Você está na página 1de 42

ID No Name Duration

1 2 x 800 MW SDS TPS, Krishnapatnam, a/c TPL 1202 d


2 Major Milestones 1202 d
3 Date of LOI 0d
4 Date of PO 0d
5 Kick off meeting 0d
6 Switch Yard Charging 0d

7 Boiler Light up Unit 1 0d

8 Rolling & Synchronization Unit 1 0d


9 Rolling & Synchonization Unit 2 0d
10 Inputs from customer 250 d
11 Receipt of HT load 0d
12 Receipt of LT load list 0d
13 Receipt of Unit Loads ( Motors and panels) 0d
14 Receipt of station loads 0d
15 Receipt of DC loads 50 d
16 Receipt of soil resistivity report 0d
17 Receipt of Plot plan 0d
18 Receipt of layout of TG building 200 d
19 Receipt of emergency loads 90 d
20 Receipt 0f Plant SLD 25 d
21 Receipt of Layout of packages/Motors 100 d
22 Receipt of UPS loads 30 d
23 eBoP Engineering Activities(Submission & Approval) 613 d
24 Submission of DBR 26 d
25 Earthing conductor sizing 17 d
26 Earthing notes and details 13 d
27 Key SLD Preparation 100 d
28 Aux Power Transformer sizing 30 d
29 Service Transformer sizing 75 d
30 UT Sizing 20 d
31 ST Sizing 27 d
32 Emergency DG set sizing 79 d
33 SPBD sizing 25 d
34 NSPBD sizing 53 d
35 HT switchgear 25 d
36 415 V LT switchear 90 d
37 220 V DC Battery & battery charger sizing calculation 63 d
38 HT Cable Sizing 25 d
39 LT cable sizing calculation 130 d
40 Cable notes & Details 69 d
41 HT cable schedule 130 d
42 LT cable schedule 160 d
43 Control cable schedule 175 d
44 UPS system sizing 30 d
45 Illumination 205 d
46 Communication system philosophy 180 d
47 Electrical layout for TG building 154 d
48 Electrical Balance of Plant -Procurement & supply 823 d
49 Transformers 717 d
50 Generator Transformer 674 d
51 Generator Transformer -1 519 d
52 Order Placement of GT 10 d
53 Technical specification preparation and issue 30 d
54 Drawings submission & approval of GT 45 d
55 Manufacturing 300 d
56 Material Inspection 15 d
57 Material despatch & recipt at site of GT -1 60 d
58 Generator Transformer -2 380 d
59 Manufacturing 300 d
60 Material Inspection 15 d
61 Material despatch & recipt at site of GT-2 60 d
62 Generator Transformer -3 380 d
63 Manufacturing 300 d
64 Material Inspection 15 d
65 Material despatch & recipt at site of GT-3 60 d
66 Generator Transformer -4 375 d
67 Manufacturing 300 d
68 Material Inspection 15 d
69 Material despatch & recipt at site of GT-4 60 d
70 Generator Transformer -5 375 d
71 Manufacturing 300 d
72 Material Inspection 15 d
73 Material despatch & recipt at site of GT-5 60 d
74 Generator Transformer -6 375 d
75 Manufacturing 300 d
76 Material Inspection 15 d
77 Material despatch & recipt at site of GT-6 60 d
78 Generator Transformer -7 375 d
79 Manufacturing 300 d
80 Material Inspection 15 d
81 Material despatch & recipt at site of GT-7 60 d
82 Station Transformer 495 d
83 Station Transformer - 1 410 d
84 Order Placement 10 d
85 Technical specification preparation and issue 30 d
86 Drawings submission & approval of ST 50 d
87 Manufacturing 255 d
88 Material Inspection 15 d
89 Material despatch & recipt at site of ST -1 30 d
90 Station Transformer - 2 300 d
91 Manufacturing 255 d
92 Material Inspection 15 d
93 Material despatch & recipt at site of ST-2 30 d
94 Unit Transfomer 585 d
95 Unit Transformer - 1 425 d
96 Order Placement 10 d
97 Technical specification preparation and issue 30 d
98 Drawings submission & approval 70 d
99 Manufacturing 220 d
100 Material Inspection 15 d
101 Material despatch & recipt at site of UT -1 30 d
102 Unit Transformer - 2 265 d
103 Manufacturing 220 d
104 Material Inspection 15 d
105 Material despatch & recipt at site 30 d
106 Unit Transformer - 3 265 d
107 Manufacturing 220 d
108 Material Inspection 15 d
109 Material despatch & recipt at site 30 d
110 Unit Transformer - 4 265 d
111 Manufacturing 220 d
112 Material Inspection 15 d
113 Material despatch & recipt at site 30 d
114 Auxiliary Power Transformers 298 d
115 Unit Auxiliary Transformer - 2 Nos 233 d
116 Technical specification preparation and issue 2d
117 Vendor offer Finalisation 40 d
118 Order Placement 3d
119 Drawings submission & approval 30 d
120 Manufacturing 120 d
121 Material Inspection 6d
122 Material despatch & recipt at site 12 d
123 Unit Auxiliary Transformer - 2 Nos 138 d
124 Manufacturing 120 d
125 Material Inspection 6d
126 Material despatch & recipt at site 12 d
127 Station Auxiliary Transformer-1 & 2 228 d
128 Technical specification preparation and issue 2d
129 Vendor offer Finalisation 40 d
130 Order Placement 3d
131 Drawings submission & approval 30 d
132 Manufacturing 110 d
133 Material Inspection 6d
134 Material despatch & recipt at site 12 d
135 CHP Auxiliary Power Transformer-1 & 2 118 d
136 Manufacturing 100 d
137 Material Inspection 6d
138 Material despatch & recipt at site 12 d
139 Service Transformers 417 d
Dry Type Service Transformers 2.5 MVA- 1st Lot ( UST- 4 Nos. & SST 2
140 Nos. ) 232 d
141 Technical specification preparation and issue 2d
142 Vendor offer Finalisation 45 d
143 Order Placement 5d
144 Drawings submission & approval 20 d
145 Manufacturing 120 d
146 Material Inspection 10 d
147 Material despatch & recipt at site 10 d
Dry Type Service Transformers 2.5 MVA- 2nd Lot ( UST- 4 Nos. & SST 2
148 Nos. ) 140 d
149 Manufacturing 120 d
150 Material Inspection 10 d
151 Material despatch & recipt at site 10 d
Oil Type Service Transformers - 1st Lot (WTP 2.5MVA-2 Nos, ECP/CW
152 1MVA-2 Nos, AWPH 1.25MA, 2Nos, CHP1 1.25MVA-2 Nos.) 222 d
153 Technical specification preparation and issue 2d
154 Vendor offer Finalisation 45 d
155 Order Placement 5d
156 Drawings submission & approval 30 d
157 Manufacturing 120 d
158 Material Inspection 10 d
159 Material despatch & recipt at site 10 d
Oil Type Service Transformers - 2nd Lot ( FW 1.6MVA- 2Nos., AWR & ADM
160 630KVA- 4Nos, AE 2.5MVA, 2Nos, CHP3 1MVA, 2Nos) 150 d
161 Manufacturing 120 d
162 Material Inspection 10 d
163 Material despatch & recipt at site 20 d
Oil Type Service Transformers - 3rd LOT ( CHP5 1MVA, 2Nos, AS 1.25MVA-
164 2NOS, ESP 1.6MVA- 4Nos.) 247 d
165 Technical specification preparation and issue 2d
166 Vendor offer Finalisation 40 d
167 Order Placement 15 d
168 Drawings submission & approval 30 d
169 Manufacturing 120 d
170 Material Inspection 10 d
171 Material despatch & recipt at site 10 d
172 Oil Type Service Transformers - 4th LOT ( ESP 1.6 MVA -12 NOS) 140 d
173 Manufacturing 120 d
174 Material Inspection 10 d
175 Material despatch & recipt at site 10 d
176 Neutral Grounding Equipments (11.5KV - 8 NOS & 3.3KV - 8 NOS ) 282 d
177 Technical specification preparation and issue 5d
178 Vendor offer Finalisation 45 d
179 Order Placement 2d
180 Drawings submission & approval 30 d
181 Manufacturing 150 d
182 Material Inspection 10 d
183 Material despatch & recipt at site 20 d
184 HT Switchgear 263 d
185 HT Switchgear 1st LOT ( 11KV Station and Unit Switchboard Unit 1 ) 203 d
186 Technical specification preparation and issue 5d
187 Vendor offer Finalisation 45 d
188 Order Placement 3d
189 Drawings submission & approval 30 d
190 Manufacturing 100 d
191 Material Inspection 10 d
192 Material despatch & recipt at site 10 d
HT Switchgear 2nd LOT ( 3.3KV Unit and Station,11KV Station and Unit
193 Switchboard Unit 1 & 2) 150 d
194 Drawings submission & approval 30 d
195 Manufacturing 100 d
196 Material Inspection 10 d
197 Material despatch & recipt at site 10 d
198 HT Switchgear 3rd Lot(CHP & AHP Aux -3.3KV) 150 d
199 Drawings submission & approval 30 d
200 Manufacturing 100 d
201 Material Inspection 10 d
202 Material despatch & recipt at site 10 d
203 LT Switchgear 350 d
204 LT Switchgear 1st LOT 250 d
205 Technical specification preparation and issue 2d
206 Vendor offer Finalisation 45 d
207 Order Placement 3d
208 Drawings submission & approval 40 d
209 Manufacturing 120 d
210 Material Inspection 10 d
211 Material despatch & recipt at site 10 d
212 LT Switchgear 2nd LOT 180 d
213 Drawings submission and approval 40 d
214 Manufacturing 120 d
215 Material Inspection 10 d
216 Material despatch & recipt at site 10 d
217 LT Switchgear 3rd LOT 180 d
218 Drawings submission & approval 40 d
219 Manufacturing 120 d
220 Material Inspection 10 d
221 Material despatch & recipt at site 10 d
222 LT Switchgear 4th LOT 183 d
223 Drawings submission & approval 43 d
224 Manufacturing 120 d
225 Material Inspection 10 d
226 Material despatch & recipt at site 10 d
227 BUSDUCT 422 d
228 SPBD 11KV 255 d
229 Technical specification preparation and issue 5d
230 Vendor offer Finalisation 45 d
231 Order Placement 5d
232 Drawings submission & approval 30 d
233 Manufacturing 140 d
234 Material Inspection 10 d
235 Material despatch & recipt at site 20 d
236 SPBD 3.3KV 255 d
237 Technical specification preparation and issue 5d
238 Vendor Offer finalisation 45 d
239 Order Placement 5d
240 Drawings submission & approval 30 d
241 Manufacturing 120 d
242 Material Inspection 10 d
243 Material despatch & recipt at site 20 d
244 NSPBD 235 d
245 Technical specification preparation and issue 5d
246 Vendor offer Finalisation 45 d
247 Order Placement 5d
248 Drawings submission & approval 30 d
249 Manufacturing 120 d
250 Material Inspection 10 d
251 Material despatch & recipt at site 20 d
252 DC System 259 d
253 Unit Battery & Battery Charger ( 6 SETS ) 214 d
254 Technical specification preparation and issue 2d
255 Vendor offer Finalisation 45 d
256 Order Placement 2d
257 Drawings submission & approval 50 d
258 Manufacturing 100 d
259 Material Inspection 10 d
260 Material despatch & recipt at site 20 d
261 24V I&C Battery & Battery Charger ( 4 SETS ) 130 d
262 Manufacturing 100 d
263 Material Inspection 10 d
264 Material despatch & recipt at site 20 d
265 CHP Battery & Battery Charger - 2 SETS 130 d
266 Manufacturing 100 d
267 Material Inspection 10 d
268 Material despatch & recipt at site 20 d
269 UPS 214 d
270 Technical specification preparation and issue 2d
271 Vendor offer Finalisation 45 d
272 Order Placement 2d
273 Drawings submission & approval 25 d
274 Manufacturing 100 d
275 Material Inspection 10 d
276 Material despatch & recipt at site 10 d
277 Cable System 692 d
278 HT Cable ( 11kV & 3.3 kV ) Lot -1 187 d
279 Technical specification preparation and issue 5d
280 Vendor offer Finalisation 45 d
281 Order Placement 2d
282 GTP & QAP submission & approval 30 d
283 Manufacturing 75 d
284 Material Inspection 10 d
285 Material despatch & recipt at site 20 d
286 HT Cable ( 11kV & 3.3 kV ) Lot -2 217 d
287 Vendor offer Finalisation 45 d
288 Order Placement 2d
289 GTP & QAP submission & approval 30 d
290 Manufacturing 90 d
291 Material Inspection 10 d
292 Material despatch & recipt at site 20 d
293 LT Power Cable Lot -1 217 d
294 Technical specification preparation and issue 5d
295 Vendor offer Finalisation 45 d
296 Order Placement 2d
297 GTP & QAP submission & approval 25 d
298 Manufacturing 90 d
299 Material Inspection 10 d
300 Material despatch & recipt at site 20 d
301 LT Power Cable Lot -2 217 d
302 Technical specification preparation and issue 5d
303 Vendor offer Finalisation 45 d
304 Order Placement 2d
305 GTP & QAP submission & approval 25 d
306 Manufacturing 90 d
307 Material Inspection 10 d
308 Material despatch & recipt at site 20 d
309 LT Power Cable Lot -3 212 d
310 Vendor offer Finalisation 45 d
311 Order Placement 2d
312 Drawings submission & approval 25 d
313 Manufacturing 90 d
314 Material Inspection 10 d
315 Material despatch & recipt at site 20 d
316 Control Power Cable Lot -1 217 d
317 Technical specification preparation and issue 2d
318 Vendor offer Finalisation 40 d
319 Order Placement 5d
320 Drawings submission & approval 30 d
321 Manufacturing 90 d
322 Material Inspection 10 d
323 Material despatch & recipt at site 20 d
324 Control Cable Lot -2 210 d
325 Vendor offer Finalisation 40 d
326 Order Placement 5d
327 Drawings submission & approval 30 d
328 Manufacturing 90 d
329 Material Inspection 10 d
330 Material despatch & recipt at site 20 d
331 Instrumentation Cable Lot -1 202 d
332 Technical specification preparation and issue 2d
333 Vendor offer Finalisation 45 d
334 Order Placement 5d
335 Drawings submission & approval 30 d
336 Manufacturing 90 d
337 Material Inspection 10 d
338 Material despatch & recipt at site 20 d
339 Instrumentation Cable Lot -2 215 d
340 Vendor offer Finalisation 45 d
341 Order Placement 5d
342 Drawings submission & approval 30 d
343 Manufacturing 90 d
344 Material Inspection 10 d
345 Material despatch & recipt at site 20 d
346 Cable Tray & Accessories 445 d
347 Cable Tray & Accessories Lot-1 204 d
348 Technical specification preparation and issue 2d
349 Vendor offer Finalisation 45 d
350 Order Placement 2d
351 Drawings submission & approval 20 d
352 Manufacturing 90 d
353 Material Inspection 10 d
354 Material despatch & recipt at site 20 d
355 Cable Tray & Accessories Lot-2 202 d
356 Vendor offer Finalisation 45 d
357 Order Placement 2d
358 Drawings submission & approval 20 d
359 Manufacturing 90 d
360 Material Inspection 10 d
361 Material despatch & recipt at site 20 d
362 Earthing & Lightning Protection 472 d
363 Earthing & Lightning Protection Lot-1 167 d
364 Technical specification preparation and issue 2d
365 Vendor offer Finalisation 45 d
366 Order Placement 5d
367 Drawings submission & approval 20 d
368 Manufacturing 50 d
369 Material Inspection 10 d
370 Material despatch & recipt at site 20 d
371 Earthing & Lightning Protection Lot-2 195 d
372 Vendor offer Finalisation 45 d
373 Order Placement 5d
374 Drawings submission & approval 20 d
375 Manufacturing 80 d
376 Material Inspection 10 d
377 Material despatch & recipt at site 20 d
378 Earthing & Lightning Protection Lot-3 210 d
379 Vendor offer Finalisation 45 d
380 Order Placement 5d
381 Drawings submission & approval 20 d
382 Manufacturing 90 d
383 Material Inspection 10 d
384 Material despatch & recipt at site 20 d
385 Illumination System 370 d
386 Indoor Lighting 205 d
387 Technical specification preparation and issue 5d
388 Vendor offer Finalisation 45 d
389 Order Placement 5d
390 Drawings submission & approval 30 d
391 Manufacturing 70 d
392 Material Inspection 10 d
393 Material despatch & recipt at site 20 d
394 Outdoor Lighting 185 d
395 Technical specification preparation and issue 5d
396 Vendor offer Finalisation 45 d
397 Order Placement 5d
398 Drawings submission & approval 30 d
399 Manufacturing 70 d
400 Material Inspection 10 d
401 Material despatch & recipt at site 20 d
402 DG System -1800 KVA - 1ST LOT,1 No 249 d
403 Technical specification preparation and issue 2d
404 Vendor offer Finalisation 45 d
405 Order Placement 2d
406 Drawings submission & approval 30 d
407 Manufacturing 120 d
408 Material Inspection 10 d
409 Material despatch & recipt at site 20 d
410 DG System -1800 KVA - 2nd LOT, 1No 150 d
411 Manufacturing 120 d
412 Material Inspection 10 d
413 Material despatch & recipt at site 20 d
414 DG System -1800 KVA - 3rd LOT, 1No 150 d
415 Manufacturing 120 d
416 Material Inspection 10 d
417 Material despatch & recipt at site 20 d
418 Communication System & Accessories 202 d
419 Technical specification preparation and issue 10 d
420 Vendor offer Finalisation 45 d
421 Order Placement 2d
422 Drawings submission & approval 25 d
423 Manufacturing 90 d
424 Material Inspection 10 d
425 Material despatch & recipt at site 20 d
426 Electrical Lab Equipments 202 d
427 Technical specification preparation and issue 10 d
428 Vendor offer Finalisation 45 d
429 Order Placement 2d
430 Drawings submission & approval 25 d
431 Manufacturing 90 d
432 Material Inspection 10 d
433 Material despatch & recipt at site 20 d
434 Erection and instlallation 715 d
435 Earthing & Lightening Protection for Unit 1 & 2 657 d
436 Readiness of earthimg fronts 0d
437 Installation of Underground Earthig Mat with Riser 60 d
438 Installation of Aboveground Earthig 260 d
439 Installation of Lightening Arrestors 100 d
440 Testing & Precommissioning Activities 90 d
441 Cabling 447 d
442 Readiness of cable cellar 0 mtr 0d
443 Erection of cable trays and structures in 0 mtr 60 d
444 Readiness of cable cellar 9.0 mtr 0d
445 Erection of cable trays and structures in 9 mtr 54 d
446 Readiness of boiler cable trays front 0d
447 Erection of cable trays in Boller area 120 d
448 Readiness of Pipe racks (TG hall, WTP,AHP) 120 d
449 Erection of Cable Trays in Racks 120 d

450 Layiing & termination of HT & LT cables inclusing cable termination 150 d
451 DC System 46 d
452 Readiness of Battery Room 0d
453 Installation of Battery Stand / Rack 10 d
454 Installation of Batteries in Sequential Polarity 10 d
455 Installation of Battery Chargers 5d
456 Installation of DCDB with float cum Boost Charger 5d
457 Testing & Precommissioning Activities 10 d
458 Commissioning 3d
459 Aux Power Transformers 318 d
460 Station Aux. Transfomer -2 Nos 272 d
461 Readiness of Founadtion for SAT 0d
462 Installation of Main Tank on Foundation for SAT 6d
463 Alignment & Roller Blocking 4d
464 Installation of Conservator Tank 8d
465 Installation of Radiator,accessories and Fan Supports 8d
466 Installation of Marshalling Box and RTCC Panel 7d
467 Installation of Radiators, Bushings, Piping & Protective Devices etc 5d
468 Oil Top up and Filteration 20 d
469 Testing & Precommissioning Activities of SAT 20 d
470 Commissioning Activities of SAT 5d
471 NGR for SAT 17 d
472 Installation of NGR 7d
473 Testing & Precommissioning Activities 10 d
474 CHP Aux. Transformer -2 Nos 216 d
475 Readiness of foundation 0d
476 Installation of Main Tank on Foundation 10 d
477 Alignment & Roller Blocking 8d
478 Installation of Conservator Tank 12 d
479 Installation of Radiator,accessories and Fan Supports 8d
480 Installation of Marshalling Box and RTCC Panel 7d
481 Installation of Radiators, Bushings, Piping & Protective Devices etc 5d
482 Oil Top up and Filteration 25 d
483 Testing & Precommissioning Activities 25 d
484 Commissioning Activities of CHP Aux.Transformer 5d
485 NGR for CHP Aux Transformer 17 d
486 Installation of NGR 7d
487 Testing & Precommissioning Activities 10 d
488 Service Transformers 380 d
489 Station Service Transformer - 4 Nos 153 d
490 Readiness of 12m floor 0d
491 Installation of SST -4 Nos 25 d
492 Testing & Precommissioning Activities of SST 30 d
493 Commissioning Activities of SST 5d
494 Water Treatment Service Transformer - 2 Nos 199 d
495 Readiness of transformer foundation 0d
496 Installation of Main Tank on Foundation 10 d
497 Alignment & Roller Blocking 8d
498 Installation of Conservator Tank 10 d
499 Installation of Radiator & accessories 8d
500 Installation of Marshalling Box and RTCC Panel 5d
501 Oil Top up and Filteration 20 d
502 Testing & Precommissioning Activities 20 d
503 Commissioning Activities 5d
504 Ash Water pump House Service Transfomer - 2 Nos 269 d
505 Readiness of foundation 0d
506 Installation of Main Tank on Foundation 10 d
507 Alignment & Roller Blocking 8d
508 Installation of Conservator Tank 10 d
509 Installation of Radiator & accessories 8d
510 Installation of Marshalling Box and RTCC Panel 5d
511 Oil Top up and Filteration 10 d
512 Testing & Precommissioning Activities 10 d
513 Commissioning Activities 5d
514 Ash Extraction Service Transformer - 2 Nos 251 d
515 Readiness of foundation 0d
516 Installation of Main Tank on Foundation 10 d
517 Alignment & Roller Blocking 8d
518 Installation of Conservator Tank 10 d
519 Installation of Radiator & accessories 8d
520 Installation of Marshalling Box and RTCC Panel 5d
521 Oil Top up and Filteration 10 d
522 Testing & Precommissioning Activities 10 d
523 Commissioning Activities 5d
524 Electro Chlorination Plant Service Transformer - 2 Nos 169 d
525 readiness of Foundation 0d
526 Installation of Main Tank on Foundation 10 d
527 Alignment & Roller Blocking 8d
528 Installation of Conservator Tank 10 d
529 Installation of Radiator & accessories 8d
530 Installation of Marshalling Box and RTCC Panel 5d
531 Oil Top up and Filteration 10 d
532 Testing & Precommissioning Activities 10 d
533 Commissioning Activities of ECP 5d
534 Ash Silo Service Transformer-2 Nos 223 d
535 Readiness of foundation 0d
536 Installation of Main Tank on Foundation 10 d
537 Alignment & Roller Blocking 8d
538 Installation of Conservator Tank 10 d
539 Installation of Radiator & accessories 8d
540 Installation of Marshalling Box and RTCC Panel 5d
541 Oil Top up and Filteration 10 d
542 Testing & Precommissioning Activities 10 d
543 Commissioning Activities 5d
544 Fire water Service Transformer - 2 Nos 160 d
545 Foundation readiness 0d
546 Installation of Main Tank on Foundation 10 d
547 Alignment & Roller Blocking 8d
548 Installation of Conservator Tank 10 d
549 Installation of Radiator & accessories 8d
550 Installation of Marshalling Box and RTCC Panel 5d
551 Oil Top up and Filteration 10 d
552 Testing & Precommissioning Activities 10 d
553 Commissioning Activities 5d
554 Ash water Recovery Service Transformer - 2 Nos 188 d
555 Radiness of foundation 0d
556 Installation of Main Tank on Foundation 10 d
557 Alignment & Roller Blocking 8d
558 Installation of Conservator Tank 10 d
559 Installation of Radiator & accessories 8d
560 Installation of Marshalling Box and RTCC Panel 5d
561 Oil Top up and Filteration 10 d
562 Testing & Precommissioning Activities 10 d
563 Commissioning Activities 5d
564 Admin Service Transfomer- 2 Nos 177 d
565 Installation of Main Tank on Foundation 0d
566 Alignment & Roller Blocking 10 d
567 Installation of Conservator Tank 8d
568 Installation of Radiator & accessories 10 d
569 Installation of Marshalling Box and RTCC Panel 8d
570 Oil Top up and Filteration 5d
571 Testing & Precommissioning Activities 10 d
572 Commissioning Activities 5d
573 ESP Service Transformers- 16 Nos 161 d
574 Foundation readiness of ESP area 0d
575 Installation of Main Tank on Foundation 25 d
576 Alignment & Roller Blocking 20 d
577 Installation of Conservator Tank 16 d
578 Installation of Radiator & accessories 25 d
579 Installation of Marshalling Box and RTCC Panel 5d
580 Oil Top up and Filteration 30 d
581 Testing & Precommissioning Activities 30 d
582 Commissioning of ESP transformers 10 d
583 UST- 8 Nos 158 d
584 Readiness of floor 0d
585 Installation of UST -8 Nos 56 d
586 Testing & Precommissioning Activities 40 d
587 Commissioning Activities of UST 5d
588 CHP - 6 Nos 154 d
589 Readiness of foundation 0d
590 Installation of Main Tank on Foundation 12 d
591 Alignment & Roller Blocking 20 d
592 Installation of Conservator Tank 15 d
593 Installation of Radiator & accessories 15 d
594 Installation of Marshalling Box and RTCC Panel 15 d
595 Oil Top up and Filteration 20 d
596 Testing & Precommissioning Activities 25 d
597 Commissioning of CHP 5d
598 UPS 52 d
599 Readiness of UPS Room 0d
600 Installation of Base Frame 7d
601 Alignment and Welding/Anchoiring 8d
602 Installation and coupling of Panels 20 d
603 Earthing of Panel 7d
604 Testing & Precommissioning Activities 5d
605 Commissioning Activites for UPS 5d
606 NSPBD 60 d
607 Erection of NSPBD 60 d
608 LT Switchgear Station 140 d
609 Readiness of 13.5 mtr panel room ( completion of 17 m Mtr floor) 0d
610 Installation of Base Frame 15 d
611 Alignment and Welding/Anchoiring 10 d
612 Installation and coupling of Panels 15 d
613 Earthing of MCC Panel 15 d
614 Testing & Precommissioning Activities 25 d
615 Commissioning Activities 10 d
616 LT Switchgear Unit 145 d
617 Installation of Base Frame 15 d
618 Alignment and Welding/Anchoiring 10 d
619 Installation and coupling of Panels 15 d
620 Earthing of MCC Panel 15 d
621 Testing & Precommissioning Activities 25 d
622 Commissioning Activities 10 d
623 415V Swgr (AHP,CHP,ESP) 320 d
624 Installation of Base Frame 15 d
625 Alignment and Welding/Anchoiring 10 d
626 Installation and coupling of Panels 15 d
627 Earthing of MCC Panel 15 d
628 Testing & Precommissioning Activities 25 d

629 Commissioning Activities 10 d


630 Illumination System 410 d
631 Indoor Lighting 410 d
632 Install Conduits 150 d
633 Install LDB / SLDB 60 d
634 Wire Pulling and Termination 100 d
635 Install Lighting Fixtures 100 d
636 Outdoor Lighting 190 d
637 Install Lighting Poles and Support 60 d
638 Install Lighting Fixtures 45 d
639 Install Junction Boxes 30 d
640 Cable laying and Termination 55 d
641 Unit - 1 567 d
642 Generator Transformer for Unit -1 456 d
643 Readiness of the foundation for GT 0d
644 Check Foundation Center line and Level 20 d
645 Installation of the Main tank of GT 30 d
646 Alignment and centering on both Axes 30 d
647 Assemble and Block Rollers 20 d
648 Install marshalling and OLTC Boxes 21 d
649 Install Coservator Tank 30 d
650 Install radiator Fan Support 20 d
651 Install headers, radiators, pipe works, bushing and breather 25 d
652 Install safety and Protective devices 10 d
653 Earthing of the equipment 25 d
654 Oil filling on main tank 35 d
655 Hot circulation of OIL 25 d
656 Testing and Pre commissioning of GT 45 d
657 Commissioning of Generator Transformer 1d
658 Unit Transformer- 2No 377 d
659 Readiness of the foundation of UT 0d
660 Check Foundation Center line and Level 10 d
661 Installation of the Main tank of UT 15 d
662 Alignment and centering on both Axes 7d
663 Assemble and Block Rollers 6d
664 Install marshalling and OLTC Boxes 12 d
665 Install Conservator Tank 15 d
666 Install radiator Fan Support 10 d
667 Install headers, radiators, pipe works, bushing and breather 10 d
668 Install safety and Protective devices 8d
669 Earthing of the equipment 8d
670 Oil filling on main tank 20 d
671 Hot circulation of OIL 17 d
672 Testing and Pre commissioning of UT 30 d
673 Commissioning of UT 1d
674 NGR for UT 22 d
675 Installation of NGR 7d
676 Testing & Precommissioning Activities 15 d
677 Station Transformer- 1 No Unit #1 255 d
678 Readiness of the foundation of ST 0d
679 Check Foundation Center line and Level 4d
680 Installation of the Main tank of ST 5d
681 Alignment and centering on both Axes 3d
682 Assemble and Block Rollers 5d
683 Install marshalling and OLTC Boxes 5d
684 Install Conservator Tank 5d
685 Install radiator Fan Support 4d
686 Install headers, radiators, pipe works, bushing and breather 3d
687 Install safety and Protective devices 5d
688 Earthing of the equipment 5d
689 Oil filling on main tank 20 d
690 Hot circulation of OIL 15 d
691 Testing and Pre commissioning of ST -1 20 d
692 Commissioning and Charging 5d
693 NGR for ST 25 d
694 Installation of NGR 10 d
695 Testing & Precommissioning Activities 15 d
696 UAT -2 Nos 285 d
697 Readiness of foundation 0d
698 Installation of Main Tank on Foundation of UAT 7d
699 Alignment & Roller Blocking 8d
700 Installation of Conservator Tank 5d
701 Installation of Radiator,accessories and Fan Supports 8d
702 Installation of Marshalling Box and RTCC Panel 8d
703 Installation of Radiators, Bushings, Piping & Protective Devices etc 10 d
704 Oil Top up and Filteration 20 d
705 Testing and Precommissioning Activities of UAT 25 d
706 commissioning Activities 5d
707 NGR for UAT 22 d
708 Installation of NGR 7d
709 Testing & Precommissioning Activities 15 d
710 SPBD 60 d
711 Erection of SPBD 11KV 60 d
712 11 kV - Station Switchgear -1 Lot 162 d
713 Readiness of 3.5 mtr ele bay 0d
714 Installation of Base Frame 15 d
715 Alignment and Welding/Anchoiring 7d
716 Installation and coupling of Panels 30 d
717 Earthing of HV MCC 10 d
718 Testing & Precommissioning Activities 25 d
719 Charging of Station Switchgear Unit 1 10 d
720 11 kV - Unit Switchgear - 1 lot 167 d
721 Installation of Base Frame 15 d
722 Alignment and Welding/Anchoiring 7d
723 Installation and coupling of Panels 30 d
724 Earthing of HV MCC 10 d
725 Testing & Precommissioning Activities 25 d
726 Charging of Unit Switchgear Unit -1 5d
727 SPBD -3.3KV 60 d
728 Erection of SPBD -3.3KV 60 d
729 3.3 kV Unit Aux. Switchgear -1 lot 177 d
730 Installation of Base Frame 20 d
731 Alignment and Welding/Anchoiring 15 d
732 Installation and coupling of Panels 20 d
733 Earthing of MCC Panel 10 d
734 Testing & Precommissioning Activities 30 d
735 Commissioning Activities of 3.3KV Unit Aux Swgr Unit -1 5d
736 DG System with AMF Panel 136 d
737 Readiness of the DG Foundation 0d
738 Install DG Set on the Foundation 22 d
739 Install exhaust & Fuel pipe Lines 30 d
740 Earthing of the Equipment 5d
741 Testing and Precommissioning 30 d
742 Commissioning of DG Set 15 d
743 Unit-2 587 d
744 Generator Transformer - 1 No 456 d
745 Readiness of the foundation of GT Unit -2 0d
746 Check Foundation Center line and Level 20 d

747 Installation of the Main tank of GT Unit -2 30 d


748 Alignment and centering on both Axes 20 d
749 Assemble and Block Rollers 10 d
750 Install marshalling and OLTC Boxes 15 d
751 Install Coservator Tank 30 d
752 Install radiator Fan Support 20 d
753 Install headers, radiators, pipe works, bushing and breather 25 d
754 Install safety and Protective devices 10 d
755 Earthing of the equipment 25 d
756 Oil filling on main tank 40 d
757 Hot circulation of OIL 20 d
758 Testing and Pre commissioning of GT Unit 2 45 d
759 Commissioning of GT -Unit -2 1d
760 Unit Transformer - 2 Nos 377 d
761 Readiness of the foundation of UT Unit 2 0d
762 Check Foundation Center line and Level 15 d
763 Installation of the Main tank of UT Unit 2 15 d
764 Alignment and centering on both Axes 7d
765 Assemble and Block Rollers 6d
766 Install marshalling and OLTC Boxes 10 d
767 Install Conservator Tank 10 d
768 Install radiator Fan Support 10 d
769 Install headers, radiators, pipe works, bushing and breather 15 d
770 Install safety and Protective devices 8d
771 Earthing of the equipment 10 d
772 Oil filling on main tank 18 d
773 Hot circulation of OIL 15 d
774 Testing and Pre commissioning of UT Unit 2 25 d
775 Commissioning of UT of Unit 2 1d
776 NGR for UT 22 d
777 Installation of NGR 7d
778 Testing & Precommissioning Activities 15 d
779 Station Transformer- 1 No 211 d
780 Readiness of the foundation of ST Unit 2 0d
781 Check Foundation Center line and Level 4d
782 Installation of the Main tank of ST Unit 2 5d
783 Alignment and centering on both Axes 3d
784 Assemble and Block Rollers 5d
785 Install marshalling and OLTC Boxes 15 d
786 Install Conservator Tank 10 d
787 Install radiator Fan Support 12 d
788 Install headers, radiators, pipe works, bushing and breather 10 d
789 Install safety and Protective devices 5d
790 Earthing of the equipment 10 d
791 Oil filling on main tank 20 d
792 Hot circulation of OIL 14 d
793 Testing and Pre commissioning 25 d
794 Commissioning of ST Unit 2 1d
795 NGR for ST 25 d
796 Installation of NGR 10 d
797 Testing & Precommissioning Activities 15 d
798 SPBD 60 d
799 Erection of SPBD 60 d
800 UAT - 2 Nos 238 d
801 Readiness of foundation of UAT 0d
802 Installation of Main Tank on Foundation of UAT 7d
803 Alignment & Roller Blocking 8d
804 Installation of Conservator Tank 10 d
805 Installation of Radiator,accessories and Fan Supports 8d
806 Installation of Marshalling Box and RTCC Panel 10 d
807 Installation of Radiators, Bushings, Piping & Protective Devices etc 10 d
808 Oil Top up and Filteration 20 d
809 Testing & Precommissioning Activities 20 d
810 Commissioning of UAT Unit 2 1d
811 NGR for UAT 25 d
812 Installation of NGR 10 d
813 Testing & Precommissioning Activities 15 d
814 11 kV - Station Switchgear -1 set 149 d
815 Installation of Base Frame 15 d
816 Alignment and Welding/Anchoiring 7d
817 Installation and coupling of Panels 30 d
818 Earthing of HV MCC 10 d
819 Testing & Precommissioning Activities Station SWGR 30 d
820 Charging of Station Swgr Unit -2 10 d
821 11 kV - Unit Switchgear - 1 set 99 d
822 Installation of Base Frame 15 d
823 Alignment and Welding/Anchoiring 7d
824 Installation and coupling of Panels 30 d
825 Earthing of HV MCC 10 d
826 Testing & Precommissioning Activities of Unit SWGR 25 d
827 Commissioning Activities of Unit SWGR 5d
828 SPBD 60 d
829 Erection of SPBD -3.3KV 60 d
830 3.3 kV Unit Aux. Switchgear - 1 Set 155 d
831 Installation of Base Frame 20 d
832 Alignment and Welding/Anchoiring 15 d
833 Installation and coupling of Panels 20 d
834 Earthing of MCC Panel 10 d
835 Testing & Precommissioning Activities 30 d
836 Commissioning of Unit Aux SWGR 5d
837 DG System with AMF Panel 136 d
838 Readiness of the DG Foundation 0d
839 Install DG Set on the Foundation 22 d
840 Install exhaust & Fuel pipe Lines 30 d
841 Earthing of the Equipment 5d
842 Testing and Precommissioning 30 d
843 Commissioning of DG Set 15 d
844 Station Packages 215 d
845 Coal handling System 178 d
846 Readiness of CHP MCC room 0d
847 Raediness for cable tray erection 0d
848 Cable tray erection 22 d
849 Cable laying and termination 35 d
850 Base Frame erection 10 d
851 Panel erection 8d
852 Internal cabling 8d
853 alignment 4d
854 External cabling 4d
855 testing and precommissioning 15 d
856 Charging of 3.3.KV Panels 5d
857 Ash Handling System 88 d
858 Readiness of AHP MCC room 0d
859 Cable laying and termination 15 d
860 Base Frame erection 10 d
861 Panel erection 8d
862 Internal cabling 8d
863 alignment 4d
864 External cabling 4d
865 testing and precommissioning 15 d
866 Charging of 3.3.KV Panels 5d
867 Water Treatment system 98 d
868 Readiness of WTP MCC room 0d
869 Cable laying and termination 20 d
870 Base Frame erection 10 d
871 Panel erection 8d
872 Internal cabling 8d
873 alignment 4d
874 External cabling & termination 4d
875 testing and precommissioning 15 d
876 Charging of 3.3KV Panels 5d
877 Cooling Water System 158 d
878 Readiness of CW System MCC room 0d
879 Readiness for cable tray erection (Cable RACK) 0d
880 Cable tray erection 30 d
881 Cable laying and termination 20 d
882 Base Frame erection 10 d
883 Panel erection 8d
884 Internal cabling 8d
885 alignment 4d
886 External cabling 4d
887 testing and precommissioning 15 d
888 Commissioning of CW Swgr 5d
Start Finish Predecessors
3/31/2009 8:00 7/14/2012 17:30
3/31/2009 8:00 7/14/2012 17:30
3/31/2009 8:00 3/31/2009 8:00
5/21/2009 17:30 5/21/2009 17:30 3FS+52 d
6/15/2009 17:30 6/15/2009 17:30 4FS+25 d
6/14/2011 8:30 6/14/2011 8:30 5FS+300 d
450,440,692,6,706,719,726,73
5,458,622,629,635,615,605,64
1/10/2012 17:30 1/10/2012 17:30 0,503
440,7,657,673,866,742,735,43
4/15/2012 17:30 4/15/2012 17:30 3,425,856,876,888,836
7/14/2012 17:30 7/14/2012 17:30 759,775,440,8,843
6/10/2009 17:30 2/15/2010 17:30
8/8/2009 17:30 8/8/2009 17:30 5FS+54 d
9/27/2009 17:30 9/27/2009 17:30 5FS+104 d
6/10/2009 17:30 6/10/2009 17:30 4FS+20 d
6/10/2009 17:30 6/10/2009 17:30 4FS+20 d
8/25/2009 8:30 10/13/2009 17:30 5FS+70 d
8/20/2009 17:30 8/20/2009 17:30 5FS+66 d
12/2/2009 17:30 12/2/2009 17:30 5FS+170 d
7/31/2009 8:30 2/15/2010 17:30 5FS+45 d
7/7/2009 8:30 10/4/2009 17:30 5FS+21 d
8/15/2009 8:30 9/8/2009 17:30 5FS+60 d
7/6/2009 8:30 10/13/2009 17:30 5FS+20 d
11/21/2009 8:30 12/20/2009 17:30 5FS+34 d
6/11/2009 8:30 2/13/2011 17:30
9/1/2009 8:30 9/26/2009 17:30 5FS+77 d
9/11/2009 8:30 9/27/2009 17:30 16,24SS+10 d
9/28/2009 8:30 10/10/2009 17:30 25
9/28/2009 8:30 1/5/2010 17:30 20,30,31,28
8/29/2009 8:30 9/27/2009 17:30 11SS+20 d
9/28/2009 8:30 12/11/2009 17:30 12
6/11/2009 8:30 6/30/2009 17:30 13
6/11/2009 8:30 7/7/2009 17:30 14
10/5/2009 8:30 12/22/2009 17:30 19
7/8/2009 8:30 8/1/2009 17:30 30,31
12/12/2009 8:30 2/2/2010 17:30 29
8/29/2009 8:30 9/22/2009 17:30 30SS,31SS,28SS
12/12/2009 8:30 3/11/2010 17:30 29
10/14/2009 8:30 12/15/2009 17:30 15
8/9/2009 8:30 9/2/2009 17:30 11,21SS+20 d
12/12/2009 8:30 4/20/2010 17:30 12SS,36SS,21
4/21/2010 8:30 6/28/2010 17:30 38,39
9/23/2009 8:30 1/30/2010 17:30 35
3/12/2010 8:30 8/18/2010 17:30 36,21
3/12/2010 8:30 9/2/2010 17:30 36
12/21/2009 8:30 1/19/2010 17:30 22
3/16/2010 8:30 10/6/2010 17:30 17FS+103 d
8/18/2010 8:30 2/13/2011 17:30 17FS+258 d
3/5/2010 8:30 8/5/2010 17:30 18FS+17 d,27
7/8/2009 8:30 10/8/2011 17:30
7/8/2009 8:30 6/24/2011 17:30
8/20/2009 8:30 6/24/2011 17:30
8/20/2009 8:30 1/20/2011 17:30
8/20/2009 8:30 8/29/2009 17:30 4FS+90 d
8/30/2009 8:30 9/28/2009 17:30 52
11/2/2009 8:30 12/16/2009 17:30 53FS+34 d
1/6/2010 8:30 11/1/2010 17:30 54FS+20 d
11/2/2010 8:30 11/16/2010 17:30 55
11/22/2010 8:30 1/20/2011 17:30 56FS+5 d
1/21/2010 8:30 2/4/2011 17:30
1/21/2010 8:30 11/16/2010 17:30 54FS+35 d
11/17/2010 8:30 12/1/2010 17:30 59
12/7/2010 8:30 2/4/2011 17:30 60FS+5 d
3/2/2010 8:30 3/16/2011 17:30
3/2/2010 8:30 12/26/2010 17:30 54FS+75 d
12/27/2010 8:30 1/10/2011 17:30 63
1/16/2011 8:30 3/16/2011 17:30 64FS+5 d
3/27/2010 8:30 4/5/2011 17:30
3/27/2010 8:30 1/20/2011 17:30 54FS+100 d
1/21/2011 8:30 2/4/2011 17:30 67
2/5/2011 8:30 4/5/2011 17:30 68
4/29/2010 8:30 5/8/2011 17:30
4/29/2010 8:30 2/22/2011 17:30 54FS+133 d
2/23/2011 8:30 3/9/2011 17:30 71
3/10/2011 8:30 5/8/2011 17:30 72
6/5/2010 8:30 6/14/2011 17:30
6/5/2010 8:30 3/31/2011 17:30 54FS+170 d
4/1/2011 8:30 4/15/2011 17:30 75
4/16/2011 8:30 6/14/2011 17:30 76
6/15/2010 8:30 6/24/2011 17:30
6/15/2010 8:30 4/10/2011 17:30 54FS+180 d
4/11/2011 8:30 4/25/2011 17:30 79
4/26/2011 8:30 6/24/2011 17:30 80
7/8/2009 8:30 11/14/2010 17:30
7/8/2009 8:30 8/21/2010 17:30
7/8/2009 8:30 7/17/2009 17:30 31
7/18/2009 8:30 8/16/2009 17:30 84
9/6/2009 8:30 10/25/2009 17:30 85FS+20 d
10/26/2009 8:30 7/7/2010 17:30 86
7/8/2010 8:30 7/22/2010 17:30 87
7/23/2010 8:30 8/21/2010 17:30 88
1/19/2010 8:30 11/14/2010 17:30
1/19/2010 8:30 9/30/2010 17:30 86FS+85 d
10/1/2010 8:30 10/15/2010 17:30 91
10/16/2010 8:30 11/14/2010 17:30 92
8/30/2009 8:30 4/6/2011 17:30
8/30/2009 8:30 10/28/2010 17:30
8/30/2009 8:30 9/8/2009 17:30 30FS+60 d
9/19/2009 8:30 10/18/2009 17:30 96FS+10 d
11/28/2009 8:30 2/5/2010 17:30 97FS+40 d
2/6/2010 8:30 9/13/2010 17:30 98
9/14/2010 8:30 9/28/2010 17:30 99
9/29/2010 8:30 10/28/2010 17:30 100
5/7/2010 8:30 1/26/2011 17:30
5/7/2010 8:30 12/12/2010 17:30 98FS+90 d
12/13/2010 8:30 12/27/2010 17:30 103
12/28/2010 8:30 1/26/2011 17:30 104
6/6/2010 8:30 2/25/2011 17:30
6/6/2010 8:30 1/11/2011 17:30 98FS+120 d
1/12/2011 8:30 1/26/2011 17:30 107
1/27/2011 8:30 2/25/2011 17:30 108
7/16/2010 8:30 4/6/2011 17:30
7/16/2010 8:30 2/20/2011 17:30 98FS+160 d
2/21/2011 8:30 3/7/2011 17:30 111
3/8/2011 8:30 4/6/2011 17:30 112
9/28/2009 8:30 7/22/2010 17:30
9/28/2009 8:30 5/18/2010 17:30
9/28/2009 8:30 9/29/2009 17:30 28
9/30/2009 8:30 11/8/2009 17:30 116
11/9/2009 8:30 11/11/2009 17:30 117
12/2/2009 8:30 12/31/2009 17:30 118FS+20 d
1/1/2010 8:30 4/30/2010 17:30 119
5/1/2010 8:30 5/6/2010 17:30 120
5/7/2010 8:30 5/18/2010 17:30 121
1/31/2010 8:30 6/17/2010 17:30
1/31/2010 8:30 5/30/2010 17:30 119FS+30 d
5/31/2010 8:30 6/5/2010 17:30 124
6/6/2010 8:30 6/17/2010 17:30 125
10/18/2009 8:30 6/2/2010 17:30
10/18/2009 8:30 10/19/2009 17:30 28FS+20 d
10/20/2009 8:30 11/28/2009 17:30 128
11/29/2009 8:30 12/1/2009 17:30 129
12/27/2009 8:30 1/25/2010 17:30 130FS+25 d
1/26/2010 8:30 5/15/2010 17:30 131
5/16/2010 8:30 5/21/2010 17:30 132
5/22/2010 8:30 6/2/2010 17:30 133
3/27/2010 8:30 7/22/2010 17:30
3/27/2010 8:30 7/4/2010 17:30 131FS+60 d
7/5/2010 8:30 7/10/2010 17:30 136
7/11/2010 8:30 7/22/2010 17:30 137
12/12/2009 8:30 2/1/2011 17:30

12/12/2009 8:30 7/31/2010 17:30


12/12/2009 8:30 12/13/2009 17:30 29
12/14/2009 8:30 1/27/2010 17:30 141
1/28/2010 8:30 2/1/2010 17:30 142
2/22/2010 8:30 3/13/2010 17:30 143FS+20 d
3/14/2010 8:30 7/11/2010 17:30 144
7/12/2010 8:30 7/21/2010 17:30 145
7/22/2010 8:30 7/31/2010 17:30 146

5/3/2010 8:30 9/19/2010 17:30


5/3/2010 8:30 8/30/2010 17:30 144FS+50 d
8/31/2010 8:30 9/9/2010 17:30 149
9/10/2010 8:30 9/19/2010 17:30 150

3/2/2010 8:30 10/9/2010 17:30


3/2/2010 8:30 3/3/2010 17:30 29FS+80 d
3/4/2010 8:30 4/17/2010 17:30 153
4/18/2010 8:30 4/22/2010 17:30 154
4/23/2010 8:30 5/22/2010 17:30 155
5/23/2010 8:30 9/19/2010 17:30 156
9/20/2010 8:30 9/29/2010 17:30 157
9/30/2010 8:30 10/9/2010 17:30 158

6/22/2010 8:30 11/18/2010 17:30


6/22/2010 8:30 10/19/2010 17:30 156FS+30 d
10/20/2010 8:30 10/29/2010 17:30 161
10/30/2010 8:30 11/18/2010 17:30 162

5/11/2010 8:30 1/12/2011 17:30


5/11/2010 8:30 5/12/2010 17:30 29FS+150 d
5/13/2010 8:30 6/21/2010 17:30 165
6/22/2010 8:30 7/6/2010 17:30 166
7/27/2010 8:30 8/25/2010 17:30 167FS+20 d
8/26/2010 8:30 12/23/2010 17:30 168
12/24/2010 8:30 1/2/2011 17:30 169
1/3/2011 8:30 1/12/2011 17:30 170
9/15/2010 8:30 2/1/2011 17:30
9/15/2010 8:30 1/12/2011 17:30 168FS+20 d
1/13/2011 8:30 1/22/2011 17:30 173
1/23/2011 8:30 2/1/2011 17:30 174
11/27/2009 8:30 9/4/2010 17:30
11/27/2009 8:30 12/1/2009 17:30 28FS+60 d
12/2/2009 8:30 1/15/2010 17:30 177
1/16/2010 8:30 1/17/2010 17:30 178
2/7/2010 8:30 3/8/2010 17:30 179FS+20 d
3/9/2010 8:30 8/5/2010 17:30 180
8/6/2010 8:30 8/15/2010 17:30 181
8/16/2010 8:30 9/4/2010 17:30 182
9/23/2009 8:30 6/12/2010 17:30
9/23/2009 8:30 4/13/2010 17:30
9/23/2009 8:30 9/27/2009 17:30 35
9/28/2009 8:30 11/11/2009 17:30 186
11/12/2009 8:30 11/14/2009 17:30 187
11/15/2009 8:30 12/14/2009 17:30 188
12/15/2009 8:30 3/24/2010 17:30 189
3/25/2010 8:30 4/3/2010 17:30 190
4/4/2010 8:30 4/13/2010 17:30 191

12/15/2009 8:30 5/13/2010 17:30


12/15/2009 8:30 1/13/2010 17:30 189
1/14/2010 8:30 4/23/2010 17:30 194
4/24/2010 8:30 5/3/2010 17:30 195
5/4/2010 8:30 5/13/2010 17:30 196
1/14/2010 8:30 6/12/2010 17:30
1/14/2010 8:30 2/12/2010 17:30 194
2/13/2010 8:30 5/23/2010 17:30 199
5/24/2010 8:30 6/2/2010 17:30 200
6/3/2010 8:30 6/12/2010 17:30 201
3/12/2010 8:30 2/24/2011 17:30
3/12/2010 8:30 11/16/2010 17:30
3/12/2010 8:30 3/13/2010 17:30 36
3/14/2010 8:30 4/27/2010 17:30 205
4/28/2010 8:30 4/30/2010 17:30 206
5/21/2010 8:30 6/29/2010 17:30 207FS+20 d
6/30/2010 8:30 10/27/2010 17:30 208
10/28/2010 8:30 11/6/2010 17:30 209
11/7/2010 8:30 11/16/2010 17:30 210
6/30/2010 8:30 12/26/2010 17:30
6/30/2010 8:30 8/8/2010 17:30 208
8/9/2010 8:30 12/6/2010 17:30 213
12/7/2010 8:30 12/16/2010 17:30 214
12/17/2010 8:30 12/26/2010 17:30 215
8/9/2010 8:30 2/4/2011 17:30
8/9/2010 8:30 9/17/2010 17:30 213
9/18/2010 8:30 1/15/2011 17:30 218
1/16/2011 8:30 1/25/2011 17:30 219
1/26/2011 8:30 2/4/2011 17:30 220
8/26/2010 8:30 2/24/2011 17:30
8/26/2010 8:30 10/7/2010 17:30 218SS+17 d
10/8/2010 8:30 2/4/2011 17:30 223
2/5/2011 8:30 2/14/2011 17:30 224
2/15/2011 8:30 2/24/2011 17:30 225
11/25/2009 8:30 1/20/2011 17:30
11/25/2009 8:30 8/6/2010 17:30
11/25/2009 8:30 11/29/2009 17:30 189SS+10 d,33
11/30/2009 8:30 1/13/2010 17:30 229
1/14/2010 8:30 1/18/2010 17:30 230
1/19/2010 8:30 2/17/2010 17:30 231
2/18/2010 8:30 7/7/2010 17:30 232
7/8/2010 8:30 7/17/2010 17:30 233
7/18/2010 8:30 8/6/2010 17:30 234
12/25/2009 8:30 9/5/2010 17:30
12/25/2009 8:30 12/29/2009 17:30 33,194SS+10 d
12/30/2009 8:30 2/12/2010 17:30 237
2/13/2010 8:30 2/17/2010 17:30 238
3/10/2010 8:30 4/8/2010 17:30 239FS+20 d
4/9/2010 8:30 8/6/2010 17:30 240
8/7/2010 8:30 8/16/2010 17:30 241
8/17/2010 8:30 9/5/2010 17:30 242
5/31/2010 8:30 1/20/2011 17:30
5/31/2010 8:30 6/4/2010 17:30 34,208SS+10 d
6/5/2010 8:30 7/19/2010 17:30 245
7/20/2010 8:30 7/24/2010 17:30 246
8/14/2010 8:30 9/12/2010 17:30 247FS+20 d
8/24/2010 8:30 12/21/2010 17:30 248FS-20 d
12/22/2010 8:30 12/31/2010 17:30 249
1/1/2011 8:30 1/20/2011 17:30 250
12/16/2009 8:30 8/31/2010 17:30
12/16/2009 8:30 7/17/2010 17:30
12/16/2009 8:30 12/17/2009 17:30 37
12/18/2009 8:30 1/31/2010 17:30 254
2/1/2010 8:30 2/2/2010 17:30 255
2/13/2010 8:30 4/3/2010 17:30 256FS+10 d
3/10/2010 8:30 6/17/2010 17:30 257SS+25 d
6/18/2010 8:30 6/27/2010 17:30 258
6/28/2010 8:30 7/17/2010 17:30 259
4/4/2010 8:30 8/11/2010 17:30
4/4/2010 8:30 7/12/2010 17:30 257
7/13/2010 8:30 7/22/2010 17:30 262
7/23/2010 8:30 8/11/2010 17:30 263
4/24/2010 8:30 8/31/2010 17:30
4/24/2010 8:30 8/1/2010 17:30 257FS+20 d
8/2/2010 8:30 8/11/2010 17:30 266
8/12/2010 8:30 8/31/2010 17:30 267
1/20/2010 8:30 8/21/2010 17:30
1/20/2010 8:30 1/21/2010 17:30 44
1/22/2010 8:30 3/7/2010 17:30 270
3/8/2010 8:30 3/9/2010 17:30 271
3/30/2010 8:30 4/23/2010 17:30 272FS+20 d
4/24/2010 8:30 8/1/2010 17:30 273
8/2/2010 8:30 8/11/2010 17:30 274
8/12/2010 8:30 8/21/2010 17:30 275
9/3/2009 8:30 7/26/2011 17:30
10/23/2009 8:30 4/27/2010 17:30
10/23/2009 8:30 10/27/2009 17:30 41SS+30 d
10/28/2009 8:30 12/11/2009 17:30 279
12/12/2009 8:30 12/13/2009 17:30 280
12/14/2009 8:30 1/12/2010 17:30 281
1/13/2010 8:30 3/28/2010 17:30 282
3/29/2010 8:30 4/7/2010 17:30 283
4/8/2010 8:30 4/27/2010 17:30 284
4/1/2010 8:30 11/3/2010 17:30
4/1/2010 8:30 5/15/2010 17:30 41FS+60 d
5/16/2010 8:30 5/17/2010 17:30 287
6/7/2010 8:30 7/6/2010 17:30 288FS+20 d
7/7/2010 8:30 10/4/2010 17:30 289
10/5/2010 8:30 10/14/2010 17:30 290
10/15/2010 8:30 11/3/2010 17:30 291
12/7/2009 8:30 7/11/2010 17:30
12/7/2009 8:30 12/11/2009 17:30 12FS+70 d
12/12/2009 8:30 1/25/2010 17:30 294
1/26/2010 8:30 1/27/2010 17:30 295
2/17/2010 8:30 3/13/2010 17:30 296FS+20 d
3/14/2010 8:30 6/11/2010 17:30 297
6/12/2010 8:30 6/21/2010 17:30 298
6/22/2010 8:30 7/11/2010 17:30 299
4/1/2010 8:30 11/3/2010 17:30
4/1/2010 8:30 4/5/2010 17:30 42SS+20 d
4/6/2010 8:30 5/20/2010 17:30 302
5/21/2010 8:30 5/22/2010 17:30 303
6/12/2010 8:30 7/6/2010 17:30 304FS+20 d
7/7/2010 8:30 10/4/2010 17:30 305
10/5/2010 8:30 10/14/2010 17:30 306
10/15/2010 8:30 11/3/2010 17:30 307
8/19/2010 8:30 3/18/2011 17:30
8/19/2010 8:30 10/2/2010 17:30 42
10/3/2010 8:30 10/4/2010 17:30 310
10/25/2010 8:30 11/18/2010 17:30 311FS+20 d
11/19/2010 8:30 2/16/2011 17:30 312
2/17/2011 8:30 2/26/2011 17:30 313
2/27/2011 8:30 3/18/2011 17:30 314
4/6/2010 8:30 11/8/2010 17:30
4/6/2010 8:30 4/7/2010 17:30 43SS+25 d
4/8/2010 8:30 5/17/2010 17:30 317
5/18/2010 8:30 5/22/2010 17:30 318
6/12/2010 8:30 7/11/2010 17:30 319FS+20 d
7/12/2010 8:30 10/9/2010 17:30 320
10/10/2010 8:30 10/19/2010 17:30 321
10/20/2010 8:30 11/8/2010 17:30 322
9/3/2010 8:30 3/31/2011 17:30
9/3/2010 8:30 10/12/2010 17:30 43
10/13/2010 8:30 10/17/2010 17:30 325
11/2/2010 8:30 12/1/2010 17:30 326FS+15 d
12/2/2010 8:30 3/1/2011 17:30 327
3/2/2011 8:30 3/11/2011 17:30 328
3/12/2011 8:30 3/31/2011 17:30 329
9/13/2010 8:30 4/2/2011 17:30
9/13/2010 8:30 9/14/2010 17:30 43
9/15/2010 8:30 10/29/2010 17:30 332
10/30/2010 8:30 11/3/2010 17:30 333
11/4/2010 8:30 12/3/2010 17:30 334
12/4/2010 8:30 3/3/2011 17:30 335
3/4/2011 8:30 3/13/2011 17:30 336
3/14/2011 8:30 4/2/2011 17:30 337
12/24/2010 8:30 7/26/2011 17:30
12/24/2010 8:30 2/6/2011 17:30 332FS+100 d
2/7/2011 8:30 2/11/2011 17:30 340
2/27/2011 8:30 3/28/2011 17:30 341FS+15 d
3/29/2011 8:30 6/26/2011 17:30 342
6/27/2011 8:30 7/6/2011 17:30 343
7/7/2011 8:30 7/26/2011 17:30 344
9/3/2009 8:30 11/21/2010 17:30
9/3/2009 8:30 3/25/2010 17:30
9/3/2009 8:30 9/4/2009 17:30 11SS+25 d
9/5/2009 8:30 10/19/2009 17:30 348
10/20/2009 8:30 10/21/2009 17:30 349
11/6/2009 8:30 11/25/2009 17:30 350FS+15 d
11/26/2009 8:30 2/23/2010 17:30 351
2/24/2010 8:30 3/5/2010 17:30 352
3/6/2010 8:30 3/25/2010 17:30 353
5/4/2010 8:30 11/21/2010 17:30
5/4/2010 8:30 6/17/2010 17:30 47SS+60 d,17
6/18/2010 8:30 6/19/2010 17:30 356
7/5/2010 8:30 7/24/2010 17:30 357FS+15 d
7/25/2010 8:30 10/22/2010 17:30 358
10/23/2010 8:30 11/1/2010 17:30 359
11/2/2010 8:30 11/21/2010 17:30 360
9/28/2009 8:30 1/12/2011 17:30
9/28/2009 8:30 3/13/2010 17:30
9/28/2009 8:30 9/29/2009 17:30 25
9/30/2009 8:30 11/13/2009 17:30 364
11/14/2009 8:30 11/18/2009 17:30 365
12/4/2009 8:30 12/23/2009 17:30 366FS+15 d
12/24/2009 8:30 2/11/2010 17:30 367
2/12/2010 8:30 2/21/2010 17:30 368
2/22/2010 8:30 3/13/2010 17:30 369
2/2/2010 8:30 8/15/2010 17:30
2/2/2010 8:30 3/18/2010 17:30 364FS+125 d
3/19/2010 8:30 3/23/2010 17:30 372
4/8/2010 8:30 4/27/2010 17:30 373FS+15 d
4/28/2010 8:30 7/16/2010 17:30 374
7/17/2010 8:30 7/26/2010 17:30 375
7/27/2010 8:30 8/15/2010 17:30 376
6/17/2010 8:30 1/12/2011 17:30
6/17/2010 8:30 7/31/2010 17:30 372FS+90 d
8/1/2010 8:30 8/5/2010 17:30 379
8/26/2010 8:30 9/14/2010 17:30 380FS+20 d
9/15/2010 8:30 12/13/2010 17:30 381
12/14/2010 8:30 12/23/2010 17:30 382
12/24/2010 8:30 1/12/2011 17:30 383
4/5/2010 8:30 4/9/2011 17:30
4/5/2010 8:30 10/26/2010 17:30
4/5/2010 8:30 4/9/2010 17:30 45SS+20 d
4/10/2010 8:30 5/24/2010 17:30 387
5/25/2010 8:30 5/29/2010 17:30 388
6/19/2010 8:30 7/18/2010 17:30 389FS+20 d
7/19/2010 8:30 9/26/2010 17:30 390
9/27/2010 8:30 10/6/2010 17:30 391
10/7/2010 8:30 10/26/2010 17:30 392
10/7/2010 8:30 4/9/2011 17:30
10/7/2010 8:30 10/11/2010 17:30 45
10/12/2010 8:30 11/25/2010 17:30 395
11/26/2010 8:30 11/30/2010 17:30 396
12/1/2010 8:30 12/30/2010 17:30 397
12/31/2010 8:30 3/10/2011 17:30 398
3/11/2011 8:30 3/20/2011 17:30 399
3/21/2011 8:30 4/9/2011 17:30 400
12/23/2009 8:30 8/28/2010 17:30
12/23/2009 8:30 12/24/2009 17:30 32
12/25/2009 8:30 2/7/2010 17:30 403
2/8/2010 8:30 2/9/2010 17:30 404
3/2/2010 8:30 3/31/2010 17:30 405FS+20 d
4/1/2010 8:30 7/29/2010 17:30 406
7/30/2010 8:30 8/8/2010 17:30 407
8/9/2010 8:30 8/28/2010 17:30 408
5/1/2010 8:30 9/27/2010 17:30
5/1/2010 8:30 8/28/2010 17:30 406FS+30 d
8/29/2010 8:30 9/7/2010 17:30 411
9/8/2010 8:30 9/27/2010 17:30 412
5/21/2010 8:30 10/17/2010 17:30
5/21/2010 8:30 9/17/2010 17:30 406FS+50 d
9/18/2010 8:30 9/27/2010 17:30 415
9/28/2010 8:30 10/17/2010 17:30 416
2/14/2011 8:30 9/3/2011 17:30
2/14/2011 8:30 2/23/2011 17:30 46
2/24/2011 8:30 4/9/2011 17:30 419
4/10/2011 8:30 4/11/2011 17:30 420
4/12/2011 8:30 5/6/2011 17:30 421
5/7/2011 8:30 8/4/2011 17:30 422
8/5/2011 8:30 8/14/2011 17:30 423
8/15/2011 8:30 9/3/2011 17:30 424
3/21/2011 8:30 10/8/2011 17:30
3/21/2011 8:30 3/30/2011 17:30 5FS+200 d
3/31/2011 8:30 5/14/2011 17:30 427
5/15/2011 8:30 5/16/2011 17:30 428
5/17/2011 8:30 6/10/2011 17:30 429
6/11/2011 8:30 9/8/2011 17:30 430
9/9/2011 8:30 9/18/2011 17:30 431
9/19/2011 8:30 10/8/2011 17:30 432
1/25/2010 17:30 1/10/2012 17:30
1/25/2010 17:30 11/13/2011 17:30
1/25/2010 17:30 1/25/2010 17:30 25FS+120 d
3/14/2010 8:30 5/12/2010 17:30 370,436,26
7/22/2010 8:30 4/7/2011 17:30 437FS+70 d,436,377FS-30 d
5/8/2011 8:30 8/15/2011 17:30 438FS+30 d,384
8/16/2011 8:30 11/13/2011 17:30 439
9/27/2010 8:30 12/17/2011 17:30
9/27/2010 8:30 9/27/2010 8:30 5FS+70 d
9/27/2010 8:30 11/25/2010 17:30 442,354
4/2/2011 8:30 4/2/2011 8:30 442FS+120 d
4/2/2011 8:30 5/25/2011 17:30 444,354
6/20/2011 17:30 6/20/2011 17:30 444FS+80 d
6/21/2011 8:30 10/18/2011 17:30 446,354
5/8/2011 8:30 9/4/2011 17:30 444FS+15 d
5/23/2011 8:30 9/19/2011 17:30 448SS+15 d,361
443FS-90 d,445FS-90 d,447FS-
90 d,449FS-90
d,40,285,300,308,323,330,338
7/21/2011 8:30 12/17/2011 17:30 ,315,345FS-6 d
3/18/2011 8:30 5/2/2011 17:30
3/18/2011 8:30 3/18/2011 8:30 5FS+200 d
3/18/2011 8:30 3/27/2011 17:30 452,260,264,268
3/28/2011 8:30 4/6/2011 17:30 453
4/7/2011 8:30 4/11/2011 17:30 454
4/12/2011 8:30 4/16/2011 17:30 455
4/17/2011 8:30 4/26/2011 17:30 456
4/30/2011 8:30 5/2/2011 17:30 614,457
10/11/2010 8:30 8/24/2011 17:30
10/11/2010 8:30 7/9/2011 17:30
10/11/2010 8:30 10/11/2010 8:30 131FS+200 d
10/26/2010 8:30 10/31/2010 17:30 461FS+15 d,134
11/1/2010 8:30 11/4/2010 17:30 462
11/5/2010 8:30 11/12/2010 17:30 463
11/13/2010 8:30 11/20/2010 17:30 464
11/21/2010 8:30 11/27/2010 17:30 465
11/28/2010 8:30 12/2/2010 17:30 466
12/3/2010 8:30 12/22/2010 17:30 467
12/23/2010 8:30 1/11/2011 17:30 468
7/5/2011 8:30 7/9/2011 17:30 469,719,473
12/3/2010 8:30 12/19/2010 17:30
12/3/2010 8:30 12/9/2010 17:30 467SS+5 d,183
12/10/2010 8:30 12/19/2010 17:30 472
1/20/2011 17:30 8/24/2011 17:30
1/20/2011 17:30 1/20/2011 17:30 131FS+360 d
1/21/2011 8:30 1/30/2011 17:30 475,138
1/31/2011 8:30 2/7/2011 17:30 476
2/8/2011 8:30 2/19/2011 17:30 477
2/20/2011 8:30 2/27/2011 17:30 478
2/28/2011 8:30 3/6/2011 17:30 479
3/7/2011 8:30 3/11/2011 17:30 480
3/12/2011 8:30 4/5/2011 17:30 481
4/6/2011 8:30 4/30/2011 17:30 482
8/20/2011 8:30 8/24/2011 17:30 483,827,487
3/12/2011 8:30 3/28/2011 17:30
3/12/2011 8:30 3/18/2011 17:30 481SS+5 d,183
3/19/2011 8:30 3/28/2011 17:30 486
12/17/2010 8:30 12/31/2011 17:30
2/1/2011 8:30 7/3/2011 17:30
2/1/2011 8:30 2/1/2011 8:30 47FS+150 d
2/1/2011 8:30 2/25/2011 17:30 490,147,151
2/26/2011 8:30 3/27/2011 17:30 491
6/29/2011 8:30 7/3/2011 17:30 492,719
12/17/2010 8:30 7/3/2011 17:30
12/17/2010 8:30 12/17/2010 8:30 156FS+200 d
12/17/2010 8:30 12/26/2010 17:30 495,159
12/27/2010 8:30 1/3/2011 17:30 496
1/4/2011 8:30 1/13/2011 17:30 497
1/14/2011 8:30 1/21/2011 17:30 498
1/22/2011 8:30 1/26/2011 17:30 499
1/27/2011 8:30 2/15/2011 17:30 500
2/16/2011 8:30 3/7/2011 17:30 501
6/29/2011 8:30 7/3/2011 17:30 502,719
3/31/2011 8:30 12/24/2011 17:30
3/31/2011 8:30 3/31/2011 8:30 495FS+100 d
3/31/2011 8:30 4/9/2011 17:30 505,171
4/10/2011 8:30 4/17/2011 17:30 506
4/18/2011 8:30 4/27/2011 17:30 507
4/28/2011 8:30 5/5/2011 17:30 508
5/6/2011 8:30 5/10/2011 17:30 509
5/11/2011 8:30 5/20/2011 17:30 510
5/21/2011 8:30 5/30/2011 17:30 511
12/20/2011 8:30 12/24/2011 17:30 512,719
4/18/2011 8:30 12/24/2011 17:30
4/18/2011 8:30 4/18/2011 8:30 495FS+110 d
4/18/2011 8:30 4/27/2011 17:30 515
4/28/2011 8:30 5/5/2011 17:30 516
5/21/2011 8:30 5/30/2011 17:30 517FS+15 d
5/31/2011 8:30 6/7/2011 17:30 518
6/8/2011 8:30 6/12/2011 17:30 519
6/13/2011 8:30 6/22/2011 17:30 520
6/23/2011 8:30 7/2/2011 17:30 521
12/20/2011 8:30 12/24/2011 17:30 522,719
1/15/2011 17:30 7/3/2011 17:30
1/15/2011 17:30 1/15/2011 17:30 495FS+30 d
1/16/2011 8:30 1/25/2011 17:30 525,159
1/26/2011 8:30 2/2/2011 17:30 526
2/3/2011 8:30 2/12/2011 17:30 527
2/13/2011 8:30 2/20/2011 17:30 528
2/21/2011 8:30 2/25/2011 17:30 529
2/26/2011 8:30 3/7/2011 17:30 530
3/8/2011 8:30 3/17/2011 17:30 531
6/29/2011 8:30 7/3/2011 17:30 532,719
5/16/2011 8:30 12/24/2011 17:30
5/16/2011 8:30 5/16/2011 8:30 495FS+120 d
5/21/2011 8:30 5/30/2011 17:30 175,535FS+5 d
5/31/2011 8:30 6/7/2011 17:30 536
6/8/2011 8:30 6/17/2011 17:30 537
6/28/2011 8:30 7/5/2011 17:30 538FS+10 d
7/6/2011 8:30 7/10/2011 17:30 539
7/11/2011 8:30 7/20/2011 17:30 540
7/21/2011 8:30 7/30/2011 17:30 541
12/20/2011 8:30 12/24/2011 17:30 542,719
7/18/2011 8:30 12/24/2011 17:30
9/5/2011 17:30 9/5/2011 17:30 603FS+130 d
7/18/2011 8:30 7/27/2011 17:30 545FS-50 d,163
7/28/2011 8:30 8/4/2011 17:30 546
8/5/2011 8:30 8/14/2011 17:30 547
8/25/2011 8:30 9/1/2011 17:30 548FS+10 d
9/2/2011 8:30 9/6/2011 17:30 549
9/7/2011 8:30 9/16/2011 17:30 550
9/17/2011 8:30 9/26/2011 17:30 551
12/20/2011 8:30 12/24/2011 17:30 552,719
6/20/2011 8:30 12/24/2011 17:30
6/20/2011 8:30 6/20/2011 8:30 495FS+140 d
6/25/2011 8:30 7/4/2011 17:30 555FS+5 d,163,171
7/5/2011 8:30 7/12/2011 17:30 556
7/13/2011 8:30 7/22/2011 17:30 557
7/28/2011 8:30 8/4/2011 17:30 558FS+5 d
8/5/2011 8:30 8/9/2011 17:30 559
8/10/2011 8:30 8/19/2011 17:30 560
8/20/2011 8:30 8/29/2011 17:30 561
12/20/2011 8:30 12/24/2011 17:30 562,719
7/1/2011 8:30 12/24/2011 17:30
7/1/2011 8:30 7/1/2011 8:30 163
7/1/2011 8:30 7/10/2011 17:30 565
7/11/2011 8:30 7/18/2011 17:30 566
7/29/2011 8:30 8/7/2011 17:30 567FS+10 d
8/8/2011 8:30 8/15/2011 17:30 568
8/16/2011 8:30 8/20/2011 17:30 569
8/21/2011 8:30 8/30/2011 17:30 570
12/20/2011 8:30 12/24/2011 17:30 571,719
7/24/2011 8:30 12/31/2011 17:30
7/24/2011 8:30 7/24/2011 8:30 495FS+150 d
7/24/2011 8:30 8/17/2011 17:30 574,171,175
8/18/2011 8:30 9/6/2011 17:30 575
9/7/2011 8:30 9/22/2011 17:30 576
9/23/2011 8:30 10/17/2011 17:30 577
10/18/2011 8:30 10/22/2011 17:30 578
10/23/2011 8:30 11/21/2011 17:30 579
11/22/2011 8:30 12/21/2011 17:30 580
12/22/2011 8:30 12/31/2011 17:30 581,726,827
2/1/2011 8:30 7/8/2011 17:30
2/1/2011 8:30 2/1/2011 8:30 47FS+150 d
2/1/2011 8:30 3/28/2011 17:30 584,147,151
3/29/2011 8:30 5/7/2011 17:30 585
7/4/2011 8:30 7/8/2011 17:30 719,726,586
7/24/2011 8:30 12/24/2011 17:30
7/24/2011 8:30 7/24/2011 8:30 495FS+150 d
7/24/2011 8:30 8/4/2011 17:30 589
8/5/2011 8:30 8/24/2011 17:30 590
8/25/2011 8:30 9/8/2011 17:30 591
9/9/2011 8:30 9/23/2011 17:30 592
9/24/2011 8:30 10/8/2011 17:30 593
10/9/2011 8:30 10/28/2011 17:30 594
10/29/2011 8:30 11/22/2011 17:30 595
12/20/2011 8:30 12/24/2011 17:30 596,719,820
3/18/2011 8:30 5/8/2011 17:30
3/18/2011 8:30 3/18/2011 8:30 5FS+200 d
3/18/2011 8:30 3/24/2011 17:30 599,276
3/25/2011 8:30 4/1/2011 17:30 600
4/2/2011 8:30 4/21/2011 17:30 601
4/22/2011 8:30 4/28/2011 17:30 602
4/29/2011 8:30 5/3/2011 17:30 603
5/4/2011 8:30 5/8/2011 17:30 604,621
1/21/2011 8:30 3/21/2011 17:30
1/21/2011 8:30 3/21/2011 17:30 251
2/24/2011 8:30 7/13/2011 17:30
2/24/2011 8:30 2/24/2011 8:30 213FS+125 d
2/24/2011 8:30 3/10/2011 17:30 609,216,211
3/11/2011 8:30 3/20/2011 17:30 610
3/21/2011 8:30 4/4/2011 17:30 611
4/5/2011 8:30 4/19/2011 17:30 612
4/5/2011 8:30 4/29/2011 17:30 607,612
7/4/2011 8:30 7/13/2011 17:30 614,493,613
2/24/2011 8:30 7/18/2011 17:30
2/24/2011 8:30 3/10/2011 17:30 610SS,211,216
3/11/2011 8:30 3/20/2011 17:30 617
3/21/2011 8:30 4/4/2011 17:30 618
4/5/2011 8:30 4/19/2011 17:30 619
4/5/2011 8:30 4/29/2011 17:30 619
7/9/2011 8:30 7/18/2011 17:30 621,587,620
2/25/2011 8:30 1/10/2012 17:30
2/25/2011 8:30 3/11/2011 17:30 221,226
3/12/2011 8:30 3/21/2011 17:30 624
3/22/2011 8:30 4/5/2011 17:30 625
4/6/2011 8:30 4/20/2011 17:30 626
4/21/2011 8:30 5/15/2011 17:30 627
628,513,523,543,553,563,572,
1/1/2012 8:30 1/10/2012 17:30 582,597
10/22/2010 8:30 12/5/2011 17:30
10/22/2010 8:30 12/5/2011 17:30
10/22/2010 8:30 3/20/2011 17:30 393SS+15 d
3/21/2011 8:30 5/19/2011 17:30 632
5/20/2011 8:30 8/27/2011 17:30 633
8/28/2011 8:30 12/5/2011 17:30 634
3/31/2011 8:30 10/6/2011 17:30
3/31/2011 8:30 5/29/2011 17:30 401SS+10 d
5/30/2011 8:30 7/13/2011 17:30 637
7/14/2011 8:30 8/12/2011 17:30 638
8/13/2011 8:30 10/6/2011 17:30 639
9/27/2010 8:30 4/15/2012 17:30
1/15/2011 8:30 4/14/2012 17:30
1/15/2011 8:30 1/15/2011 8:30 54FS+270 d
1/15/2011 8:30 2/3/2011 17:30 643
2/5/2011 8:30 3/6/2011 17:30 644,57,61,65FS-45 d
3/7/2011 8:30 4/5/2011 17:30 645
4/6/2011 8:30 4/25/2011 17:30 646
4/26/2011 8:30 5/16/2011 17:30 647
5/17/2011 8:30 6/15/2011 17:30 648
6/16/2011 8:30 7/5/2011 17:30 649
7/6/2011 8:30 7/30/2011 17:30 650
7/31/2011 8:30 8/9/2011 17:30 651
8/10/2011 8:30 9/3/2011 17:30 652
9/4/2011 8:30 10/8/2011 17:30 653
10/9/2011 8:30 11/2/2011 17:30 654
11/3/2011 8:30 12/17/2011 17:30 655
4/14/2012 8:30 4/14/2012 17:30 656
4/5/2011 8:30 4/15/2012 17:30
4/5/2011 8:30 4/5/2011 8:30 98FS+240 d
4/5/2011 8:30 4/14/2011 17:30 659
4/15/2011 8:30 4/29/2011 17:30 660,105,101
4/30/2011 8:30 5/6/2011 17:30 661
5/7/2011 8:30 5/12/2011 17:30 662
5/13/2011 8:30 5/24/2011 17:30 663
5/25/2011 8:30 6/8/2011 17:30 664
6/9/2011 8:30 6/18/2011 17:30 665
6/19/2011 8:30 6/28/2011 17:30 666
6/29/2011 8:30 7/6/2011 17:30 667
7/7/2011 8:30 7/14/2011 17:30 668
7/15/2011 8:30 8/3/2011 17:30 669
8/4/2011 8:30 8/20/2011 17:30 670
8/21/2011 8:30 9/19/2011 17:30 671
4/15/2012 8:30 4/15/2012 17:30 672,676
7/15/2011 8:30 8/5/2011 17:30
7/15/2011 8:30 7/21/2011 17:30 669,183
7/22/2011 8:30 8/5/2011 17:30 675
10/7/2010 8:30 6/18/2011 17:30
10/7/2010 8:30 10/7/2010 8:30 86FS+210 d
10/7/2010 8:30 10/10/2010 17:30 678
10/11/2010 8:30 10/15/2010 17:30 679,89
10/16/2010 8:30 10/18/2010 17:30 680
10/19/2010 8:30 10/23/2010 17:30 681
10/24/2010 8:30 10/28/2010 17:30 682
10/29/2010 8:30 11/2/2010 17:30 683
11/3/2010 8:30 11/6/2010 17:30 684
11/7/2010 8:30 11/9/2010 17:30 685
11/10/2010 8:30 11/14/2010 17:30 686
11/15/2010 8:30 11/19/2010 17:30 687
11/20/2010 8:30 12/9/2010 17:30 688
12/10/2010 8:30 12/24/2010 17:30 689
12/25/2010 8:30 1/13/2011 17:30 690
6/14/2011 8:30 6/18/2011 17:30 6,691,695
11/20/2010 8:30 12/14/2010 17:30
11/20/2010 8:30 11/29/2010 17:30 688SS+5 d,183
11/30/2010 8:30 12/14/2010 17:30 694
9/27/2010 8:30 7/8/2011 17:30
9/27/2010 8:30 9/27/2010 8:30 119FS+120 d
9/27/2010 8:30 10/3/2010 17:30 697,122
10/4/2010 8:30 10/11/2010 17:30 698
10/12/2010 8:30 10/16/2010 17:30 699
10/17/2010 8:30 10/24/2010 17:30 700
10/25/2010 8:30 11/1/2010 17:30 701
11/2/2010 8:30 11/11/2010 17:30 702
11/12/2010 8:30 12/1/2010 17:30 703
12/2/2010 8:30 12/26/2010 17:30 704
7/4/2011 8:30 7/8/2011 17:30 705,726
11/12/2010 8:30 12/3/2010 17:30
11/12/2010 8:30 11/18/2010 17:30 703,183
11/19/2010 8:30 12/3/2010 17:30 708
1/5/2011 8:30 3/5/2011 17:30
1/5/2011 8:30 3/5/2011 17:30 235
1/18/2011 8:30 6/28/2011 17:30
1/18/2011 8:30 1/18/2011 8:30 5FS+400 d
1/18/2011 8:30 2/1/2011 17:30 713,192
2/2/2011 8:30 2/8/2011 17:30 714
2/9/2011 8:30 3/10/2011 17:30 715
3/11/2011 8:30 3/20/2011 17:30 716
3/21/2011 8:30 4/14/2011 17:30 717,711
6/19/2011 8:30 6/28/2011 17:30 718,692
1/18/2011 8:30 7/3/2011 17:30
1/18/2011 8:30 2/1/2011 17:30 713
2/2/2011 8:30 2/8/2011 17:30 721
2/9/2011 8:30 3/10/2011 17:30 722
3/11/2011 8:30 3/20/2011 17:30 723
3/21/2011 8:30 4/14/2011 17:30 724,711
6/29/2011 8:30 7/3/2011 17:30 719,725
1/10/2011 8:30 3/10/2011 17:30
1/10/2011 8:30 3/10/2011 17:30 243
1/18/2011 8:30 7/13/2011 17:30
1/18/2011 8:30 2/6/2011 17:30 197,713
2/7/2011 8:30 2/21/2011 17:30 730
2/22/2011 8:30 3/13/2011 17:30 731
3/14/2011 8:30 3/23/2011 17:30 732
3/24/2011 8:30 4/22/2011 17:30 733,728
7/9/2011 8:30 7/13/2011 17:30 706,709,734
9/4/2011 8:30 1/17/2012 17:30
9/4/2011 8:30 9/4/2011 8:30 406FS+200 d
9/4/2011 8:30 9/25/2011 17:30 737,409,413
9/26/2011 8:30 10/25/2011 17:30 738
10/26/2011 8:30 10/30/2011 17:30 739
10/31/2011 8:30 11/29/2011 17:30 740
1/3/2012 8:30 1/17/2012 17:30 741
12/6/2010 8:30 7/14/2012 17:30
4/15/2011 8:30 7/13/2012 17:30
4/15/2011 8:30 4/15/2011 8:30 54FS+270 d
4/15/2011 8:30 5/4/2011 17:30 745
77FS-50 d,73FS-4 d,69,81FS-
5/6/2011 8:30 6/4/2011 17:30 50 d,746
6/5/2011 8:30 6/24/2011 17:30 747
6/25/2011 8:30 7/4/2011 17:30 748
7/5/2011 8:30 7/19/2011 17:30 749
7/20/2011 8:30 8/18/2011 17:30 750
8/19/2011 8:30 9/7/2011 17:30 751
9/8/2011 8:30 10/2/2011 17:30 752
10/3/2011 8:30 10/12/2011 17:30 753
10/13/2011 8:30 11/6/2011 17:30 754
11/7/2011 8:30 12/16/2011 17:30 755
12/17/2011 8:30 1/5/2012 17:30 756
1/6/2012 8:30 2/19/2012 17:30 757
7/13/2012 8:30 7/13/2012 17:30 758
7/4/2011 8:30 7/14/2012 17:30
7/4/2011 8:30 7/4/2011 8:30 98FS+240 d
7/4/2011 8:30 7/18/2011 17:30 761
7/19/2011 8:30 8/2/2011 17:30 762,113,109
8/3/2011 8:30 8/9/2011 17:30 763
8/10/2011 8:30 8/15/2011 17:30 764
8/16/2011 8:30 8/25/2011 17:30 765
8/26/2011 8:30 9/4/2011 17:30 766
9/5/2011 8:30 9/14/2011 17:30 767
9/15/2011 8:30 9/29/2011 17:30 768
9/30/2011 8:30 10/7/2011 17:30 769
10/8/2011 8:30 10/17/2011 17:30 770
10/18/2011 8:30 11/4/2011 17:30 771
11/5/2011 8:30 11/19/2011 17:30 772
11/20/2011 8:30 12/14/2011 17:30 773
7/14/2012 8:30 7/14/2012 17:30 774,778
10/18/2011 8:30 11/8/2011 17:30
10/18/2011 8:30 10/24/2011 17:30 771,183
10/25/2011 8:30 11/8/2011 17:30 777
12/6/2010 8:30 7/4/2011 17:30
12/6/2010 8:30 12/6/2010 8:30 86FS+210 d
12/6/2010 8:30 12/9/2010 17:30 780
12/10/2010 8:30 12/14/2010 17:30 93,781
12/15/2010 8:30 12/17/2010 17:30 782
12/18/2010 8:30 12/22/2010 17:30 783
12/23/2010 8:30 1/6/2011 17:30 784
1/7/2011 8:30 1/16/2011 17:30 785
1/17/2011 8:30 1/28/2011 17:30 786
1/29/2011 8:30 2/7/2011 17:30 787
2/8/2011 8:30 2/12/2011 17:30 788
2/13/2011 8:30 2/22/2011 17:30 789
2/23/2011 8:30 3/14/2011 17:30 790
3/15/2011 8:30 3/28/2011 17:30 791
3/29/2011 8:30 4/22/2011 17:30 792
7/4/2011 8:30 7/4/2011 17:30 793,6,797
2/13/2011 8:30 3/9/2011 17:30
2/13/2011 8:30 2/22/2011 17:30 789,183
2/23/2011 8:30 3/9/2011 17:30 796
3/1/2011 8:30 4/29/2011 17:30
3/1/2011 8:30 4/29/2011 17:30 235
12/26/2010 8:30 8/20/2011 17:30
12/26/2010 8:30 12/26/2010 8:30 697FS+10 d
12/26/2010 8:30 1/1/2011 17:30 801,126
1/2/2011 8:30 1/9/2011 17:30 802
1/10/2011 8:30 1/19/2011 17:30 803
1/20/2011 8:30 1/27/2011 17:30 804
1/28/2011 8:30 2/6/2011 17:30 805
2/7/2011 8:30 2/16/2011 17:30 806
2/17/2011 8:30 3/8/2011 17:30 807
3/9/2011 8:30 3/28/2011 17:30 808
8/20/2011 8:30 8/20/2011 17:30 809,827,813
2/17/2011 8:30 3/13/2011 17:30
2/17/2011 8:30 2/26/2011 17:30 807,183
2/27/2011 8:30 3/13/2011 17:30 812
3/19/2011 8:30 8/14/2011 17:30
3/19/2011 8:30 4/2/2011 17:30 714SS+60 d
4/3/2011 8:30 4/9/2011 17:30 815
4/10/2011 8:30 5/9/2011 17:30 816
5/10/2011 8:30 5/19/2011 17:30 817
5/20/2011 8:30 6/18/2011 17:30 818,799
8/5/2011 8:30 8/14/2011 17:30 819,794
5/13/2011 8:30 8/19/2011 17:30
5/13/2011 8:30 5/27/2011 17:30 721FS+100 d
5/28/2011 8:30 6/3/2011 17:30 822
6/4/2011 8:30 7/3/2011 17:30 823
7/4/2011 8:30 7/13/2011 17:30 824
7/14/2011 8:30 8/7/2011 17:30 825
8/15/2011 8:30 8/19/2011 17:30 826,820
2/25/2011 8:30 4/25/2011 17:30
2/25/2011 8:30 4/25/2011 17:30 243
3/24/2011 8:30 8/25/2011 17:30
3/24/2011 8:30 4/12/2011 17:30 734SS
4/13/2011 8:30 4/27/2011 17:30 831
4/28/2011 8:30 5/17/2011 17:30 832
5/18/2011 8:30 5/27/2011 17:30 833
5/28/2011 8:30 6/26/2011 17:30 834,829
8/21/2011 8:30 8/25/2011 17:30 835,810
9/4/2011 8:30 1/17/2012 17:30
9/4/2011 8:30 9/4/2011 8:30 406FS+200 d
9/4/2011 8:30 9/25/2011 17:30 838,417
9/26/2011 8:30 10/25/2011 17:30 839
10/26/2011 8:30 10/30/2011 17:30 840
10/31/2011 8:30 11/29/2011 17:30 841
1/3/2012 8:30 1/17/2012 17:30 842
2/1/2011 8:30 9/3/2011 17:30
3/10/2011 8:30 9/3/2011 17:30
4/30/2011 8:30 4/30/2011 8:30 5FS+300 d
3/10/2011 8:30 3/10/2011 8:30 443
3/10/2011 8:30 3/31/2011 17:30 847
4/1/2011 8:30 5/5/2011 17:30 848
4/30/2011 8:30 5/9/2011 17:30 846,202
5/10/2011 8:30 5/17/2011 17:30 850
5/18/2011 8:30 5/25/2011 17:30 851
5/26/2011 8:30 5/29/2011 17:30 852
5/30/2011 8:30 6/2/2011 17:30 853
6/3/2011 8:30 6/17/2011 17:30 854,849
8/30/2011 8:30 9/3/2011 17:30 855,484FS+5 d
4/25/2011 8:30 7/21/2011 17:30
4/25/2011 8:30 4/25/2011 8:30 5FS+300 d
6/17/2011 8:30 7/1/2011 17:30 449SS+25 d
4/25/2011 8:30 5/4/2011 17:30 858,202
5/5/2011 8:30 5/12/2011 17:30 860
5/13/2011 8:30 5/20/2011 17:30 861,292
5/21/2011 8:30 5/24/2011 17:30 862
5/25/2011 8:30 5/28/2011 17:30 863
7/2/2011 8:30 7/16/2011 17:30 864,859
7/17/2011 8:30 7/21/2011 17:30 865,470FS+5 d
4/15/2011 8:30 7/21/2011 17:30
4/15/2011 8:30 4/15/2011 8:30 5FS+300 d
6/12/2011 8:30 7/1/2011 17:30 449SS+20 d
4/15/2011 8:30 4/24/2011 17:30 868,197
4/25/2011 8:30 5/2/2011 17:30 870
5/3/2011 8:30 5/10/2011 17:30 871,292
5/11/2011 8:30 5/14/2011 17:30 872
5/15/2011 8:30 5/18/2011 17:30 873
7/2/2011 8:30 7/16/2011 17:30 874,869
7/17/2011 8:30 7/21/2011 17:30 875,470FS+5 d
2/1/2011 8:30 7/8/2011 17:30
4/17/2011 8:30 4/17/2011 8:30 5FS+300 d
2/1/2011 8:30 2/1/2011 8:30 442FS+80 d
4/17/2011 8:30 5/16/2011 17:30 879,878
5/17/2011 8:30 6/5/2011 17:30 880
4/17/2011 8:30 4/26/2011 17:30 878
4/27/2011 8:30 5/4/2011 17:30 882
5/5/2011 8:30 5/12/2011 17:30 883,292
5/13/2011 8:30 5/16/2011 17:30 884
5/17/2011 8:30 5/20/2011 17:30 885
6/6/2011 8:30 6/20/2011 17:30 886,881
7/4/2011 8:30 7/8/2011 17:30 887,533

Você também pode gostar