Form No: XXX

NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Records of Revisions
Effective
Revision Description
Date

- XX Jun ’19 Initial Issue

Page 1 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Contents
Page No.
1. Introduction 4
2. Specification Clauses 4
3. Reference / Code of Practices 4
4. Scope Of Work 4
4.1 Site Location 4
4.2 Site Layout 5
4.3 Scope 5
5. Organization Chart 7
6. Schedule 7
7. Plants and Machinery 7
8. Sequence of Works 8
9. Work Procedure 9
9.1 Piling to be carried out by competent person 9
9.2 Construction of Concrete Guide Wall 9
9.3 Formation of Secant Bored Pile 12
10. Safety, Health and Environment 23
10.1 Personnel PPE 24
10.2 Equipment & Operator 24
10.3 Environmental Protection 25
10.4 Certificates 25
10.5 Sign Boards 26
10.6 Noise Control 26
10.7 Safety & Health Hazard Log (Risk Analysis) 26
11. Quality Assurance 26
11.1 Tolerances 27
11.2 Concrete 27
11.3 Pile Excavation 28
11.4 Placement of Reinforcement 29
11.5 Concreting in Wet Hole 31
11.6 Drilling Fluids and Soil Tests 32
11.7 Dry Hole Construction 32
11.8 Casting Level 32
11.9 Concrete Cover 32
11.10 Inspection and Test Plan 32
11.11 Forms and Checklist 32
Page 2 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

12. Emergency Response plans 32


12.1 Emergency Response Team (ERT) 33
12.2 Emergency Action 33
12.3 List of Emergency Contact Numbers 34
12.4 Emergency Reporting Procedures 34

Appendices

Appendix A : Organization Chart


Appendix B : Schedule
Appendix C : Machinery Photos and Catalogue
Appendix D : Sign Board
Appendix E : Risk Assessment
Appendix F : Safe Work Procedure
Appendix G : Emergency Reporting Procedures
Appendix H : Inspection and Test Plan for Bored Pile Work
Appendix I: Checklist

Page 3 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

1. Introduction

This method statement outlines the proposed work method for secant bored pile on the Proposed
Contract N109A – Design & Construction of North-South Corridor (Tunnel) Between Sin Ming
Avenue and Ang Mo Kio Avenue 4. The purpose of the secant bored pile work is to construct a
temporary earth retaining structure.

Secant bored piles are interlocking piles that form a continuous watertight wall. A continuous
reinforced concrete guide wall is to be constructed to pinpoint the location of each overlapping
pile. Piles are spaced at a distance according to the Specifications.

2. Specification Clauses
The following clauses, but not limited to, from the contract specifications are applicable:

No Specification Clause Description


1 Particular Specification - Secant Bored Pile Wall
M&W Specification – Civil
2 5 Piling Works
& Structural Works

3. Reference / Code of Practices

Singapore Standards:
 SS CP 79: Safety management system for construction worksites
 SS CP 4: Foundations

Code of Practice
o BS 8002: Code of practice for Earth Retained Structures
o BS 8004: Code of practice for Foundations
o BS 5228: Noise and vibration control on construction and open sites
o Part 1(1997) Code of practice for basic information and procedures for noise and
vibration control
o Part 4 (1992) Code of practice for noise and vibration control applicable to piling
operation

Page 4 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

4. Scope of Work

4.1 Site Location

4.2 Site Layout

Page 5 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

4.3 Scope

The scope of work includes the installation of secant bored piles of assumed diameter of
1200mm~1800mm reinforced secondary piles and 1200mm~1800mm unreinforced primary
piles.

4.3.1 Design Requirement

Item ERSS Wall Toe Level Avg Depth /Avg Rock Wall detail
FUI Station
1 ERSS 1 5m into GIII below FEL or 62mRL 40.0m / 15.9m 1.8m dia
2 ERSS 2 3.5m into GIII below FEL or 71mRL 28.6m / 6.0m 1.5m dia
3 ERSS 3 2m into GIII below FEL or 76.5mRL 30.0m / 7.2m 1.5m dia
4 ERSS 4 5m into GIII below FEL or 62mRL 40.0m / 15.9 1.8m dia
5 ERSS 5 1m into GIII below FEL or 83mRL 22.0m / 1.0m 1.2m dia
NSC Tunnel
6 ERSS F1 3.6m into GV-N100 or 86mRL 23.0m / 6.0m 1.2m dia
7 ERSS S 7.1m below FEL 25.0m / 8.0m 1.2m dia

Note: The Toe Level will be changed as per design confirmation and approval.

5. Organization Chart

 Please refer to Appendix A : Organization Chart

6. Schedule

 Please refer to Appendix B : Schedule

Page 6 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

7. Plants and Machinery

Below table is according to 1 set/gang of equipment and plants. Subject to geological


condition and site situation. Machinery and equipments will be adjust according to the
construction sequence given based on site situation.

Equipment Specification Unit Quantity

Pile Driver BG 36 set 1

RCD Drill Rig Buama RCD R1815/20 set 1 1

Oscillator Buama C2000G set 1 1

Auger Moto 200HP set 1

Service Crane 100 ton to 150 ton set 1

Excavator 1.0 m3 set 1

Air Hammer D1200 to D1800 set 1

Generator Set 600 KW set 1

Compressor 900 CFM set 1

Steel Casing Various set 1

Tremie Pipe Ø300 mm set 1

Please refer to Appendix C : Machinery Photos Catalogue

Page 7 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

8. Sequence of Works

The general work procedures shall be as follows:

Ground Leveling

Survey

Guide Wall Construction

Drilling (Casing)

Rock Drilling / Hammering

Slime / Surging and Cleaning

Rebar Cage Installation (with Steel Pipe)

Concrete Casting

Casing Extraction

Page 8 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

9. Work Procedure

The construction of the secant bored piles are critical along the whole stretch of structure whereby
there is a possibility of an existence of underground rock layer that might hinder to the boring
works. This method statement was prepared for the implementation of the typical piling works
using BG method on soft layer and using Reverse circulation drilling method on the hard/rock
geological formation.

The basic concept of BG is to apply a drilling technique wherein the outer casing advances
through the rock layer by reverse circular drilling method. Hammering action at the bit is
triggered by a compressed air which is use as a medium to wash out the cuttings. Upon reaching
the required penetration length; the borehole is eventually casted by either concrete or reinforced
concrete depending on the type of SBP (primary or secondary) being considered. The process is
then repeated until it formed continuous bored pile columns for the purpose of earth retaining
structure during the cut and cover tunnel excavation works.

Aside from BG ’s, auger drill machine and other conventional type of boring machine, Rotator
and Oscillator adopted in assistance casing installation into hard/rock formation.

9.1 Piling to be carried out by competent person

Piling works will be carried out by a trained operators, site supervisors, and foreman who
are well experienced with piling works.

Foreman or workers directly involved in the maintenance work at heights will be provided
with Fall Protection Equipment (fall arrester, full body harness) and should possess a valid
Work at Height certification.

9.2 Construction of concrete guide wall

Prior to the construction of the Secant Bored Pile (SBP), a reinforced concrete guide wall.

The concrete guide wall will form a template for the layout of the secant pile wall and ensur
e the accurate positioning of the primary and secondary piles in order to achieve the require
d interlocking of the piles.

The concrete guide wall is to be constructed accurately in line and level. All setting out will
be checked and verified by maincon surveyor to ensure correct position.

Steps of construction for concrete guide wall

Page 9 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Step 1: Set out axis and corner points.

Step 2: Position prefabricated formwork and to be checked by the surveyor.

Step 3: Striking of forms.

Step 4: Backfill with excavated materials to top of the guide wall.

1.2 m
1.0 m

SECTION A-A

Page 10 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Sample Photos of Concrete Guide Wall

Page 11 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

9.3 Formation of Secant Bored Pile

9.3.1 Primary Pile (Soft Pile without reinforcement cage)

The surveyor will set a reference level prior to commencement of work to determine and
measure the toe level of the pile.

Surveyor to peg the center point of primary or secondary pile.

Using upper and lower auger, temporary casing will be driven until the top of rock head.
Steel casing more than 12m shall be joined using welding.

Drilling/hammering of primary (as well as secondary) bored pile as per required


penetration length.

The verticality can be check with the following method:

 Using automatic plumb system installed at the drilling machine.

 Using two plumb bob hanged into a stand approx. 20 ~ 30 meters away, plumb the
vertical face of the steel casing with that of the plumb bob. Hand signal will be used as
a means of communication.

Continue boring until the required depth.

Page 12 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Boring using BG Machine will stop when the required penetration depth is achieved. Aside
from conventional BG machine, Reverse Circulars Drilling method will also be adopted for
cutting through rock layers with assistance from rotator and. This RCD drilling technique us
es casing with assistance of oscillator or rotary to drill to required hard rock formation.

Bauer BG 36

Page 13 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Cleaning bucket shall be use in cleaning of bored pile toe.

The borehole will be checked and confirmed by the QP(S) prior to casting.

Ready mixed concrete will be discharged into the borehole using either tremie pipe method
or pumped through the 4” pipe (rod) installed at drilling machine using a portable concrete
pump. With the discretion of the Engineer, concrete can also be discharged directly into the
borehole as long as the borehole is completely dry and stable. Before placing of concrete,
all loose materials must be cleaned out. Accepted measures shall be taken to avoid
loosening of the sidewalls of the shaft, concrete segregation, bleeding and to ensure that the
concrete at the bottom of the borehole is not deficient.

After the completion of casting, the temporary casing will be extracted by reverse rotary
method thru the boring rig. Casing extraction shall be completed within 2 hours after
concrete casting had been completed. Alternatively, vibro hammer will be on standby for
emergency purposes in the event that steel casing cannot be easily extracted.

Page 14 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 15 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

9.3.2 Excavation at Rock/hard Geological Formation using Reverse Circulation Drill


(RCD) Method

Due to shallow rock/hard geological formation encountered and deep drilling


required, Reverse Circulation Drill (RCD) method is selected to increase the
productivity of the drilling rate compare to conventional BG drill machines.

1. Outline of construction method

Reverse Circulation Drill Method has a special Roller Bit installed at the end of the
drill rod to break the rock by rotating 360 degrees. The crushed excavated soil is
discharged through the drill rod pipe, and the discharged circulating water is
returned through the settler tank. It is a method to circulate to excavator.

2. Characteristics of construction method

1) It is advantageous for construction of a deep pile, and the casing is inserted into
the soil layer.
2) It is used for foundation of bridges, foundation of large buildings, foundation of
overpasses, etc., and it is applied in parallel with top-down construction method.
3) Method to cope with the demand for large bearing capacity due to the trend of
enlarging the structure
4) Low noise and less noise make it suitable for urban construction
5) Replacement of some parts (clamp, stabile eyes, drill bit)
6) Durability is excellent by installing special drill bit.

3. Specifications of equipment

3.1 - RCD (Reverse Circulation Drilling Machine)

Page 16 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

The RCD Machine excavates the upper soil layer with a CASING OSCILLATOR or
ROTATOR and then excavates the rock by rotating a special bit attached to the end of
the drill rod when drilling the soft rock and light rock layer and DRILL ROD PIPE
SUCTION by AIR to excavate to the ground, and it is a key method of large-scale spotting
and TOP DOWN construction method used for bridge foundation, large building
foundation, and overpass construction. Maximize excavation speed with powerful power
by hydraulic system.

o Suitable for urban construction with low vibration and low noise.
o Can be used with a casing diameter as stated in drawing by replacing some parts
(clamp, stabilize, drill bit).

Page 17 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

3.2 - Oscillator

The Oscillator used in the Benoto method moves the casing tube to the left and right
while inserting the casing into the ground and simultaneously the Hammer Grab or Chisel
is concurrently completed. After the excavation is completed to a predetermined depth,
the inner slime is removed and the reinforcing cage is inserted Con'c It is a machine to
make a pile in the field.

o It can be used with casing diameter as stated in drawing only with adapter.
o Clamping collar consisting of 5 links prevents cracking by perfect clamping on
excavation
o Vertical adjustment is easy when crimping.
o Superior stability and durability are realized with the super strength frame and the
optimum structural design completed with state-of-the-art computer engineering.
The adoption of the advanced hydraulic system and the adoption of the remote
control system enable safe operation.

Page 18 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

3.3 - Hammer Grab - for excavation

It is applied to the operation of inserting the casing into the casing by sandwiching the
casing by Oscillator or Rotator in the base work of large diameter, and it is easier to
repair and repair than the existing type.

o Can be used in soil layer.


o BM-H150 model can be used for both Casing diameter Ø1200 and Ø2000 only
by replacing Middle part, Weight guide and Shovel.

Page 19 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

4. Construction Sequence (With Site photo)

1) Site surveying 2) Equipment setting

3) Installation drilling bit 4) Surging

5) Fabrication of Rebar Cage 6) Reinforced cage TREMIE pipe


installation

Page 20 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Overall Sequence of RCD

Casing installation with the assistance of Once Casing reached to designated depth, setup of
Oscillator and BG/Grab machines. RCD drilling rig and commence drilling at the hard
geological formation.

Once reached the pile toe level, installation of After installation of rebar cage, pour concrete using
rebar cage using crane termie method.

Page 21 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

One the concrete is harden, remove of casing.

Page 22 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

9.3.3 Secondary Pile (Hard Pile)

The secondary pile (hard pile) to be cored in between two soft piles using steel casing
method. (Equipped with a ring of cutting teeth)

It will be connected to the rotary drive adapter of the boring rig.

Using boring rig, the casing will be installed above the rock strata to prevent collapse.

After the casing penetrated few meters into the ground, the verticality of the casing will be
checked by using automatic plumbness measuring system installed at the drilling machine
and counter checked by the two plumb bob (20-30) away from the pile location.

Steel casing more than 12m shall be joined using welding.

Continue boring until the required depth.

Boring using BG Machine will stop when the required penetration depth is achieved.
Aside from conventional BG machine, Core Barrel Hammer System (CBHMS) will also
be adopted for cutting through rock layers. This drilling technique uses a core barrel to
take out the cuttings from the rock layers.(see Appendix C for machine specifications)

Cleaning bucket will be use in cleaning up to the pile toe of soil debris.

The borehole will be checked and confirmed by all parties prior to lowering of the
reinforcement cages.

Page 23 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

If the required reinforcement cage is more than 12 meters long, it will be spliced to the
second cage by the use of U-bolt or as specified on shop drawing.
.
Page 24 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Concrete spacer shall be used to ensure 75mm concrete cover or as specified on shop
drawing. Vertical distance between adjacent spacers will be approximately 3 meters apart
and shall be properly attached to the rebar cage.

Hanging bar (lifting hook) welded to per-fabricated lifting plate for loading and lifting
point will be used in accordance with the shop drawing. PE endorsed design calculation
shall be submitted to confirm safe to use.

During rebar cage lapping/joining, per-fabricated stopper plate will be utilized to ensure
safety. Appropriate quantity of stopper bars will also be welded on the main bar for added
security. PE endorsed design calculation shall be submitted to confirm safe to use.

Page 25 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Joining of reinforcement cages shall be done using U-bolts. Size and quantity of U-bolts
shall be in accordance to the PE endorsed design calculations.

Page 26 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

The borehole will be poured with designed ready mix concrete, 600mm above the design
cut-off level.

When concreting is complete, the casing will be extracted within 2hrs (after concrete
casting) by the used of boring rig reverse rotary method.

Page 27 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

9.3.3 Concreting

9.3.3.1 Placing Concrete in Dry Shafts


If the pile shaft is completely dry and stable, concrete to be discharged directly into the
borehole at the discretion of the Engineer. Before placing of concrete, all loose materials must
be cleaned out. Accepted measures shall be taken to avoid loosening of the sidewalls of the
shaft, concrete segregation and bleeding and to ensure that the concrete at the bottom of the
borehole is not deficient in grout.

9.3.3.2 Placing Concrete using 4” Pipe (rod) Installed at the Boring Machine

Using a portable pump, concrete placement can be done through the 4” pipe (rod) provided
in the boring machine. This method shall be adopted when there is no water in the borehole.

9.3.3.3 Placing Concrete Under Water or Drilling Fluid


a) When water in the bored hole cannot be removed, concrete will be placed by tremie
method. (under water concreting)

b) The tremie pipe should be extended to the bottom of the bored hole. A plug or a barrier
(vermiculite plug) should be placed inside the tremie pipe to prevent direct contact between
the first charge of concrete inside the tremie pipe with the water or drilling mud.

c) Concrete shall be placed through a hopper attached to the top section of the tremie pipe.

d) For placing concrete by tremie method, the following precautions are needed to prevent
choke of tremie pipe during the placing of concrete.
1) Concrete slump shall be 150 mm to 200 mm.

2) The pipe must be watertight throughout its length.

3) The first charge of concrete should be placed in such way that there is no direct contact
with water within the tremie pipe.

4) The tremie pipe should be at all times embedded at least 1.5 metre in the concrete and
at no time should it be withdrawn out from the concrete until completion of casting.

Page 28 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

5) Sufficient concrete should be maintained within the tremie pipe to ensure that the
pressure from it exceeded the water pressure outside the pipe.

6) For load test pile, concrete shall be casted until ground level or as specified by the
Engineer.

9.3.4 Installation Sequence for Secant Bored Pile

Boring for the secant pile will be carried out at an interval of two (2) pile distance in
alternate manner.

For instance, form piles no. P1, P3, P5, P7, P9 and so forth on the first stage of operation.

Return to the starting position of wall and form piles P2, P4, P6, P8 and so forth on the
second stage.

Similar operation to repeat until the secant pile wall is formed for the entire zone.

Bored pile P2, P4, P6, P8 can be started 1 day or 24 hours after P1, P3, P5, P7, P9 were
casted.

Page 29 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Typical Bored Piling Sequence

10. Safety, Health and Environment

Personal Protection Equipment (PPE) shall be issued to all personnel involved in the works and
wearing of PPE shall be enforced to the team as a whole. All site personnel shall wear the
following PPE at all times:

- Safety Footwear
- Safety Helmet
- High Visibility Safety Vest
- Gloves
- Eye/Face protection
- Hearing Protection
- Full Body Safety Harness

Page 30 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

10.1 Personal PPE

10.1.1 Traffic Controller Attire / Equipments

1. Safety Helmet
2. Safety Footwear
3. High visibility safety vest with
Traffic Controller initial at the
back
4. Traffic Hand glove
5. Whistle
6. Stop and Go Signage
7. Traffic Stick light

10.1.2 Banksman Attire / Equipments

1. Safety Helmet
2. Safety Footwear
3. High visibility safety vest with
Banksman initial at the back
4. Whistle

10.2 Equipment & operator

10.2.1 Excavator (Safety / Environmental Features)

 Additional safety features, excavator is installed with rear view camera.

Page 31 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

10.2.2 Operator (Safety / Environmental Features)

 All operators fasten the seat belt during operation.

10.3 Environmental Protection

10.3.1 Heavy Vehicular Movement

 Environmental impact: - Excessive dust emission from heavy vehicles can cause dirt,
earth spillage within workplace and on public roads during transportation can cause dirt
accumulation on the road which can affect other road users.

 Mitigation measures:

i. Regular maintenance.
ii. Vehicle transporting load e.g. earth, aggregates or other loose materials shall be
provided with proper cover sheet to prevent it from falling on the road.
iii. Provision of vehicle washing bay for the site at entrance/ exit point.
iv. All vehicles going out from work site to pass through washing bay.

10.4 Certificates

All safety supervisor(s), site supervisor(s), excavator operator(s) shall carry relevant
certificates during the execution of the work.

A copy of the said certifications shall be submitted to Samsung Safety Officer for Verifications
prior to work commencement.

Page 32 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

10.5 Sign boards

Warning signs for excavation works shall be displayed on site during the work process.

Please refer to Appendix D: Sign Board

10.6 Noise Control

The total noise level produce by all plants, equipment and machineries shall be monitored and
not to exceed the allowable limit set by the authority. Appropriate housing or cover (noise
barrier) must be placed around machineries to minimize noise level, as and if deemed required.

10.7 Safety & Health Hazard Log (Risk Analysis)

 Please refer to Appendix E : Risk Assessment

 Please refer to Appendix F : Safe Work Procedure

11. Quality Assurance

a) Samples of quality assurance records can be found in Appendix.

b) Our supervisor will carry out inspection before and during the work at each stage.

c) Soil/Rock Samples shall be collected and recorded for every change of strata or every 5m
whichever is applicable and upon Engineers request. Samples will be made available for
checking and verification at all times.

d) Joint inspection together QP(S)/LTA will be carried out at every stage to assure the quality
of work. The next stage of work shall commence only after approval from QP(S)/LTA’s
representative.

e) All necessary reports and record shall be completed and submitted to authorities for
verification and approval within the next day after each pile is completely installed.

Page 33 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

11.1 Tolerances

Position

The pile heads shall be positioned as shown on the drawings within the deviation of
75mm in either direction from its design position (as per LTA M&W Specifications –
Chapter 5)

Verticality

The maximum permitted deviation of the finished pile from the vertical is 1 in 75 (as per
LTA M&W Specifications – Chapter 5)

Correction

Piles are installed outside these tolerances affecting the design of the structure, a
remedial action must be proposed.

Trimming

Unless otherwise specified, bored pile trimming and cutting-off shall be executed such
that a construction joint with maximum deviation of +0.04m /- 0.07m at the design cut-
off level is formed.

11.2 Concrete

Trial Mix

To be carried out by maincon

Strength

Concrete grade will be based on the approved drawing.

Concrete testing

A set of 6 cubes shall be taken as per the sampling requirement stated in M&W
Specification.

Page 34 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Workability

Slump test shall be undertaken for every truck load of concrete. Slump measured at the
time of the discharge into pile shaft or at time of discharge into the concrete pump hopper
shall be in accordance with the standards below.

Failure of concrete

If the concrete cube as tested failed to satisfy the criteria as described in specification, a
remedial or compensating action must be proposed for approval.

11.3 Pile Excavation

Pile size and length

Probing of bedrock shall be carried out along the proposed wall line at intervals.

Boring near recently cast piles

Piles shall not be bored next to the other piles which recently been cast less than 24 hours
or contain unset concrete, whichever longer to avoid damaged to any of these piles.

Stability of borehole

A temporary casing shall be provided for boreholes with a presence of ground water to
prevent loose materials to fall into the bottom of the borehole. The casing shall be install
until the top of hard strata to prevent the inflow of soil and the formation of cavities in the
surrounding ground.

The center to center distance for bored pile produced with a time difference of 4 hours
should be at least four times diameter or width with a minimum of 2 meters.

Pile excavated shall be cast within 24 hours unless otherwise agreed. If the bored piles are
constructed in ground in which is likely to deteriorate with time and it’s not possible to
finish the bored pile by the end of the working day, a depth equivalent to at least twice the
shaft diameter but not less than 1.5m

Inspection

Where applicable, all pile excavations shall be inspected for their full length before
concreting. Inspection shall be carried out either from the ground or below ground level at

Page 35 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

the sole discretion of the engineer.

11.4 Placement of Reinforcement

Concrete spacer shall be provided at every 3m interval, size and minimum yield strength
shall be as specified on the drawing.

To maintain the concrete cover of SBP, during installation of rebar cages concrete cover
shall be made up of concrete block instead of the typical plastic made.

The minimum concrete cover to all reinforcement shall not be less than 75mm unless
stated otherwise.

The longitudinal reinforcing bars in piles not exceeding 12 meters in length shall be in
one continuous length unless otherwise specified.

It is noted that reinforcement for the hard piles are not symmetrical, hence it is necessary
that lowering of the reinforcement cage is in the correct orientation. Markings shall be
provided so that the site personnel will be aware of the proper rebar cage positioning. On
the other hand, strict compliance to the approved shop drawings with respect to its
lapping requirement shall be adopted to ensure that the rebar cages are joined at the
correct level.

Notes on Rebar Cage Installation:-

1. Once the final toe level is confirmed, prepare rebar cages in accordance with the design
length requirement. Measure and clearly mark the total length requirement for each rebar
cage on the main bar where hanging bars are to be located. Demarcate lapping lengths with
respect to the previous markings.

Page 36 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

2. Provide PE endorsed design calculations on the proposed hanging bars (lifting hooks),
lapping details, hanging plates, stopper plates, etc. deemed necessary to make certain that
they are “safe to use”.

3. Follow installation details for hanging bars (lifting plate), rebar cage hanging arrangement
with stopper plates and rebar cage lapping.

4. Surveyor to set out reference and offset points for monitoring the rebar cage movement after
the removal of steel casing. Monitoring of rebar cage relative movement shall be done
during the initial stage and will be adjusted accordingly as soon as allowable tolerance was
established.

Also, we propose to install additional main bar (same as shown on the design) on the single
main bar side in order to prevent grave consequences in case an excessive rotation of rebar
cage occur. This will be monitored during initial stage of SBP work and will also be
adjusted accordingly as soon as allowable tolerance was established.

Page 37 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Proposed measures to ensure proper placement of rebar cages:-

1. Generally setting out of bored pile center lines will be carried out by Dongah surveyor in
accordance with the design drawing and specifications.

2. Matching reference point at rebar cages will also be located and clearly marked for
monitoring purposes. This will be matched to the reference/offset point installed at guide
wall for proper rebar cage orientation.

3. During the initial stage of SBP works, we proposed to install additional main bars (to
match with the design) in order to make the rebar cages symmetrical thus avoiding the
grave consequences in case an excessive rotation of rebar does occur.

4. Pattern of rotation will be recorded and verified and shall be adjusted accordingly as soon
as soon as allowable tolerance was established.

11.5 Concreting in wet hole

A tremie concrete pipe shall be use and shall consist of a series of metal pipes with
internal diameter not less than 250mm.

The tremie outlet shall be kept at least 1.5 meters below the surface of the concrete at all
stages in the pour.

Temporary casings shall be extracted in not more than 2 hours after concreting has
completed.

Page 38 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

11.6 Drilling fluids (if necessary) and soil tests

Steel casing installed until rock layer will be provided in lieu of the drilling fluid.
.
11.7 Dry hole construction (If directed by engineer only)

Whenever practicable, concrete bored piles may be placed into a clean dry hole. All dry holes
shall be inspected and approved prior to placing of concrete. The concrete shall be placed by
tremie. The free fall of the concrete from the bottom of the tube shall not exceed 1.5 times the
diameter of the pile. The concrete shall be placed as quickly as possible where the ground is
liable to deteriorate on exposure.

11.8 Casting level

Concrete shall be finished not less than 600mm above the cut-off level (overcast) to ensure
that all concrete at and below the cut-off level is homogeneous and free of laitance and
deleterious matter.

11.9 Concrete Cover

Unless otherwise noted, all concrete cover for SBP works shall be 75mm. Concrete spacer
shall be provided at a vertical distance of not more than 3.0m to ensure enough concrete
cover.

11.10 Inspection and Test Plan (ITP)

Please refer to Appendix H : Inspection and Test Plan for Bored Pile Work

11.11 Forms and Checklist

Please refer to Appendix I : Checklist

12. Emergency Response Plan

This plan addresses the following types of foreseeable emergency situations relating to
installation hoarding & gate Operation:

- Worksite Fire
- Adverse weather
- Workers injured (by equipment / machineries etc.)
- Any other incident such as topple of equipment

Page 39 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

12.1 Emergency Response Team (ERT)

Appointment Project Designated Staff


Site Incident Commander (SIC) Project Manager or his deputy
Staging Area Commander (SAC) Construction Managers / Senior Engineer
Assembly Area Coordinator (AAC) HSE Manager / WSHO
Section heads/ Site Engineers / Supervisors /
Area Fire Wardens (AFW)
WSH Coordinators / Subcontractors’ in-charge
First Aiders (FA) Trained First Aiders
Rescue Task Force (RTF) Trained Supervisors / HSE personnel
Security Controller (SC) Security Personnel
Media Liaison Officer (MLO) Public Relation Officer (PRO)

12.2 Emergency Action

1) Actions to be taken during an emergency (office hours)


 on identification of the emergency, SIC will determine if immediate evacuation of all
work site personnel to the designated assembly area is necessary;
 assess situation if summon relevant authority for assistance is necessary;
 perform first-aid treatment to casualty, if any;
 perform firefighting / rescue operations if necessary;
 control the crowd i.e. prevent unauthorized entry and exit of personnel / vehicle from
the work site without approval by the SIC; and
 Keep the crowd in orderly manner until permission for dismissal given by SIC.

2) Actions to be taken during an emergency after office hours


 Person who discovers the emergency shall alert the supervisor and alert others by
shouting / ringing the manual bell and then attempt to control the situation if
practicable, e.g. extinguishing of incipient fire.
 The supervisor who has been informed will then verify and confirm the emergency, and
notify the ERT.
 In the event of uncontrolled fire or medical attention required, the SCDF will be
notified;
 In the meantime, the supervisor shall assume command until arrival of SIC or SCDF.
 Leave further firefighting and rescue efforts to the EPT / RTF / SCDF.

Page 40 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

12.3 List of Emergency Contact Numbers

DESIGNATION NAME CONTACT NO

Shanghai PROJECT MANAGER Kelvin Wathan 9271 4785

Tunnel CONSTRUCTION MANAGER K Jeyarasan 9088 3339

WSHO Xxxx xxxx XXX XXXX

PROJECT MANAGER Park Hen Kook 9890 8897

Dongah CONSTRUCTION MANAGER Lee Srung Bae 9795 3771

SAFETY SUPERVISOR XXX XXX

EMERGENCY AUTHORITY LINES

EMERGENCY AMBULANCE 995

POLICE 999

TRAFFIC POLICE 6547 1818

RAFFLES HOSPITAL 6311 1555

NEA (CHEMICAL SPILLAGE) 1800-225 5632

NEA HOTLINE 1800-225 5632

PUB 1800-284 6600

SP POWERGRID/ SP TELECOM 1800-778 6666

SINGTEL 1800-288 4099

CITY GAS 1800-752 1800

STARHUB PIPELINE 1800-782 7482

12.4 Emergency Reporting Procedures

 Please refer to Appendix G : Emergency Reporting Procedures

Page 41 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

APPENDICES

Page 42 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

APPENDIX A
Organization Chart

Page 43 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 44 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

APPENDIX B
Schedule

Page 45 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 46 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

APPENDIX C
Machinery Catalogue

Page 47 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 48 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 49 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 50 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 51 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 52 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 53 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 54 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 55 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 56 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 57 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 58 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 59 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 60 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 61 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 62 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 63 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 64 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 65 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 66 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 67 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 68 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 69 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 70 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 71 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 72 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 73 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 74 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 75 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 76 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 77 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 78 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

APPENDIX D

Sign Board

Page 79 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 80 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 81 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 82 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

APPENDIX E

Risk Assessment

Page 83 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Severity (S) Risk Index Description Definition


(1) (2) (3) (4) A Intolerable Risk shall be reduced by whatever means possible.
Catastrophic Critical Marginal Negligible B Undesirable Risk shall only be accepted if further risk reduction is not practicable.

Risk Category
(1) Frequent A A A B C Tolerable Risk shall be accepted subject to demonstration that the level of risk is as low as reasonably practicable.
Frequency (F) (2) Probable A A B C D Acceptable Risk is acceptable.
(3) Occasional A B C C
(4) Remote B C C D
(5) Improbable C C D D

Page 84 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Initial risk Initial risk


Possible Accidents Action by
Existing controls index Additional Preventive & index
S / No Work Ativity Hazards / lll- Health &
measures control meassure
Persons at risk F S R F S R Designation Date

Mobilisation / Assigned worker towash the


Dust and polluction of Environmental Workers to remove any earth spill
Dmobilisation vehicle throughly and Safety Co-
2 road after vehicl is out pollution,inconvenie 3 3 C / debris drop on road an public 5 3 C immediate
of machenary maintain proper washing ordinator
of site nce to public area
to site bay

Assemble / Dismantling
Pre-task briefing to be carried
Crushing or serious Severe injury to works must be performed by Safety/Site
4 2 C out by the erector to all 5 2 C immediate
injury to workmen workman trained member ( I.e. supervisor
members involved
Assemble approved erector )
/Dismantling
3
of boring rig To provide work platform for Safety harness is inspected and
and crane mechanic to work where workmen are trained on proper
Severe injury to Safety/Site
Falling from height working at heights required 3 2 B usage. RA and SWP briefing 4 1 B immediate
workman supervisor
use of safety harness and to before work start during TBM
be anchored at all times and JSA

Damage to property Barricade the lifting zone and


and serious and fatel provide signage "Lifting works in
provide qualified rigger and
Struck by lifting object accident to 4 1 B progress" No workers shall work 4 1 B Crane operator immediate
signalman
workers,operator and under the swing radius /
public suspended load

Damage to property Qualified rigger to carry out


All personnel to stay clear of
and serious and fatel rigging works. Use of LG
lifting path. Lifting supervisor to
Falling object accident to with valid certificate. Daily 3 1 A 4 1 B Lifting supervisor immediate
Crane and conduct monthly check on LG
workers,operator and permit to work need to be
4 Lifting for any wear and tear
public applied before start work
operation

Crane operator must have


Crane platform/access to be
Damage to property certified valied licenses and be
inspect and endorse by PE.
and serious and fatel approved by main Lifting
Crane operated by qualified
Crane topple injury to 3 1 A contractor.Dongah 5 1 C supervisor/Rigger immediate
crane operator.Ensure lifting
workers,operator and representative,barricade the signal man
work is carry out with the
public lifting zone and provide signage
SWL install load indicator
"Lifting work in progress"

Severity (S) Risk Index Description Definition


Risk Category (1) (2) (3) (4) A Intolerable Risk shall be reduced by whatever means possible.
Catastrophic Critical Marginal Negligible B Undesirable Risk shall only be accepted if further risk reduction is not practicable.
(1) Frequent A A A B C Tolerable Risk shall be accepted subject to demonstration that the level of risk is as low as reasonably practicable.
Frequency (2) Probable A A B C D Acceptable Risk is acceptable.
(F) (3) Occasional A B C C
(4) Remote B C C D
(5) Improbable C C D D

Page 85 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Initial risk Initial risk


Possible Accidents Action by
Existing controls index Additional Preventive & index
S / No Work Ativity Hazards / lll- Health &
measures control meassure
Persons at risk F S R F S R Designation Date

Damage to property
Operator to understand load
and serious and fatel Provide load indicator in
chart. All LG used to shall have
Overload injury to working condition,DO NOT 3 1 A 5 1 C Safety supervisor immediate
valied certificate and in good
workers,operator and OVER LOAD THE CRANE
condition
Crane and public
5 Lifting
Arrangements and location
operation Damage to property Avoide stacking materials in 2
of materials to unload must
Poor unloading and serious and fatel layers and provide accessible / Lifting supervisor
be clear to the rigger
arrangement/communi injury to 3 1 A wide unloading location of 5 1 C / rigger immediate
signalman and lifting team
cation workers,operator and materials,RA and SWP briefing signalman
members.provide proper
public before work start
communication channel

ensure workers stay a clear


Workers struck by bore damage to property distance of 3m from the rig provide warning signboard. All
soil during spinning of and injury to during spinning soil, provide 3 2 B workers briefed during "tool box 4 2 C Operator immediate
auger workman a locallized barrier to the meeting "
height of the auger

supervisor to check and ensure


Temporary casing must be all openings area covered up
Workers fall in to deep
at least 1.0m above ground with mes and or properly
excavations and serious and fatel
Boring rig level. Warning signboard of 4 1 B barricated at the end of daily 5 1 C Safety supervisor immediate
opening non-enclosed injury to workman
operation drill "Boring works in progress" operation. Tool box talk to
area
cor from the Shallbe displayed remind all personnel of this
toe of hazard
6
1200mm ( SBP
) dia steel Ensure Pre-condition survey has
Damage to property vibration monitoring to
casing 900mm been carried out on sorrounding
Excessive vibration on sorrounding ensure vibration is below the 2 3 B 4 3 C site supervisor immediate
pipe pile neighbours prior to commence
neighbourhood stop work level of 15mm/s
work

Ensure all workers working


near machines are provide All site personnel must be briefed
Excessivenoice don by noice polluction &
with appropriate ear 3 3 A and trained on the use of the ear 4 3 C Safety supervisor immediate
equipments NID
protection,provide sound protection
barriers

Severity (S) Risk Index Description Definition


Risk Category (1) (2) (3) (4) A Intolerable Risk shall be reduced by whatever means possible.
Catastrophic Critical Marginal Negligible B Undesirable Risk shall only be accepted if further risk reduction is not practicable.
(1) Frequent A A A B C Tolerable Risk shall be accepted subject to demonstration that the level of risk is as low as reasonably practicable.
Frequency (2) Probable A A B C D Acceptable Risk is acceptable.
(F) (3) Occasional A B C C
(4) Remote B C C D
(5) Improbable C C D D

Page 86 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Initial risk Initial risk


Possible Accidents Action by
Existing controls index Additional Preventive & index
S / No Work Ativity Hazards / lll- Health &
measures control meassure
Persons at risk F S R F S R Designation Date

Boring rig
operation drill
All bored pill shall be
cor from the Any stockpile shall not be
Disposal of silt water Damage to property, dispose daily. Stock pile
toe of morethan 5х 5m area and maintain
7 and loose earth at the polluction of site earth must be covered to 3 3 A 4 3 C Safety supervisor immediate
1200mm ( SBP a gap of at least 1m between earth
drinage surrounding prevent washing off the
) dia steel bund to allow slow surface run off
drain
casing 900mm
pipe pile

Any cement bag shall be


Polluction,Health
workers handling cement automatically put in waste bin
Dust and breathing 2 3 B 4 3 C site supervisor immediate
shall put on dust mask and do not leave unused cement
problem
at the site after works hours
Handling and
8
use of cement
Workers to wash hand when in
Workers to put on PPE when
Cement burns Dermatitis 2 3 B contact cement. SDS breaf to 4 3 B Safety supervisor immediate
handling cement
workmen involved

All personnel to stay clear of


Qualified rigger to carry out lifting area. Lifting supervisor to
Installation of rigging works. Use of LG conduct monthly check on LG
Serious and fattel
9 reinforcement Falling object with valid certificate. Daily 4 1 B for any wear and tear. Supervisor 5 1 C Lifting supervisor immediate
injury to workers
(Re-bar) Cage permit to work need to be to check and ensure that the
applied before start work reinforcement is adequately tie
and provide spot welding

Tool Box Talk to be remind all


Newely formed pile to be
Workers falling in to personnal of this hazard and
Concreating Serious and fattel provided with temporary
10 newely formed bored 4 1 B remind workers not to remove 5 2 C Safety supervisor immediate
works injury to workers barricade with warning
pile area's the barricade without permission
signages.
from safety co-ordination

Severity (S) Risk Index Description Definition


Risk Category (1) (2) (3) (4) A Intolerable Risk shall be reduced by whatever means possible.
Catastrophic Critical Marginal Negligible B Undesirable Risk shall only be accepted if further risk reduction is not practicable.
(1) Frequent A A A B C Tolerable Risk shall be accepted subject to demonstration that the level of risk is as low as reasonably practicable.
Frequency (2) Probable A A B C D Acceptable Risk is acceptable.
(F) (3) Occasional A B C C
(4) Remote B C C D
(5) Improbable C C D D

Page 87 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Initial risk Initial risk


Possible Accidents Action by
Existing controls index Additional Preventive & index
S / No Work Ativity Hazards / lll- Health &
measures control meassure
Persons at risk F S R F S R Designation Date

Provide banksman totrucks Trucks are equipped with audible


Concrete truck hit
Concreating entering site and to warning when reverse in to site.
11 workers and /or Severe injury 4 2 C 5 2 C safety supervisor immediate
works concreating location as well Traffic controller with STOP/GO
pedestrians(s)
as when truck leaving site sign to guide the pedestrain

Propper use of PPE and "Tool


01.Fumes / gases Inhale of poisonous Carry out hot work at opn
4 3 C box" talk to remind all workers of 5 3 D Safety supervisor immediate
asphyxiation fumes,fainting space. PTW must be comply
the hazard

Licesence electrical workers


All connection work on (LEW) to conduct monthly
General
Serious and fattel electric powered equipement check on all electrical wirings
12 welding, Repair 02.Electric shock / Fire 3 1 A 4 1 B site supervisor immediate
injury to workers must be carried out by and distribution boxes. Provide
of tools
qualified electrician fire extinguisher near hot work
zone

Health and unsafe Use approved eye protection use screens to protect other
03.Ultraviolet radiation 4 3 C 5 3 D site engineer immediate
work environment equipment and apron personnel

Signboard to put up during this


01.Accidently machin Operator switch of the operation; barricading to be done
Serious and fattel
move and hit onto engine and ignation key 3 1 A to warn of and prevent workers 4 1 B safety supervisor immediate
injury to workers
General worker or repairman handover to machanic from standing near to this
repairing machinery
13 maintenance
of machinery
Ensure safety harness is
or equipment's Tool box talk to all personal
Serious and fattel worn and secure properly
02.Fall from height 4 1 B involved. RA and SWP Breaf to 4 1 B Safety supervisor immediate
injury to workers while performing these
all workmen
repairing at height

Severity (S) Risk Index Description Definition


Risk Category (1) (2) (3) (4) A Intolerable Risk shall be reduced by whatever means possible.
Catastrophic Critical Marginal Negligible B Undesirable Risk shall only be accepted if further risk reduction is not practicable.
(1) Frequent A A A B C Tolerable Risk shall be accepted subject to demonstration that the level of risk is as low as reasonably practicable.
Frequency (2) Probable A A B C D Acceptable Risk is acceptable.
(F) (3) Occasional A B C C
(4) Remote B C C D
(5) Improbable C C D D

Page 88 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Initial risk Initial risk


Possible Accidents Action by
Existing controls index Additional Preventive & index
S / No Work Ativity Hazards / lll- Health &
measures control meassure
Persons at risk F S R F S R Designation Date

Slipping hazard. Provide tray or oil drum to


03.Overspilled of fuel or All personnel must put on PPE
General Polluction to contain any overspill from 3 3 C 5 3 D Safety supervisor Immediate
disel and tool box talkto all
repairing environment machin
14 maintenance
of machinery
or equipment's
Only qualified electrician is
04.Electric shock / Serious and fatel
Provide fire extinguisher 4 1 B allowed to carry out all electrical 5 1 C Safety supervisor Immediate
explosion injury to workers
connections

High pressure,poor Starting before check all


Once a month inspection of
Air compressor maintenance, earth Serious and fatel whip arrestor, valves, oil and
15 4 1 B qualified mechanic that can 5 1 C Site engineer Immediate
/ Generator ground not properly injury to workers disel spills, proper tray
provide LEW certificate
connected should be provided

Damaged property
Truck transporting of
and serious and fatel Provide early warning device
disel hit workers when Provide banksman / provide Site/Lifting/Safet
injury to workers / 3 1 A when reversing and proper sign 5 1 C Immediate
travel / reverse, disel the diesel tray y supervisor
enviroment board, fire extinguisher
leakage
polluction

General :
16 Refilling of fuel
/ disel
All personnel to stay clear of
Damaged property Qualified rigger to carry out
Falling object (diesel lifting path. Lifting supervisor to Site/ Lifting
and serious and fatel rigging works, Use of lLG 3 1 A 5 1 C Immediate
drum) conduct monthly check on the Supervisor
injury to workers with valid certificate
LG for any wear and tear

Severity (S) Risk Index Description Definition


Risk Category (1) (2) (3) (4) A Intolerable Risk shall be reduced by whatever means possible.
Catastrophic Critical Marginal Negligible B Undesirable Risk shall only be accepted if further risk reduction is not practicable.
(1) Frequent A A A B C Tolerable Risk shall be accepted subject to demonstration that the level of risk is as low as reasonably practicable.
Frequency (2) Probable A A B C D Acceptable Risk is acceptable.
(F) (3) Occasional A B C C
(4) Remote B C C D
(5) Improbable C C D D

Page 89 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Initial risk Initial risk


Possible Accidents Action by
Existing controls index Additional Preventive & index
S / No Work Ativity Hazards / lll- Health &
measures control meassure
Persons at risk F S R F S R Designation Date

Workers deployed to remove Must contain any possible water


any watter bearing receptails ponding as early as possible (e
Water pounding causes Dangue and air and drain away any stagnant .g. punctured drums, and water
General mosquito breeding, polluction, tripping water around work area. Site buckets) workers developed to
17 3 2 B 5 2 C Safety supervisor Immediate
housekeeping poor housekeeping at hazzard, workmen office to be kept remove qny water bearing
site /rest area injury 300mmabove from the receptacles, rubbish. Workers all
ground roof covering slap briefied and educate no littering
tops provision of rubbish bin around site

Severity (S) Risk Index Description Definition


Risk Category (1) (2) (3) (4) A Intolerable Risk shall be reduced by whatever means possible.
Catastrophic Critical Marginal Negligible B Undesirable Risk shall only be accepted if further risk reduction is not practicable.
(1) Frequent A A A B C Tolerable Risk shall be accepted subject to demonstration that the level of risk is as low as reasonably practicable.
Frequency (2) Probable A A B C D Acceptable Risk is acceptable.
(F) (3) Occasional A B C C
(4) Remote B C C D
(5) Improbable C C D D

Page 90 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

APPENDIX F

Safe Work Procedure

Page 91 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

General

 Workers shall be briefed on the scope of works and safety issues highlighted.
 All workers shall wear proper personal protective equipment i.e.; safety helmet, safety glasses, eye
goggles, hand glove, safety boots, body harness as required depend on the scope of work.
 Tool box meeting must be conducted and ensure that every activities are explained and understand
by all workers.

* Key control points

A. Mobilization

-Provide and designate traffic men and traffic signage to control all vehicles coming in and out the
construction site premises. Further coordination with the Main Contractor for other vehicular
movement in order to avoid traffic congestion within the site.

-Conduct a special toolbox meeting regarding planning, scheduling, and designated work assignment
of all personnel relative to mobilization works. In addition, appropriate traffic gears, i.e., vest gloves,
etc. to traffic men for easy recognition.

-If possible, it is best to carry out mobilization during day time wherein sufficient lighting and clear
visibility for all site personnel while performing the work.

B. Plant and Machineries Set-up and Maintenance

1. Plant Set-up & Installation

-Check access path of all lifting machines prior transport and operation. Provision of steel plate as an
additional stability for working platform.

-All lifting machine and lifting gears to be used must be checked and certified by an approved
examiner before usage. Likewise, daily check of all lifting machines and lifting gears must be done to
ensure that all are in good working conditions by Lifting Supervisor.

-Only competent personnel must carry out the work. Wearing of PPE is a must to avoid any injuries
to site personnel.

-Barricading/hoarding and appropriate warning signs must be provided along the perimeter to keep
unauthorized personnel out of the lifting zone.

-All lifting/hoisting operations must be supervised full-time by competent lifting supervisor. Any
unsafe act or condition must be immediately reported to the lifting supervisor so as to formulate
remedial measures. Implementation of work permit system prior lifting operation is a must. All lifting
activities must have a lifting plan.

Page 92 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

-Always practice safe work procedure. Operate within the safe working load of lifting machine,
equipment and accessories as specified thereon.
-All electrical set-up shall be done by a qualified electrician and check and endorse by License
Electrical Worker (LEW). All electrical materials and equipments shall follow all specifications in
accordance with the design specifications, equipment/machinery operating manual, and all provisions
contain in the code of practice.

-Checking, inspection and commissioning shall be done by an approved examiner prior operations of
all electric-driven machineries of the plant. Related certificate and license must be acquired from
local authorities (i.e. LEW certificate, EMA license).

2. Excavation Works

Trench excavation works shall be carried-out by BCB 40, BC30 in a manner in which two primary
panels shall be excavated first then followed by a middle secondary panel. This is done in order to
ensure inter-locking of adjacent panels to form a wall.

a) Secure a very stable working platform for BC Cutter rig while performing excavation works.
If necessary, provide steel plate for additional platform support. Platform must be design and
endorse by a Professional Engineer.
b) Only trained and qualified personnel shall operate the BC Cutter rig.
c) Signalman and operator shall closely coordinate the work together to avoid any accident.
d) During taking of bentonite sample check worker shall put on safety harness with 100% tie off
or Life Vest when entering open trench.
e) Perform daily routine check and/or maintenance of machine and its accessories prior operation.

C. Rebar Cage installation

1. Pre-Lifting

a) Site Engineer and Lifting Supervisor to check and ensure all re-bars are
tightened properly.
b) Site Engineer and Lifting Supervisor to check and ensure all necessary
fittings are installed properly.
c) Attach spreader bar unto the lifting hook of the crane.
d) Attach the spreader bar to the lifting re-bar using a shackle. (see the
attached P.E design and calculation of the lifting re-bar and spreader
bar)
e) The lifting area must be barricaded prior to lifting activities.
f) Keep the area clear of unauthorised personnel.
g) Plan the crane path with corresponding lifting plan.
h) Attach tag line to the cage.
i) Ensure qualified lifting team is on site.
j) Provide proper communication device / hand signal by experienced
signalman.
Page 93 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

2. During Lifting

a) Lift up the cage at about 300mm above ground to the stability


b) Signalman shall be visible to the crane operators
c) As the crane main block hoists the cage by spreader, the wire ropes that of crane AUX
hook shall be tension. (Tandem lift shall always be carried out in rebar cage lifting)
d) The lifting operation shall be carried out slowly until the cage is vertically aligned
e) Detach the wire ropes of the crane by lowering down the AUX hook of the crane
f) Tag lines shall be used at all times to control and adjust the position of the cage
g) Hoist the cage to the intended trench
h) The rebar cage shall be constructed as near as possible to the trench to eliminate the
movement of crane with heavy load

D. Concrete Casting

a) Concreting of diaphragm wall panel shall be carried out by tremie method. Upon placement of
rebar cage, tremie pipes shall be assembled to its correct length with approximately 3m spacing.
b) Provision of banksman to ensure a smooth traffic flow.
c) Secure the connection of tremie pipes.
d) The readiness of the bentonite pumping, piping and storage capacity shall be confirmed prior
to casting.
e) Bentonite hoses connection must be properly connected and butterfly clamp tighten & cover
with canvas properly.
f) The access for concrete truck shall be cleared of obstruction.
g) All pumps shall be check and inspected by an approved LEW.
h) All personnel working near the open trench must wear a safety belt with lanyard attached at a
secure point.
i) All open sides of the concreting trench must be cover by a steel grating.

E. Environmental

.
a) Monthly machineries maintenance to be done to minimize the exhaust smoke emission.
b) Chemical to be storage inside chemical store with drip tray attached.
c) All generator set, welding gen-set to be supplied with drip tray.
d) Water ponding to be clear and backfill with sand.
e) Bunds wall to be erected around silo base area.
f) All construction waste to be disposed at designated collection area.
g) Chemical spillage to be contains & control immediately.

Page 94 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

PPE:

Long Sleeve Shirt Long Trousers Safety Footwear Hard Hat Safety Glasses
Hearing Protection Goggles Dust Mask Overalls Gloves
High Visibility Vest Body Harness

Prepared By Review By Approved By

Signature

Name

Designation

Page 95 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

APPENDIX G

Emergency Reporting Procedures

Page 96 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 97 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

APPENDIX H

Inspection and Test Plan for Bored Pile Work

Page 98 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 99 of 104
Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 100 of 104


Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

APPENDIX I

Checklist

Page 101 of 104


Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 102 of 104


Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 103 of 104


Form No: XXX
NCS N109A
Doc Title Method Statement for Secant Bored Pile Work
Doc No DOC/XX
Transmittal No N109A/XX/XX

Page 104 of 104