Escolar Documentos
Profissional Documentos
Cultura Documentos
WHAT IS AN ESTIMATE
Before taking up any work for its execution, the owner or builder should have a thorough knowledge
about the volume of work that can be completed within the limits of his funds or the probable cost that may
be required to complete the proposed work.
It is therefore necessary to prepare the probable cost or estimate for the proposed work from its plan
and specification.
Otherwise, it may so happen that the work has to be stopped before its completion due to the
shortage of funds or of materials.
Besides the above, an estimate for any public construction work is required to be prepared and
submitted beforehand so that sanction of necessary funds may be obtained from the authority concerned.
Thus an estimate for any construction work may be defined as the process of calculating the
quantities and costs of the various items required in connection with the work .
It is prepared by calculating the quantities, from the dimensions on the drawings for the various items
required to complete the project and multiplied by unit cost of the item concerned.
To prepare an estimate , drawing consisting of the plan , the elevation and the section through
important points, along with a detailed specification giving specific description of all workmanship ,
properties and proportion of materials , are required.
PURPOSE OF ESTIMATING:-
To ascertain the necessary amount of money required by the owner to complete the proposed work .
For public construction work, estimates are required in order to obtain administrative approval , allotment
of funds and technical sanction.
To ascertain quantities of materials required in order to programme their timely procurement. To
procure controlled materials, if any, like cement , steel, etc. quantities of such materials are worked out
from the estimate of the work and attached with the application for verification.
To calculate the number of different categories of workers that is to be employed to complete the
work within the scheduled time of completion.
To assess the requirements of tool , plants and equipment required to complete the work according to
the programmed.
To fix up the completion period from the volume of works involved in the estimate.
To draw up a construction schedule and programmed and also to arrange the funds required
according to the programming.
To justify the investment from benefit cost ratio.(for ideal investment ,this ratio should be more than
one)
To invite tenders and prepare bills for payment.
An estimate for an existing property is required for valuation
DATA REQUIRED FOR ESTIMATING:-
1. Drawings i.e. plans, elevations, sections etc.
2. Specifications.
3. Rates.
DRAWINGS
If the drawings are not clear and without complete dimensions the preparation of estimation become very
difficult. So, it is very essential before preparing an estimate.
SPECIFICATIONS
a) General Specifications: This gives the nature, quality, class and work and materials in general terms to
be used in various parts of wok. It helps no form a general idea of building.
b) Detailed Specifications: This gives the detailed description of the various items of work laying down the
Quantities and qualities of materials, their proportions, the method of preparation workmanship and
execution of work.
RATES
For preparing the estimate the unit rates of each item of work are required.
1. for arriving at the unit rates of each item.
2. The rates of various materials to be used in the construction.
3. The cost of transport materials.
4. The wages of labor, skilled or unskilled of masons, carpenters, Amador, etc.
LUMPSUM
While preparing an estimate, it is not possible to work out in detail in case of petty items. Items other than
civil engineering such items are called lump sum items or simply L.S.Items.
PLINTH AREA:
• The built up area of a building measured at floor level of any story is called plinth area.
• It is calculated for the roofed area of a building by taking external dimensions, excluding the plinth
offsets.
• The area of the courtyard, open areas, balconies and cantilever projections should not be included
in it.
FLOOR AREA:
• Total area of floors in between walls i.e. areas of floor of all rooms, verandas, corridors, stores,
bath and lavatories etc. is called floor area.
• Floor Area=Plinth Area – Area occupied by walls which should include the area of doors and other
opening’s, intermediate pillars or supports
CIRCULATION AREA :
• The floor area of the verandas, corridors, passages, entrance halls, staircase room and amenities,
porticos, balconies, shafts, lifts is known as circulation area. such area is used for movement of
persons using the buildings
CARPET AREA:
• The livable area of buildings is called carpet area. It is the total floor area minus the circulation
area and minus the other inhabitable area such as bathrooms, water closets, air conditioning room
etc.
• It should exclude kitchen, pantry, stores and similar other rooms which are not used for living
purposes in residential buildings.
Approximate estimate
• As Preparation of detailed estimate involves lot of time and resource, the approximate cost of a
structure is determined by short cut method based on same available data about similar structure.
• Such an estimate is called an approximate estimate.
• The approximate estimate is also called as proforma estimate /preliminary estimate/ rough
estimate.
Need for approximate estimate
Approximate estimates are used when
Exact precision is not necessary
Time is short
At the stage of preliminary planning of the work
To accompany a proposed for technical sanction/administrative approval.
Taxation, Insurance, mortgaging, registration of property etc.
Problem 1
Prepare an approximate estimate for residential building with the following data
• Plinth area --- 110m2
• Plinth area rate for structural cost ---Rs. 3,200/m2
Solution
• Structure cost = Plinth area x plinth area rate
= 110 x 3,200 = Rs. 3, 52,000/-
Other provisions:
• Water supply and sanitation
= 3,52,000 x 12.5/100 = Rs 44,000
• Electrification = 3,52,000 x 7.5/100 = Rs 26,400
• Architectural = 3,52,000 x 1/100 = Rs 3,520
• Work charged establishment
= 3,52,000 x 3.0/100 = Rs 10,560
Total cost = Rs. 3, 52,000 + Rs 44,000 + Rs 26,400+ Rs 3,520+ Rs 10,560
= Rs 436480.00
• Total cost of residential building
= 3,52,000+ 84,480
= Rs 4,36,480
Or say Rs 4.4 lakhs.
• This method is similar to plinth area method and is suitable for multistoried structures & buildings
with thatched roofs.
• The cubical content of a building is the volume obtained by product of its plinth area and height.
The height is taken as follows
Multi stored structures:
• Height per storey = Difference in elevation between the adjacent floors (Ceiling height + slab
thickness includes floor finishes)
• The building cost = cubical content of building x
cubical content rate
• The total cost = cost of building (structure)
+ cost of building services
+ over head charges as a percentage of structural cost.
• The cost per unit volume is determined from the cost of a building already constructed with similar
specifications in the same locality
• Cost of a building = Total cubical content x cost/m³ of a building with similar specifications in that
locality
Problem 1
Prepare an approximate estimate for a proposed commercial complex for the following data.
• Plinth area = 1000 sqm/floor
• Height of each floor = 3.5 m
• No. Of floors = ground floor +3
• Cubic content rate= Rs 1000/m3
• Provided for the following as a percentage of structural cost
• Water supply and sanitary arrangement ----- 8 %
• (b) Electrification ------ 6 %
• (c) Fluctuation of rates ------ 5 %
Solution
Cubical content = No of floors x (plinth area x
height each floor)
=4 x (1000 x 3.5)
=14,000 cum
Structural cost =cubical content x cubical content rate
Roads Per Km
Problem :
Prepare an approximate estimate of a hospital building in a PHC for 20 beds. The cost of
construction for each bed is arrived at Rs. 70,000/- by considering the hospital building constructed
recently in near locality. Determine the total cost of hospital building.
Solution:
No. of beds = 20
Cost of construction per bed = Rs. 70000/-
Total cost of Hospital Building = Rs 20 X 70000 = 14,00.000/-
The rates for various materials and labour are maintained in the Engineering Departments of
government in a printed book are called as standard schedule of rates.
It gives the rates of material and labour for preparation of estimates
S.S.R. is prepared by state government and central government separately
State government Revises it’s S.S.R yearly
Central government Revises once in 5years/10 years
These rates are only for guide lines