Você está na página 1de 2

Concrete

Q&A
Repair of Joint Spalling

Q.
Floor slabs in our warehouse are experiencing (0.25 mm) for trucks with small hard wheels and 0.020 in.
spalling at joints in the lift-truck traffic lanes. (0.51 mm) for trucks with large, cushioned rubber wheels.3,4
How can we restore the joints to provide a These recommendations are appropriate provided that the
smooth ride? joint saw cut is filled full-depth with semi-rigid joint filler and
the filler is properly maintained.4 Regardless of wheel type,

A.
Joint spalling caused by hard-wheeled traffic is, when joint stability values are above 0.060 in. (1.5 mm), the
perhaps, the most common problem for industrial joint is considered unstable and will experience reduced
concrete floor slabs. It is a result of “shear failure service life.2
of unsupported slab edges due to lack of properly-installed The primary purpose of the joint filler is to provide
joint/crack filler, the impact of lift-truck wheels on the joint compressive lateral support to the joint wall to resist shear and
edge due to insufficient joint stability, or both.”1 In contrast to impact stresses leading to fracture. As some joint movement is
pneumatic tires, hard wheels create a small contact area when required due to normal fluctuations in ambient conditions
crossing joints, which increases the risk of joint spalling. The (temperature and relative humidity), joint filler should not be a
smaller and harder the wheel, the greater the risk of spalling. rigid product. Flexible material, such as exterior pavement
To increase safety and efficiency with taller racking systems, joint “sealers,” do not provide enough compressive lateral
material handling equipment is incorporating smaller and support, so a joint filler with a Shore A Hardness equal to or
harder wheels; therefore, joint spalling is becoming more and greater than that of the wheel is often recommended.
more common. However, if joints are unstable and adjacent slab panels
Joint stability (“differential deflection of adjacent slab deflect independently, semi-rigid joint fillers can separate
panel edges when a service load crosses the joint”1) is a from the joint wall and become dislodged from the joint,
measure of load transfer provided by the joint. Joint stability exposing it to spalling risk.
can be determined using any device that measures the relative Repair of spalled joints depends on the extent of the
change in surface elevation between adjacent panels.2 Lower damage. In general, if joint spalling is less than 1 in. (25 mm)
differential deflection numbers indicate better joint stability. wide (as shown in Fig. 1(a)), the joint can typically be routed
For joints subjected to lift-truck traffic, good service life out, cleaned, and refilled with a semi-rigid filler. If joint
should be expected with joint stability readings below 0.010 in. spalling is greater than 1 in. (as shown in Fig. 1(b)), it may be

(a) (b)

Fig. 1: Joint spalling: (a) less than 1 in. (25 mm) wide; and (b) wider than 1 in.

www.concreteinternational.com | Ci | APRIL 2019 79


Concrete Q&A

shrinkage over the first year, semi-rigid fillers typically


separate from the concrete face. If the filler does not separate
and stretches as the joint widens, it becomes ineffective
against spalling as it no longer provides compressive lateral
support (stretched filler is in tension). As they generally have
low elongation, two-part epoxies typically serve well as the
initial filler, as they separate from the concrete and thereby
signal the need for refilling of the joint. Polyurea fillers allow
faster cure time than epoxies, and they permit quicker refilling
after drying shrinkage and joint widening. They therefore are
preferred for refilling.
In contraction joints, refilling and spall repairs are typically
effective if the new filler is installed to a minimum depth of
1/2 to 3/4 in. (13 to 19 mm). In construction joints, it is
important to create a shelf to prevent the filler from dropping
Fig. 2: Repaired joint with reinstalled filler or extend the filler at least 2 in. (50 mm) deep to increase the
bond area to the joint wall.2
necessary to use a concrete saw to cut along the spall
perimeter and remove the distressed concrete. The excavated References
joint can then be filled with a repair mortar. To complete the 1. ACI Committee 302, “Guide to Concrete Floor and Slab Construction
repair, the joint should be recut and filled with semi-rigid joint (ACI 302.1R-15),” American Concrete Institute, Farmington Hills, MI,
filler (as shown in Fig. 2). For either repair case, it is 2015, 76 pp.
important to restore a crisp vertical joint wall as the bearing 2. Tarr, S.M., “Industrial Slab-on-Ground Joint Stability,” Concrete
surface for the new joint filler. Note that installing filler into Repair Bulletin, May/June 2004, pp. 6-9.
spalled joints is generally ineffective. In some cases, when 3. Garber, G., Design and Construction of Concrete Floors, second
spalling is deeper than half the slab thickness, full-depth edition, Elsevier Press, 2006, 233 pp.
repairs may be needed.1,2 4. ACI Committee 360, “Guide to Design of Slabs-on-Ground (ACI
For long-term performance, the filler needs to be installed 360R-10),” American Concrete Institute, Farmington Hills, MI, 2010, 72 pp.
full-depth of the sawed portion of the joint. Typically, for
saw-cut contraction joints, this is 1/4 the slab thickness. Thanks to Scott M. Tarr, North S.Tarr Concrete Consulting, PC, Dover,
However, as the joint widens due to normal concrete NH, for providing the answer to this question.

Get
Connected with

Visit www.concrete.org
80 APRIL 2019 | Ci | www.concreteinternational.com

Você também pode gostar