PROJECT SCHEDULE MONITORING - SHOP DRAWINGS

PROJECT: ONE VERTIS PLAZA

PERIOD OF:
Year: 2019
Month:
Dates: As of 18 May 2019

SHOP DRAWINGS
1ST SUBMISSION
DURATION REMARKS
ITEM PERCENT
SHEET NO. DESCRIPTION RESPONSIBLE  (i.e. Ref. Docs., CB, SI, 
NO. NO. OF  AGE
PERSON START END Design Changes from 
DAYS (%)
Workshop, Reasons for 
PLANNED SCHEDULE
SHOP DRAWING 100.0%

1 CP 1 Cover Page JSB 0.5 20‐May‐19 20‐May‐19 100.0%


2 DL 1 Drawing List JSB 1 24‐Jun‐19 24‐Jun‐19
3 DL 2 Drawing List JSB 1 24‐Jun‐19 24‐Jun‐19

4 MS 1 Material Specifications (Aluminum Extrusion) JSB 24‐Jun‐19 24‐Jun‐19


0.5
5 MS 2 Material Specifications (Aluminum Extrusion) JSB 24‐Jun‐19 24‐Jun‐19
0.5
6 MS 3 Material Specifications (Aluminum Extrusion) JSB 24‐Jun‐19 24‐Jun‐19
0.5
7 MS 4 Material Specifications (Steel) JSB 0.5 24‐Jun‐19 24‐Jun‐19
8 MS 5 Material Specifications (Accessories) JSB 0.5 24‐Jun‐19 24‐Jun‐19
ZONE ELEVATION RAM
9 ZE 1 North Elevation RAM 2 21‐May‐19 21‐May‐19 100.0%
10 ZE 2 East Elevation RAM 2 21‐May‐19 21‐May‐19 100.0%
11 ZE 3 West Elevation RAM 2 21‐May‐19 21‐May‐19 100.0%
12 ZE 4 South Elevation RAM 2 21‐May‐19 21‐May‐19 100.0%
GENERAL ELEVATION RAM

13 GE 1 FRONT ELEVATION (LOW ZONE, LEVEL 4‐14) RAM 22‐May‐19 22‐May‐19 100.0%


2
14 GE 2 FRONT ELEVATION (MID ZONE, LEVEL 15‐24) RAM 22‐May‐19 22‐May‐19 100.0%
2
15 GE 3 FRONT ELEVATION (HIGH ZONE, LEVEL 25‐36) RAM 22‐May‐19 22‐May‐19 100.0%
2
16 GE 4 RIGHT ELEVATION (LOW ZONE, LEVEL 4‐14) RAM 22‐May‐19 22‐May‐19 100.0%
2
17 GE 5 RIGHT ELEVATION (MID ZONE, LEVEL 15‐24) RAM 23‐May‐19 23‐May‐19 100.0%
2
18 GE 6 RIGHT ELEVATION (HIGH ZONE, LEVEL 25‐36) RAM 23‐May‐19 23‐May‐19 100.0%
2
19 GE 7 REAR ELEVATION (LOW ZONE, LEVEL 4‐14) RAM 23‐May‐19 23‐May‐19 100.0%
2
20 GE 8 REAR ELEVATION (MID ZONE, LEVEL 15‐24) RAM 23‐May‐19 23‐May‐19 100.0%
2
21 GE 9 REAR ELEVATION (HIGH ZONE, LEVEL 25‐36) RAM 24‐May‐19 24‐May‐19 100.0%
2
22 GE 10 LEFT ELEVATION (LOW ZONE, LEVEL 4‐14) RAM 2 24‐May‐19 24‐May‐19 100.0%

23 GE 11 LEFT ELEVATION (MID ZONE, LEVEL 15‐24) RAM 24‐May‐19 24‐May‐19 100.0%


2
24 GE 12 LEFT ELEVATION (HIGH ZONE, LEVEL 25‐36) RAM 24‐May‐19 24‐May‐19 100.0%
2
KEYPLAN
25 KP 2 Keyplan (4th Floor)  MML 1 25‐May‐19 25‐May‐19 100.0%
26 KP 3 Keyplan (5th to 16th Floor)  MML 1 25‐May‐19 25‐May‐19 100.0%
27 KP 4 Keyplan (17th to 23rd Floor)  MML 1 25‐May‐19 25‐May‐19 100.0%
28 KP 5 Keyplan (24th Floor)  MML 1 27‐May‐19 27‐May‐19 100.0%
29 KP 6 Keyplan (25th Floor)  MML 1 27‐May‐19 27‐May‐19 100.0%
30 KP 7 Keyplan (26th ‐ 31st Floor)  MML 1 27‐May‐19 27‐May‐19 100.0%
31 KP 8 Keyplan (32nd to 36th Floor)  MML 1 27‐May‐19 27‐May‐19 100.0%
PARTIAL ELEVATION RAM
32 PE 1 Partial Elevation, Plan and Section 4th to 5th Floor (North Elevation) RAM 2 18‐Jun‐19 18‐Jun‐19 75.0%
33 PE 2 Partial Elevation, Plan and Section 4th to 5th Floor (North Elevation) RAM 2 18‐Jun‐19 18‐Jun‐19 75.0%
34 PE 3 Partial Elevation, Plan and Section 4th to 5th Floor (East Elevation) RAM 2 18‐Jun‐19 18‐Jun‐19 75.0%
35 PE 4 Partial Elevation, Plan and Section 4th to 5th Floor (East Elevation) RAM 2 18‐Jun‐19 18‐Jun‐19 75.0%
36 PE 5 Partial Elevation, Plan and Section 4th to 5th Floor (East Elevation) RAM 2 18‐Jun‐19 18‐Jun‐19 75.0%
37 PE 6 Partial Elevation, Plan and Section 4th to 5th Floor (South Elevation) RAM 2 18‐Jun‐19 18‐Jun‐19 75.0%
38 PE 7 Partial Elevation, Plan and Section 4th to 5th Floor (South Elevation) RAM 2 18‐Jun‐19 18‐Jun‐19 75.0%
39 PE 8 Partial Elevation, Plan and Section 4th to 5th Floor (West Elevation) RAM 2 18‐Jun‐19 18‐Jun‐19 75.0%
40 PE 9 Partial Elevation, Plan and Section 4th to 5th Floor (West Elevation) RAM 2 18‐Jun‐19 18‐Jun‐19 75.0%
41 PE 10 Partial Elevation, Plan and Section 4th to 5th Floor (West Elevation) RAM 2 18‐Jun‐19 18‐Jun‐19 75.0%
42 PE 11 Partial Elevation, Plan and Section 6th to 23rd Floor (North Elevation) RAM 2 19‐Jun‐19 19‐Jun‐19 75.0%
43 PE 12 Partial Elevation, Plan and Section 6th to 23rd Floor (North Elevation) RAM 2 19‐Jun‐19 19‐Jun‐19 75.0%
44 PE 13 Partial Elevation, Plan and Section 6th to 23rd Floor (East Elevation) RAM 2 19‐Jun‐19 19‐Jun‐19 75.0%
45 PE 14 Partial Elevation, Plan and Section 6th to 23rd Floor (East Elevation) RAM 2 19‐Jun‐19 19‐Jun‐19 75.0%
46 PE 15 Partial Elevation, Plan and Section 6th to 23rd Floor (East Elevation) RAM 2 19‐Jun‐19 19‐Jun‐19 75.0%

1 of 4
1ST SUBMISSION
DURATION REMARKS
ITEM PERCENT
SHEET NO. DESCRIPTION RESPONSIBLE  (i.e. Ref. Docs., CB, SI, 
NO. NO. OF  AGE
PERSON START END Design Changes from 
DAYS (%)
Workshop, Reasons for 
PLANNED SCHEDULE
SHOP DRAWING 100.0%

47 PE 16 Partial Elevation, Plan and Section 6th to 23rd Floor (South Elevation) RAM 2 19‐Jun‐19 19‐Jun‐19 75.0%


48 PE 17 Partial Elevation, Plan and Section 6th to 23rd Floor (South Elevation) RAM 2 19‐Jun‐19 19‐Jun‐19 75.0%
49 PE 18 Partial Elevation, Plan and Section 6th to 23rd Floor (West Elevation) RAM 2 19‐Jun‐19 19‐Jun‐19 75.0%
50 PE 19 Partial Elevation, Plan and Section 6th to 23rd Floor (West Elevation) RAM 2 19‐Jun‐19 19‐Jun‐19 75.0%
51 PE 20 Partial Elevation, Plan and Section 6th to 23rd Floor (West Elevation) RAM 2 19‐Jun‐19 19‐Jun‐19 75.0%

52 PE 21 Partial Elevation, Plan and Section 24th to 25th Floor (North Elevation) RAM 19‐Jun‐19 18‐Jun‐19 75.0%


2
53 PE 22 Partial Elevation, Plan and Section 24th to 25th Floor (North Elevation) RAM 20‐Jun‐19 19‐Jun‐19 75.0%
2
54 PE 23 Partial Elevation, Plan and Section 24th to 25th Floor (East Elevation) RAM 2 20‐Jun‐19 19‐Jun‐19 75.0%
55 PE 24 Partial Elevation, Plan and Section 24th to 25th Floor (East Elevation) RAM 2 20‐Jun‐19 19‐Jun‐19 75.0%
56 PE 25 Partial Elevation, Plan and Section 24th to 25th Floor (East Elevation) RAM 2 20‐Jun‐19 19‐Jun‐19 75.0%

57 PE 26 Partial Elevation, Plan and Section 24th to 25th Floor (South Elevation) RAM 20‐Jun‐19 19‐Jun‐19 75.0%


2
58 PE 27 Partial Elevation, Plan and Section 24th to 25th Floor (South Elevation) RAM 20‐Jun‐19 19‐Jun‐19 75.0%
2
59 PE 28 Partial Elevation, Plan and Section 24th to 25th Floor (West Elevation) RAM 2 20‐Jun‐19 19‐Jun‐19 75.0%
60 PE 29 Partial Elevation, Plan and Section 24th to 25th Floor (West Elevation) RAM 2 21‐Jun‐19 20‐Jun‐19 75.0%
61 PE 30 Partial Elevation, Plan and Section 24th to 25th Floor (West Elevation) RAM 2 21‐Jun‐19 20‐Jun‐19 75.0%

62 PE 31 Partial Elevation, Plan and Section 26th to 35th Floor (North Elevation) RAM 21‐Jun‐19 20‐Jun‐19 75.0%


2
63 PE 32 Partial Elevation, Plan and Section 26th to 35th Floor (North Elevation) RAM 21‐Jun‐19 20‐Jun‐19 75.0%
2
64 PE 33 Partial Elevation, Plan and Section 26th to 35th Floor (East Elevation) RAM 2 21‐Jun‐19 20‐Jun‐19 75.0%
65 PE 34 Partial Elevation, Plan and Section 26th to 35th Floor (East Elevation) RAM 2 21‐Jun‐19 21‐Jun‐19 75.0%
66 PE 35 Partial Elevation, Plan and Section 26th to 35th Floor (East Elevation) RAM 2 21‐Jun‐19 21‐Jun‐19 75.0%

67 PE 36 Partial Elevation, Plan and Section 26th to 35th Floor (South Elevation) RAM 21‐Jun‐19 21‐Jun‐19 75.0%


2
68 PE 37 Partial Elevation, Plan and Section 26th to 35th Floor (South Elevation) RAM 21‐Jun‐19 21‐Jun‐19 75.0%
2
69 PE 38 Partial Elevation, Plan and Section 26th to 35th Floor (West Elevation) RAM 2 21‐Jun‐19 21‐Jun‐19 75.0%
70 PE 39 Partial Elevation, Plan and Section 26th to 35th Floor (West Elevation) RAM 2 21‐Jun‐19 21‐Jun‐19 75.0%
71 PE 40 Partial Elevation, Plan and Section 26th to 35th Floor (West Elevation) RAM 2 21‐Jun‐19 21‐Jun‐19 75.0%
PLAN DETAIL
72 DT 101 Plan Detail of Intermediate Mullion (Vision ‐ Vision) JSB 1.5 20‐May‐19 20‐May‐19 100.0%
73 DT 102 Plan Detail of Intermediate Mullion (Vision ‐ Vision) at Stackjoint Level JSB 1.5 20‐May‐19 20‐May‐19 100.0%
74 DT 103 Plan Detail of Intermediate Mullion (Vision ‐ Operable) JSB 1.5 20‐May‐19 20‐May‐19 100.0%
75 DT 104 Plan Detail of Intermediate Mullion (Operable ‐ Vision) JSB 1.5 20‐May‐19 20‐May‐19 100.0%
76 DT 105 Plan Detail of Intermediate Mullion (Operable ‐Operable) JSB 1.5 20‐May‐19 20‐May‐19 100.0%
Plan Detail of Intermediate Mullion (Spandrel‐Spandrel) at BMU Socket 
77 DT 106 JSB 20‐May‐19 20‐May‐19 0.0%
Location 1.5
78 DT 107 Plan Detail of Intermediate Mullion with Bullnose (Vision‐Vision) JSB 1.5 21‐May‐19 21‐May‐19 100.0%
79 DT 108 Plan Detail of Intermediate Mullion with Bullnose (Vision‐Operable) JSB 1.5 21‐May‐19 21‐May‐19 100.0%
80 DT 109 Plan Detail of Intermediate Mullion with Bullnose (Operable‐Vision) JSB 1.5 21‐May‐19 21‐May‐19 100.0%
81 DT 110 Plan Detail of Intermediate Mullion with Bullnose (Operable‐Operable) JSB 1.5 21‐May‐19 21‐May‐19 100.0%
Plan Detail of Intermediate Mullion with Bullnose (Spandrel‐spandrel) at 
82 DT 111 JSB 21‐May‐19 21‐May‐19 0.0%
BMU Socket Location 1.5
Plan Detail of Intermediate Mullion with Bullnose (Vision‐Vision) at 
83 DT 112 JSB 22‐May‐19 22‐May‐19 100.0%
Stackjoint Level 1.5
84 DT 113 Plan Detail of 90˚ Inside Corner Mullion (Vision ‐ Vision) JSB 1.5 22‐May‐19 22‐May‐19 100.0%

85 DT 114 Plan Detail of 90˚ Inside Corner Mullion (Vision ‐ Vision)  at Stackjoint Level JSB 22‐May‐19 22‐May‐19 100.0%


1.5
86 DT 115 Plan Detail of 90˚ Outside Corner Mullion (Vision ‐ Vision) JSB 1.5 22‐May‐19 22‐May‐19 100.0%

87 DT 116 Plan Detail of 90˚ Outside Corner Mullion (Vision ‐ Vision)   at Stackjoint Level JSB 22‐May‐19 22‐May‐19 100.0%


1.5
88 DT 117 Plan Detail of 90˚ Outside Corner Mullion (Vision ‐ Vision) JSB 1.5 23‐May‐19 23‐May‐19 100.0%

89 DT 118 Plan Detail of 90˚ Outside Corner Mullion (Vision ‐ Vision)   at Stackjoint Level JSB 23‐May‐19 23‐May‐19 100.0%


1.5
90 DT 119 Plan Detail of Intermediate Mullion Box Type (Vision‐Vision) JSB 1.5 23‐May‐19 23‐May‐19 100.0%
Plan Detail of Intermediate Mullion Box Type (Vision‐Vision)  at Stackjoint 
91 DT 120 JSB 23‐May‐19 23‐May‐19 100.0%
Level 1.5
Plan Detail of 90˚ Inside Corner Box Type Mullion (Spandrel‐spandrel) at 
92 DT 121 JSB 23‐May‐19 23‐May‐19 100.0%
Bracket Area @ 4th Flr. 1.5
Plan Detail of Intermediate Mullion (Spandrel‐Spandrel) at Bracket Area 
93 DT 122 JSB 24‐May‐19 24‐May‐19 100.0%
(Level 4&5 Lower Support) 1.5
Plan Detail of Intermediate Mullion (Spandrel‐Spandrel) at Bracket Area 
94 DT 123 JSB 24‐May‐19 24‐May‐19 100.0%
(Level 4&5 Upper Support) 1.5
Plan Detail of Intermediate Mullion (Spandrel‐Spandrel) at Bracket Area 
95 DT 124 JSB 24‐May‐19 24‐May‐19 100.0%
(Level 6‐23 & Level 26‐29) 1.5
Plan Detail of Intermediate Mullion (Spandrel‐Spandrel) at Bracket Area 
96 125 JSB 00‐Jan‐00 100.0%
(Level 24 & 25)
Plan Detail of Intermediate Mullion (Spandrel‐Spandrel) at Bracket Area 
97 DT 126 JSB 24‐May‐19 24‐May‐19 100.0%
(Level 30‐36) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
98 DT 127 JSB 24‐May‐19 24‐May‐19 100.0%
Bracket Area (Level 4 Lower Support) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
99 DT 128 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 4 Lower Support & Level 5) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
100 DT 128.1 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 4 Lower Support & Level 5) 1.5

2 of 4
1ST SUBMISSION
DURATION REMARKS
ITEM PERCENT
SHEET NO. DESCRIPTION RESPONSIBLE  (i.e. Ref. Docs., CB, SI, 
NO. NO. OF  AGE
PERSON START END Design Changes from 
DAYS (%)
Workshop, Reasons for 
PLANNED SCHEDULE
SHOP DRAWING 100.0%

Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
101 DT 129 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 6‐36) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
102 DT 129.1 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 6‐36) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
103 DT 130 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 5‐29) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
104 DT 130.1 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 5‐29) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
105 DT 130.2 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 5‐29) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
106 DT 131 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 30‐36) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
107 DT 131.1 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 30‐36) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
108 DT 131.2 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 30‐36) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
109 DT 132 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 4 @ Slab Connection) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
110 DT 132.1 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 4 @ Slab Connection) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
111 DT 132.2 JSB 25‐May‐19 25‐May‐19 100.0%
Bracket Area (Level 4 @ Slab Connection) 1.5
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
112 DT 133 JSB 27‐May‐19 27‐May‐19 100.0%
Bracket Area (Level 4 Lower Support) 2
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
113 DT 133.1 JSB 27‐May‐19 27‐May‐19 100.0%
Bracket Area (Level 4 Lower Support) 2
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
114 DT 134 JSB 27‐May‐19 27‐May‐19 100.0%
Bracket Area (Level 4 Slab Connection) 2
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
115 DT 134.1 JSB 27‐May‐19 27‐May‐19 100.0%
Bracket Area (Level 4 Slab Connection) 2
Plan Detail of Intermediate Mullion w/ Bullnose (Spandrel‐Spandrel) at 
116 DT 134.2 JSB 27‐May‐19 27‐May‐19 100.0%
Bracket Area (Level 4 Slab Connection) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
117 DT 135 JSB 28‐May‐19 28‐May‐19 100.0%
Area (Level 5 to 36) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
118 DT 135.1 JSB 28‐May‐19 28‐May‐19 100.0%
Area (Level 5 to 36) 2
Plan Detail of 90˚ Inside Corner Mullion @ Slab (Spandrel‐SPandrel) at 
119 DT 136 JSB 28‐May‐19 28‐May‐19 100.0%
Bracket Area (Level 5 to 36) 2
Plan Detail of 90˚ Inside Corner Mullion @ Slab (Spandrel‐SPandrel) at 
120 DT 136.1 JSB 28‐May‐19 28‐May‐19 100.0%
Bracket Area (Level 5 to 36) 2
Plan Detail of 90˚ Inside Corner Mullion @ Beam (Spandrel‐SPandrel) at 
121 DT 137 JSB 29‐May‐19 29‐May‐19 100.0%
Bracket Area (Level 5 to 36) 2
Plan Detail of 90˚ Inside Corner Mullion @ Beam (Spandrel‐SPandrel) at 
122 DT 137.1 JSB 29‐May‐19 29‐May‐19 100.0%
Bracket Area (Level 5 to 36) 2
Plan Detail of 90˚ Outside Corner Mullion @ Slab (Spandrel‐SPandrel) at 
123 DT 138 JSB 29‐May‐19 29‐May‐19 100.0%
Bracket Area (Level 5 to 23 & Level 26 to 36) 2
Plan Detail of 90˚ Outside Corner Mullion @ Slab (Spandrel‐SPandrel) at 
124 DT 138.1 JSB 29‐May‐19 29‐May‐19 100.0%
Bracket Area (Level 5 to 23 & Level 26 to 36) 2
Plan Detail of 90˚ Outside Corner Mullion @ Slab (Spandrel‐SPandrel) at 
125 DT 139 JSB 30‐May‐19 30‐May‐19 100.0%
Bracket Area (Level 24 & 25) 2
Plan Detail of 90˚ Outside Corner Mullion @ Slab (Spandrel‐SPandrel) at 
126 DT 139.1 JSB 30‐May‐19 30‐May‐19 100.0%
Bracket Area (Level 24 & 25) 2
Plan Detail of 90˚ Outside Corner Mullion @ Slab (Spandrel‐SPandrel) at 
127 DT 139.2 JSB 30‐May‐19 30‐May‐19 100.0%
Bracket Area (Level 24 & 25) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
128 DT 140 JSB 30‐May‐19 30‐May‐19 100.0%
Area (Level 4&5 Upper Support) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
129 DT 140.1 JSB 30‐May‐19 30‐May‐19 100.0%
Area (Level 4&5 Upper Support) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
130 DT 141 JSB 30‐May‐19 30‐May‐19 100.0%
Area (Level 4 Lower Support) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
131 DT 141.1 JSB 30‐May‐19 30‐May‐19 100.0%
Area (Level 4 Lower Support) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
132 DT 142 JSB 30‐May‐19 30‐May‐19 100.0%
Area (Level 4 Upper Support) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
133 DT 142.1 JSB 30‐May‐19 30‐May‐19 100.0%
Area (Level 4 Upper Support) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
134 142.1 JSB 30‐May‐19 30‐May‐19 100.0%
Area (Level 4 Upper Support) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
135 DT 143 JSB 31‐May‐19 31‐May‐19 100.0%
Area (Level 4 Lower Support) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
136 DT 143.1 JSB 31‐May‐19 31‐May‐19 100.0%
Area (Level 4 Lower Support) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
137 DT 143.2 JSB 31‐May‐19 31‐May‐19 100.0%
Area (Level 4 Lower Support) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
138 DT 144 JSB 31‐May‐19 31‐May‐19 100.0%
Area (Level 4 ) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
139 DT 144.1 JSB 01‐Jun‐19 01‐Jun‐19 100.0%
Area (Level 4 ) 2
Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
140 DT 144.2 JSB 01‐Jun‐19 01‐Jun‐19 100.0%
Area (Level 4 ) 2

3 of 4
1ST SUBMISSION
DURATION REMARKS
ITEM PERCENT
SHEET NO. DESCRIPTION RESPONSIBLE  (i.e. Ref. Docs., CB, SI, 
NO. NO. OF  AGE
PERSON START END Design Changes from 
DAYS (%)
Workshop, Reasons for 
PLANNED SCHEDULE
SHOP DRAWING 100.0%

Plan Detail of 90˚ Outside Corner Mullion (Spandrel‐SPandrel) at Bracket 
141 DT 144.3 JSB 03‐Jun‐19 03‐Jun‐19 100.0%
Area (Level 4 ) 2
SECTION DETAIL
142 DT 201 Section Detail of Intermediate Transom (Vision‐Vision) ANTHONY 2 18‐Jun‐19 18‐Jun‐19
143 DT 202 Section Detail of Intermediate Transom (Spandrel‐Vision) ANTHONY 2 18‐Jun‐19 18‐Jun‐19
144 DT 203 Section Detail of Intermediate Transom (Operable‐Vision) ANTHONY 2 18‐Jun‐19 18‐Jun‐19
145 DT 204 Section Detail of Intermediate Transom (Spandrel ‐ Operable) ANTHONY 2 18‐Jun‐19 18‐Jun‐19
146 DT 205 Section Detail of Starter Sill Transom (Vision) at Bracket Area ANTHONY 2 19‐Jun‐19 19‐Jun‐19

147 DT 206 Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ANTHONY 19‐Jun‐19 19‐Jun‐19


2
148 DT 207 Section Detail of Head Stack Joint Transom (Spandrel) at Bracket Area ANTHONY 2 19‐Jun‐19 19‐Jun‐19
149 DT 208 Section Detail of Intermediate Transom (Vision‐Vision) w/ BMU Socket ANTHONY 2 19‐Jun‐19 19‐Jun‐19
Section Detail of Intermediate Transom (Vision‐Vision) at Box Type Mullion 
150 DT 209 ANTHONY 20‐Jun‐19 20‐Jun‐19
4th Floor 2
Section Detail of Intermediate Transom (Spandrel‐Vision) at Box Type 
151 DT 210 ANTHONY 20‐Jun‐19 20‐Jun‐19
Mullion 4th Floor 2
Section Detail of Intermediate Transom (Vision‐Vision) at Box Type Mullion 
152 DT 211 ANTHONY 20‐Jun‐19 20‐Jun‐19
38th Floor 2
Section Detail of Intermediate Transom (Spandrel‐Vision) at Box Type 
153 DT 212 ANTHONY 20‐Jun‐19 20‐Jun‐19
Mullion 38th Floor 2
Anchor at Beam ANTHONY 15‐Jan‐00 15‐Jan‐00
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
154 DT 213 ANTHONY 21‐Jun‐19 21‐Jun‐19
Hotspot (1/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
155 DT 213.1 ANTHONY 21‐Jun‐19 21‐Jun‐19
Hotspot (2/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
156 DT 214 ANTHONY 21‐Jun‐19 21‐Jun‐19
Typical (1/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
157 DT 214.1 ANTHONY 21‐Jun‐19 21‐Jun‐19
Typical (2/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
158 DT 215 ANTHONY 22‐Jun‐19 22‐Jun‐19
Hotspot High Floors (1/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
159 DT 215.1 ANTHONY 22‐Jun‐19 22‐Jun‐19
Hotspot High Floors (2/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
160 DT 216 ANTHONY 22‐Jun‐19 22‐Jun‐19
Typical High Floors (1/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
161 DT 216.1 ANTHONY 22‐Jun‐19 22‐Jun‐19
Typical High Floors (2/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
162 DT 217 ANTHONY 23‐Jun‐19 23‐Jun‐19
Typical Overhang Panels (1/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
163 DT 217.1 ANTHONY 23‐Jun‐19 23‐Jun‐19
Typical Overhang Panels (2/2) 2
Anchor at Slab ANTHONY 15‐Jan‐00 15‐Jan‐00
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
164 DT 218 ANTHONY 25‐Jun‐19 25‐Jun‐19
Hotspot (1/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
165 DT 218.1 ANTHONY 25‐Jun‐19 25‐Jun‐19
Hotspot (2/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
166 DT 219 ANTHONY 25‐Jun‐19 25‐Jun‐19
Typical (1/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
167 DT 219.1 ANTHONY 25‐Jun‐19 25‐Jun‐19
Typical (2/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
168 DT 220 ANTHONY 25‐Jun‐19 25‐Jun‐19
Hotspot High Floors (1/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
169 DT 220.1 ANTHONY 26‐Jun‐19 26‐Jun‐19
Hotspot High Floors (2/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
170 DT 221 ANTHONY 26‐Jun‐19 26‐Jun‐19
Typical High Floors (1/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
171 DT 221.1 ANTHONY 26‐Jun‐19 26‐Jun‐19
Typical High Floors (2/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
172 DT 222 ANTHONY 26‐Jun‐19 26‐Jun‐19
Typical Overhang Panels (1/2) 2
Section Detail of Stack Joint Transom (Vision ‐ Spandrel) at Bracket Area ‐ 
173 DT 222.1 ANTHONY 26‐Jun‐19 26‐Jun‐19
Typical Overhang Panels (2/2) 2
TOTAL 76.7%

306.5 HOURS

4 of 4