PROJECT TITLE: CONSTRUCTION OF CODON BHS INTO A BEMONC ( BASIC

EMERGENCY MATERNAL OBSTETRIC AND NEONATAL CARE) FACILITY

LOCATION: CODON ,San Andres Catanduanes

NARRATIVE REPORT ON THE PROPOSED CONSTRUCTION

Demolition / excavation / Earthworks

Construction of the BEmonc facility will include excavation and major


earthworks . The existing BHS will be demolished and will be extended as shown
in the plan, The existing BHS is 5.5 m x 6.0 while the proposed one is 8.5 x 12..
additional columns and masonry wal shall be erected and thus , needs
additional excavation and earthworks.

Plan/ elevations / sections/ description

The plan and specs of the proposed BEMONC is indicated in the plan including
the sections and elevation. The Proposed Bemonc facility is 12.o m x 8.50 m to
include Labor room , Delivery room ward and a room intended for the midwife
as required during maternal procedures. A small pantry is also included for
domestic use like cooking, washing etc…

Roof and Roof Framing

The Building will be provided with a new roof including the provision of Concrete
gutter around the roof line .Downspouts and catch basins would be provided
.Storm rain storage ( rain water collector) would also be constructed at the back
of the building to harness rain water during monsoon months. Trusses, hip trusses
and rafters will be installed to the new building. Machine bolts shall be used to
fasten the web members. The Roof plan indicates that the roof is planned to be
hip roof.

Masonry/ carpentry

The floor shall be made of concrete and shall be provided with .40 x .40 ceramic
tiles as prescribed in the plans. All masonry walls shall be of 5 “CHB. Carpentry
wall would be on doubled walled marine plywood (¼”). It shall be fastened on a
2x2 vertical and horizontal studs resting on 2x4 bases. Cabinets and lavatory
shall be provided according to plan. All concrete walls shall be plastered and
finished accordingly. Opening a Partition between the Labor and Delivery room
is necessary to provide easy access to expectant mother. A midwife room will
constructed adjacent to the birthing rooms because the midwife will assist in the
delivery procedures even after her duty. it would serve as her resting area. A rain
water collector shall be constructed at the back portion of the building to
harness rainfall during monsoon months. Gravel sand filter shall be provided for
the collector to ensure GOOD QUALITY of water. Provide sun and wind buffles in
front and on the right part of the Bemonc facility.

Placenta pit and sharp vault shall also be constructed for proper disposal of
health care waste. (See plan for specs.)

Painting

New painting work would be applied to the new building. Complete painting of
the new building will include application of concrete neutralizer and
succeeding coats of appropriate brand of paint. Paint emulsion will also be
applied to protect the building form wear and tear. Roof paint shall be double
coated to ensure proper protection of GI sheets from corrosion for reasons that
the location of the BHS is near the coast and therefore is prone to fast corrosion.

Provide :

Flat latex paint – Boysen or its equivalent


Gloss latex paint– Boysen or its equivalent
Flat wall enamel– Boysen or its equivalent
QDEname– Boysen or its equivalent
emulsion– Boysen or its equivalent

Electrical / Plumbing

Plumbing works-

Plumbing works will include the installation of new water and sewer lines to the
Bemonc facilty. A new designed septic tank will also be constructed for the new
building. (Watertight).all plumbing fixtures shall be provided as new as required
in the plans. Lavatory for the pantry and scrub up shall be stainless (.40 x .60 m
with wings) .

2 sets- Lavatory- American standard or its equivalent


2 sets- Water Closet-- American standard or its equivalent
3 sets- Kitchen Sink-stainless sink ( .40 x .60 m) with comp acc.
3 sets- Floor Drain- Stainless 4x4
5 sets- Faucet- goose neck stainless
1 Catch Basin
1 Water Meter

Electrical Works

Electrical works shall be completely new for the Bemonc building. It shall be in in
conformity to the electrical code of the Philippines. OR lights with high
illumination settings will be provided to the Delivery room and shall be
provided with a dedicated AVR to suppress power low voltage / and electrical
surges.
19 pcs.- Double gang Convenience Outlet- National Toshiba or its equivalent
3 pcs.- Single Gang Switch- National Toshiba or its equivalent
8 pcs.- Double Gang Switch- National Toshiba or its equivalent
2 pcs.- Triple Gang Switch- National Toshiba or its equivalent
8 sets- Plug In Type Circuit Breaker- brand of high quality
1 set- 8 Branches Panel Board- brand of high quality
1 set-Double Throw Switch- brand of high quality
1 set- Single Phase Kilowatthour Meter (Class 100)
1 set- Special Purpose Outlet (30A)
25 pcs- 22W Pinlight
1 set-2500 watts AVR ( ZEBRA or its equivalent)

Doors and Windows

All doors for the bemonc facility would be provided as new including door knob
and door closer ( see details at plan). Windows shall be of steel casement
including the provision of ¼ clear glass as panel and shall be fastened by silicon
as required.

Z bars for the steel casement shall be standard quality as specified in the plans. .
Double even and swing doors shall have a heavy duty jambs ( yakal or its
equivalent)

8 set- (1.2 x 3.0) Steel Casement Window(7/8 z-bar w/ ¼ thk. clear glass)
2 sets- (1.2 x 1.0) Steel Casement Window(7/8 z-bar w/ ¼ thk. clear glass)
1 sets- (0.4 x 0.4) Steel Casement Window(7/8 z-bar w/ ¼ thk. clear glass)
1 set-(2- .80x 2.10- .80 x 2.10) Double Action Swing Door w/ Clear Glass
1 set-(2- .60x2.10- .60 x 2.10) Double action swing Door w/ Clear Glass
3 sets- (.40 x 2.10)(.60 x 2.10) Uneven Door w/ Clear Glass
4 sets- (0.90 x 2.10) Flush Door
2 sets- (0.60 x 2.10) PVC Door w/ complete accessories
9 sets- Yale Door Knob

PREPARED BY:

LEO ARMAND ALA GAPAZ

Engineer III, PHO , Catanduanes