A. pile foundation
B. sheet piling
C. retaining wall
D. shear wall
Q.3) When the soil beneath the building is not exceptionally well drained and it is
necessary to exclude dampness, the best material to be used which is installed
beneath the concrete slab is
Q.4) The vertical and horizontal surface is reinforced concrete where concreting was
stopped and continued later is called
A. expansion joint
B. control joint
C. cold joint
D. construction joint
Q.1) For very large roof spans (for auditoria, transport buildings, exhibition halls) of
over 150 ft., these structures are suggested economical solutions
A. pre-stressed concrete
B. reinforced concrete
C. space frames, light steel skeleton structures
D. post tensioned concrete
Q.5) What is the height of a curtain wall for a downfeed water tank at the deck roof
with 60,000 gallons capacity and diameter of 3 meters, freeboard of 0.30 meters,
shall be as high as the water tank
A. 3.513 meters
B. 3.550 meters
C. 3.625 meters
D. 3.573 meters
Q.6) Instrument or tool capable of vertical and horizontal line check is called
A. plumb bob
B. spirit level
C. try square
D. caliper
A. tirante
B. tahilan
C. madre
D. soleras
A. an aqueduct
B. a fortification
C. a moat
D. a bridge
A. masonry finish
B. adobe stone work
C. wood siding
D. marble flooring
Q.10) A door lock with a spring bolt controlled by one or both knobs and dead bolt
controlled by a key is a
A. dead lock
B. knob latch
C. knob lock
D. knob bolt
Q.12) A climatic factor that is considered in the structural and architectural design of
tall buildings
A. thunderstorm
B. gusts
C. lightning
D. humidity
A. meter stick
B. try square
C. plumb bob
D. water hose
A. kostilyahe
B. tirante
C. espejo
D. senepa
A. raked
B. struck
C. weathered
D. broom-finish
A. 2 corr.
B. 2 ½ corr.
C. 3 corr.
D. 3 ½ corr.
Q.17) Rafters laid diagonally from corner of a plate or girts to the ridge
A. jack rafter
B. valley plate
C. hip rafter
D. valley rafter
A. lally
B. composite
C. cast-in-place
D. ready-mixed
A. vise
B. wood screw
C. clamp nail
D. miter
Q.20) Select the grouping one subject of which is a general criterion used by architects
in planning and design of buildings
A. suelo
B. guililan
C. soleras
D. sepo
Q.22) Rise is the vertical distance between the upper surface of two consecutive steps.
The horizontal distance between the nosing of two consecutive steps is the
A. “leaving”
B. “string”
C. “newel”
D. “going”
Q.23) A door consisting of two separate leaves, one above the other, this leaves may
operate independently or together is a
A. dwarf door
B. dutch door
C. window door
D. swing door
Q.24) Standard concrete mix for beams, girders, slabs, stairs and columns is
A. “AAA”
B. “AA”
C. “A”
D. "B"
A. torsion
B. shear
C. moment
D. tension
Q.26) A continuous recess built into a wall to receive pipes, ducts, etc. is called
A. alcove
B. chase
C. duct works
D. pipeline
A. shear
B. bending
C. moment
D. torsion
Q.28) The most common materials used for roofing of urban residential houses
A. R.C. slabs
B. wood shingles
C. G.I. sheets
D. asphalt shingles
Q.29) This is a ground condition that determines the size, type and shape of the
building footing/foundation
A. rodapis
B. perdano
C. batidora
D. guililan
A. guililan
B. sepo
C. rodapis
D. kilo
Q.32) A joint formed by overlapping the edges of metal sheet or plated and joining
them by riveting, soldering or brazing is a
A. lap joint
B. lap seam
C. lap splice
D. lap edge
Noise inside the building is o two kinds, namely, airborne noise and impact noise
Q.33) . Insulation must be provided against both of these by internal walls and floors.
Examples of better sound insulation are
Q.34) The horizontal boards nailed to corner post to assist in the accurate layout of
foundation and excavation lines are called
A. form boards
B. box boards
C. batter boards
D. nail boards
Q.35) A clay roofing tile approximately semi cylindrical in shape laid in courses with
units having their convex side alternately up and down is a
A. pantile
B. mission tile
C. roman tile
D. japanese tile
Q.36) A continuous recess built into a wall to receive pipes, ducts, etc. is called
A. alcove
B. ductwork
C. chase
D. sleeve
A. fish block
B. wood block
C. fish plate
D. split-ring
Q.38) This material holds less moisture, is very light with less absorptive capacity and
is very good in exterior sidings of residential houses in tropical regions
Q.39) The part of a foundation system which supports the exterior wall of the super
structure and bears directly on the column footing is a
A. grade course
B. foundation wall
C. foundation course
D. grade beam
A. channel strip
B. reinforced wood
C. kalamein
D. dry stud