AREA (SQ.M)
COBBLE STONE -SIDE WALK 526.52
COBBLE STONE -ROAD 6,716.91
TOTAL AREA : 7,243.43
LA INSULAR CIGAR - BLOCK 2
MATERIAL CO
ITEM DESCRIPTION QTY. UNIT
UNIT COST
DIVISION 1. GENERAL REQUIREMENTS
A. Mobilization/Demobilization 5.00 months
B. Salary and Wages
1 - Project Engineer 5.00 months
1 - Quantity Surveyor 5.00 months
1 - Checker 5.00 months
2 - Security Guard 5.00 months
2 - Safety Crew
26 days/8 hours/2 safety crew @ 580.00 5.00 months
26 days/OT 5 hours per day/2 safety crew @ 72.50 5.00 months
4 Sundays/8 hours /2 safety crew @ 754.00 5.00 months
1 - Driver 5.00 months
C. Electricity 5.00 months
D. Water 5.00 months
SUB-TOTAL :
SUB-TOTAL :
B. SLAB
Formworks 916.37 sq.m 440.00
Concreting (4000 PSI) 104.55 cu.m 5,260.00
Rebars -10mm dia. 4,379.76 kgs. 37.35
Tie Wire 2.19 Rolls 980.00
C. PEDESTAL
Formworks 104.00 sq.m 440.00
Concreting (4000 PSI) 26.00 cu.m 5,260.00
D. FOOTING
Formworks 78.00 sq.m 440.00
Concreting (4000 PSI) 29.25 cu.m 5,260.00
Page 2 of 5
Hor.Rebar -16mm dia. 1,538.78 kgs. 33.35
Vert.Rebar -16mm dia. 538.57 kgs. 33.35
Tie Wire 1.04 Rolls 980.00
SUB-TOTAL :
B. ROOFING
G.A 24 PRE-PAINTED LONG SPAN-RIB TYPE - 3'x12'x0.45mm 275.94 sq.m 660.00
Angle Bar - 1 1/2 x 1 1/2 x 1/4" (6mm) 2,352.00 kgs. 49.91
C-Purlins - 2'' x 4'' x 1.6mm 1,270.20 kgs. 500.00
Gutter - 04.mm x 0.61mm x 2.44m 93.92 Lm 142.62
SUB-TOTAL :
Page 3 of 5
JULY 17, 2019
1,845,210.00
39,487.50
Page 4 of 5
51,318.45 3.70 5,693.50 57,011.95
17,961.46 3.70 1,992.73 19,954.18
1,017.91 1,017.91
2,559,153.88
6,697,443.94
11,141,295.32
SQ.M 871.29
PESO/SQ.M 12,787.13
Page 5 of 5