Objectives:
1. Assess the Unit’s level in the PGS pathway using the SRT;
2. Validate the elements of PGS Proficiency through the Performance Audit;
3. Identify areas for improvement to further embed PGS in the organization; and
4. Present Performance Governance Report (PGR) for the Proficiency Stage.
3. Interview – provides deeper insights on the progress of the unit in the PGS. It
also gives an indication on the level of understanding and commitment of the
personnel to the PNP P.A.T.R.O.L. Plan 2030.
Page 2 of 10
PNP Unit Certification and Performance Governance Reporting
Proficiency Evaluation Process
Documents Review
Personnel Interview
On-Site Visits
Page 3 of 10
PNP Unit Certification and Performance Governance Reporting
Proficiency Evaluation Process
Audit Guide
The following documents must be prepared and submitted to CPSM for the
Performance Audit.
Page 4 of 10
PNP Unit Certification and Performance Governance Reporting
Proficiency Evaluation Process
a. Implementation Plan
b. List of initiatives in communicating
the PNP P.A.T.R.O.L. Plan 2030
Implementation of (AAR, photos, other documentary
the Communications evidence)
Plan c. Impact assessment of the
implementation of the CommPlan
(internal and external stakeholders)
d. Other supporting documents
Sharing and
Implementation of
Project Fact Sheets, photos, other
Identified Best
supporting documents
Practices in the
Compliance Stage
Link to Human a. Letter Order, Staffing Pattern
Resource b. Training Profile
a. Annual Operations Plans and
Budget
b. Updated Measures Profile
c. Updated Initiatives Profile
d. Program Review and Analysis
Link to Budget
(PRA) Report
Initiatives e. Fact Sheets of the Initiatives
Management
f. Any monitoring and evaluation tool
to monitor milestone or progress of
initiatives (e.g. GANTT Chart)
Any document which shows allocation
and utilization of logistical resources
Link to Logistics
necessary per initiative (e.g. TEA,
TSA)
Link to Systems and Any document which shows process
Processes flow in the implementation of initiatives
Emerging Breakthrough Results on a. Accomplishment Report
the 2015 Commitment b. All available documents
*The audit is not restricted to the documents above. The Audit team may
request for other materials which they deem necessary to ascertain
assessment of the unit’s performance. The unit may submit or present other
data, information, or documents that will support their claim for the Proficiency
stage.
Page 5 of 10
PNP Unit Certification and Performance Governance Reporting
Proficiency Evaluation Process
The unit shall undergo a one-hour PNP Unit Certification and Performance
Governance Reporting where the head of office shall deliver a 30-minute
presentation of their accomplishments and a 30-minute panel examination
which covers the following:
ITEMS/CONTENT
CONTEXT SETTING (AVP or PPT Slides)
Current realities and reasons for adopting a good governance program
Strategic change agenda, or major transformations expected as a result
of implementing the strategy
Major issues encountered in strategy implementation
Page 6 of 10
PNP Unit Certification and Performance Governance Reporting
Proficiency Evaluation Process
FUNCTIONAL SCORECARD
A. REGULAR MONITORING, REVIEW, AND REPORTING OF STRATEGIES
Regular conduct of Strategy Reviews and facilitation of Operations Reviews
B. ALIGNMENT OF SCORECARD AND DASHBOARD TO INDIVIDUAL LEVEL
Status of Second level scorecards
Page 7 of 10
PNP Unit Certification and Performance Governance Reporting
Proficiency Evaluation Process
INITIATIVES MANAGEMENT
A. LINK TO HUMAN RESOURCE
Proof of actual results of engagement, adequacy and competencies
B. LINK TO BUDGET
How the strategy drives key strategic initiatives
Link to Initiatives and strategy to budget
Proof of allocation and utilization
C. LINK TO LOGISTICS
Proof of allocation of resources to initiatives
D. LINK TO SYSTEMS AND PROCESSES
Establishment of organizational systems and structures
I. Preliminaries
a. Title page
b. Foreword from the head of the organization
c. Table of contents
II. Context Setting
a. Current realities and reasons for adopting a good governance program
b. Strategic change agenda, or major transformations expected as a
result of implementing the strategy
c. Major issues encountered in strategy implementation
Page 8 of 10
PNP Unit Certification and Performance Governance Reporting
Proficiency Evaluation Process
Strategy Map
Governance Scorecard
Strategic Initiatives
Page 9 of 10
PNP Unit Certification and Performance Governance Reporting
Proficiency Evaluation Process
A. Pre-presentation Activities
1. Submission of one soft copy of the Presentation and Formal
Report to the Center for Police Strategy Management thru
srd@cpsm.pnp.gov.ph five days prior to the date of
reporting.
2. Submission of at least 8 hardcopies of the formal report for
the panel on the day of the presentation.
3. Submission of the names of Advisory Council members who
will join the reviewing panel at least three days before the
presentation.
B. Presentation Proper
1. The Unit Certification and Performance Governance Report must
be delivered by the head of office. No representative will be
allowed.
C. Delegation
1. The head of office must be accompanied by his command group.
Their names and corresponding designations must be
submitted to CPSM three days prior to the date of reporting.
2. Any additional staff/personnel shall be coordinated with the CPSM.
Page 10 of 10