5 Fire Curtain drop down vertically - Fire Contractor standby at Atrium Area (UG)
10 Smoke Detector / Heat Detector Testing for M&E Rooms - Fire Contractor standby
11 Fire Pump Room (LG) - Wet Riser System / Hose Reel System / Sprinkler System - Fire Contractor standby
13 Fire Pump Room (L8) - Wet Riser System / Hose Reel System - Fire Contractor standby
14 Fire Pump Room (L20) - Wet Riser System / Hose Reel System - Fire Contractor standby
19 Shooting 3nos of Test Wet Riser at Lower Roof - Fire Contractor standby
21 Fire Pump Room (LG) - Wet Riser System / Hose Reel System / Sprinkler System - Fire Contractor standby
* The Fire Pumps to be activated within 30 seconds time after the essential power supply cut-in