Você está na página 1de 12

Available online at www.sciencedirect.

com

ScienceDirect
International Journal of Project Management 33 (2015) 889 – 900
www.elsevier.com/locate/ijproman

Workforce-related risks in projects with a contingent workforce


Karen Becker ⁎, Michelle Smidt
Queensland University of Technology, 2 George St, Z Block, Level 9, Brisbane 4000, QLD, Australia

Received 20 June 2014; received in revised form 24 October 2014; accepted 29 October 2014
Available online 14 November 2014

Abstract

Our research examined how projects can draw together the fields of human resource management (HRM) and risk management (RM) to consider
workforce-related risks on projects; particularly those with a large contingent workforce. It is argued that RM frameworks could be enhanced by a more
comprehensive understanding of the specific potential non-technical “people risks” in projects. The study focussed on the Oil and Gas industry and
undertook interviews with experts in the field. The findings are considered within the framework of key HRM areas; Management Practices, General
Employment Practices, Staffing, HR Development, and Compensation and Benefits, along with Project Completion. Drawing together RM and HRM
in a project environment, our research provides a unique opportunity to identify critical workforce-related risks. Such identification is the first step
towards a more comprehensive approach to risk assessment and planning for mitigation of such risks in projects.
© 2014 Elsevier Ltd. APM and IPMA. All rights reserved.

Keywords: Risk management; HRM; Workforce-related risk; Contract workers; Project risk; Non-technical risk; Risk identification

1. Introduction organisations often occur without a formal HRM function (Bredin


and Soderlund, 2011).
Risk management (RM) is increasingly recognised as a critical Typically these two fields, RM and HRM, have co-existed
activity for all organisations, and in the project management (PM) without necessarily recognising the potential intersection and
arena it has certainly been a focus of research (Bowers, 1994; Carr unique perspectives that could result from drawing them together.
and Tah, 2001; Chapman, 1997; Chapman and Ward, 2003; Dey, In fact, there have been calls for the “forging” of these two fields
2002; Floricel and Miller, 2001). Potential risks cover a wide range with one author arguing, “Risk management is about mitigating
of areas, from operational and financial risks, to less tangible risks risk and protecting resources. What is the most valuable resource of
referred to as internal non-technical risks, organisational risks or any company? Its people.” (Nickson, 2001, p.25). Therefore our
personnel risks (Belout, 1998; Dey, 2002; Jaafari, 2001; Pinto and research aimed to study how HRM could be considered through a
Prescott, 1988). Likewise, the important role that human resource RM lens, and how RM frameworks could be enhanced by a more
management (HRM) can play in projects has also been a subject of comprehensive understanding of the potential “people risks” in
interest to those in the PM sphere (Bredin, 2008; Huemann et al., projects.
2007; Keegan et al., 2012; Popaitoon and Siengthai, 2014). Whilst The mainstream HRM discourse, and even the literature
effective HRM is critical for all organisations, it has been argued focussing specifically on HRM in PM, typically focusses on the
that a project-oriented organisation may face additional and unique added value HRM practices can bring, emphasising their critical
challenges in relation to its workforce (Huemann et al., 2007), importance to organisational success (Belout and Gauvreau, 2004).
particularly because operational HRM activities in project-based We argue however that a deeper understanding of the risks inherent
⁎ Corresponding author. Tel.: + 61 7 3138 2743. in ineffective or inappropriate management of human resources
E-mail addresses: Karen.Becker@qut.edu.au (K. Becker), will provide further imperative for managers to consider the critical
M.Smidt@qut.edu.au (M. Smidt). nature of human factors within their projects. Our intent is to use

http://dx.doi.org/10.1016/j.ijproman.2014.10.014
0263-7863/00/© 2014 Elsevier Ltd. APM and IPMA. All rights reserved.
890 K. Becker, M. Smidt / International Journal of Project Management 33 (2015) 889–900

the lens of RM to address this gap and to analyse the critical technical approach to strategy, tactics, operations and compli-
workforce-related risks in a project environment. To allow for an ance requirements (Culp, 2001; Elahi, 2013; Hopkin, 2013).
in-depth analysis of risks within projects, the Oil and Gas industry This is not surprising, as technical risks have typically been
was chosen as a focus for the research. This industry represents a viewed as having the biggest influence on profitability and
large and growing international industry (International Energy ultimate success. The importance of RM in the overall
Agency (IEA), 2013a) built largely on projects, comprised of a management of projects is increasingly being recognised (del
tiered system of international oil companies, national oil companies Caño and de la Cruz, 2002; Zhang and Fan, 2014), most likely
and a range of contracting organisations and individual contract due to the increase in project-based work (DeFillippi and
workers. This heavy reliance on a contingent workforce raises the Arthur, 1994). In the field of PM, one important source of
potential for workforce-related risks beyond those in projects with information is the 2013 Project Management Body of
a predominance of full-time employees. Therefore, the research Knowledge (PMBOK) guide 5th edition (Project Management
question that guided our research was, “What are the potential Institute, 2013). This guide outlines ten knowledge areas for
workforce-related risks in Oil and Gas projects that rely on a PM, one of which is PRM (Project Management Institute,
contingent workforce?” 2013). Because projects operate in an ever-changing and
complex environment, the need to systematically and formally
2. Literature review identify risks and uncertainties is critical to ensure cost,
schedule, and quality targets are met (Zhang and Fan, 2014).
The literature critical to this research relates to two key Although not always explicit, the primary reason for the
areas: risk management in projects and HRM in projects. Each adoption of PRM appears to be first and foremost to prevent
research area in its own right offers insights into the issue of budget overruns (Williams, 1995). Whilst managing financial
workforce-related risks in projects however very few authors risks is fundamental to ensuring project continuity, there is
have drawn together these two areas in a comprehensive way. growing recognition that other risks may also present
Prior to an in-depth exploration of the literature in these two significant challenges to the ongoing viability of projects.
fields it is necessary to articulate the focus of our research and Even with the growing recognition of the significance of
the definitions applied; particularly in relation to projects and RM, there is some disagreement between practitioners and
project-based organisations. academics concerning the definition of risk. In reviewing the
Many contemporary organisations make use of projects many perspectives on RM, there appear to be two predominant
however the extent to which an organisation's work is based on approaches to defining risk (Lehtiranta, 2014). The first (and
projects versus more permanent structures is of key concern. most traditional) definition describes risk in terms of the
For the purpose of this paper, we adopt the term project-based possibility of negative impact and outcomes (Barber, 2005;
organisation (Hobday, 2000; Project Management Institute, Chapman and Cooper, 1983; Dey, 2002; Lehtiranta, 2014) and
2013; Sydow et al., 2004), to denote organisations that carry aligns with the dictionary definition of risk (Ward and
out the majority of their work through projects in order to meet Chapman, 2003). The second, and more recently advocated
client demands. definition takes a broader perspective and includes both
It is suggested that in project-based organisations “knowl- negative and positive sources of impact also referred to as
edge, capabilities and resources are built up through the opportunities and threats (Lehtiranta, 2014; Ward and
execution of major projects” (Hobday, 2000, p.875) and that Chapman, 2003). For this research we have defined risk, in
such organisations are most typically found where “complex, line with the traditional approach, as any threat to the planned
non-routine tasks require the temporary employment and project outcomes whilst recognising that risk often co-exists
collaboration of diversely skilled specialists” (DeFillippi and with a level of uncertainty that may lead to either positive or
Arthur, 1998, p.125) and therefore many of those individuals negative consequences.
working on the projects are contract workers who move The majority of publications relating to PRM focus on
amongst different employing firms (DeFillippi and Arthur, methodologies and processes available, the calculations, scales
1998, p.125). Oil and Gas is one industry that relies heavily on and theories behind these, and how these should be used or
projects and often employs a large number of highly skilled adapted by organisations (Raz and Michael, 2001; Ward and
contract workers who move between projects and employers; Chapman, 2003; Williams, 1995). Most of these PRM methods
referred to by Redpath et al. (2009) as contingent knowledge consider a range of risk types including: external (market,
workers. In particular, our research focusses on projects as the environmental, political), technical (operating), legal (integration,
unit of analysis rather than on the organisation that may be force majeure) and internal non-technical (organisational, sched-
managing a range of major projects, recognising that there may ule, cost estimate, financing) (Jaafari, 2001; Wideman, 1992).
be variation in workforce-related risks even between projects Although the last variable (internal non-technical risks) often
managed by the same organisation. includes management issues, when specified this often encom-
passes a broad range of challenges and inadequacies including
2.1. Project risk management inadequate coordination or PM, or changes to senior staff
(Wideman, 1992). Whilst this variable could be assumed to also
RM has predominantly focussed on managing potential include risks relating specifically to the workforce, these have not
threats to organisations' operations and costs by taking a very been detailed sufficiently to provide a clear understanding of the
K. Becker, M. Smidt / International Journal of Project Management 33 (2015) 889–900 891

range of potential risks inherent in the workforce and its 2013). This would indicate a need to further refine and
management. delineate the key elements required for effective HRM in
A variety of PRM processes and frameworks have been projects and project-based organisations.
developed by practitioners and researchers in the field. Some of It has been argued for some time that project-based
the more widely recognised frameworks are outlined in Table 1. organisations face unique challenges due to the unstable and
The range of frameworks demonstrates at least a level of temporary nature of the work processes and environment and
agreement on a number of critical steps in PRM, although the that they require specialised HRM practices and processes,
number of steps or details of activities differ (Raz and Michael, however this area has yet to be fully explored (Bredin and
2001). In all of the frameworks one of the first steps is Soderlund, 2011; Huemann et al., 2007). Based on their review
identification of risks and it is here that workforce-related risks of research into HRM in projects, Huemann et al. (2007)
should be identified along with other types of risks. In most propose a model of HRM in projects which includes two
cases, however, it has been argued that the identification phase separate HRM processes; one occurring at organisational level
may lack rigour and detail in classifying and examining the less and one at project level. However, even this model assumes that
tangible non-technical risks (Lopes and Flavell, 1998). Until the workforce is largely permanent and simply moved between
such time as potential workforce-related risks are more projects until such time as they leave the organisation.
systematically identified, the first step of RM in relation to In many organisations like the Oil and Gas industry where
the HRM aspects will be compromised. Therefore, it is large-scale projects are the mode of operation, this may not be
pertinent to consider whether the literature relating to HRM in the case. In these projects, a small number of key personnel
projects offers some more definitive workforce-related risks may be employed by an operating organisation and therefore be
that might be considered within the identification phase of full-time permanent employees rotated amongst projects.
PRM. However, a large part of the workforce on individual projects
may be contract workers employed specifically for a single
2.2. Human resource management in projects project or as temporary specialists. Storey et al. (2002) identify
that contingent workers are often used as technical experts and
Similar to RM, the PMBOK (Project Management Institute, managers on projects and can be employed on either fixed-term
2013) also acknowledges HRM as a key capability for effective or temporary contracts, moving beyond a contract workforce
PM. However, unlike PRM which comprises six elements in for lower skilled positions towards the use of contingent
the PMBOK, the HRM element remains as a single item; ‘Plan knowledge workers (Redpath et al., 2009). These temporary
Human Resource Management’ (Project Management Institute, employees may be working side by side with core, ongoing,

Table 1
Project risk management frameworks.
PRM frameworks Steps/phases
Project Risk Analysis and Management (PRAM) Define,
(Chapman, 1997), Focus,
Identify,
Structure,
Ownership,
Estimate,
Evaluate,
Plan,
Manage.
Risk Analysis and Management for Projects (RAMP) Multi-level break down structure. Top level processes: process launch, risk review, risk
(Institution of Civil Engineers (ICE), 1998) management, and process closedown. These are broken down further in the lower level
processes according to (Carr and Tah, 2001)
Shape, Harness, and Manage Project Uncertainty (SHAMPU) Project definition,
(Chapman and Ward, 2003) Focussing the uncertainty management process,
Identifying sources of uncertainty,
Structuring issues,
Clarifying ownership,
Estimating variability,
Evaluating implications of uncertainty,
Harnessing plans,
Managing implementation
Project Management Body of Knowledge (PMBOK) 6 elements within the risk management component:
(Project Management Institute, 2013) Plan risk management,
Identification,
Qualitative analysis
Quantitative analysis,
Plan risk response,
Control.
892 K. Becker, M. Smidt / International Journal of Project Management 33 (2015) 889–900

full-time, permanent employees (Storey et al., 2002). Whilst from a risk perspective, a qualitative methodology was
Burgess and Connell (2006) argue that the growing use of a considered to be most appropriate.
temporary workforce introduces the potential for unique HRM
challenges, these have not as yet been the subject of extensive
3.1. Research context
research and analysis. This research aimed to analyse in more
depth the risks associated with a contingent workforce particularly
In order to examine the workforce-related risks likely to be
focussing on what Redpath et al. (2009) call contingent
encountered on projects our research focussed on the Oil and
knowledge workers. For the purpose of this paper ‘contingent
Gas industry for a number of reasons. First, the Oil and Gas
workers’ covers temporary workers employed on a contract,
industry relies heavily on major projects in order to carry out
through an employment agency or who are self-employed but
their work and in particular they rely heavily on a contingent
contracting to the project.
workforce. Second, according to the International Energy
Regardless of the nature of employment in a project, it is
Agency (IEA) the demand for Oil and Gas is predicted to
argued that many of the mainstream HRM practices such as
increase steadily through to 2035 (International Energy Agency
career development, performance evaluation, and appraisal are
(IEA), 2013b). Such growth is certain to put a strain on project
applicable to projects (Huemann et al., 2007), even if there is no
and HR managers to manage the risks this ever-increasing
dedicated HRM function within the project. Furthermore, it is
workforce brings. For these reasons Oil and Gas projects
recognised that other traditional HRM practices such as
provided an ideal setting to investigate workforce-related risks
recruitment and selection, performance standards/management,
in projects with a contingent workforce.
training and development and workforce planning are crucial to
project success (Belout and Gauvreau, 2004). A wide range of
activities can be considered within the realm of HRM, however 3.2. Data collection
Rynes et al. (2002), identified the core areas of HRM as
Management Practices (motivation, leadership, performance An interview study was determined to be an appropriate way
management, employee involvement, and HRM roles); General to gather data about potential workforce-related risks from a
Employment Practices (legal issues, performance appraisal and wide variety of perspectives. Interview studies allow for the
employee attitudes); Staffing (recruitment, selection, and career collection of a range of experiences (DiCicco-Bloom and
planning); HR Development (training and development, evalu- Crabtree, 2006), and in the case of the Oil and Gas industry it
ation of training effectiveness), and Compensation and Benefits was determined that those who have been exposed to a range of
(job pricing, pay structures, compensation strategies and projects will be able to offer unique insight into the potential
effectiveness), and we have chosen to adopt these dimensions workforce-related risks. In particular, convergent interviewing
in this research. In addition to these areas, we have also added was chosen as it can be utilised as a form of both data collection
Project Completion. Most of the traditional HRM literature and data analysis (Dick, 1990). Convergent interviewing is an
assumes an ongoing working relationship however in iterative process where the content of the interview is limited in
project-based organisations the end of a project often means the structure, but across multiple interviews, the process used is
completion of employment contracts and may therefore present relatively structured and involves an iterative review of
unique workforce-related risks. outcomes from each successive interview in order to continue
Whilst consideration of HRM and PM is widespread (Fabi to refine questions as data collection progresses. As interviews
and Pettersen, 1992; Huemann et al., 2007; Nickson, 2001), the progress, the interviewer is seeking convergence both within
links between HRM in projects and PRM have not been the interview and across interviews. Interviewing should
extensively researched. When examining the overlap of HRM continue until subsequent interviewing is not likely to raise
and RM the main focus has been occupational health and safety significant new data (convergence) and any divergence
including discrimination and harassment (Nickson, 2001). amongst interviews can be anticipated and explained.
However, other areas of HRM also involve risk; if not to the The interviews were undertaken by a single researcher
health or physical safety of employees, at least to the effective however checking occurred during the process to provide rigour
operations of the business particularly when a large section of to the process (Baxter and Eyles, 1997). A second researcher was
the workforce is contract workers. Therefore, using the HRM involved in a pilot of the questions and two subsequent interviews
framework provided by Rynes et al. (2002), the research to ensure consistency of application of questions and probing. The
question guiding this research was: questions were structured around the HRM areas identified in the
literature review to guide the interview but were sufficiently broad
“What are the potential workforce-related risks in Oil and to allow new themes to emerge e.g. “What do you consider to be
Gas projects that rely on a contingent workforce?” the risks associated with staffing a project?”, “What do you
consider the workforce-related risks when reaching the comple-
tion of a project?”. In line with a convergent interviewing
3. Research method approach, these stem questions remained stable across interviews
but with each successive interview, prompts were added to be
Given the exploratory nature of the research question, and used when necessary, whilst being cognisant not to lead the
the limited number of studies considering HRM in projects participant.
K. Becker, M. Smidt / International Journal of Project Management 33 (2015) 889–900 893

3.3. Participants data rather than being predetermined. Analysis was undertaken
by one researcher and checked by the second researcher to
In order to access a wide range of perspectives purposeful enhance the trustworthiness of the findings.
sampling was used. Palinkas et al. (2013, p.3) advises that
when variation is preferred, a strategy that focusses on “intense
4. Empirical findings
examples of the phenomenon of interest” can be appropriate to
give a deep understanding. In this research, this variation was
This section presents the findings from the interview study and
achieved by identifying, through industry networks, a range of
outlines the key people-related risks when managing projects with
interviewees who had worked internationally across multiple
a contingent workforce, particularly in the Oil and Gas industry. It
types of projects in the Oil and Gas industry. After interviews
should be noted that when referring to this contingent workforce,
with 13 participants it was determined that no significantly new
the most common term used in the industry is “contractors”
data was emerging and a number of key themes were evident
although this term can also be used to describe large contracting
(convergence was occurring). An overview of the roles and
firms that operate within the industry or individual contract
experience of interviewees, along with the locations in which
workers. For the purposes of the research, we referred to the use of
they have worked, are shown in Table 2. To comply with
contract workers however some of the interview excerpts may
ethical clearance requirements, no participant can be identified
refer to “contractors”. In all cases, references are intended to refer
and therefore quotes from interviewees use the interviewee
to individual contract workers and not the contract organisation.
number as a unique identifier.
In our analysis, people-related risks were grouped into the
five dimensions proposed by Rynes et al. (2002): Management
3.4. Data analysis
Practices, General Employment Practices, Staffing, HR Devel-
opment, and Compensation and Benefits, with Project Com-
Data analysis was undertaken in two stages or “rounds”
pletion/Demobilisation added as a sixth dimension to recognise
(Saldaña, 2013). In the first round of coding, referred to as
the unique nature of projects. Table 3 provides an overview of
descriptive coding (Wolcott, 1994), broad topics of interest
the key themes emerging in each of these dimensions and the
were identified, particularly in relation to the HRM function of
following sections provide further detail and discussion.
reference, for example, recruitment and selection. Importantly,
this stage did not analyse actual content but allocated responses
according to the function or topic to which they were referring. 4.1. Management practices
The second round of coding (focussed coding) reviewed the
content within each of the codes from the first round coding There were three key risks identified within this dimension:
(Saldana, 2009), and identified themes relating to risks within loyalty and engagement, management support and attitude, and
those initial codes. This allowed for risks to emerge from the managing performance and behaviour of contract workers.

Table 2
Details of interview participants.
Interviewee No. Current role Experience Locations
001 Project risk and loss prevention 20 years' oil and gas exposure in varying roles: Norway, Kazakhstan, Australia,
coordinator Project risk & loss coordinator, technical director,
safety and environment consultant
002 General manager 20 years' experience, geologist, technical/operational UK, PNG, Australia, Yemen, Kazakhstan
roles,
003 Human resource manager 25 years' experience, resources sector, workforce Australia, USA
management
004 Contract advisor 5 years' experience, contract administration, Australia, Scotland
portfolio management,
005 Drilling manager 5 years' experience in oil and gas drilling Australia
006 HSSE manager 18 years' experience, Engineer, Manager, Safety Arab Emirates, Middle East, Libya, Egypt, PNG
007 Associate director and Global 25 years contract recruitment in power and oil and gas UK, Middle East, Africa
account manager industry,
008 Human resource manager 9 years' resourcing and recruitment for large LNG Asia Pacific
projects,
009 Project manager 3 years' oil and gas contracting, Shipping industry, Australia, Singapore, Vietnam, Philippines, the Asia
managing director 15 years, Pacific region, Nigeria, the United Kingdom and Europe,
and the Americas
010 Strategic advisor 5 years' operational informer LNG and commercial PNG, Australia
operations, consulting,
011 Project manager 14 years' oil and gas experience, Middle East, Australia,
012 HSSE manager 20 years' safety experience on mega projects, Middle East, Asia, Australia, North America, Canada,
013 Engineering manager 25 years' oil and gas experience in variety of Australia, USA, Canada
engineering, ops and commercial leadership positions
894 K. Becker, M. Smidt / International Journal of Project Management 33 (2015) 889–900

Table 3 the company is about, and making them support that and become
Summary of key findings according to HRM dimensions. aligned with that. That's important…” (009).
Dimensions Key risks In combination with alignment was fostering a willingness to
Management Loyalty and engagement look beyond immediate tasks and role requirements and instead
practices Management support and attitude consider the wider issues of the project. One interviewee
Managing performance and behaviour of contract workers explained: ‘they [the contract workers] don't have the same
General employment Cultural alignment
ownership as the company people. So if you give them typically a
practices Country compliance
Clarity of responsibilities between operating company and specific task, they will take care of it, but not as proactive about
intermediaries going outside the additional scope that might be required for the
Compliance with company employment policies job…’ (013).
Staffing Project appeal The second risk within the management practices dimension
Skills shortage
was that of management support and attitude. One aspect of this
Poaching
Clarity of skill requirements risk was the extent to which support is offered by managers
Filling critical roles through sharing information, giving advice, providing interesting
HR policies and processes tasks as well as autonomy (intangible benefits), empowering and
Mobilisation time creating trust: ‘[some organisations] have more of a nurturing,
Setting expectations
support to help the team, help the contractor to deliver what you
HR development Induction
Approach to upskilling want them to deliver and that culture is different, depending on the
Career development opportunities for contract workers project manager that is driving it.’ (007), ‘That is one of the other
Compensation and Remuneration and benefits general challenges of these sorts of projects is maintaining
benefits Equity in contract worker vs staff pay and benefits management support over the longer term’ (009).
Project completion/ Retaining skills for project completion and future projects
Another aspect was the attitude of management on the project,
demobilisation Capturing, retaining and securing knowledge
which was seen as a more collective concern than support by
individual managers. Generally, management could either view
The first finding relates to both creating and retaining loyalty contract workers as integral to the operating company or as
and engagement from the workforce, particularly with a large separate from the company and therefore engaged in a
number of contract workers working on a project: ‘There's a small transactional relationship for the purpose of completing the
degree of loyalty’ (007). The explanations given for this risk were project, as illustrated by the following interviewees: ‘…for them
twofold. First, it was claimed that contract workers are [the contract workers] is how you treat them and how you want to
predominantly motivated by extrinsic rewards, for example higher include them in your business, how that fits in your model.’ (003),
rates or longer contracts, which can easily be duplicated by ‘…they [the contract workers] feel like they are not treated equally
competitors: ‘Just pay them [the contract workers] more and they … as staff employees’ (011). As such, the view which prevails in
stay. They will go down the road for 50 cents more …’ (003), the company will greatly influence the extent to which the project
‘Typically, we see individuals moving because they [competitors] workforce is seen as a “whole” or comprised of staff and contract
[offer] longer durations’ (008). A second explanation provided by workers as separate groups. Interviewees explained that this
interviewees was that temporary work often attracts individuals manifests in several ways such as whether contract workers are
who enjoy being independent and having the freedom and invited to company functions such as Christmas parties, whether
flexibility to move according to their interests and circumstances the HRM function or the procurement function manages contract
at any given time. As interviewees explained: ‘…that is the nature workers, and generally whether they are treated equally to
of those types [contract workers]; they like to move around.’ permanent staff of the organisation.
(006), ‘Because contractors, particularly, tend to be always The final element of this dimension relates to the risk
looking for the next big, exciting thing’ (010). associated with managing the performance and behaviour of
In addition to loyalty within this dimension, the risks inherent contractors to ensure the workforce is meeting expectations,
with a lack of engagement were also highlighted during the especially if there is no standard procedure for doing so,
interviews. Although not entirely separate from loyalty, engage- particularly in the case of contract workers. The interviewees
ment related more to reducing the risk of turnover by ensuring that reported; ‘I think it's performance managing, really, is the key
those working on the project were fully engaged. Often this might one [risk]’ (006), ‘[a risk is] performance management. It's a
be achieved by providing stimulating tasks that engender different world where you have got all of these people who are
commitment to the goals of the project in a way that motivates day raters.’ (010). If the company views the contract workers as
and encourages the workforce to see these goals achieved: ‘… you ‘separate’, this in turn means that he or she is not included in usual
have to make sure that they [the contract workers] identify with the performance management processes. As a result, if performance
goals of the company and the project; and that they are motivated and/or behaviour is not being consistently monitored, this could
well to see the project succeed; they are not just time servers’ lead to a higher likelihood of unwanted behaviours and less than
(009). From a management point of view this involves alignment optimum performance.
between the individual, the goals of the operating company and In summary, the workforce-related risks found within the
the project: ‘…certainly with contract workers, there's a lot about dimension of management practices related to three elements
motivation; having to understand what the project is about, what that are highly interconnected. First is building loyalty and
K. Becker, M. Smidt / International Journal of Project Management 33 (2015) 889–900 895

fostering a sense of engagement on the project. This may be of labour hire agencies is a common practice. The challenge in
more or less of a risk depending on the level of management these situations is creating clarity very early in the project
support offered to contract workers by the individual manager concerning the division of responsibilities and liability between
and whether contract workers are viewed as part of the greater the intermediary or the individual contract worker (often with
workforce and treated as such (the second element of this their own legal entity) and the operating company of the
dimension). The treatment of contract workers will also more project. In relation to establishing such clarity one interviewee
specifically influence the extent to which the performance and explained: ‘It's down to having those open communications
behaviour of contract workers is managed. Lack of appropriate [with labour hire providers], the sort of compliance piece. I
approaches to any of these three elements were considered to don't think a lot of people have that as part of their upfront
present risks to effective PM. discussion. … [having] a good dialogue early in the piece to
establish the ground rules’ (002).
4.2. General employment practices Another reported risk under general employment practices
was ensuring compliance with company employment policies;
Under the general employment practices dimension, the in particular ensuring contract workers are aware of and follow
potential risks identified include: cultural alignment, compliance company policies such as health and safety polices and bribery/
with country legislation, establishing clarity of responsibilities corruption policies. Under the broader theme of health and
with intermediaries, and compliance with company employment safety, various aspects were mentioned including, ensuring
policies. fitness for work (physical fitness, compliance with drug and
A critical risk reported in this dimension was that of not alcohol policies), preventing harassment, and ensuring sick
creating effective cultural alignment particularly when consid- contract workers do not attend work. The need to address these
ering a workforce comprised of both permanent and contract risks was raised by many of the interviewees: ‘… we often have
workers. This involved ensuring that contract workers demon- a lot of challenges around our fitness for work issues and that
strate the values of the company through their behaviours could be things from alcohol-related policies through to actual
which is reportedly very difficult to achieve. In addition to physical fitness, to be working on site’ (008), ‘They [the
cultural alignment, contract workers also had to fit within the contract workers] tend to not want to take sick days, even when
project team. Creating such alignment on multiple levels was they are sick as a dog because they won't get paid if they don't
reported as challenging because contract workers often come come in. There is a lot of people coming in…germs everywhere
from a variety of previous projects each with their own unique and people get upset’ (012).
culture, as one interviewee explained: ‘[…] you have to take an In summary, the risks relating to general employment
individual who has been drawn from a wide range of diverse practices were related significantly to compliance (both at the
cultures and technical experience and try to bring them into country and organisational level), aligning contract workers
your culture or into the way that you want to operate’ (012). with the organisation and ensuring an understanding between
The general employment practices category also includes all stakeholders in the employment relationship, particularly
country compliance risks. Our research revealed that not when intermediaries were involved. The inability to address
staying abreast of the legislation of the country in which the these risks represents the increased possibility of breaches of
project is operating to ensure that all employment requirements either legislative requirements or company policy and resultant
are met presents substantial risk to the project. This especially financial sanctions or at least disruption to work as these are
relates to ensuring that the appropriate visa and work permits addressed.
are obtained and current immigration legislation is adhered to.
It was emphasised by the interviewees that compliance could be 4.3. Staffing
particularly difficult if the company was setting up a project in a
location for the first time and would therefore be unfamiliar An area presenting significant risks for projects, is maintaining
with the legal system within the country. Moreover, some appropriate staffing. The findings in the area of staffing related to
locations were identified as requiring continued efforts to appeal of the project, skills shortage, poaching, clarity of skill
ensure compliance regardless of previous experience in the requirements, filling critical roles, HRM policies and processes,
country: ‘[…] at the moment we have had a lot of challenges mobilisation time, and setting expectations.
with the Philippines, for example. They seem to change their Lack of ability to attract an appropriately skilled workforce
immigration policies almost on a fortnightly basis’ (008). It was for a particular project was seen as a substantial risk for
reported that meeting some of the requirements of particular projects. Interviewees reported that project appeal was a
countries could add significant time to the process of obtaining critical factor in the attraction of an effective workforce. In
an appropriate project workforce and this was seen as a particular, the project location, size, duration, timing, state and
significant risk to timely acquisition of key skills for a project. operating company all played a vital role when attracting the
An additional risk was identified in this dimension related to necessary skills. The observation made by a number of the
the prevalent use of intermediaries in the employment of interviewees was that contract workers generally prefer to work
contract workers, and ensuring clarity of responsibility between in locations that are regarded as safe and where taxation
operating company and intermediaries. In addition to the use legislation is less onerous. One of the interviewees explained,
of freelance or individual contract workers on projects, the use ‘The tax rate in various countries is one of the main barriers to
896 K. Becker, M. Smidt / International Journal of Project Management 33 (2015) 889–900

being able to source individuals in a particular location’ (008). you get that wrong, you are setting yourself up for internal
In addition to location, it was reported to be easier to attract issues and those are the biggest risks […]’ (002)
contract workers if the project is of a larger size and in the early On a more systemic level than those mentioned previously,
stages of operation, making the duration of the project longer the lack of, or inconsistent application of, sufficiently rigorous
for those who join: ‘[…] you won't always get the guy you want and effective HRM policies and processes, was seen as another
because if, for example, [Company name] has got a big key risk in the staffing dimension. As illustrated by the
lucrative job going’ (004) and another reported: ‘Typically, we following quotes, this includes having standard procedures for
see individuals moving because there are longer durations’ reference checking, contract finalisation, and consistent and
(008). Another element of project appeal is that of timing: ‘[…] errorfree payment: ‘I am also intrigued by the lack of formal
it's all about timing, there's a timing window when other reference checking.’ (002), ‘And they [the contract workers]
clients, other projects are going to be in a situation where they will move because you stuffed up their pay once.’ (010), ‘Our
[the contract workers] will have available slots’ (007). More biggest challenge is making sure people actually have a
skilled candidates will be available if the project is recruiting at contract when they walk in the door’ (004). Interviewees
a time when few other projects are hiring or when other projects reported that a lack of thorough reference checking has
are in the completion phase. previously led to inappropriate appointments, and that issues
Summing up how the overall makeup of a project can affect relating to pay and contracts have often meant the loss of highly
recruitment, one interviewee reported: ‘…it's about how you skilled workers.
articulate/sell them [the non-monetary elements of the project]; Moreover, whether or not policies and procedures are in
but that's around things like the culture/structure of the place, interviewees reported that another risk was the time it
organisation that you have, how many tiers of management takes to source, hire, and upskill contract workers before they
are there, what opportunities are there for progression and for can contribute fully to the project. Thus mobilisation time was a
new roles; what locations the individual is going to be working risk reported by numerous interviewees: ‘Lead-in time has been
in; what's the cultural mix of individuals within your much longer than I would have envisaged. So we are basically
organisation; all of these types of things create unique selling under-resourced because we can't get the people in place
points for organisations and it is not so much about the dollars’ quickly enough.’ (005), ‘I don't want to recruit them today and
(008). spend three weeks with them until they are actually delivering
Another key risk in this dimension was skills shortages and something back’ (006).
the difficulty that can arise in finding sufficient individuals with Finally, in regards to the staffing dimension was the issue of
the required skills for the project when these are of limited setting expectations and ensuring a realistic picture was
supply and in high demand: ‘There seems to be just not a lot of provided to potential workers relating to the position, the
people in the marketplace that have operating…skills right now’ specifics of the project, and information about the location of
(013), ‘We are all in that same space, looking for much the the project. As two of the interviewees explained: ‘Quite often,
same skills’ (003). Poaching is very closely related to skills the people who come in are not given the correct image of what
shortage as it relates to the retention of skilled workers in an we are actually asking […]’ (002), ‘And that's very important,
environment where competing projects may be offering to be sure that people come here with the right understanding of
attractive packages in order to encourage contract workers to what is required of them and what is put in place to look after
‘jump ship’ as one interviewee reported: ‘So you have got a them’ (009).
constant situation where companies are trying to entice your In summary, the staffing dimension received a significant
best people off the project.’ (007), ‘[…] you are always at risk amount of focus from the interviewees and the risks within this
that that person could leave, if someone came headhunting and dimension ranged from external conditions such as lack of
had a better offer tomorrow’ (010). appropriately skilled workers in the labour market, to internal
Another staffing risk identified was a lack of clarity about risks such as a lack of clarity of needs or inadequate application
the capabilities required for particular positions, in terms of of HRM policies and procedures. Each of these risks was seen
both technical and soft skills. It was reported that a lack of as having the potential to slow the progress of projects through
understanding of the necessary capabilities can lead to either the loss of capable workers or the inability to attract them
appointment of inappropriate individuals and risk premature in the first instance.
turnover or at least a lack of critical skills. In the haste to
appoint individuals, sometimes roles are not sufficiently 4.4. HR development
detailed to brief either internal or external recruiters on specific
project needs: ‘[…] it's understanding what you need, what The main risks identified in the HR development dimension
stage your business might be at.’ (003), ‘[…] having a clear related to induction, approaches to upskilling, and career
understanding of scope of work and what it is that we are development opportunities. The first risk in this area related to
looking for somebody to do is really critical […]’ (008). the processes for induction, often referred to in this industry as
Filling critical roles was also mentioned as a staffing risk, as ‘onboarding’. In particular, it was identified that even though
some roles will be more central to the success of a project and induction is critical for integration of all new workers onto the
therefore have a greater influence on the project: ‘I think getting project, often contract workers in particular were not given
the right people in half a dozen key boxes is fundamental. If appropriate inductions: ‘[t]he first challenge with on-boarding
K. Becker, M. Smidt / International Journal of Project Management 33 (2015) 889–900 897

is that it's not there’ (004). As another interviewee explained, relating to equity in the rates and benefits of contract workers.
when these processes are present, effectiveness is enhanced: ‘If The remuneration of contract workers was a topic raised
you invest and have an on-boarding process which is quite consistently in the interviews, and was reported as being of
detailed, then I think you get a faster return.’ (012). It was great importance to effective operations and a large potential
recognised that it does take time to get contract workers up to risk for retention of those employed on a contract basis. In the
date with technical skills and familiarise them with policies and first instance, the remuneration or compensation offered highly
procedures, but it was also emphasised that it is critical to influences whether contract workers will join the project as it is
induct for culture: ‘establishing the way we work’ (006) and one of first criteria upon which contract workers will judge a
aligning contract workers’ values and behaviours with the project: ‘[…] when you are talking about a contingent
culture of the project: ‘[…] it's always the soft stuff that is the workforce of a big project, it will depend on how much you
hardest to get going’ (004). are paying. Money is very influential; salary is very influential;
When inducting individuals on a project it is essential that much more so than in a normal environment’ (010).
they are equipped to function in the intended role; often However compensation is not just of critical importance in
requiring upskilling of contract workers. Frequently it was the early phases of the project. It was reported that the rates
assumed that individuals would have all the necessary paid will continuously influence the retention of contract
competencies but this was often not the case: ‘Not a lot of workers, and that strategies need to be in place to retain these
people have specific technical experience. We end up getting workers: ‘the best people will leave, because we don't put
someone who is close and having to invest a lot of time training retention bonuses, we don't put short-term/long-term incentives
them’ (013). Reportedly, ensuring that contract workers possess in our contingent labour hire packages’ (004).
the needed skills and competencies was of increased difficulty The other dimension of the findings concerns the establishment
due to skills shortages in the industry and in times of high of perceived equity in the rates of contract workers; between
competition from other projects. According to one interviewee contract workers under differing arrangements (various labour
this sometimes resulted in ‘promoting people into levels hire agencies, individual contract workers) and between contract
beyond experience because we [the company] don't have workers and permanent employees. It was reported that the lack of
enough people to fill the roles with qualified people’ (005). equity in rates paid for similar roles can create problems and foster
Interviewees also pointed out that career development negative feelings in all those working on the project: ‘[…] ensuring
opportunities on projects often do not extend to contract workers that we keep parity between the individuals that we have in place’
and this presents a risk to retaining these critical individuals: ‘[…] (008), ‘As a manager, I think that's where you need to work
you are often not looking at career progression. You know that with the staff on understanding the intangible benefits that they
you are there to do a job, to get paid and finish and that's it. When have – and they are things like career development and future
you are in a staff role, there is a whole different set of expectations; opportunities – and to express that; that they are being looked after
training, advancement, pension’ (004). It is often not seen as and there's benefits there that the contract people don't have’
necessary or appropriate to consider the career development of (010).
contract workers: ‘…at the end of the day the project is a finite In summary, compensation and benefits was seen as one of
period of time that, in the order of two/three years usually, and so the key sources of risk in terms of both attracting the necessary
it's very much a “here and now, this is the job you need to do” and workforce for the project and retaining individuals working on
the contractor will manage their own career move as to where they the project. There was both an absolute and comparative focus
go next’ (010). However, the consequence of not providing these in this area; that what was on offer was attractive and that it was
opportunities was recognised by some: ‘[…] it just gives you [the also perceived to be equitable within the project and between
manager] a lot less ability to secure the person, I suppose, and to individuals. The lack of equity was reported to be a source of
use those intangible benefits to motivate them’ (010). labour turnover and of reduced morale with the potential to
In summary, not appropriately inducting contract workers impact the success of the project overall.
who join the project and getting them up to speed both
regarding technical and non-technical aspects is seen as a risk 4.6. Project completion/demobilisation
to projects, and it is reported that there is often a lack of
procedures for doing so. Ensuring contract workers possess the Because projects are by definition temporary in nature,
necessary capabilities required, or are sufficiently upskilled is another dimension was added to the Rynes et al. (2002)
problematic and only made worse by the skills shortage and framework to capture the risks presented by the last phase of a
competition from other projects. Moreover, career development project, the demobilisation phase. Interviewees reported two
and progression is also a risk as contract workers are often not primary people-related risks in the final stages of projects:
offered such opportunities due to the less permanent nature of retention of skills for project completion and for future projects
their employment. and knowledge management.
The risk of not retaining the necessary skills to complete the
4.5. Compensation and benefits project was reported to be a critical risk: ‘I think if your project
is coming to an end, then contractors start looking for other
As is the case for most organisations, interviewees reported jobs, which is understandable, so that they can leave before the
remuneration and benefits to be a major risk, along with risks end of that contract.’ (005), ‘So the greatest risks to a project are
898 K. Becker, M. Smidt / International Journal of Project Management 33 (2015) 889–900

losing people in the final throes.’ (007). Retention was viewed organisations however our research reinforces the importance of
not only as critical for the current project but also for the benefit consideration of these risks in this particular context. Indeed, our
of future projects. For example the need to identify where research may also assist to dispel beliefs that some HRM practices
contract workers can be utilised upon project completion was are not necessary for contract workers; a claim currently being
often mentioned: ‘the biggest challenge is how to find them the questioned (Popaitoon and Siengthai, 2014). In fact it was found
next job; that's their biggest concern at that time’ (11). in our research that issues such as career development and
Second, at the demobilisation and completion stage of projects performance management were expected to be appropriately
was a specific risk relating to knowledge management and applied to these workers, and their absence presented risks of
capturing the knowledge of contract workers before they leave, turnover and lack of engagement.
whether their departure is planned or due to unexpected Project-based organisations represent a unique organisational
circumstances: ‘The biggest issue with the contractor stuff, you form however even these organisations can configure themselves
are not retaining the corporate knowledge, the experience in a range of different ways. A critical issue for most projects is the
in-house, obviously’ (002), ‘But it's always a risk that as different creation and utilisation of knowledge (Hobday, 2000) and this
people leave, you are going to have that corporate knowledge go becomes a particular challenge when a large component of the
out the door’ (010). In particular, knowledge management also workforce is contingent. Maintaining knowledge both within and
relates to securing any confidential information: ‘So there is across projects is critical, and recent research argues the
always a tendency or inclination, temptation, call it what you like, importance of developing absorptive capacity in these projects
for contractors to take with them information about how they did and the critical role HRM practices can play in developing this
the project they just left or finished on; what they did, what was critical capability (Popaitoon and Siengthai, 2014).
involved, what it cost, schedule information, procedures’ (009). Ultimately, the risks identified by this research represent
So it is clear that as a project draws to completion it is significant threats to a project in terms of cost overruns,
critical to consider the increasing risk of turnover, even though inability to meet project schedules, and financial, legal and
it is a risk throughout the project, and to also consider how to reputational damage. As a result of this research, an approach is
capture, retain and secure the knowledge assets of the operating offered to expand the single HRM element in the PMBOK
company that will be required for future projects. (2013) by documenting specifically some of the HRM aspects
that may need to be managed and addressed on projects,
5. Discussion and conclusion particularly with a contingent workforce.
Most importantly, we have drawn together the two areas of
The need to effectively manage risks in projects is certainly RM and HRM in projects; an outlook that has been argued to be
acknowledged, and Barber (2005) argued that internally generated essential for some time (Belout, 1998; Belout and Gauvreau,
risks are an important risk category to consider, but they are 2004; Nickson, 2001), but not addressed to any large extent.
difficult to quantify or classify and require further investigation. Our research advances ‘a more holistic picture of project risks’
This research has provided a unique opportunity to identify as called for by Lehtiranta (2014, p.11), and in turn increases
internal risks, particularly those relating to a workforce comprised awareness and ability of managers to act on and mitigate these
of a large proportion of contingent workers. The significance of risks. Whilst the paper refers to HRM functions, it is critical to
the workforce to project success has been previously acknowl- note that we are not necessarily referring to the role of specific
edged (Belout, 1998; Huemann et al., 2007; Popaitoon and HRM professionals or an HRM function within a project.
Siengthai, 2014), however in this research we have argued for a Indeed, it is often the case that an HRM function does not exist
new way of thinking about workforce-related risks and have within a project, and HRM practices are implemented by
considered these within a framework of key HRM areas, where project managers and operational managers (Bredin and
specific risks were identified. Soderlund, 2011). In fact, a recent study by Medina and
Whilst each HRM function was considered separately, it was Medina (2014) emphasises the importance of project managers
also evident that there were relationships between functions and understanding HRM issues, particularly in relation to selection,
between key risks identified. For example, remuneration and training and development, performance measurement and
benefits was a key theme in and of itself and had ongoing internal promotion. Indeed, as a part of this understanding we
implications for management of the project, but also played a role also argue that knowledge of the risks associated with these
in the appeal of a project for the purposes of talent attraction in the HRM functions is equally important for project managers.
first instance. Likewise, the level of support and the attitude of As with all research there are limitations of our study, and
managers within the management practices area could certainly be opportunities to build upon our findings. The information
linked to elements of cultural alignment in general employment gathered relates specifically to the perception of the inter-
practices; managers set the tone that enables effective alignment of viewees and in the future, the impact of identified risks could be
all workers within the organisational and project objectives. In this further validated by quantitative approaches to measuring their
respect our findings reinforce the calls in the mainstream HRM impact on project outcomes. Likewise, this research was
literature to consider the configurations of practices rather than conducted in a specific industry context and therefore any
practices in isolation (Verburg et al., 2007). application to alternate industries would need to be undertaken
It is acknowledged that many of the risks identified as critical with care. However, even though the research was conducted
for project-based organisations may apply to other forms of in a single industry with a large contingent workforce, it is
K. Becker, M. Smidt / International Journal of Project Management 33 (2015) 889–900 899

possible that many of the risks identified may be relevant to Culp, C.L., 2001. The Risk Management Process: Business Strategy and
other industries and workforces, and future research should Tactics. J. Wiley, New York.
DeFillippi, R.J., Arthur, M.B., 1994. The boundaryless career: a competency-
seek to explore these different contexts. Furthermore, a based perspective. J. Organ. Behav. 15, 307–324.
relationship is likely to exist between the different risks DeFillippi, R.J., Arthur, M.B., 1998. Paradox in project-based enterprise: the
identified and future research could more fully explore these case of film making. Calif. Manag. Rev. 40, 125–139.
relationships. It is also critical for future research to go beyond del Caño, A., de la Cruz, M., 2002. Integrated methodology for project risk
management. J. Constr. Eng. Manag. 128, 473–485.
the identification of risks and continue on the journey of RM to
Dey, P.K., 2002. Project risk management: a combined analytic hierarchy
identify appropriate risk mitigation strategies. Whilst a process and decision tree approach. Cost Eng. 44, 13–26.
significant number of risks emerged, it is likely that mitigation DiCicco-Bloom, B., Crabtree, B.F., 2006. The qualitative research interview.
strategies may serve to address more than one risk and reinforce Med. Educ. 40, 314–321.
the complex interactions between HRM functions. Dick, R., 1990. Convergent interviewing. Interchange, Chapel Hill, Qld.
In conclusion, it is clear that although the importance of Elahi, E., 2013. Risk management: the next source of competitive advantage.
Foresight J. Futur. Stud. Strateg. Think. Policy 15, 117–131.
HRM and RM in projects has been recognised, we believe that Fabi, B., Pettersen, N., 1992. Human resource management practices in project
these two bodies of literature could well be enhanced by management. Int. J. Proj. Manag. 10, 81–88.
looking for the interplays between them. This research has Floricel, S., Miller, R., 2001. Strategizing for anticipated risks and turbulence in
served to build a level of detail into the identification of large-scale engineering projects. Int. J. Proj. Manag. 19, 445–455.
workforce-related risks in projects that has previously been Hobday, M., 2000. The project-based organisation: an ideal form for managing
complex products and systems? Res. Policy 29, 871–893.
absent. However this is just the first step. Project-based Hopkin, P., 2013. Risk Management. Kogan Page, London.
organisations need to be prepared to not only identify these Huemann, M., Keegan, A., Turner, J.R., 2007. Human resource manage-
internal risks, but to begin to build mitigation strategies into ment in the project-oriented company: a review. Int. J. Proj. Manag. 25,
project planning for the long-term success of projects. 315–323.
Institution of Civil Engineers (ICE), 1998. RAMP: Risk Analysis and
Management for Projects. Thomas Telford, London.
Conflict of inrterest International Energy Agency (IEA), 2013a. Key world energy statistics. http://
www.iea.org/publications/freepublications/publication/KeyWorld2013.pdf.
The authors declare they have no conflicts of interest. International Energy Agency (IEA), 2013b. Medium-term gas market report 2013 —
market trends and projections to 2018. http://www.iea.org/Textbase/npsum/
MTGMR2013SUM.pdf.
Acknowledgements Jaafari, A., 2001. Management of risks, uncertainties and opportunities on
projects: time for a fundamental shift. Int. J. Proj. Manag. 19, 89–101.
This work was supported by the Australian Government's Keegan, A., Huemann, M., Turner, J.R., 2012. Beyond the line: exploring the
Department of Industry's Researchers in Business Program in HRM responsibilities of line managers, project managers and the HRM
conjunction with Air Energi. department in four project-oriented companies in the Netherlands,
Austria, the UK and the USA. Int. J. Hum. Resour. Manag. 23,
3085–3104.
References Lehtiranta, L., 2014. Risk perceptions and approaches in multi-organizations: a
research review 2000–2012. Int. J. Proj. Manag. 32, 640–653.
Barber, R.B., 2005. Understanding internally generated risks in projects. Int. J. Lopes, M.D.S., Flavell, R., 1998. Project appraisal—a framework to assess
Proj. Manag. 23, 584–590. non-financial aspects of projects during the project life cycle. Int. J. Proj.
Baxter, J., Eyles, J., 1997. Evaluating qualitative research in social geography: Manag. 16, 223–233.
establishing ‘rigour’ in interview analysis. Trans. Inst. Br. Geogr. 22, Medina, R., 2014. The project manager and the organisation's long-term
505–525. competence goal. Int. J. Proj. Manag. 32, 1459–1470.
Belout, A., 1998. Effects of human resource management on project effectiveness Nickson, S., 2001. The human resources balancing act. Risk Manag. 48,
and success: toward a new conceptual framework. Int. J. Proj. Manag. 16, 25–29.
21–26. Palinkas, L., Horwitz, S., Green, C., Wisdom, J., Duan, N., Hoagwood, K.,
Belout, A., Gauvreau, C., 2004. Factors influencing project success: the impact 2013. Purposeful sampling for qualitative data collection and analysis in
of human resource management. Int. J. Proj. Manag. 22, 1–11. mixed method implementation Research. Administration and Policy in
Bowers, J.A., 1994. Data for project risk analyses. Int. J. Proj. Manag. 12, 9–16. Mental Health and Mental Health Services Research, pp. 1–12.
Bredin, K., 2008. People capability of project-based organisations: a conceptual Pinto, J.K., Prescott, J.E., 1988. Variations in critical success factors over the
framework. Int. J. Proj. Manag. 26, 566–576. stages in the project life cycle. J. Manag. 14, 5–18.
Bredin, K., Soderlund, J., 2011. The HR quadriad: a framework for the analysis Popaitoon, S., Siengthai, S., 2014. The moderating effect of human resource
of HRM in project-based organizations. Int. J. Hum. Resour. Manag. 22, management practices on the relationship between knowledge absorptive
2202–2221. capacity and project performance in project-oriented companies. Int. J. Proj.
Burgess, J., Connell, J., 2006. Temporary work and human resources Manag. 32, 908–920.
management: issues, challenges and responses. Pers. Rev. 35, 129–140. Project Management Institute, 2013. A Guide to the Project Management Body
Carr, V., Tah, J.H.M., 2001. A fuzzy approach to construction project risk of Knowledge (PMBOK Guide). Project Management Institute, Newtown
assessment and analysis: construction project risk management system. Square, Pa.
Adv. Eng. Softw. 32, 847–857. Raz, T., Michael, E., 2001. Use and benefits of tools for project risk
Chapman, C., 1997. Project risk analysis and management—PRAM the generic management. Int. J. Proj. Manag. 19, 9–17.
process. Int. J. Proj. Manag. 15, 273–281. Redpath, L., Hurst, D., Devine, K., 2009. Knowledge workers, managers, and
Chapman, C., Cooper, D.F., 1983. Risk analysis: testing some prejudices. Eur. contingent employment relationships. Pers. Rev. 38, 74–89.
J. Oper. Res. 14, 238–247. Rynes, S.L., Colbert, A.E., Brown, K.G., 2002. HR professionals' beliefs about
Chapman, C., Ward, S., 2003. Project Risk Management: Processes, effective human resource practices: correspondence between research and
Techniques, and Insights. Wiley, Hoboken, NJ. practice. Hum. Resour. Manag. 41, 149–174.
900 K. Becker, M. Smidt / International Journal of Project Management 33 (2015) 889–900

Saldana, J., 2009. The Coding Manual for Qualitative Researchers. Sage Ward, S., Chapman, C., 2003. Transforming project risk management into
Publications Inc., Thousand Oaks, CA. project uncertainty management. Int. J. Proj. Manag. 21, 97–105.
Saldaña, J., 2013. The Coding Manual for Qualitative Researchers. SAGE, LA, Wideman, R.M., 1992. Project and Program Risk Management: a Guide to
USA. Managing Project Risks and Opportunities. Project Management Institute,
Storey, J., Quintas, P., Taylor, P., Fowle, W., 2002. Flexible employment Drexel Hill, PA.
contracts and their implications for product and process innovation. Int. J. Williams, T., 1995. A classified bibliography of recent research relating to
Hum. Resour. Manag. 13, 1–18. project risk management. Eur. J. Oper. Res. 85, 18–38.
Sydow, J., Lindkvist, L., DeFillippi, R., 2004. Project-based organizations, Wolcott, H.F., 1994. Transforming qualitative data: description, analysis, and
embeddedness and repositories of knowledge: editorial. Organ. Stud. 25, interpretation. Sage Publications, Thousand Oaks, CA.
1475–1489. Zhang, Y., Fan, Z.-P., 2014. An optimization method for selecting project risk
Verburg, R.M., Hartog, D.N.D., Koopman, P.L., 2007. Configurations of response strategies. Int. J. Proj. Manag. 32, 412–422.
human resource management practices: a model and test of internal fit. Int.
J. Hum. Resour. Manag. 18, 184–208.

Você também pode gostar