average using ‘‘model’’ for Group B)
consists of 8 risk indexes (4 before corrective action and 4 after was calculated using the model (the model equation for the
corrective action). Groups B, C and E are similarly structured. Group A data) developed in the calibration step and plotted against
field data (Yassigned for average for Group B). If the slope comes out to be
3.2. Limitations of study close to unity, the method can be believed to be validated. As seen
from Fig. 6, the slope was obtained by forcing it through the origin
In order to perform the risk assessment, ship recycling yards and was found to be 0.974 and R2 = 0.925. The slope was nearly
(plots) were not chosen randomly. Risk assessment was conducted equal to unity and the calculated 95% confidence interval was
only on those plots where yard management voluntarily took the ±0.261. The hypothesis that there is no significant difference
initiative to improve Health Safety and Environmental Quality between the observed risks index in the field and assigned risk
(HSEQ). The selection of the plots depended largely on the attitude index using model for a large enough data set is thus validated.
of the yard management and their perception on the value of the The area between dashed lines on the graph represents the 95%
information they gave out. It was essential to respect and accept confidence interval zone as shown in Fig. 6. The error bars for
the yard management’s decisions to share/not share information. individual data points are also shown.
It is to be noted that workers were not interviewed because of The analysis is based on the 12 data sets having 8 risk indexes
language limitations. English and Hindi (the Indian national lan- each. Averages of the 12 data sets are plotted along the X axis
guage) were used in the data collection and interview process. and assigned values of risk index (rounded-off to the nearest inte-
Since most of the workers came from different regions of the coun- ger) corresponding to the averages of the 12 data sets are plotted
try and were conversant only with their regional language, it was along Y axis. The regression yielded the slope (a) of 1.064 ± 0.217.
impractical to interview them in English or Hindi. Therefore, this The analysis is based on 12 data sets of Group B having 8 risk
risk assessment study focused on production managers, safety offi- indexes each. Averages assigned (rounded-off to the nearest
cers and safety supervisors because they were conversant with integer) of the 12 data sets are plotted along X axis.
English or Hindi. Yassigned for average using the model was plotted along Y axis by using slope
184 K. Garmer et al. / Safety Science 76 (2015) 175–189

Fig. 5. Linear regression of Yassigned for average for Group A versus Yobserved average of Group A for
calibration of the risk assessment model based on Hypothesis 1. Fig. 7. Linear regression of Yobserved average of Group A versus Yexpert average of Group E for
calibration of model for risk assessment based on Hypothesis 2.

Fig. 6. Linear regression of Yassigned for average using ‘‘Model’’ for Group B (model data) versus Fig. 8. Linear regression of Yobserved average using model of Group E versus
Yassigned for average of Group B (field data) for the purpose of validation of the risk assessment Yaverage observed of Group C for the purpose of validation of the risk assessment model
model based on the Hypothesis. based on the Hypothesis 2.

value of calibration graph as shown in Fig. 6 multiplied with aver- origin. The 95% confidence interval for the slope was determined
age of data set of Group B. The regression yielded the slope of to be ±0.216. The area between dashed lines on the graph repre-
0.974 ± 0.261. sents the 95% confidence interval zone as shown in Fig. 7. The error
bars for individual data points are also shown.
4.2. Validation Protocol 2 Validation: Validation was carried out using Group C data set. If
the slope came out to be close to unity, the method was effectively
Hypothesis: There is no significant difference between the validated. The slope was obtained by forcing it through the origin
perception of risk by experts and the perception and was found to be 1.011 and R2 = 0.913. Since the slope was very
of risk by the ‘‘analysis team’’ comprising of close to unity and the calculated 95% confidence interval was
production managers, safety officers, safety ±0.295 hypothesis that there is no significant difference between
supervisors and the designated expert monitor. perception of risk by experts and perception of risk by field person-
nel is indeed validated.
Model : Y observed average ¼ b  Y expert average The area between dashed lines on the graph represents the 95%
confidence interval zone as shown in Fig. 8. The error bars for
Calibration (i.e. Estimation of b): Data from Group A was used individual data points are also shown.
for calibration. The ordinate for the validation plot The analysis for Yobserved average is based on 12 data sets of Group
(Yobserved average for Group A) was calculated using the field data and A having 8 risk indexes each and Yexpert average of Group E consists of 9
plotted against Yexpert average of Group E) which yielded a straight line data sets of Group E with 8 risk indexes each. The regression
with the slope of 1.036 and R2 = 0.956 by forcing it through the yielded the slope (b) of 1.036 ± 0.216.
K. Garmer et al. / Safety Science 76 (2015) 175–189 185

Fig. 11. The linear regression with slope of 0.991 (R2 = 0.942) depicting the
consistency of the data groups mainly combination of Yaverge observed of group (B+C)
Fig. 9. Linear regression of Dassigned versus Dobserved where Dassigned = Abs versus combination of Y averge observed of group (A+E). Both axes represent 24 data sets
(Yobserved i  Yassigned for average using model for Group A) and Dobserved = Abs (Yobserved i  each. The regression yielded the slope of 0.991 ± 0.209.
Yobserved average of Group A). The regression yielded the slope of 1.012 ± 0.133. Graph
also represents number of repetition of data points.

Table 6
Combination of data groups for consistency check of data set used in the analyses.

Combination Abscissa data set Ordinate data set


combination (X axis) combination (Y axis)
Yobserved average Yobserved average
1 Group (A + B) Group (C + E)
2 Group (A + E) Group (B + C)
3 Group (B + E) Group (A + C)

Fig. 12. The linear regression with slope of 0.991 (R2 = 0.942) depicting the
consistency of the data groups mainly combination of Yaverge observed of group (A+C)
versus combination of Yaverge observed of group (B+E). Both axes represent 24 data sets
each. The regression yielded the slope of 0.991 ± 0.128.

4.3. Check for deviation of individual’s opinion from group average

Hypothesis: There is no significant difference between an


individual’s perception and the perception of the
entire group as long as the data set is large
enough.
Fig. 10. The linear regression with slope of 0.98 (R2 = 0.96) depicting the consis- Dassigned = Abs
tency of combination of data groups. Namely, combination of average observed of (Yobserved i  Yassigned for average using model for Group A)
group (A + B) versus combination of average observed of group (C + E). Both axes
represent 24 data sets each. The regression yielded the slope of 0.979 ± 0.178.
Dobserved = Abs
(Yobserved i  Yobserved average of Group A)
Dassigned = e  Dobserved where ideally e = 1
The analysis is based on 12 data sets of Group C with 8 risk
indexes each. Averages of the 12 data sets are plotted along X axis. All individual data points from Group A data set (96 points) were
Yobserved average using model of Group E was plotted along Y axis by using used in this analysis. Dassigned was plotted against the Dobserved, as
slope (b) of calibration graph as shown in Fig. 8 multiplied with shown in Fig. 9. As stated in the Hypothesis 3 if an individual field
averages of data set of Group C. The regression yielded the slope person’s perception is different than the perception of the entire
of 1.011 ± 0.295. group then the linear relationship will not be established through
186 K. Garmer et al. / Safety Science 76 (2015) 175–189

linear model. The plotted graph yielded straight line with the slope Since the number of data points was large (96) an R2 value of
of 1.012 and R2 = 0.744 by forcing it through the origin. The 95% 0.744 may be considered acceptable. Further, since the confidence
confidence interval for the slope was determined to be ±0.133. interval was ±0.133 it indicates that the straight line can be fitted
The area between dashed lines on the graph represents the 95% con- through these data. Essentially there is no significant difference
fidence interval zone as shown in Fig. 9. between an individual field personnel’s perception and the percep-
tion of the group as a whole. This is indeed a remarkable result
Table 7 given the variability in personal views and affiliation with different
Summary of data consistency check analyses for linear regression of combination of yards and differences in levels of experience between individuals.
groups. Based on these results, it is safe to conclude that there is no signifi-
Sr. Abscissa data set Ordinate data set R2 Slope 95% cant difference between an individual’s perception and the percep-
no. combination (X combination (Y Confidence tion of the entire group as long as the data set is large indeed is
axis) axis) interval for validated.
slope
1 Y avg observed Y avg observed 0.960 0.979 ±0.178
for group (A + B) for group (C + E) 4.4. Check for consistency of data sets
2 Y avg observed Y avg observed 0.942 0.991 ±0.209
for group (A + E) for group (B + C) The consistency check on the data sets was also performed.
3 Y avg observed Y avg observed 0.942 0.991 ±0.128
for group (B + E) for group (A + C)
Table 6 shows the different Groups (A, B C and E) and total number
of data points within each group. For the data consistency check,
two of the four data groups were combined into one data set and
remaining two data sets were combined into another data set. For
Table 8 example, Groups C and E were combined and Groups A and B were
Job task operations for Work Activity 9 i.e. cutting of slice and transporting to combined as shown in Fig. 10 where Yaverage observed for Group (C+E) was
workplace at Alang.
plotted against Yaverage observed for Group (A+B). Also,
Job Job task name Yaverage observed for Group (B+C) and (A+C) were plotted against
tasks Yaverage observed for Group (A+E) and (B+E) in Figs. 11 and 12 respectively.
A Slice section falls by gravity in inter-tidal zone when water recedes If the relationship is linear with the slope close to unity, it
completely shows that there is consistency between data sets. Table 7
B Major cuts of the slice with gas cutter to make liftable pieces by
summarizes results from these analyses and also gives the 95%
cranes
C Cleaning of wastes emerged from slice (oil, rags, paint chips, tins, confidence interval for the slope for each analysis. Based on results
etc.) presented in Table 7 it is concluded that the data sets are indeed
D Loading for transportation onto cranes (wire ropes) consistent.

5. Case study: Application of three-step method


Table 9
Job task operations for Work Activity 10 i.e. segregation, grading, cutting and loading You may recall that Fig. 3 showed the typical ship recycling
for transportation activity.
procedure being followed at Alang. During the discussion with
Job tasks Job task name ‘‘analysis team’’ comprising of production managers, safety
A Work area; further cleaning and cutting of sections officers, safety supervisors and the designated expert monitor well
B Loading onto trucks using manual efforts or cranes as Regulatory Authority, it was realized that the major work force
for ship recycling is involved in the work activity no. 9 and 10.

Table 10
Work activity – Cutting of slice and transporting to workplace and the representation of identified Not OK job task – Major cuts of the slice with gas cutter to make liftable pieces by
cranes at Alang.

Job task Job task name Hazard description


Sr. #
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
A Slice section falls by gravity in inter-tidal zone
when water recedes completely
B Major cuts of the slice with gas cutter to make NOK OK NA OK NOK OK NOK NA OK NA NA NA NA NA OK OK OK OK
liftable pieces by cranes
C Cleaning of wastes emerged from slice (oil,
rags, paint chips, tins, etc.)
D Loading for transportation onto cranes (wire
ropes)

Table 11
Work Activity 10 – Segregation, grading, cutting and loading for transportation and the representation of identified Not OK job task – Work area; further cleaning and cutting at Alang.

Job task Sr. Job task name Hazard description


#
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
A Work area; further cleaning and cutting OK OK NA NA NOK OK OK OK OK OK NA NA NA NA OK OK OK OK
B Loading onto trucks using manual efforts or
cranes
Table 12
Sample representation of deeper risk assessment for Job task operation – Major cuts of the slice with gas cutter to make liftable pieces by cranes in work activity no. 9 of ‘‘Typical ship recycling plan’’ followed in ship recycling yards in Alang.

Co-ordinate Causal risk factors Location in ship Potential effects, Risk Level Hazard control/Safety measure Risk level Responsible position
of job task or ship yard e.g. harm (R) before (R) after (and finish date)
& hazard risk risk
description reduction reduction
S P R S P R
B1  Improper cleaning of fuel pipes and Primary zone Major and minor 3 3 3  Inspection by Safety officer 2 2 2 Safety officer, field
flammable materials physical injury  Proper fuel oil clean up supervisor (Not Given)
 Inadequate fire protection measures  Adequate fire protection
measures and emergency response
B5  Wire failure due to tension in rope/cable Primary zone Disability/Major 4 2 4  Inspection by Safety officer, Crane operator 2 2 2 Crane Operator, Safety
 Splitting of plate’s hole physical injury  Alarming siren while moving the objects officer (Not Given)
 Negligence by workers while crane is operating  PPE Mandatory for all the workers
B7  Failure of crane’s boom Primary zone Major and minor 5 3 4  Periodic maintenance and replacement 3 2 3 Safety officer (Not Given)
 Poor maintenance of winch, crane/wire rope physical injury of machinery

K. Garmer et al. / Safety Science 76 (2015) 175–189


 Negligence of safety measures while working  Inspection by Safety officer, Crane operator

Table 13
Sample representation of deeper risk assessment for Job task operation – Work area; further cleaning and cutting in work activity no. 10 of ‘‘Typical ship recycling plan’’ followed in ship recycling yards in Alang.

Co-ordinate of job task Causal risk factors Location in ship Potential effects, Risk level (R) Hazard control/ Safety measure Risk level (R) Responsible
& hazard description or ship yard e.g. harm before risk after risk position (and
reduction reduction finish date)
A5  Splitting of plate’s hole Secondary Zone Disability/Major 4 3 4  Inspection by Safety supervisor, Crane operator 3 2 3 Crane Operator, Safety
 Negligence by workers physical injury  Alarming siren while moving the objects officer (Not Given)
while crane is operating

187
188 K. Garmer et al. / Safety Science 76 (2015) 175–189

Therefore, this case example is concentrated on these two work only one subsystem, it will make the whole risk reduction work
activities for implementing the three-step risk assessment method much more complicated and time consuming.
at ship recycling yards at Alang. As represented in Table 8, the The three-step risk assessment was performed in 35 ship recy-
work activity no. 9 i.e. cutting of slice & transporting to work place cling yards through questionnaire surveys and door-to-door com-
was divided into four job task operations. It is to be noted that munication. Thus, 35 data sets from field personnel at the ship
more than 70% of the workforce is involved in these two activities. recycling yards, each data set with 8 risk indexes (4 risk indexes
Further, the work activity 10 i.e. Segregation, grading, cutting each, before and after implementing corrective action) were col-
and loading for transportation is divided into two job task opera- lected. In addition, 9 data sets were collected to document the per-
tions as mentioned in Table 9. ceptions of experts. In all, a total of 44 data sets were collected and
Further, as part of the three-step risk assessment method, used to validate the risk assessment method. Validation of the
questionnaires were designed to elicit information from ‘‘analysis three-step method, essentially addresses the differences (or simi-
team’’ comprising of production managers, safety officers, safety larities) in ‘‘perception of risk’’ by several health, safety and
supervisors and the designated expert monitor of the ship environment (HSE) managers who volunteered for the risk assess-
recycling yards with respect to perceived risks. Team went door- ment exercise. In order to validate the risk assessment method,
to-door, interviewed the analysis team and collected pools of data two validation protocols were developed. The first protocol with
specific to work activity and job task. Similar activity was the slope of 0.974 and R2 = 0.925 validated the hypothesis that
continued with more than 35 ship recycling yards in Alang. Thus, there was no significant difference between the observed average
in-depth follow-up information was obtained from ship recycling risk index based on the field data and the assigned risk index
yards, the field personnel involved in risk assessment when they corresponding to the averaged values when average is based on
indicated (in the interviews) that certain activities posed unaccept- ‘‘large enough’’ number of observations. The second protocol with
able levels of risk. the slope of 1.011 and R2 = 0.913 validated the second hypothesis
Table 10 shows that the Document D was used for job task that there was no significant difference between perception of risk
operation B i.e. ‘‘A major cut of the slice with gas cutter to make lif- by experts and perception of risk by field personnel. Further, it was
table pieces by cranes’’ was checked in detail by using the checklist validated that there was no significant difference between an
for ‘‘Job tasks Hazards for Hazards Screening’’ (1–18, from individual’s perception and the perception of the entire group as
Document E). Table 10 also represents the identified NOT OK job long as the data set was large enough on the basis of the obtained
tasks in work activity no. 9. Similarly, Table 11 represents the job slope of 1.012 and R2 = 0.744. Lastly, the consistency check on the
task A i.e. work area; further cleaning and cutting was checked in data sets was also performed and it was found that the relationship
detail using Document E. The NOT OK job tasks in work activity was linear with the slope close to unity. The example illustrating
10 are also mentioned in Table 11. the application of Three Step Method in identifying and minimiz-
Once the NOT OK job tasks are identified, the next step is to use ing risks provides clear understanding for the users of this method.
Document F to perform in-depth risk assessment. Table 12 repre- Evidently, the three-step risk assessment method developed in this
sents the deeper risk assessment for the job task ‘‘Major cuts of research appeared to give consistent results in a variety of scenar-
the slice with gas cutter to make liftable pieces by cranes’’. ios of validation. Indian policy makers and regulators of ship dis-
Table 13 shows the deeper risk assessment for the job task mantling sector are in the process of making amendments in the
‘‘Work area; further cleaning and cutting’’. To determine the risk existing laws by bringing the developed Three Step Method for
level, Risk Matrix (as shown in Fig. 2) of Document G was used. minimizing occupational risks in ship breaking and recycling
The causal factors which were responsible for this hazardous situa- yards. This method is also implementable in any ship recycling
tion, potential harm and risk level were mentioned before the yard in the world.
implementation of the safety measures. Further, discussing with
the safety manager and the safety delegate, the safety measures
Acknowledgments
that can be implemented to minimize the risk level are identified
and listed in Tables 12 and 13 respectively. The reduced risk level
The authors of this paper acknowledge the Ship Recycling yards
for those hazardous situations is also mentioned. Hence, using the
at Alang for their interest and for applying our ideas in real-life in a
three-step risk assessment method, the risk is identified; and the
ship recycling context. Authors also acknowledge the European
improvement measures were suggested to minimize the risk.
Union funded project ‘‘DIVEST’’ and Gujarat Maritime Board
funded project ‘‘Green Alang Initiative’’ as well as Indian Institute
of Technology Bombay for partial funding for this work. Inputs
6. Conclusions
for field work and generous co-operation offered by Pradip P.
Kalbar and Paritosh C. Deshpande is highly acknowledged.
Based on an extensive literature review, checklists as well as
assessment documents were developed. The conventional risk
level matrix (can also be called as index) was used in conjunction References
with these checklists as well as assessment documents and orga-
Amponsah-Tawiah, Kwesi, Leka, Stavroula, Jain, Aditya, Hollis, David, Cox, Tom,
nized in the so-called Three Step Method for application in ship 2014. The impact of physical and psychosocial risks on employee well-being
recycling and ship repairing sector. and quality of life: the case of the mining industry in Ghana. Saf. Sci. 65, 28–35.
Three-step risk assessment method developed and validated in Asolekar, S.R., 2006. Status of Management of Solid Hazardous Wastes Generated
during Dismantling of Obsolete Ships in India. Presented at the First
this study using pedagogic approach, is easy to learn, use and International Conf. on Dismantling of Obsolete Vessels, Glasgow, Scotland, UK.
administer in ship recycling yards. The so far gained experience Asolekar, S.R., 2012. Greening of ship recycling in India: upgrading facilities in
of the Three Step Method indicates that this method could be a dia- Alang. In: The Proceedings of 7th Annual Ship Recycling Conference organized
by Informa Maritime Events and Lloyd’s List London, UK.
log tool for the ‘‘analysis team’’ comprising of production man-
Asolekar, S.R., Hiremath, A.M., 2012. India’s Contribution in Preventive
agers, safety officers, safety supervisors and the designated Environmental Management of Obsolete Vessels Indian Ports and
expert monitor and serve as a systematic method for risk reduction Infrastructure Magazine, August 2012; 5–7.
to enhance health and safety in ship yards. It is an advantage for Ayyub, B.M., 2003. Risk Analysis in Engineering and Economics. Chapman & Hall/
CRC, ISBN 1-58488-395-2.
the Alang ship yard, if only one method has to be maintained. If Bahn, S.T., 2013. Workplace hazard identification and management: the case of an
they have to learn and administer different methods tailored for underground mining operation. Saf. Sci. 57, 129–137.
K. Garmer et al. / Safety Science 76 (2015) 175–189 189

Cao, Suzhen, Duan, Xiaoli, Zhao, Xiuge, Ma, Jin, Dong, Ting, Huang, Nan, Sun, Li, Daiqing, Zhang, Chen, Pizzol, Lisa, Critto, Andrea, Zhang, Haibo, Lv, Shihai,
Chengye, He, Bin, Wei, Fusheng, 2014. Health risks from the exposure of Marcomini, Antonio, 2012. Regional risk assessment approaches to land
children to As, Se, Pb and other heavy metals near the largest coking plant in planning for industrial polluted areas in China: the Hulunbeier region case
China. Sci. Total Environ. 472, 1001–1009. study. Environ. Int. 50, 47–55.
Demaria, F., 2010. Ship recycling at Alang-Sosiya (India): an ecological distribution Mahindrakar, A.B., Das, S.K., Asolekar, S.R., Kura, B., 2008. Environmental issues in
conflict. Ecol. Econ. 70, 250–260. the ship breaking industry in India. In: The Proceedings of the A&WMA’s Annual
Deshpande, P.C., Tilwankar, A.K., Kalbar, P.P., Asolekar, S.R., 2012. A novel approach Conference, Portland, Oregon, USA, June 24–26, 2008.
to estimating potential maximum heavy metal exposure to ship recycling yard Marhavilas, P.K., Koulouriotis, D.E., Mitrakas, C., 2009. Development of a
workers in Alang, India. Sci. Total Environ. 438, 304–311. quantitative risk assessment technique and application on an industry’s
Deshpande, P.C., Kalbar, P.P., Tilwankar, A.K., Asolekar, S.R., 2013. A novel worksite using real accidents data. Sci. J. Hellinic Assoc. Mech. Electr. Eng.
methodology to develop emission factors for pollutants from ship recycling 415, 14–20.
yards based on input output studies. J. Cleaner Prod. 59, 251–259, Elsevier Marhavilas, P.K., Koulouriotis, D.E., Gemini, V., 2011. Risk analysis and assessment
Publication. methodologies in the work sites: on a review, classification and comparative
Ehsani, J.P., McNeilly, B., Ibrahim, J.E., Ozanne-Smith, J., 2013. Work-related fatal study of the scientific literature of the period 2000 to 2009. J. Loss Prevent.
injury among young persons in Australia, July 2000–June 2007. Saf. Sci. 57, 14– Process Ind., 1–47.
18. MARPOL, 1973. International Convention for the Prevention of Pollution from
EU Ship Recycling Legislation, 2013. Regulation (EU) No 1257/2013 of the European Ships. <http://www.imo.org/About/Conventions/ListOfConventions/Pages/
Parliament and of the Council of 20 November 2013 on ship recycling and International-Convention-for-the-Prevention-of-Pollution-from-Ships-%28
amending Regulation (EC) No 1013/2006 and Directive 2009/16/EC <http://eur- MARPOL%29.aspx>.
lex.europa.eu/legalcontent/EN/ALL/?uri=CELEX:32013R1257>. Moen, 2008. Breaking Basel: The elements of the Basel Convention and its
Fruhen, L.S., Keith, N., 2014. Team cohesion and error culture in risky work application to toxic ships. Mar. Policy 32, 1053–1062.
environments. Saf. Sci. 65, 20–27. Mohammadzadeh Moghaddam, A., Ayati, E., 2014. Introducing a risk estimation
Grant, A., Hinze, J., 2014. Construction worker fatalities related to trusses: an index for drivers: a case of Iran. Saf. Sci. 62, 90–97.
analysis of the OSHA fatality and catastrophic incident database. Saf. Sci. 65, Reddy, M.S., Basha, S., Sravan Kumar, V.G., Joshi, H.V., Ghosh, P.K., 2003.
54–62. Quantification and classification of ship scrapping waste at Alang-Sosiya,
Hardison, Dylan, Behm, Michael, Hallowell, Matthew R., Fonooni, Hamid, 2014. India. Mar. Pollut. Bull. 46, 1609–1614.
Identifying construction supervisor competencies for effective site safety. Saf. Reddy, M.S., Basha, S., Sravan Kumar, V.G., Joshi, H.V., Ramachandriah, G., 2004.
Sci. 65, 45–53. Distribution, enrichment and accumulation of heavy metals in coastal
Harms-Ringdahl, L., 2001. Principles and Practice in Occupational Safety. Safety sediments of Alang-Sosiya ship scrapping yard, India. Mar. Pollut. Bull. 48,
Analysis, second ed. CRC Press, ISBN 9780415236553, p. 302. 1055–1059.
Hiremath, A.M., Tilwankar, A.K., Asolekar, S.R., 2014. Significant steps in ship Reniers, G.L.L., Dullaert, W., Soudan, K., 2005. The use risk analysis tools evaluated
dismantling vis-a-vis wastes generated in a cluster of yards in Alang: a case towards preventing external domino accident. J. Loss Prevent. Process Ind. 18
study. J. Cleaner Prod. 87, 520–532. (3), 119–126.
Høj, N.P., Kroger, W., 2002. Risk analyses of transportation on road and railway from SAFEREC, 2007. Occupational Safety and Health Manual, for the Ship Recycling
a European Perspective. Saf. Sci. 40 (1–4), 337–357. Workers in Bangladesh, ILO, Ministry of Labor and Employment Bangladesh and
International Labour Organization (ILO), 2004. Safety and Health in Shipbreaking. UNDF within the SAFEREC Project 2003–2007.
International Maritime Organization (IMO), 2009. <http://www.imo.org/About/ Sarraf, M., Stuer-Lauridsen, F., Dyoulgerov, M., Bloch, F., Wingfield, S., Watkinson, R.,
Conventions/ListOfConventions/Pages/The-Hong-Kong-International-Convention- 2010. Ship Breaking and Recycling Industry in Bangladesh and Pakistan. World
for-the-Safe-and-Environmentally-Sound-Recycling-of-Ships.aspx>. Bank (2010).
Kumar, R., 2009. EU-India Action Plan Support Facility, Ship Dismantling: A Status Zhang, Wen-Li, Du, Yu, Zhai, Miao-Miao, Shang, Qi, 2014. Cadmium exposure and its
Report on South Asia. <http://bit.ly/15D6zP1>. health effects: a 19-year follow-up study of a polluted area in China. Sci. Total
Kurt-Karakus, P.B., 2012. Determination of heavy metals in indoor dust from Environ. 470–471, 224–228.
Istanbul, Turkey: estimation of the health risk. Environ. Int. 50, 47–55.

Você também pode gostar