Escolar Documentos
Profissional Documentos
Cultura Documentos
V.N. Prasad
• Department of Mechanical
Engineering
• RGUKT, R K Valley
Gating systems refer to all those elements, which are connected
with the flow of molten metal from the ladle to the mold cavity.
Elements of gating system are:
1. Pouring basin,
2. Sprue,
3. Sprue base well,
4. Runner,
5. Runner extension,
6. In- gates (Gates)
7. Riser
Any gating system designed should aim at providing a defect – free
casting.
This can be achieved by making provision for certain requirements
while designing the gating system.
These are as follows:
1. The mold should be completely filled in the smallest time possible
without having to raise the metal temperatures or use higher metal
heads.
2. The metal should flow smoothly into the mold without any
turbulence. A turbulent metal flow tends to form dross in the mold.
3. Unwanted material such as slag, dross and other mold material
should not be allowed to enter the mold cavity.
4. The metal entry into the mold cavity should be properly controlled
in such a way that aspiration of the atmospheric air is prevented.
5. A proper thermal gradient be maintained so that the casting is
cooled without any shrinkage cavities or distortions.
6. Metal flow should be maintained in such a way that no gating or mould
erosion takes place.
7. The gating system should ensure that enough molten metal reaches the
mould cavity.
8. The gating system design should be economical and easy to implement
and remove after casting solidification.
9. Ultimately, the casting yield should be maximized.
Elements of a Gating system
Pouring basin
• Skim Core or Skimmer is provided to stop the slag and dirt from
entering the mould cavity which floats on the top and only allows the
clean metal underneath it into the sprue.
• The pouring basin may be cut into the cope directly or a separate dry
sand pouring basin may be prepared and used as shown in figure.
• A ceramic filter (Fig.b) completely stops slag allowing only clean metal
to go into the sprue, and also ensures a constant flow of metal.
• Sprue is the channel through which the molten metal is brought into
the parting plane, where it enters the runners and gates to ultimately
reach the mould cavity.
• A sprue is tapered with its bigger end at top to receive the liquid metal.
The smaller end is connected to runner.
The design of the sprue is based on the Law of continuity of mass:
Assuming
– entire mould is at atmospheric pressure (no point below atmospheric)
– metal in the pouring basin is at zero velocity (reservoir assumption)
•• What
is Law of continuity of mass?
• The rate of flow of mass of the fluid is constant at any cross – section.
• Mass flow rate = A V = constant
2
Q2
Where Q = Volume rate of flow
•Q
2
we get
∴
• As the liquid flows down, the cross section of the fluid decreases. So
the taper is provided in the sprue.
• Liquid loses contact if the sprue is straight which could cause
“aspiration”.
(Or)
• If the sprue were to be straight cylindrical, then the metal flow would
not be full at the bottom, but some low-pressure area would be
created around the metal in the sprue.
• Since the mould is permeable, atmospheric air would be breathed
into this low-pressure area which would then be carried to the mould
cavity.
• To eliminate this problem of air aspiration, the sprue is tapered to
gradually reduce the cross section as it moves away from the top of
Sprue Base Well
Reasonable
proportions for a
sprue base well are
shown in the figure
Fig. (a)
Fig. (b)
• Non-uniform, long path,
and/or slow metal flow
may produce unfilled
sections or solidification
shrinkage in the casting.
Bottom Gates
Parting Gate
• It is most commonly used gate and is a compromise between
top and bottom gates.
• The gate is provided at the parting line of the mould.
• Of all the gates, this is also the easiest and most economical
in preparation.
Step Gate
• They are used for heavy and large
castings.
• The molten metal enters mold
cavity through a number of ingates,
which are arranged in vertical
steps.
• The size of in-gates is normally
increased from top to bottom.
• This ensures the gradual filling of
the mold without mold erosion and
produces sound casting
a) Simple system
b) Simple inclined steps
c) Inclined steps with common junction
d) Reversed down runner
In-gate Design
• Multiple ingates often are preferable for large parts
• The minimum ingate length should be three to five times the
ingate’s width, depending on the metal being cast.
• And generally made wider compared to the depth, up to a ratio
of 4.
• This facilitates in the severing of gating from the casting after
solidification.
• Sometimes it is preferable to reduce the actual connection
between the in-gate and the casting by means of a neck down,
wash burn for easy removal of the gating.
• Curved ingates should be avoided, as far as possible.
To make for more uniform flow through all the gates, progressively, the
runner area should be reduced after each-in-gate, such that restriction
on the metal flow would be provided.
Gating Ratios
• The gating ratio refers to the proportion of the cross
sectional areas between the sprue, runner and in-gates and is
generally denoted as
The total cross sectional area The total cross sectional area
decreases towards the mould cavity. increases towards the mould cavity.
Complex and thin sections can be Complex and thin sections may not be
successfully cast. successfully cast.
Slag Trap Systems
• To obtain sound casting quality, it is essential that the slag and other
impurities be removed from the molten metal fully before it enters
the mould cavity.
• Apart from the use of pouring basin and strainer cores follows are the
two methods to trap the slag and other impurities.
1. Runner Extension:
• A runner extension having a minimum of twice the runner width is
desirable.
2. Whirl Gate:
• This utilizes the principle of centrifugal
action to throw the dense metal to the
periphery and retain the lighter slag at
the centre.
• In order to achieve this action, it is
necessary that the entry area should be at
least 1.5 times the exit area so that the
metal is built up at the centre quickly.
• Also, the metal should revolve 270o
before reaching the exit gate so as to
gain enough time for separating the
impurities.
Chill
• Chills are provided in the mould so as to increase the heat extraction
capability of the sand mould.
• A chill provides a steeper temperature gradient so that directional
solidification as required in a casting can be obtained.
• The chills are metallic objects having higher heat absorbing
capability than the sand mould. Chills are large heat sinks.
3. External:
• Placed in the mould cavity
adjoining the mould cavity at any
required position.
• Providing a chill at the edge may
hot have the desired effect as the
temperature gradient is steeper at
the end of the casting.
• It would have maximum effect if it
is placed between two risers.
Internal chills:
• Placed inside the mould cavity where an external chill cannot be provided.
• The material of the chill should approximately resemble the composition of
the pouring metal for proper fusing.
• The chill is located inside of the casting and becomes part of the casting.
• Cleanliness of internal chills is far more important because they are
surrounded on all sides by the molten metal.
• Because of the serious problems associated with internal chills, they should be
sparingly used.
• Chills never can compensate shrinkage, but will only relocate shrinkage!
• It will never decrease the liquid shrinkage of a material but it will concentrate
the shrinkage into locations close by or in the influence zone (feeding zone) of
the risers.
Figure: Typical internal and external chills
• In those castings which
have ribs or bosses, the
joint is a source of hot
spot.
• This hot spot could be
eliminated by using a
chill of appropriate size
at the end of the rib or
the appendage.
Casting yield =
The higher the casting yield, the higher is the economics of the foundry practice.
Castin yield depends to a great extent on the casting materials and the
complexity of the shape.
Heavily shrink materials have lower casting yields.
Massive and simple shape have higher casting yields compared to small and
complex parts.
Figure: Utilization of the metal in the foundry
Table: Casting Yields
Choke Area
• It is the main control area which
meters the metal flow into the
mould cavity so that the mould
is completely filled within the
calculated pouring time.
• The smallest area that occurs
at the bottom of the sprue is
known as “choke area”.
• Hence, the first element to be
designed in the gating system is
the sprue size and its
proportions.
• The main advantage in having sprue bottom as the choke area is
that proper flow characteristics are established early in the mould.
• Choke area is designed based on Bernoulli’s theorem.
Bernoulli’s equation
• Bernoulli’s theorem states that the total energy head remains
constant at any section and
• the equation from ignoring frictional losses is
• choke area can be calculated by applying Bernoulli’s
The
equation between 1 and 3, we get.
Where,
Ac = Choke area, mm2 (at section (3))
W = casting mass, kg
t = Pouring time, (seconds)
d = mass density of the molten metal, kg/mm3
g = acceleration due to gravity, mm/s2
H = effective metal head (Sprue height), mm
C = efficiency factor which is a function of the gating system used
Where,
h = height of sprue
p = height of mould cavity in cope
c = total height of mould cavity
Efficiency factor:
• The efficiency coefficient of the gating system depends on the various
sections that are normally used in a gating system.
• For aluminimum castings, a metal flow rate of 4.044 g/min for 1 mm2 of
sprue area in an unpressurized gating is found to be sufficient for
achieving sound castings.
Pouring Time
• One of the objectives, for design the gating system is to fill the mould
in the smallest time.
• The time for complete filling of a mould termed as Pouring time, is
a very important criterion for design.
• Too long a pouring time requires a higher pouring temperature.
• Low pouring rate may not permit the complete filling of the mould
cavity in time if the molten metal freezes fast and thus defects like
cold shuts may develop
• Too less a pouring time means turbulent flow in the mould which
leads to mould erosion, rough surface, excessive shrinkages etc.
(makes the casting defect prone).
• It is very necessary to know optimum pouring rate or pouring time for
metals to be cast.
• The pouring time depends on the casting materials, complexity of the
casting, section thickness and casting size.
• The various relations used are not theoretically obtained but established
generally by the practice at various foundries and by experimenters.
• The general considerations for choosing pouring time for grey cast iron
may not be much relevant for steels since they lose heat very fast and
therefore the pouring time should be very less.
• For non ferrous materials, a longer pouring time would be beneficial
since they lose heat slowly and also tend to form dross if metal is
poured too quickly.
• Since the thickness of casting is effected to a great extent, by the ratio
of surface area to volume of the casting, it is an important variable in
calculating the optimum pouring time in addition to the mass of the
casting itself.
• Normally,
while considering the mass of casting, it may not be
necessary to consider the mass of the gating system.
• However, if gating systems are in comparable size to the actual
casting, it may be desirable to include them for the calculation.
Where
T = average section thickness, mm
W = mass of the casting, kg
•(2) Grey cast iron, mass greater than 450 kg
Pouring time,
(3)Steel castings
Pouring time, seconds
• For castings above 450 kg and up to 1000 kg
7.
Pouring time,
• Typical pouring times for castings whose mass is less than 200 kg
and average section thickness of 25 mm are
• Typical pouring rates used for different casting alloys are given in
the following table. The calculated values from any of the above
formulae may be checked from the table.
Solution:
Grey cast iron,
Since mass is less than 450 Kg.
Pouring time,
•Steel,
• Pouring time, seconds
seconds
•
Problem2: Calculate the optimum pouring time for a casting
whose mass is 100 kg and a thickness of 25 mm. Fluidity of iron
is 32 inches. Calculate both for cast iron and steel.
Solution:
Grey cast iron
Pouring time,
Steel
Pouring time, seconds
= 16.429 seconds
Example 3:
For the casting shown in the Figure, which is to be
made in cast iron, calculate the choke area.
•
Solution:
= 366.648 mm2
• In a pressurized gating system, the choke is located
in in-gates, with four ingates, the in-gate area of
each is 90 mm2,
• assuming rectangular cross sections for in-gates, the
ingate dimensions would be 15×6 mm.