Escolar Documentos
Profissional Documentos
Cultura Documentos
FACTS: In July 1990, PNR and Kanlaon entered into contracts for the repair of three
PNR station buildings and passenger shelters.By November 1990, Kanlaon alleged that
it had already completed the three projects.
On 30 June 1994, Kanlaon sent a demand letter to PNR requesting for the release of
the retention money. However, PNR denied Kanlaon’s demand because of the Notices
of Suspension issued by the Commission on Audit (COA). Thus, forcing Kanlaon to file
a complaint for collection of sum of money plus damages against PNR. In its amended
complaint, Kanlaon even impleaded the COA.
In its answer, PNR admitted the existence of the three contracts but alleged that
Kanlaon did not comply with the conditions of the contract. Moreover, they alleged that
Kanlaon did not complete the projects. Thus, they did not have any unpaid balance. In
addition to that, PNR added that it had a valid ground to refuse the release of the
retention money because of the COA orders suspending the release of payment to
Kanlaon.
The TC ruled in favor of Kanlaon and ordered PNR to to pay the retention money and
unpaid contract price with 12% legal interest while COA was absolved of any liability
for actual or moral damages. Thus, prompting PNR to file a motion for reconsideration.
As a result, the TC modified its decision by lowering the legal interest rate from 12% to
6% per annum from the date of the first written demand. The CA affirmed the lower
court’s decision and held that the only reason PNR refused to pay Kanlaon was because
of COA’s Notices of Suspension and not Kanlaon’s non-completion of the projects.
ISSUE:
The clear purpose of these requirements is to insure that government contracts are
never signed unless supported by the corresponding appropriation law and fund
availability. In the case at hand, the three contracts between PNR and Kanlaon do not
comply with the requirement of a certification of appropriation and fund availability.
Even if a certification of appropriation is not applicable to PNR if the funds used are
internally generated, still a certificate of fund availability is required. Thus, the three
contracts between PNR and Kanlaon are void.
Therefore, the CA erred in affirming the decision of the lower court and its is reversed
and set aside.
Petitioners appeal was denied by the CAO II, which affirmed the MGC Corporate
Auditors findings.Unperturbed, petitioner sought a reconsideration of the CAO II
ruling from respondent COA arguing that his assignment to MGC was required by the
primary functions of his office and was also authorized by law, namely Executive Order
No. 284 issued on July 25, 1987. In turn, respondent COA denied petitioners appeal in
herein assailed COA Decision No. 2002-213.It upheld the CAO IIs ruling that
characterized the disallowed allowances and reimbursements as prohibited by the
Constitution.Furthermore, it also ruled that the said allowances and reimbursements
claimed by petitioner failed to pass the test of public purpose requirement of the law
and further emphasized that it is not enough that payments made to petitioner be
authorized by the Board of Directors of the MGC but it is likewise necessary that said
payments do not contravene the principles provided for under Section 4 of Presidential
Decree No. 1445 on the use of government funds, more specifically on the public
purpose requirement that is provided in Section 4(2) of Presidential Decree No. 1445,
otherwise known as the Government Auditing Code of the Philippines.A Motion for
Reconsiderationwas subsequently filed by petitioner, but this was likewise denied by
respondent COA in COA Decision No. 2003-087.
ISSUE:
In view of the public purpose requirement, the disbursement of public funds, salaries
and benefits of government officers and employees should be granted to compensate
them for valuable public services rendered, and the salaries or benefits paid to such
officers or employees must be commensurate with services rendered.In the same vein,
additional allowances and benefits must be shown to be necessary or relevant to the
fulfillment of the official duties and functions of the government officers and
employees.Petitioners theory that the compensation and benefits of public officers are
intended purely for the personal benefit of such officers, or that the mere payment of
salaries and benefits to a public officer satisfies the public purpose requirement is
wrong.That theory would lead to the anomalous conclusion that government officers
and employees may be paid enormous sums without limit or without any justification
necessary other than that such sums are being paid to someone employed by the
government.Public funds are the property of the people and must be used prudently at
all times with a view to prevent dissipation and waste.
DISMISSED
18. VERCELES v. COA
On June 11, 2001, the Sangguniang Panlalawigan (SP), through Resolution No. 067-
2001, gave blanket authority to the governor to enter into contracts on behalf of the
province. The SP reaffirmed the authority given to the governor through Resolution Nos.
068-2001 and 069-2001. On the same date, the SP also resolved to give the governor the
power to realign, revise, or modify items in the provincial budget.
The cost of the project was allegedly paid out of the Economic Development Fund (EDF)
allocation in the provincial budget for calendar years (CY) 2001 and 2002. The EDF is
the 20% portion of the province's internal revenue allotment (IRA) required by law to be
spent on development projects.
On October 12, 2001, the SP issued Resolution No. 104-A-2001, which effectively
revoked the blanket authority given to the governor to enter into contracts on behalf of
the Province.
On February 4, 2003, the COA Audit Team Leader issued an Audit Observation
Memorandum (AOM), finding that Verceles should have sought prior authority from the
SP pursuant to Sections 22 (c) and 465 (b) (1) (vi) of Republic Act No. 7160 or the Local
Government Code (LGC) before executing any MOA after the issuance of Resolution No.
104-A-2001.
Verceles filed his comments. The Audit Team Leader forwarded the AOM to the COA
Regional Office. The Regional Office affirmed the AOM and issued Notices of
Disallowance in the total amount of P7,528,175.46.
Verceles moved but failed to obtain reconsideration of the Notices of Disallowance. The
Legal and Adjudication Office also denied his appeal and motion for reconsideration.
Verceles elevated the case to the COA proper (national office) to challenge the disallowed
payments.
In his petition before the COA, Verceles mainly argued that the payments for the project
were covered by appropriations under the EDF allocation of the provincial budget for
CYs 2001 and 2002. Verceles argued that the local chief executive need not secure
express or specific authorization from the SP as long as a budget for a contract is already
appropriated. He claimed that the first and third MOAs were funded by the EDF
allocation in the CYs 2001 and 2002 budgets, and that, the second, fourth,
and fifth MOAs were funded by valid augmentations from other items also under the
EDF allocation.
ISSUE: WON the Notice of Disallowance issued by the COA Regional Office is proper.
The COA held that the augmentations or realignments made by Verceles to fund
the second, fourth, and fifth MOAs were contrary to Section 336 of the LGC. The COA
ruled that the disbursements also violated Section 85 (1), of Presidential Decree (PD) No.
1445 or the Government Auditing Code of the Philippines and Section 305 (1) of the
LGC. These provisions underscore the need for an appropriation before contracts
involving the expenditure of public funds may be entered into.
The COA further ruled that at the time Verceles made the augmentations to fund
the second, fourth, and fifth MOAs, he was not authorized by the SP, and that the CY
2003 appropriation ordinance could not ratify the MOAs entered into in CYs 2001 and
2002.
The COA also explained that Resolution Nos. 067-2001, 068-2001, and 069-2001
authorized Verceles' predecessor only (former Governor Hector Sanchez) and that the
grant of authority did not extend to Verceles. The COA reasoned that a resolution does
not have the attribute of permanence. Consequently, the public funds spent to pay for
the project had no legal basis. Thus, the first and third MOAs were still unauthorized
even assuming they were funded by the EDF allocation in CYs 2001 and 2002.
WHEREFORE, premises considered, the instant appeal is hereby DENIED for lack of
merit. Accordingly, LAO-Local Resolution No. 2007-002 dated January 16, 2007
affirming the Notices of Disallowance in the aggregate amount of P7,528,175.46 is
hereby AFFIRMED.
Verceles moved but failed to obtain reconsideration of the COA decision.He came to this
Court for relief through the present petition for certiorari. On August 12, 2014, the Court
granted Verceles' prayer for the issuance of a temporary restraining order enjoining the
implementation of the assailed COA decision.
Thereafter, a Notice of Garnishment was issued against the funds of NEA with
Development Bank of the Philippines (DBP) to the extent of ₱16,581,429.00.
In its Order of May 17, 2000, the RTC denied the Motion to Quash but, at the same time,
held in abeyance the implementation of the Writ of Execution, thus:
WHEREFORE, the motion to quash writs of execution/ garnishment is DENIED but the
implementation of the judgment is placed on hold for ninety (90) days reckoned from
this day. The respondents are directed to formally inform this Court and the
petitioners of the prospect of obtaining funds from Department of Budget
and Management within 30 days from receipt and every 30 days
thereafter, until the 90 day period has lapsed.
The motion to direct DBP to release to the petitioners the NEA funds garnished earlier
amounting to ₱16,591.429 is also DENIED.
Meanwhile, in a letter dated June 28, 2000, former DBM Secretary Benjamin E. Diokno
informed NEA Administrator Conrado M. Estrella III of the denial of the NEA request
for a supplemental budget on the ground that the claims under R.A. No. 6758 which the
RTC had ordered to be settled cannot be paid because Morales, et al. are not "incumbents
of positions as of July 1, 1989 who are actually receiving and enjoying such benefits."
Subsequently, the RTC issued an Order dated January 8, 2001, denying the Motion for
an Order to Implement Writ of Execution, citing the same SC Administrative Circular
No. 10-2000.
Upon a Petition for Certiorari filed by Morales, et al., the CA rendered the July 4, 2002
Decision assailed herein, the decretal portion of which reads:
WHEREFORE, the petition is hereby GRANTED. The Order dated January 8, 2001 and
the Resolution of December 11, 2000 of the public respondent Judge are declared NULL
and VOID.
Accordingly, the respondent judge is directed to implement the Writ of Execution
relative thereto.
Under Commonwealth Act No. 327, as amended by Section 26 of P.D. No. 1445, it is the
COA which has primary jurisdiction to examine, audit and settle "all debts and claims of
any sort" due from or owing the Government or any of its subdivisions, agencies and
instrumentalities, including government-owned or controlled corporations and their
subsidiaries. With respect to money claims arising from the implementation of R.A. No.
6758, their allowance or disallowance is for COA to decide, subject only to the remedy of
appeal by petition for certiorari to this Court.
All told, the RTC acted prudently in halting implementation of the writ of execution to
allow the parties recourse to the processes of the COA.
In fine, it was grave error for the CA to reverse the RTC and direct immediate
implementation of the writ of execution through garnishment of the funds of petitioners,
WHEREFORE, the petition is GRANTED. The July 4, 2002 Decision of the Court of
Appeals is REVERSED and SET ASIDE. The Resolution dated December 11, 2000
and Order dated January 8, 2001 of the Regional Trial Court, Branch 88, Quezon City in
Special Civil Action No. Q-99-38275 are REINSTATED.
SO ORDERED.
Facts: The controversy had its origin in the stabbing of Reynaldo de la Cerna, the son
of the de la Cerna Spouses. He was rushed to the Cebu City Medical Center, but died due
to severe loss of blood. The de la Cerna Spouses claimed that their son died because of
the ineptitude, gross negligence, irresponsibility, stupidity and incompetence of the
medical staff. They filed a complaint for damages in the Regional Trial Court of Cebu
City against the city of Cebu, the Sangguniang Panlungsod, and five physicians. The City
of Cebu was impleaded as defendant on the theory that as employer of the doctors, it was
vicariously responsible for the latter’s negligence.
An amicable settlement was entered into between the parties whereby the City of Cebu
agreed to pay the plaintiff the sum of P30,000.00 as financial assistance. This
agreement was ratified by the Sangguniang Panlungsod and the City Budget Officer was
authorized to include in the Supplemental Budget for the year 1989 the amount of
P30,000.00. The agreement was approved by the Regional Trial Court.
About eleven (11) months later, the Commission on Audit (COA) disallowed the financial
assistance declaring that it is not within the powers of the Sangguniang Panlungsod to
provide monetary assistance that would promote the economic condition and private
interests of certain individuals only.
The Motion for Reconsideration of the City was denied by COA, hence, this petition
ascribing grave abuse of discretion to the COA and its Members.
Issue: Whether or not COA committed grave abuse of discretion in disallowing the
city’s appropriation of P30,000.00 made conformably with the compromise agreement
in the civil suit against the City of Cebu.
That the City of Cebu complied with the relevant formalities contemplated by law can
hardly be doubted. The compromise agreement was submitted to its legislative council,
the Sangguniang Panlungsod, which approved it conformably with its established rules
and procedure. Neither may it be disputed that since, as a municipal corporation, Cebu
City has the power to sue and be sued, it has the authority to settle or compromise suits,
as well as the obligation to pay just and valid claims against it.
The COA failed to realize that payment thereof was part of the consideration, not merely
for the settlement of a claim, but for the settlement of an actual controversy. By making
reciprocal concessions, the parties put an end to the action in a manner acceptable to all
of them, thus eliminated the contingency of being made to assume heavier liability in
said suit for damages instituted against it in connection with activities being undertaken
by it in its proprietary functions and in accordance with which it may be held liable ex
contractu or ex delito, for the negligent performance of its corporate, proprietary or
business functions.