Você está na página 1de 1

Pre-Bomba Testing Date: 16/07/2019

Power Source - Normal Supply

1 Fire Alarm Bell Trigger-off

2 Lift Homing - Lift Lobby (UG) - Lift Contractor standby

3 Public Annoucement (PA) System

4 Roller Shutter - Need Roller Shutter Supplier standby

5 Fire Curtain drop down vertically - Fire Contractor standby at Atrium Area (UG)

6 Smoke Spill trigger-off at Atrium Area (UG)


* Smoke Gun trigger-off and shooting at Atrium Area (UG) - ACMV Contractor standby

7 Smoke Spill trigger-off at Car Park (LG)


* Smoke Gun trigger-off and shooting at Car Park (LG) - ACMV Contractor standby

8 Pressurization System trigger-off for ST01 / ST02/ ST03 / ST04 /ST 05


* Smoke Gun trigger-off and shooting at the staircase

9 EM Lock System c/w Break Glass at staircase in random basis


* Fire Alarm System deactivated and reactivated again to check the functionality

10 Smoke Detector / Heat Detector Testing for M&E Rooms - Fire Contractor standby

11 Fire Pump Room (LG) - Wet Riser System / Hose Reel System / Sprinkler System - Fire Contractor standby

12 The Bomba Lift will be tested by trigger-off the Fireman Switch.


* All the relevant NSCs (Fire / ELV / Elec) will use the lift to reach to upper floors

13 Fire Pump Room (L8) - Wet Riser System / Hose Reel System - Fire Contractor standby

14 Fire Pump Room (L20) - Wet Riser System / Hose Reel System - Fire Contractor standby

15 Magnetic Door Holder Testing in random basis


* Fire Alarm System deactivated and reactivated again to check the functionality

16 Smoke Detector Testing in random basis


* Fire Alarm System deactivated and reactivated again to check the functionality

17 Fireman Intercom Testing in random basis


* Fire Contractor need to standby at the Control Room

18 Fireman Switch Testing in random basis


* Electrical Contractor need to standby

19 Shooting 3nos of Test Wet Riser at Lower Roof - Fire Contractor standby

Power Source - Essential Supply

20 Generator Set - Interchange Over Testing


* Electrical Contractor need to standby

21 Fire Pump Room (LG) - Wet Riser System / Hose Reel System / Sprinkler System - Fire Contractor standby
* The Fire Pumps to be activated within 30 seconds time after the essential power supply cut-in