Você está na página 1de 6

SRA - GEN

Document Type: Risk evaluation and risk assessment


Disassembling of Generator, rotating rectifier, shaft
pump
(Evacuation of stator winding, circuit ring, rotor winding, No: 004 Revision: 1
exhaust (primary water-)SS-System, activate pipeline,
Energy Sector Activity: remove elevated tanks)

Location: Site Date: 01/2013


Document reviewed:
Generator TYPES (THDF,THFF( only by using of Issued by: HSE- Department
Document released: Work area: following title ALL Types))
Document Handling: For Siemens internal use only
Persons Affected (e.g. operators, maintenance, visitors, public etc): Preliminary
Status: Review: Following any significant legislation or
Those performing the task and others in the work area Final  procedure changes but no later than: - 12 Months

The Risk Assessment Severity (S) Likelihood of harm (L) Risk Rating (R) = S x L
1. Identify and record for each hazard/risk 1 = No Injury 1= Very Unlikely 1 to 6 = Low Risk (L) (Acceptable, Monitor & Review) Likelihood of harm
identified the appropriate rating for 1 2 3 4 5
severity and likelihood without controls. 2 = Minor Injury 2 = Unlikely 8 to 12 = Medium Risk (M) (Acceptable with controls)
1 1 2 3 4 5

Severity
3 = Lost time Injury 3 = Likely >12 = High Risk (H) Unacceptable
2. Identify and record the control 4 = Major Injury 4 = Very Likely
2 2 4 6 8 10
measures to be used then repeat the
5 = Death or Permanent Disability 5 = Certain
3 3 6 9 12 15
assessment with the controls in place
4 4 8 12 16 20
NOTE: If after risk evaluation and with all the necessary controls in place; the risk rating (R) is HIGH,
the HS&E department are to be contacted for guidance on the task/process. 5 5 10 15 20 25
Assessment Assessment
(No Controls) (With Controls)
Hazard/Risk Controls
S L R S L R

• Maintain distance from load


• Keep transport routes free
• Use edge protection to prevent damage to lifting gear due to
sharp edges
• Prepare lifting plan if complex crane operations are to be
WORKING WITH BUILDING/CEILING CRANE
5 4 H performed 5 1 L
• Weight measurement (if possible), use load cell or truck scales
• Lifting gear / load rigging shall be visually inspected before use
• Check inspection tag
• Notify supervisor of defective lifting gear/load rigging
• Mark the defective lifting gear red and block for further use
• Always monitor load and crane
• Use chain hoist for small lifting operations or use chain hoist on
crane hook; use the actual crane for larger operations
• Do not give any direction commands while the weight is
swinging from the crane hook; wait until the weight has come
to a standstill
• Keep slack hoist chain as short as possible
• When lifting with the crane hook, take care to ensure that the
chain does not become snagged
• Plan all crane activities in advance and prepare the set down
area
• Never work under a suspended load.
• Ensure clear and precise signals between rigger and crane
operator
• Only the rigger shall give signals to the crane operator
• Do a walk down of the lift path before crane work and warn
personnel working in the hazardous area
• All personnel shall clear the hazardous area if the load is to be
moved above work areas
• Always use the correct device for lifting operations; consult
your supervisor if you are uncertain
• Never turn your back on the load
• Use only appropriately trained and qualified personnel
• Schedule sufficient breaks
• Prevent exertion which is too frequent (unbalanced) or too
long, over excessive distances, or insufficient recovery time
• Use lifting or carrying aids if possible
• Take employee’s physiological condition into account
• Characteristics of the load such as size, weight, manageability,
WORKING UNDER ELEVATED PHYSICAL STRESS location of center of gravity, external and/or internal properties
3 4 M 3 2 L
shall be accounted for
• Characteristics of the work area such as insufficient space,
uneven floor and climatic conditions shall be accounted for
• Appropriate instruction on correct handling of loads and on the
hazards resulting from incorrect handling
• Only use personnel who are physically suited to perform the
task
USE / HANDLING OF HAZARDOUS SUBSTANCES • Barricade off work area if possible
3 3 M 3 1 L
(solid, liquid, gas, dust, fumes) • Substitution with substances not hazardous to health
• Safety instructions in the safety data sheets shall be observed
• Immediately remove escaped liquids and dispose of in
accordance with statutory and local guidelines
• Prevent ingress of hazardous substances in confined spaces
by complete physical separation
• Immediately clean up oil and spills of any type – oil absorbents
shall be available
• Follow the instructions in the safety data sheet or the operating
instructions when using hydraulic fluid
• Store minimal quantities
• Perform risk assessment in accordance with safety data sheet
• Keep risk assessments in hazardous goods cabinet
• Use exhaust equipment such as air cleaning, ventilation or
respirator helmets
• Wear personal protective equipment
• Barricade off work area if possible
• Accessing the barricaded area is strictly prohibited
• Only use tools which are suitable or intended for the activity
• Safety instructions and operating instructions shall be
HAZARD DUE TO HIGH PRESSURES observed
5 3 H 5 1 L
• Visual inspection before use
• Check to ensure that safety equipment is intact
• Check tools for inspection tags
• Use only appropriately trained and qualified personnel
• Wear appropriate personal protective equipment
• Barricade off work area if possible
HAZARD DUE TO PINNING AND CRUSHING • Use only appropriately trained and qualified personnel
2 4 M 2 3 L
• Keep personnel who are not required from the hazardous area
• Wear gloves
• Use low-vibration equipment or schedule sufficient breaks
• Secure tools in such a way that slipping away during operation
is prevented
• Shield adjacent work areas if injuries to others are possible
due to flying particles or slung parts
• check inspection tag
• Safety instructions in the instruction manual shall be observed
WORKING WITH POWER TOOLS
• Only use tools which are appropriate or intended for the activity
(e.g., pneumatic, electric, hydraulic) 4 4 H 4 1 L
• Visual inspection before use
• Check to ensure that safety equipment is intact
• Use only appropriately trained and qualified personnel
• Lines (electrical, pneumatic, compressed and process air) shall
be safely routed and secured
• If hydraulic fluid is used, follow the instructions in the safety
data sheet or the operating instructions
• Wear appropriate personal protective equipment
• Only use tools which are appropriate or intended for the activity
• Visual inspection before use
WORKING WITH HAND TOOLS/MEASURING EQUIPMENT 3 3 M • Safety instructions in the instruction manual shall be observed 3 1 L
• Wear appropriate personal protective equipment

• Obtain permit to work


• Perform visual inspection of Tag out and lockout for correct
implementation before entering confined spaces
• Only use electrical equipment with safety extra-low voltage
(SELV) or protected extra-low voltage (PELV)
WORKING IN CONFINED SPACES • Assign manhole watch
(inadequate evacuation and rescue possibilities, poor communication to • Maintain constant contact with manhole watch
the outside, risk of panic attacks, poor ventilation conditions, insufficient 5 3 H • Check atmosphere (oxygen concentration) before start of work, 5 1 L
room to move)
keep rescue equipment ready if necessary
• Ensure tidiness and cleanliness during maintenance work in
confined spaces
• Working alone is prohibited; 2 employees as a minimum
• Suitable persons
• Use respirator equipment if necessary
• Install continuous ambient air monitoring if necessary
• Installation of scaffolding or barriers, only access scaffolding
that has been inspected and approved
HAZARD DUE TO FALLING 4 4 H 4 1 L
• Observe work instruction on use of PPE to prevent falling!
• Use PPE to prevent falling
• Permit to work shall be issued
UNINTENTIONAL ACTIVATION OF SYSTEMS/COMPONENTS
5 4 H • NOTE: Permit to work shall be prepared and issued only by 5 1 L
person tested and authorized by the customer
Supervisors must review the work activity & complete the following sections, before commencing work to ensure that all risks are identified and controlled.

Assessment Assessment
(No Controls) (With Controls)
Additional Hazard/Risk Additional Controls
S L R S L R
• CORRECT PPE AT ALL TIMES
• TOOLBOX TALK TO BE GIVEN BEFORE
COMMENCEMENT OF WORK
• ALL PERSONNEL TO BE SUITABLY QUALIFIED AND
EXPERIENCED(SQEP)
UNAUTHORIZED PERSONS/ OTHER SUBCONTRACTORS IN
• Mark areas and barricade off if necessary
WORK AREA 5 4 H 5 2 M
• Inform subcontractors of risks

POOR LIGHTING 3 4 M 2 1 L
• Lighting that is appropriate to the situation shall be provided
• Select low-noise work procedures
• Observe all noise protection and hearing protection
NOISE / AMBIENT SOUNDS 4 4 H 4 1 L
instructions
• Wear appropriate personal protective equipment if necessary
• Try to route lines overhead
• Materials and tools which are not required shall be removed
SLIPPING, STUMBLING AND FALLING ON SAME LEVEL 3 3 M from the work area 3 1 L
• Traffic routes shall be kept free
• ensure area is tidy and clean

Primary Legislation: Associated Documentation:


ArbSchG: GV 02 Risk Assessment(s):-
Method Statement(s)
BGV: A3,C16, Lifting Plan if Required
COSHH Assessment(s)
BGR: 189, 191,192,193,194,195,197.198,500 Process Specification Sheet:-
Site Procedure:-
BGI: 515, 593, Local Management Instruction(s)

TRBS:2131,2111-1/2/3/4,2210

Assessed by Supervisor: Name: Date:


“This document contains proprietary information. It is submitted in confidence and is to be used solely for the purpose for which it is furnished and returned upon request.
This document and such information are not to be reproduced, transmitted, disclosed, or used otherwise in whole or in part without written authorization.”

Você também pode gostar