Você está na página 1de 12

WATCH TOWER SHELL NDP TERMINAL''B'' KMR KARACHI

EXTERNAL WORKS
CIVIL WORKS - Measurment Sheet
NATIONAL TECHNICAL SERVICES
Item No. Description Nos. Measurements Quantities
L B H
1.0 EXCAVATION work
1.1 Excavation for foundation 1 x 1 4.26 4.26 2.43 44.10 cu.m
TOTAL FOR EXCAVATION 44.10 cu.m
2.0 STONE SOLING
2.1 Watch Tower Foundation Area 1 x 1 3.73 3.73 0.300 4.17 cu.m
2.2 Ground Floor Area 1 x 1 1.82 1.82 0.160 0.53 cu.m
2.3 Stair platfoam Area 1 x 1 1.60 1.82 0.160 0.47 cu.m
TOTAL FOR STONE SOLING 5.17 cu.m
3.0 PLAIN CEMENT CONCRETE
3.1 Foundation (1:4:8) 1 x 1 3.73 3.73 0.100 1.39 cu.m
1.0 Ground Floor (1:4:8) 1 X 1 1.82 1.82 0.100 0.33 cu.m
2.0 Stair platfoam (1:4:8) 1 x 1 1.60 1.82 0.100 0.29 cu.m
3.0 Stair Case side walls(1:4:8) 1 x 3 1.82 0.30 0.100 0.16 cu.m
4.0 Stair Case Front wall(1:4:8) 1 x 1 2.28 0.30 0.100 0.07 cu.m
4.0 Plintth Protection 1 x 3 2.28 0.30 0.100 0.21 cu.m
TOTAL FOR 1:4:8 2.45 cu.m
3.2 PCC (1:3:6)
1.0 SITU UPTO PLINTH 1 X 4 1.82 1.82 0.82 10.86 cu.m
TOTAL FOR SITU( 1:3:6) 10.86 cu.m
3.3 PCC (1:2:4)
1 Watch Tower Ground Floor Finshing 1 x 1 1.82 1.82 0.100 0.33 cu.m
2 Stair Case Floor Finshing 1 x 1 2.28 1.82 0.100 0.41 cu.m
3 First Floor Finshing 1 x 1 1.82 1.82 0.100 0.33 cu.m
4 Plinth Protection Finshing 1 x 3 2.29 0.61 0.150 0.63
TOTAL FOR PCC(1:2:4) 1.71 cu.m
4.0 REINFORCED CEMENT CONCRETE
4.1 RAFT FUONDATION (1:2:4) 1 X 1 3.58 3.58 0.46 5.90 cu.m
4.2 RCC Columns upto plinth level 1 x 4 0.23 0.23 2.14 0.45 cu.m
4.3 RCCPlinth Beam 1 x 4 1.83 1.83 0.75 10.05 cu.m
4.4 RCC Columns upto Bracing Beam 1 x 4 0.23 0.23 2.14 0.45 cu.m
4.5 Bracing Beam outer Side 1 x 2 2.29 0.23 0.23 0.24 cu.m
4.6 Bracing Beam inside 1 x 2 1.83 0.23 0.23 0.19 cu.m
4.7 RCC Columns upto Drop Beam 1 x 4 0.23 0.23 0.69 0.15 cu.m
4.8 Drop Beams outside 1 x 2 2.29 0.23 0.48 0.51 cu.m
4.9 Drop Beams inside 1 x 2 1.83 0.23 0.48 0.40 cu.m
4.10 Ground Floor Slab 1 x 1 2.29 2.29 0.15 0.79 cu.m
4.11 First Floor Columns uptoDrop Beam 1 x 4 0.23 0.23 2.29 0.48 cu.m
4.12 RCC Lintel 1 X 4 1.83 0.23 0.3 0.51 cu.m
4.13 First Floor Drop Beam side 1 x 2 2.29 0.23 0.48 0.51 cu.m
4.14 First Floor Drop Beam inside 1 x 2 1.83 0.23 0.48 0.40 cu.m
4.15 First Floor Roof Slab 1 x 1 3.28 3.28 0.15 1.61 cu.m
4.16 First Floor Door Front Slab 1 1 0.71 0.91 0.1 0.06 cu.m
4.17 Door Slab wall 1 X 2 0.71 0.1 1.06 0.15 cu.m
TOTAL RCC(1:2:4) 22.85 cu.m
4.19 RCC Vertical Stair case Pipe (1:1:2) 0.082 cu.m
TOTAL FOR 1:1:2 0.08 cu.m
5.0 STEEL REINFORCEMENT
5.1 Deformed Steel 1940.16 KG
6.0 BLOCK MASONRY
6.1 First Floor 1 x 4 1.83 1.98 14.49 Sq.m
6.2 Deduction For Window 1 x 3 0.91 1.21 -3.30 Sq.m
6.3 Deduction For Door 1 x 1 0.76 1.98 -1.50 Sq.m
6.4 Stair Platfoam Side 1 x 3 1.83 0.76 4.17 Sq.m
6.5 Stair Platfoam front Step 1 x 1 2.29 0.30 0.69 Sq.m
TOTAL B/W 14.54 Sq.m
7.0 PLASTERING
7.1 Ground Floor Ceiling 1 x 1 1.83 1.83 3.35 Sq.m
7.2 Drop Beam Inside 1 x 4 1.83 0.48 3.51 Sq.m
7.3 Drop Beam side 1 x 4 2.29 0.61 5.59 Sq.m
7.4 Drop Beam Bottom face 1 x 4 1.83 0.23 1.68 Sq.m
7.5 Bracing Beam 1 x 16 1.83 0.23 6.73 Sq.m
7.6 Columns upto Drop Beam 1 x 16 0.23 0.61 2.24 Sq.m
TOTAL FOR GF 23.11 Sq.m
First Floor Plaster
7.7 Inside Walls upto Drop Beam 1 x 4 1.83 2.29 16.76 Sq.m
7.8 Window Deduction 1 x 3 0.91 0.21 -0.57 Sq.m
7.9 Door Deduction 1 x 1 0.76 1.98 -1.50 Sq.m
7.9 Drop Beam Inside 1 x 4 1.83 0.48 3.51 Sq.m
7.10 First Floor Ceiling 1 x 1 1.83 1.83 3.35 Sq.m
7.11 First Floor Side plaster 1 x 4 2.29 2.74 25.10 Sq.m
7.12 Window Deduction 1 x 3 0.91 0.21 -0.57 Sq.m
7.13 Door Deduction 1 x 1 0.76 1.98 -1.50 Sq.m
7.14 Shade Ceiling E/W side 1 x 2 3.28 0.50 3.28 Sq.m
7.15 Shade Ceiling Front&Back side 1 x 2 2.29 0.50 2.29 Sq.m
7.16 Shade Side 1 x 4 3.28 0.18 2.36 Sq.m
7.17 Inside window Faces 1 x 6 0.92 0.23 1.27 Sq.m
7.18 Inside window Faces 1 x 6 1.22 0.23 1.68 Sq.m
7.19 Door Inside Faces 1 x 2 0.76 0.23 0.35 Sq.m
7.18 Door Vertical Sides 1 x 2 0.98 0.23 0.45 Sq.m
7.19 Door Slab T/B 1 X 2 0.91 0.91 1.66 Sq.m
7.20 Door Raling Walls 1 x 4 0.71 1.06 3.01 Sq.m
TOTAL FOR FIRST FLOOR PLASTER 60.92 Sq.m
8.0 WEATHER SHIELD PAINTS
8.1 Ground Floor Ceiling 1 x 1 1.83 1.83 3.35 Sq.m
8.2 Drop Beam Inside 1 x 4 1.83 0.48 3.51 Sq.m
8.3 Drop Beam side 1 x 4 2.29 0.61 5.59 Sq.m
8.4 Drop Beam Bottom face 1 x 4 1.83 0.23 1.68 Sq.m
8.5 Bracing Beam 1 x 16 1.83 0.23 6.73 Sq.m
8.6 Columns upto Drop Beam 1 x 16 0.23 0.61 2.24 Sq.m
8.7 First Floor Paint 0.00 Sq.m
8.9 Inside Walls upto Drop Beam 1 x 4 1.83 2.29 16.76 Sq.m
8.10 Window Deduction 1 x 3 0.91 0.21 0.57 Sq.m
8.11 Door Deduction 1 x 1 0.76 1.98 1.50 Sq.m
8.12 Drop Beam Inside 1 x 4 1.83 0.48 3.51 Sq.m
8.13 First Floor Ceiling 1 x 1 1.83 1.83 3.35 Sq.m
8.14 First Floor Side Paint 1 x 4 2.29 2.74 25.10 Sq.m
8.15 Door /Winddow Deduction 0.00 Sq.m
8.16 Shade Ceiling E/W side 1 x 2 3.28 0.50 3.28 Sq.m
8.17 Shade Ceiling Front&Back side 1 x 2 2.29 0.50 2.29 Sq.m
8.18 Shade Side 1 x 4 3.28 0.18 2.36 Sq.m
8.19 Inside window Faces 1 x 6 0.92 0.23 1.27 Sq.m
8.20 Inside window Faces 1 x 6 1.22 0.23 1.68 Sq.m
8.21 Door Inside Faces 1 x 2 0.76 0.23 0.35 Sq.m
8.22 Door Vertical Sides 1 x 2 0.98 0.23 0.45 Sq.m
8.23 Door Slab T/B 1 X 2 0.91 0.91 1.66 Sq.m
8.24 Door Raling Walls 1 x 4 0.71 1.06 3.01 Sq.m
8.24 Stair step paint Top 1 x 19 0.76 0.34 4.91 Sq.m
8.25 Stair step paint Bottom 1 x 19 0.76 0.34 4.91 Sq.m
8.26 Stair Raling Side / Insie 1 x 2 6.86 0.92 12.62 Sq.m
TOTAL FOR PAINT 112.71 Sq.m
9.0 ROOFING MATERIAL
9.1 Bitumin (Grade 10/20) 1 x 1 3.27 3.27 10.69 Sq.m
9.2 Fiber Based Bituminized Roofing 1 x 1 3.27 3.27 10.69 Sq.m
9.3 PEA Gravel 1 x 1 3.27 3.27 10.69 Sq.m
10.0 PRECAST SPAIRAL STAIR CASE
11.0 BITUMIN COATING
11.1 Bitumin on Roofing 1 x 1 3.27 3.27 10.69 Sq.m
11.2 Foundation Outside E/W 1 x 2 0.65 3.58 4.65 Sq.m
11.3 Foundation Outside F/B 1 x 2 0.65 2.29 2.98 Sq.m
11.4 Inside Base 1 x 1 1.83 1.83 3.35 Sq.m
11.5 Bed Vertical Side 1 x 4 3.58 0.46 6.59 Sq.m
11.6 Outside walls 1 x 4 2.29 2.43 22.26 Sq.m
11.7 Inside Walls 1 x 4 1.83 2.13 15.59 Sq.m
11.8 Stair Plate Form side 1 x 3 2.29 0.45 3.09 Sq.m
TOTAL FOR BITUMIN 69.20 Sq.m
12.0 DISMENTLING WORK
12.1 EXISTING BLOCK MASONRY 1 x 1 7.62 1.22 9.30 Sq.m
12.2 Trench Walls 1 x 2 1.22 2.43 5.93 Sq.m
TOTAL BLOCK DISMENTLING 15.23 Sq.m
12.3 Trench Foundation 1 x 1 0.91 2.43 0.30 0.66 cu.m
12.4 Ground Floor Columns 1 x 4 0.23 0.23 0.30 0.06 Cu.m
TOTAL CONCRETE DISMENTLING 0.73 Cu.m
NTS

SECURITY WATCH TOWER SHELL NDP TERMINAL''B'' KMR KARACHI


CIVIL WORK
Measurment Sheet
NATIONAL TECHNICAL SERVICES
Item No. Description Nos. Measurements Quantities
L B H
1.0 EXCAVATION worK
1.1 Excavation for foundation 1 x 1 4.26 4.26 2.43 44.10 cu.m
TOTAL FOR EXCAVATION 44.10 cu.m
2.0 STONE SOLING
2.1 Watch Tower Foundation 1 x 1 3.73 3.73 0.300 4.17 cu.m
2.2 Ground Floor 1 x 1 1.82 1.82 0.160 0.53 cu.m
2.3 Stair platfoam 1 x 1 1.60 1.82 0.160 0.47 cu.m
2.4 Around Plinth Beam For Protection 1 x 4 2.29 0.92 0.300 2.53 cu.m
TOTAL FOR STONE SOLING 7.70 cu.m
3.0 PLAIN CEMENT CONCRETE (1:4:8)
3.1 Foundation (1:4:8) 1 x 1 3.73 3.73 0.100 1.39 cu.m
1.0 Ground Floor (1:4:8) 1 X 1 1.82 1.82 0.100 0.33 cu.m
2.0 Stair platfoam (1:4:8) 1 x 1 1.60 1.82 0.100 0.29 cu.m
3.0 Stair Case side walls(1:4:8) 1 x 3 1.82 0.30 0.100 0.16 cu.m

7
NTS

4.0 Stair Case Front wall(1:4:8) 1 x 1 2.28 0.30 0.100 0.07 cu.m
4.0 Plintth Protection 1 x 3 2.28 0.30 0.100 0.21 cu.m
TOTAL FOR 1:4:8 2.45 cu.m
3.2 PLAIN CEMENT CONCRETE (1:3:6)
1.0 SITU UPTO PLINTH 1 X 4 1.82 0.23 0.82 1.37 cu.m
TOTAL FOR SITU( 1:3:6) 1.37 cu.m
3.3 PLAIN CEMENT CONCRETE (1:2:4)
1 Watch Tower Ground Floor Finshing 1 x 1 1.82 1.82 0.100 0.33 cu.m
2 Stair Case Floor Finshing 1 x 1 2.28 1.82 0.100 0.41 cu.m
3 First Floor Finshing 1 x 1 1.82 1.82 0.100 0.33 cu.m
4 Plinth Protection Finshing 1 x 3 2.29 0.61 0.150 0.63 cu.m
5 Stair case protection 1 x 2 1.82 0.87 0.076 0.24 cu.m
TOTAL FOR PCC(1:2:4) 1.95 cu.m
4.0 REINFORCED CEMENT CONCRETE (RCC 1:2:4)
4.1 RAFT FUONDATION (1:2:4) 1 X 1 3.58 3.58 0.46 5.90 cu.m
4.2 RCC Columns upto plinth level 1 x 4 0.23 0.23 2.14 0.45 cu.m
4.3 RCC Plinth Beam 1 x 4 1.83 1.83 0.75 10.05 cu.m
4.4 RCC Columns upto Bracing Beam 1 x 4 0.23 0.23 2.14 0.45 cu.m
4.5 Bracing Beam External Side 1 x 2 2.29 0.23 0.23 0.24 cu.m
4.6 Bracing Beam Internal side 1 x 2 1.83 0.23 0.23 0.19 cu.m
4.7 RCC Columns upto Drop Beam 1 x 4 0.23 0.23 0.69 0.15 cu.m
4.8 Drop Beams External Side 1 x 2 2.29 0.23 0.48 0.51 cu.m
4.9 Drop Beams Internal side 1 x 2 1.83 0.23 0.48 0.40 cu.m
4.10 Ground Floor Slab 1 x 1 2.29 2.29 0.15 0.79 cu.m
4.11 First Floor Columns upto Drop Beam 1 x 4 0.23 0.23 2.29 0.48 cu.m
4.12 RCC Lintel 1 X 4 1.83 0.23 0.3 0.51 cu.m
4.13 First Floor Drop Beam side 1 x 2 2.29 0.23 0.48 0.51 cu.m
4.14 First Floor Drop Beam inside 1 x 2 1.83 0.23 0.48 0.40 cu.m

8
NTS

4.15 First Floor Roof Slab 1 x 1 3.28 3.28 0.15 1.61 cu.m
4.16 First Floor Door Front Slab 1 1 0.71 0.91 0.1 0.06 cu.m
4.17 Door Slab wall 1 X 2 0.71 0.1 1.06 0.15 cu.m
TOTAL RCC(1:2:4) 22.85 cu.m
4.19 RCC Vertical Stair case Pipe (1:1:2) 0.083 cu.m
TOTAL FOR 1:1:2 0.083 cu.m
5.0 STEEL REINFORCEMENT
5.1 Deformed Steel 1940.16 KG
6.0 BLOCK MASONRY
6.1 First Floor 1 x 4 1.83 1.98 14.49 Sq.m
6.2 Deduction For Window 1 x 3 0.91 1.21 -3.30 Sq.m
6.3 Deduction For Door 1 x 1 0.76 1.98 -1.50 Sq.m
6.4 Stair Platfoam Side 1 x 3 1.83 0.76 4.17 Sq.m
6.5 Stair Platfoam front Step 1 x 1 2.29 0.30 0.69 Sq.m
TOTAL FOR BLOCK MASONRY 14.54 Sq.m
7.0 PLASTERING WORK
7.1 Ground Floor Under Sofit 1 x 1 1.83 1.83 3.35 Sq.m
7.2 Drop Beam Inside East/West side 1 x 4 1.83 0.48 3.51 Sq.m
7.3 Drop Beam side Front/Back 1 x 4 2.29 0.61 5.59 Sq.m
7.4 Drop Beam Bottom face 1 x 4 1.83 0.23 1.68 Sq.m
7.5 Bracing Beam 1 x 16 1.83 0.23 6.73 Sq.m
7.6 Columns upto Drop Beam 1 x 16 0.23 0.61 2.24 Sq.m
TOTAL FOR GROUND FLOOR 23.11 Sq.m
First Floor Plaster
7.7 Inside Walls upto Drop Beam 1 x 4 1.83 2.29 16.76 Sq.m
7.8 Window Deduction 1 x 3 0.91 0.21 -0.57 Sq.m
7.9 Door Deduction 1 x 1 0.76 1.98 -1.50 Sq.m
7.9 Drop Beam Inside 1 x 4 1.83 0.48 3.51 Sq.m

9
NTS

7.10 First Floor Under sofit 1 x 1 1.83 1.83 3.35 Sq.m


7.11 First Floor Side plaster 1 x 4 2.29 2.74 25.10 Sq.m
7.12 Window Deduction 1 x 3 0.91 0.21 -0.57 Sq.m
7.13 Door Deduction 1 x 1 0.76 1.98 -1.50 Sq.m
7.14 Shade Under sofit E/W side 1 x 2 3.28 0.50 3.28 Sq.m
7.15 Shade Under sofit Front&Back side 1 x 2 2.29 0.50 2.29 Sq.m
7.16 Shade Side 1 x 4 3.28 0.18 2.36 Sq.m
7.17 Inside window Faces 1 x 6 0.92 0.23 1.27 Sq.m
7.18 Inside window Faces 1 x 6 1.22 0.23 1.68 Sq.m
7.19 Door Inside Faces 1 x 2 0.76 0.23 0.35 Sq.m
7.18 Door Vertical Sides 1 x 2 0.98 0.23 0.45 Sq.m
7.19 Door Slab T/B 1 X 2 0.91 0.91 1.66 Sq.m
7.20 Door Raling Walls 1 x 4 0.71 1.06 3.01 Sq.m
TOTAL FOR FIRST FLOOR PLASTER 60.92 Sq.m
TOTAL PLASTER FIRST & GROUND FLOOR 84.11
8.0 WEATHER SHIELD PAINTS
8.1 Ground Floor Ceiling 1 x 1 1.83 1.83 3.35 Sq.m
8.2 Drop Beam Inside 1 x 4 1.83 0.48 3.51 Sq.m
8.3 Drop Beam side 1 x 4 2.29 0.61 5.59 Sq.m
8.4 Drop Beam Bottom face 1 x 4 1.83 0.23 1.68 Sq.m
8.5 Bracing Beam 1 x 16 1.83 0.23 6.73 Sq.m
8.6 Columns upto Drop Beam 1 x 16 0.23 0.61 2.24 Sq.m
8.7 First Floor Paint 0.00 Sq.m
8.9 Inside Walls upto Drop Beam 1 x 4 1.83 2.29 16.76 Sq.m
8.10 Window Deduction 1 x 3 0.91 0.21 -0.57 Sq.m
8.11 Door Deduction 1 x 1 0.76 1.98 -1.50 Sq.m
8.12 Drop Beam Inside 1 x 4 1.83 0.48 3.51 Sq.m
8.13 First Floor Ceiling 1 x 1 1.83 1.83 3.35 Sq.m

10
NTS

8.14 First Floor Side Paint 1 x 4 2.29 2.74 25.10 Sq.m


8.15 Shade Ceiling E/W side 1 x 2 3.28 0.50 3.28 Sq.m
8.16 Shade Ceiling Front&Back side 1 x 2 2.29 0.50 2.29 Sq.m
8.17 Shade Side 1 x 4 3.28 0.18 2.36 Sq.m
8.18 Inside window Faces 1 x 6 0.92 0.23 1.27 Sq.m
8.19 Inside window Faces 1 x 6 1.22 0.23 1.68 Sq.m
8.20 Door Inside Faces 1 x 2 0.76 0.23 0.35 Sq.m
8.21 Vertical Door Sides 1 x 2 0.98 0.23 0.45 Sq.m
8.22 Door Slab T/B 1 X 2 0.91 0.91 1.66 Sq.m
8.23 Door Raling Walls East/West 1 x 4 0.71 1.06 3.01 Sq.m
8.24 Stair Top Step Paint 1 x 19 0.76 0.34 4.91 Sq.m
8.25 Stair Bottom Step paint 1 x 19 0.76 0.34 4.91 Sq.m
8.26 Stair Raling Internal/External 1 x 2 6.86 0.92 12.62 Sq.m
8.27 Vertical Stair Pipe 1 x 1 0.52 4.57 2.38 Sq.m
TOTAL FOR PAINT 110.93 Sq.m
9.0 ROOFING MATERIAL
9.1 Bitumin (Grade 10/20) 3 Coat 1 x 1 3.27 3.27 10.69 Sq.m
9.2 Fiber Based Bituminized Roofing 2 Layers 1 x 1 3.27 3.27 10.69 Sq.m
9.3 PEA Gravel 2 Layer 1 x 1 3.27 3.27 10.69 Sq.m
10.0 PRECAST SPAIRAL STAIR CASE
11.0 BITUMIN COATING
11.1 Bitumin on Roofing 1 x 1 3.27 3.27 10.69 Sq.m
11.2 Foundation External side E/W 1 x 2 0.65 3.58 4.65 Sq.m
11.3 Foundation Internal side F/B 1 x 2 0.65 2.29 2.98 Sq.m
11.4 Inside Foundation 1 x 1 1.83 1.83 3.35 Sq.m
11.5 Foundation Vertical Side 1 x 4 3.58 0.46 6.59 Sq.m
11.6 Side Underground Walls 1 x 4 2.29 2.43 22.26 Sq.m
11.7 Underground Internal Wall side 1 x 4 1.83 2.13 15.59 Sq.m

11
NTS

11.8 Spairal Stair Platfoam side 1 x 3 2.29 0.45 3.09 Sq.m


TOTAL FOR BITUMIN 69.20 Sq.m
11.9 G.M Emreen Sheete 1.0 x 4.0 2.29 2.44 22.35 Sq.m
12.0 DISMENTLING WORK
12.1 EXISTING BLOCK MASONRY 1 x 1 7.62 1.22 9.30 Sq.m
12.2 Trench Side Walls 1 x 2 1.22 2.43 5.93 Sq.m
TOTAL BLOCK DISMENTLING 15.23 Sq.m
12.3 Trench Foundation 1 x 1 0.91 2.43 0.30 0.66 cu.m
12.4 Ground Floor Columns 1 x 4 0.23 0.23 0.30 0.06 Cu.m
TOTAL CONCRETE DISMENTLING 0.73 Cu.m