=6 pcs per bar

Metal
Reinforcement
 CHB
Reinforcement
Total Ext Wall Area = 257.38 m2
No of Steel Bar= Total No steel bar/ 6
Vertical Reinforcement: 0.60 m =360/ 6
Horizontal Reinforcement: 3 Layers
= 60 pcs @ 12mm ø x 6 m
Solution:

Vertical Reinforcement:  Column


= Area x 2.13
= 257.38 x 2.13 No of Column: 18
= 548.2194 m Main Reinforcement Bar (4) : 8.50
Horizontal Reinforcement: meters @
= Area x 2.15
= 257.38 x 2.15 No of Lateral Ties:
= 553.367 m = 8.50/ 0.30
= 28.33
≈ 29 spacing + 1
No of Steel Bar = (VR + HR) / 6.00 ≈ 30 pcs per column
Total No. of Lateral Ties:
= (548.2194 + 553.367) / 6
= 30 x 18
=183.5977 = 540 pcs
Length of Lateral Ties: 0.80 meters
≈ 184 pcs @ 10 ø x 6 m Pcs of Lateral Ties in 6.00:
= 6.00/ 0.80
=7.50
 Footing = 7 pcs
No of Steel Bars for Lateral Ties
No. of Footing: 18 = 540/ 7
No of cut bar: 20 @12mm ø x 1.0 m = 77.14
≈ 78 pcs @ 10 mm ø x 6.0 m
Solution:
No of Steel Bar for Main
Total No of cut bar= 20/ footing x 18 Reinforcement
footing = 4 x 9 ( 8.50) x 18
= 648 pcs @ 16 mm ø x 9.0 m
= 360 meters
Pcs of steel bar in 6.00
=6.00/ 1.00
 Beam = 59.6 x 3.221
= 191.97
≈ 192 pcs @ 12 mm ø x6.0 m
No of Beams
B1 (18) – 3 m
B2 (5) – 5 m
B3 (4) – 4 m

Main ReBar:(4)

No of Steel Bar for Main


Reinforcement
B1= 9/ 3
B1 = 3 pcs
B2 and B3 = 9/ (5+4)
B2 & B3 = 1 pc
Total: 4 pcs
= 4 pcs x No of Beam x No of
Main bar
= 4 x 27 x 4
= 432 pcs @ 16 mm ø x 9.0 m

No of Stirrups:
B1 (18): 16
B2 (5): 26
B3 (4): 21
Total: 502 pcs
Pcs of Stirrups in 9.00:
= 9.00/ 0.80
=11.25
= 11 pcs
No of Steel Bar for Stirrups
= 502/ 11
= 45.63
≈ 46 pcs @ 12 mm ø x 9.0 m

 Slab
Floor Area
S1(4) – 3.0 x 3.0 = 9
S2 (3) – 3.0 x 5.0 = 15
S3 (1) – 4.0 x 5.0 = 20
S4 (4) – 3.0 x 4.0 =12
S5 (1) – 3.0 x 1.2 = 3.60
Total Area = 59.6 m2
Solution
@ 15.0 Spacing, 6 meters
= Area x 3.221